CONCRETING WORKS COST DATA:

UNIT COST
ITEM WORK UNIT QTY. TOTAL REMARKS
MATERIAL QTY. TOTAL
DESCRIPTION AMOUNT
Concreting
1.0 Column m3 5.44 Cement 732 Bags 250.00 183,000.00
1.1 Footing m3 32.32 Sand 30.47 m3 1,100.00 33,517.00
1.03 Stairs m3 1.65 Gravel 60.94 m3 1,150.00 70,081.00
1.04 Slab m3 15.71
1.05 Lintel Beam m3 0.62
1.06 Beam m3 4.39
Total Volume: 60.13 Total Concreting Works: Php 286,598.00
SOLUTION:

CONCRETING FOR COLUMN

Concrete Volume for C1 for the First Floor


Vol. for 1 Column = 0.175 x 0.45 x (2.80 + 0.90) = 0.291375 m3
Total Volume = 0.291375 m3 x 4 pcs = 1.1655m3

Concrete Volume for C2 for the First Floor


Vol. for 1 Column = 0.175 x 0.40 x (2.80 + 0.90) = 0.259 m3
Total Volume = 0.259 m3 x 4 pcs = 1.036m3

Concrete Volume for C3 for the First Floor


Vol. for 1 Column = 0.15 x 0.35 x (2.80 + 0.90) = 0.19425 m3
Total Volume = 0.19425 m3 x 2 pcs = 0.3885m3

Concrete Volume for C4 for the First Floor


Vol. for 1 Column = 0.15 x 0.375 x (2.80 + 0.90) = 0.208125 m3
Total Volume = 0.208125 m3 x 1 pc = 0.208125m3

Concrete Volume for C5 for the First Floor


Vol. for 1 Column = 0.3 x 0.3 x (2.80 + 0.90) = 0.333m3
Total Volume = 0.333 m3 x 2 pcs = 0.666m3

Concrete Volume for C1 for the Second Floor


Vol. for 1 Column = 0.15 x 0.35 x 2.60 = 0.1365m3
Total Volume = 0.1365 m3 x 4 pcs = 0.546m3

Concrete Volume for C2 for the Second Floor


Vol. for 1 Column = = 0.15 x 0.35 x 2.60 = 0.1365m3
Total Volume = 0.1365 m3 x 4 pcs = 0.546m3

Concrete Volume for C3 for the Second Floor


Vol. for 1 Column = 0.15 x 0.35 x 2.60 = 0.1365m3
Total Volume = 0.1365 m3 x 2 pcs = 0.273m3

Concrete Volume for C4 for the Second Floor


Vol. for 1 Column = 0.15 x 0.375 x 2.60 = 0.14625m3
Total Volume = 0.14625 m3 x 1 pc = 0.14625m3
Concrete Volume for C5 for the Second Floor
Vol. for 1 Column = 0.3 x 0.3 x 2.60 = 0.234m3
Total Volume = 0.234 m3 x 2 pcs = 0.468m3

TOTAL CONCRETE VOLUME FOR COLUMNS


= 1.1655m3 + 1.036m3 + 0.3885m3 + 0.208125m3 + 0.666m3 + 0.546m3 + 0.546m3 +
0.273m3 + 0.14625m3 + 0.468m3
= 5.443375m3 ≈ 5.44m3

CONCRETING FOR FOOTING

Concrete Volume for F1


Vol. for 1 Footing = 1.1m x 1.2m x 0.3m = 0.396m3
Total Volume = 0.396m3 x 4 pcs = 1.584m3

Concrete Volume for F2


Vol. for 1 Footing = 0.9m x 1.05m x 0.3m = 0.2835m3
Total Volume = 0.2835m3 x 4 pcs = 1.134m3

Concrete Volume for F3


Vol. for 1 Footing = 0.7m x 0.7m x 0.3m = 0.147m3
Total Volume = 0.147m3 x 2 pcs = 0.294m3

