Download as pdf or txt
Download as pdf or txt
You are on page 1of 104

KCAB Arbitral Awards

KCAB
Arbitral Awards
Korean Commercial Arbitration Board

www.kcab.or.kr

Main office Busan Branch

43rd Floor, 511 Yeongdong-daero (Trade Tower, 176 Jungang-daero (Korea Express Building,
Samseong-dong), Gangnam-gu, Seoul Choryang-dong), Dong-gu, Busan

TEL: +82-2-551-2000/2021, FAX: +82-2-551-2020 TEL:+82-51-441-7032, FAX:+82-51-441-7039


Table of
Contents
1. Damages, etc 8. Contract Price, etc
Construction Company (Singapore) v. Power Company (Korea) 3 Engineering Company (Korea) v. Manufacturer (Italy) 144
2. Repayment of Contract Price, etc 9. Damages
Construction Company (Korea) v. Technology Company (USA) & Energy Company (Korea) 9 John Doe (Korea) v. Electronic Company (Vietnam) 165
3. Contract Price, etc 10. Liquidated Damages
Resources Company (Singapore) v. Power Company (Korea) 23 Aircraft Manufacturing Company (Indonesia) v. The Republic of Korea (Korea) 176
4. Damages, etc 11. Damages, etc
Wholesale Trade Company (Turkey) v. Component Manufacturing Company (Korea) 44 Cosmetic Company A (Israel) v. Cosmetic Company B (Korea) 193
5. Damages, etc
Construction Company (Korea) v. Power Company (France) 60
6. Damages, etc
Laboratories Ltd. (New Zealand) v. Softgel Ltd. (Korea) 109
7. Damages
Energy Company (Korea) v. Seller Company (Vietnam) 127

1 2
Korean Commercial Arbitration Board

Excerpt
I. TERMINATION OF SUBCONTRACT
[1] 
“Respondent relies on Article 24.2.1 of the Subcontract in asserting that its
KCAB case no.1 termination of the Subcontract was valid. The Article provides as follows:

‘24.2 Termination by CONTRACTOR due to default of SUBCONTRACTOR
Parties Claimant (Counter-Respondent) : Construction Company
24.2.1 Without derogating from any other right or remedy to which
(Singapore)
CONTRACTOR is entitled under the provisions of the Subcontract or at law,
Respondent (Counter-Claimant) : Power Company (Korea)
Place of CONTRACTOR shall be entitled to immediately terminate the Subcontract by
Arbitration Seoul, Republic of Korea written notice to SUBCONTRACTOR for any of the following: [...]

Language Original in Korean & English (b) If SUBCONTRACTOR abandons the Subcontract Works or otherwise
Subject matters - termination of contract plainly demonstrates the intention not to continue performance of his
- calculation of damages obligations under the Subcontract; or

Facts (c) If SUBCONTRACTOR fails to execute the Subcontract Works or


to perform any obligation under the Subcontract within seven (7) days
From a company contracted for construction of gas fields in Myanmar, the after being required in writing to do so by CONTRACTOR; or
Respondent obtained a subcontract to perform part of the project. The Respondent
in turn concluded the Subcontract for the project with the claimant. The claimant (d) If SUBCONTRACTOR fails to take any and all necessary steps to
had continuously fallen behind schedule set by the Subcontract in performing the ensure that performance of the Subcontract Works will comply with the
project. In response, the Respondent notified the Claimant that it was terminating provisions of the Subcontract within seven (7) days after being required
the Subcontract relying on Claimant’s failure to comply with the Respondent’s work in writing to do so by CONTRACTOR; [...].’
instructions and other defaults. The Claimant refused to accept the termination.
A dispute arose between the parties regarding the termination and the payments [2] “First, the Tribunal examines the Respondent’s claim that its termination of the
of damages with respect to the Subcontract. By initiating arbitration the Claimant Subcontract was valid due to Claimant’s failure to comply with Respondent’s
sought damages of unpaid progress payments and unpaid additional construction instructions regarding the Project.
costs; early withdrawal costs; lost profits; and amounts withheld as a guarantee for
performance and defects liability. Disputing the Claimant’s arguments for damages, Under clause (c) or (d) of Article 24.2.1, Respondent may immediately terminate
the Respondent filed counterclaim to recover the balance due to the overpayment. the Subcontract if it gives written notice of specific events of default to Claimant
and Claimant fails to cure the same within 7 days after being so notified.
The Arbitral Tribunal found that the Respondent failed to prove giving a written
notice to the Claimant for termination under the Subcontract and the Claimant’s … [S]uch requests, in order to serve as a valid ground for termination, must be
abandonment of the project. Consequently, the Arbitral Tribunal was of the opinion contained in a written notice expressly stating that Respondent will terminate
that the Respondent’s termination was not valid under the Subcontract. The Arbitral the Subcontract if Claimant fails to cure the default within 7 days of receipt of
Tribunal granted in part the Claimant’s claim for damages for progress payments the notice. It is only after such notice is given, and Claimant fails to cure the
and additional construction costs and for amounts withheld as a guarantee, denied relevant default within the 7-day period, that Respondent becomes entitled to
the remainder of the claim and dismissed the counterclaim filed by the Respondent. terminate the Subcontract immediately by written notice.

