Situation
Huawei Signed SWAP Contract with X Company for 5 years. In Tender RFP we found
that, customer has own rollout delivery Rollout Platform “Y”. All network planning,
rollout and acceptance controlled in “Y” Rollout Platform, including FLM project,
network alarm and Work Order also. Huawei proposed in delivery project used ISDP but
that was clearly mention in RFP requirement all information should update by vendor in
Project team start work with customer rollout team and requested training for “Y” Rollout
Platform. Huawei team requested specially VPN and account for “Y” Rollout Platform.
Installed VPN for Huawei staff and created account for access to customer internal
platform.
After first trail project (several sites) delivered by Huawei end to end, solution team
analyzed with project delivery team “Y” Rollout Platform flow chart step by step, and
services to X Company.
need to upload to “Y” Rollout Platform and also Huawei requirement from project
delivery team upload all doc to ISDP. This two operation manually and separately(2
times operation), and the on Air data also need to update in ISDP and “Y” Rollout
Platform separately(2 times operation). For one sites, the manually system operation
times will be 10 times, for whole project, the manually system operation work will have
1470*10= 14700 times. During trail sites delivery time it shows that all this process
Below picture, you can see actual situation before our solution
Huawei analyzed all proses and discussed with region IT team for solution. Met with customer IT
team, build both company team for discussion solution and integration task. Customer high
management and Huawei high management reviewed all process together and agreed solution.
Solution as below:
X Company and “Y” Rollout Platform Insist on ‘Site to Site’ VPN-industrial standard,
safe, stable
Result
After ISDP and “Y” Rollout Platform connection, TSSR report/SSV report/NP
report/Acceptance doc only need to upload to ISDP 1 time. Totally need to operate in
ISDP and “Y” Rollout Platform 5 times manually, X Company can get this information
Signing security: avoid papers missing during posting process; avoid documents
Cost saving: save the manpower cost, paper cost, risk cost and borrowing cost etc.
Suggestion or Review
Digital transformation bring our project more efficiency. 1. Project team avoid make
mistake, all work reviewed by each approval and no need transfer one system two other
by manual. 2. Cost saving, 3. Approval log and comment always Cleary in system, not
any email or verbal. All record till close project save in system. No need additional time