Concrete Volume for F4


Vol. for 1 Footing = 0.85m x 0.7m x 0.3m = 0.1785m3
Total Volume = 0.1785m3 x 1 pc = 0.1785m3

*Concrete Volume for F5 (N/A: This footing is not used in the plan)
Vol. for 1 Footing = 0.7m x 0.85m x 0.3m = 0.1785m3
Total Volume = 0.1785m3 x 0 = 0m3

Concrete Volume for F6


Vol. for 1 Footing = 0.8m x 0.8m x 0.25m = 0.16m3
Total Volume = 0.16m3 x 2 pcs = 0.32m3

Concrete Volume for WF1


Vol. for 1 Footing = 0.5m x 27.775m x 0.25m = 3.471875m3
Total Volume = 3.471875m3 x 7 pcs = 24.303125m3

Concrete Volume for WF2


Vol. for 1 Footing = {[2 x (1/2 x 0.15m x .15)] + (0.3m x 0.15m)} x 11.1375m =
0.75178125m3
Total Volume = 0.75178125m3 x 6 pcs = 4.5106875m3
Concrete Volume for WF3 (N/A: This footing is not used in the plan)
Vol. for 1 Footing = 0.5m x 27.775m x 0.25m = 3.471875m3
Total Volume = 3.471875m3 x 0 = 0m3

TOTAL CONCRETE VOLUME FOR FOOTINGS


= 1.584m3 + 1.1340m3 + 0.294m3 + 0.1785m3 + 0.32m3 + 24.303125m3 + 4.5106875m3
= 32.3243125m3 ≈ 32.32m3

CONCRETING FOR STAIRS

Powder Room FL to Ground FFL


Rise = 0.175m
Run = 0.25m
Width = 1.075

Getting the Cross-sectional Area:


1st Step Rise – GRD FLR Slab Thickness = 0.175 – 0.1 = 0.075m
A = 0.25(0.075 + 0.175(3)) + 0.25(0.175(3)) + 0.25(0.175(2)) + 0.25(0.175)
= 0.4125m2

Volume = 0.4125(1.075) = 0.4434375m3

Ground FFL to 8th Step


Rise: 1st Step = 0.1337m
2nd Step to 8th Step = 0.1737m
Run = 0.25m
Width = 1.075m

Getting the Cross-sectional Area:


Cross-sectional Area including the space below the stairs…
A = 0.1337(2) + 0.1737(1.75 + 1.5 +1.25 + 1 + 0.75 + 0.5 + 0.25)
A = 1.4833m2
Cross-sectional Area of Space below the stairs…
1.3495(1.7371)
A= = 1.172108225m2
2
Total Cross-sectional Area = 1.4833m2 - 1.172108225m2 = 0.311191775m2

Volume = 0.311191775 (1.075) = 0.3345311581m3

9th Step
Width = 1.075
0.1277(0.0887) 0.2053(0.1427)
A = 0.1(0.6) + 0.085(0.0447) + 0.1737(0.2053) + +
2 2
A = 0.11977176m2

Volume = 0.11977176(1.075) = 0.1287540142m3

10th Step
Rise = 0.1737m
0.85(0.855)
A (top view) = 0.85(0.1064) + = 0.453815m2
2
Volume = 0.453815(0.1737) = 0.0788276655m3
11 Step
th

Rise = 0.1737m
Total height = 0.1737 + 0.03 = 0.2037m
A (top view) = 0.945(1.005) = 0.949725m2
Volume = 0.949725(0.2037) = 0.1934589825m3

12th Step
Rise = 0.1737m
0.8611(0.8806)
A (top view) = = 0.37914233m2
2
Volume = 0.37914233(0.1737) = 0.06585702272m3

13th to 18th Step


Rise = 0.1737m
Width = 1.005

Getting the Cross-sectional Area:


Cross-sectional Area including the space below the stairs…
A = 0.3163(1.5) + 0.1737(1.25 + 1 + 0.75 + 0.5 + 0.25)
A = 1.125825m2
Cross-sectional Area of Space below the stairs…
1.0421(1.5)
A= 2
= 0.781575m2
Total Cross-sectional Area = 1.125825m2 – 0.781575m2 = 0.34425m2

Volume = 0.34425(1.005) = 0.34597125m3

19th Step
Rise = 0.1737m

0.031(0.0447) 0.1125(0.0774) 0.1426(0.2053)


A = 0.1737(0.2053) + 0.1426(0.0447) + + +
2 2 2
A = 0.06171932m2

Volume = 0.06171932(1.005) = 0.0620279166m3


Total Volume
= 0.4434375 + 0.3345311581 + 0.1287540142 + 0.0788276655 + 0.1934589825 +
0.06585702272 + 0.34597125 + 0.0620279166
= 1.65286551m3

CONCRETING FOR SLAB

Total Concrete Volume for the First Floor


Thickness = 0.1m
Total Volume = [(1.25m x 3.25m ) + (4.75 x 10 )] x 0.1m = 4.90625m3

Total Concrete Volume for Carport


Thickness = 0.125m
Total Volume = [(5.5m x 10m) – (1.25m x 3.25m)] x 0.125m = 6.6367188m3

Total Concrete Volume for Bedroom 3 (2nd Floor)


2S-1
Thickness = 0.1m
Volume1 = 1.25m x 3.25m x 0.1m = 0.040625m3
2S-3
Thickness = 0.1m
Volume2 = (3.20m - 1.25m) x 3.25m x 0.1m = 0.63375m3
Total Volume = 0.040625m3 + 0.63375m3 = 0.674375m3

Total Concrete Volume for T&B 2, Bedroom 2, and Hall (2nd Floor)
2S-2
Thickness = 0.1m
Total Volume = [(2.8m x 3.25m) + (1.75m x 4.75m)] x 0.1m = 1.74125m3

Total Concrete Volume for T&B 1, and Front of Stairwell (2nd Floor)
2S-3
Thickness = 0.1m
Total Volume = [(1.25m x 3.75m) + (2m x (3.05m-1.25m)] x 0.1m = 0.82875m3

Total Concrete Volume for Master’s Bedroom (2nd Floor)


2S-3
Thickness = 0.1m
Total Volume = 3.05m x 3m x 0.1m = 0.0915m3
Total Concrete Volume for Balcony (2nd Floor)
2S-4
Thickness = 0.1m
Total Volume = 1m x 3.05m x 0.1m = 0.305m3

TOTAL CONCRETE VOLUME FOR SLAB ON GRADE


= 4.90625m3+ 6.6367188m3 + 0.674375m3 + 1.74125m3 + 0.82875m3 + 0.0915m3
+ 0.82875m3
= 15.707594m3 ≈ 15.71m3

LINTEL BEAM

Wall Thickness:
Exterior = 150mm
Interior = 100mm

For Arched Windows and Doors


W-1: 4 sets
W-2: 2 sets
W-3: 4 sets
W-4: 1 set
W-5: 1 set
W-6: 1 set
W-7: 1 set
W-8: 3 sets
W-9: 1 set
W-10: 1 set
D-8: 1 set
Total: 20 sets

Volume = 0.15 x 0.2 x 0.15 = 0.0045m 3


Total Volume = 0.0045m3 x 2 sides x 20 sets = 0.18m3

For Flat Top Windows and Doors


D-1:
Length = 1 + 0.3 + 0.3 = 1.6m
Volume = 1.6 x 0.2 x 0.15 = 0.048m3
Total Volume = 0.048 x 1 set = 0.048m3

D-2:
Length = 0.9 + 0.3 + 0.3 = 1.5m
Volume = 1.5 x 0.2 x 0.15 = 0.045m3
Total Volume = 0.045 x 3 sets = 0.135 m3
D-3:
Length = 0.9 + 0.3 + 0.3 = 1.5m
Volume = 1.5 x 0.2 x 0.1 = 0.03m3
Total Volume = 0.03 x 3 sets = 0.09 m3

D-4:
Length = 0.85 + 0.3 + 0.3 = 1.45m
Volume = 1.45 x 0.2 x 0.1 = 0.029m3
Total Volume = 0.029 x 1 set = 0.029 m3
D-5:
Length = 0.8 + 0.3 + 0.3 = 1.4m
Volume = 1.4 x 0.2 x 0.1 = 0.028m3
Total Volume = 0.028 x 2 sets = 0.056 m3
D-6:
Length = 0.7 + 0.3 + 0.3 = 1.3m
Volume = 1.3 x 0.2 x 0.1 = 0.026m3
Total Volume = 0.026 x 1 set = 0.026 m3

D-7:
Length = 0.7 + 0.3 + 0.3 = 1.3m
Volume = 1.3 x 0.2 x 0.1 = 0.026m3
Total Volume = 0.026 x 2 sets = 0.052 m3

Total Volume
= 0.18 + 0.048 + 0.135 + 0.09 + 0.029 + 0.056 + 0.026 + 0.052
= 0.616m3

CONCRETING FOR BEAM

Concrete Volume for 2B-1


Total Vol. for 1 Beam = 0.175 x 0.45 x 5.35 = 0.4213125m3

Concrete Volume for 2B-2


Total Vol. for 1 Beam = 0.175 x 0.45 x 4.20 = 0.33075m3

Concrete Volume for 2B-2A


Total Vol. for 1 Beam = 0.175 x 0.45 x 0.95 = 0.0748125m3

Concrete Volume for 2B-3


Total Vol. for 1 Beam = 0.175 x 0.45 x 4.46 = 0.351225m3
Concrete Volume for 2B-4
Total Vol. for 1 Beam = 0.175 x 0.45 x 1.94 = 0.152775m3

Concrete Volume for 2B-4A


Total Vol. for 1 Beam = 0.175 x 0.45 x 0.96 = 0.0756m3

Concrete Volume for 2B-5


Total Vol. for 1 Beam = 0.175 x 0.45 x 4.25 = 0.3346875m3

Concrete Volume for 2B-5A


Total Vol. for 1 Beam = 0.175 x 0.45 x 0.96 = 0.0756m3

Concrete Volume for 2B-6


Total Vol. for 1 Beam = 0.15 x 0.35 x 1.50 = 0.07875m3

Concrete Volume for 2B-6A


Total Vol. for 1 Beam = 0.15 x 0.35 x 0.95 = 0.049875m3

Concrete Volume for 2B-7


Total Vol. for 1 Beam = 0.175 x 0.45 x 1.60 = 0.126m3

Concrete Volume for 2B-7A


Total Vol. for 1 Beam = 0.175 x 0.45 x 4.60 = 0.36225m3

Concrete Volume for 2B-8


Total Vol. for 1 Beam = 0.175 x 0.45 x 2.95 = 0.2323125m3

Concrete Volume for 2B-9 (N/A: This Beam is not used in the plan)

Concrete Volume for 2B-10


Total Vol. for 1 Beam = 0.175 x 0.45 x 3.43 = 0.2701125m3

Concrete Volume for 2B-10A


Total Vol. for 1 Beam = 0.175 x 0.45 x 2.53 = 0.1992375m3

Concrete Volume for 2B-11


Vol. for 1st Beam = 0.15 x 0.45 x 3.45 = 0.232875m3
Vol. for 2nd Beam = 0.15 x 0.45 x 2.40 = 0.162m3
Vol. for 3rd Beam = 0.15 x 0.45 x 2.55 = 0.172125m3
Total Volume = 0.232875 m3 + 0.162 m3 + 0.172125 = 0.567m3

Concrete Volume for 2B-12


Total Vol. for 1 Beam = 0.15 x 0.45 x 2.73 = 0.184275m3

Concrete Volume for 2B-12A


Vol. for 1st Beam = 0.15 x 0.35 x 0.80 = 0.042m3
Vol. for 2nd Beam = 0.15 x 0.35 x 0.65 = 0.034125m3
Total Volume = 0.042 m3 + 0.034125 m3 = 0.076125m3

Concrete Volume for TB-1


Vol. for 1 Beam = 0.15 x 0.35 x 4.10 = 0.21525m3
Total Volume = 0.21525m3 x 2 pcs = 0.4305m3

TOTAL CONCRETE VOLUME FOR BEAM


= 0.4213125m3 + 0.33075m3 + 0.0748125m3 + 0.351225m3 + 0.152775m3 + 0.0756m3 +
0.3346875m3 + 0.0756m3 + 0.07875m3 + 0.049875m3 + 0.126m3 + 0.36225m3 +
0.2323125m3 + 0.2701125m3 + 0.1992375m3 + 0.567m3 + 0.184275m3 + 0.076125m3 +
0.4305m3
= 4.3932m3 ≈ 4.39m3

ADDITIONAL CONCRETING

Kitchen Countertops
Countertop 1:
Length = 2.325m
Width = 0.6m
Thickness = 0.08m

Volume of countertop 1 = 2.325 x 0.6 x 0.08 = 0.1116m3


Volume of the hole for the sink = 0.4 x 0.45 x 0.08 = 0.0144m3
Total Volume of the countertop 1 = 0.1116 - 0.0144 = 0.0972m3
Vol. of Elevation from GRD FFL = 2.325 x 0.6 x 0.1125 = 0.1569375m 3
Total Volume = 0.0972 + 0.1569375 = 0.2541375m3

Countertop 2:
Length = 1.6623m
Width = 0.6m
Thickness = 0.05m

Volume of countertop 2 = 1.6623 x 0.6 x 0.05 = 0.049869m3


Vol. of Elevation from GRD FFL = 2.325 x 0.6 x 0.1125 = 0.1569375m 3
Total Volume = 0.049869 + 0.1569375 = 0.2068065m3

Laundry Area Countertops


Countertop 1:
Length = 1.4m
Width = 0.6m
Height = 0.9m
Thickness = 0.15m

Volume of Sides = [0.15 x 0.6 x (0.9 – 0.15)] x 2 sides = 0.135m3


Volume of the top part = 1.4 x 0.6 x 0.15 = 0.126m3
Volume of the hole for the sink = 0.6 x 0.4 x 0.15 = 0.036m3
Total Volume = 0.135 + 0.126 - 0.036 = 0.225m3

Countertop 2:
Length = 0.6m
Width = 0.6m
Height = 0.9m
Thickness = 0.15m

Volume of Side = 0.15 x 0.6 x (0.9 – 0.15) = 0.0675m3


Volume of the top part = 0.6 x 0.6 x 0.15 = 0.054m3
Total Volume = 0.0675 + 0.054 = 0.1215m3

Total Volume for Additional Concreting


= 0.2541375 + 0.2068065 + 0.225 + 0.1215 = 0.807444m3
COSTING FOR CONCRETING

Class A Mixture 1:2:4 (40kg Cement)

Total Volume for Concreting


= 5.44 m3 + 32.32 m3 + 1.65 m3 + 15.71 m3 + 0.62 m3 + 0.807444m3
+ 4.39 m3
= 60.94m3

12 𝑏𝑎𝑔𝑠
Cement: 60.94 m3 x = 731.28 ≈ 732 bags
𝑚3

Sand: 60.94 m3 x 0.5 = 30.47 ≈ 30.47m3

Gravel: 60.94 m3 x 1 = 60.94 ≈ 60.94m3

Costing:

𝑃ℎ𝑝 250.00
Cement = x 732 bags = Php 183,000.00
1 𝑏𝑎𝑔

𝑃ℎ𝑝 1100.00
Sand = x 30.47m3 = Php 33,517.00
𝑚3

𝑃ℎ𝑝 1150.00
Gravel = x 60.94m3 = Php 70,081.00
𝑚3