3 4
Korean Commercial Arbitration Board

In the present case, however, the evidence submitted by Respondent is II. DAMAGES
insufficient to support a finding that such a notice under clause (c) or (d) of
1. Damages Requested by Claimant
Article 24.2.1 was in fact given to Claimant; rather, the evidence only shows that a. Progress Payments and Additional Construction Costs
Respondent unilaterally terminated the Subcontract on July 16, 2012, without
giving such notice.
[5] “… Claimant requests payment of unpaid progress payments for its work from ...,
in the amount of …, and unpaid additional construction costs in the amount of …,
… [T]he Tribunal is of the view that Respondent’s claim that it validly terminated
for a total of ….
the Subcontract under clause (c) or clause (d) of Article 24.2.1 is without merit.
Claimant’s request for payment of the above amounts is apparently supported
by the documents presented as Claimant’s Exhibit …. These documents,
[3] “Second, the Tribunal examines the Respondent’s claim that its termination of however, are documents unilaterally prepared by Claimant, and as such
the Subcontract was valid due to Claimant’s abandonment of the Project. are insufficient to support a finding in favor of Claimant in the absence of
While clause (b) of Article 24.2.1, unlike clauses (c) or (d) of the same Article, independent corroborating evidence. The record, however, is devoid of any such
permits immediate termination of the Subcontract without a grace period, evidence, except for Respondent’s own statements, to wit, that US$63,157.85 do
clause (b) by its terms is applicable only if Claimant ‘abandons’ or ‘otherwise qualify as additional construction costs ….
plainly demonstrates the intention not to continue performance of its Accordingly, the Tribunal finds that there are additional construction costs of
obligations.’ US$63,157.85 as admitted by Respondent and, applying the formula set forth in
In the present case, Respondent alleges that Claimant’s workers did not report … the Subcontract, holds that Respondent must pay Claimant US$43,391.84 as
for work or assembly …, and that Claimant subsequently removed some of additional construction costs ….”
the construction equipment from the work site. … Respondent asserts that
Claimant’s conduct was tantamount to an abandonment of the Project and thus b. Early Withdrawal Costs
its termination of the Subcontract was valid under clause (b) ….
The Tribunal is of the view, however, that Claimant cannot be deemed to have [6] “… Claimant requests payment for premature recall costs and compensation
abandoned the Project merely on the strength of the above allegations by costs for Claimant’s Korean workers, expected to amount to … and …,
Respondent …. … [T]he record contains no other evidence in favor of Respondent respectively, TCN 1500’s monthly pay, expected to amount to … and other
with respect to this issue. withdrawal costs, expected to amount to …, for a total of ….
Claimant’s Exhibit … are apparently submitted to support Claimant’s request for
… [T]he Tribunal finds Respondent’s claim of valid termination under clause (b) payment of the above amounts. These documents, however, are insufficient to
of Article 24.2.1 to be without merit. support a finding in favor of Claimant, and there is no other supporting evidence.
Accordingly, Claimant’s above request cannot be granted.

[4] Therefore, Respondent’s sending of the notice of termination to Claimant c. Lost Profits
on July 16, 2012, was tantamount to an arbitrary termination of the
Subcontract, and was not a valid termination permitted under Article 24.2.1 [7] “… Claimant requests payment for lost profits in the amount of …. Claimant’s
of the Subcontract.” Exhibit … are apparently submitted to support Claimant’s request for payment
of the above amount. These documents, however, are insufficient to support a
finding in favor of Claimant, and there is no other supporting evidence.
Accordingly, Claimant’s above request cannot be granted.”

d. Performance Guarantee

5 6
Korean Commercial Arbitration Board

[8] “… Claimant requests payment of amounts withheld as a performance III. COSTS
guarantee by Respondent from construction payments for work performed by
[12] “Considering the total circumstances of the Claim and the Counterclaim, the
Claimant up to …, amounting to ….
Tribunal finds it appropriate to hold each Party responsible for its own costs of
In response, Respondent, while not disputing the amounts withheld, argues
arbitration.”
that it is entitled to retain these amounts since the Project has neither been
completed nor certified as complete and defect-free.
IV. DECISION
With respect to the first prong of Respondent’s argument, since Claimant’s
incompletion of the Project was due to Respondent’s unilateral and arbitrary [13] “… [T]he Tribunal finds that Respondent is obligated to pay to Claimant
termination of the Subcontract, Respondent’s refusal to pay based on such …, which consists of (i) the additional construction costs as admitted by
ground is improper. Respondent in the amount of … and (ii) the performance guarantee withheld
With respect to the second prong of Respondent’s argument, as there is in the amount of …, and the interest thereon accrued at 6% per annum as
no evidence that Claimant’s performance of the Project was defective, determined appropriate by the Tribunal, from …, the date on which Claimant
Respondent’s refusal to pay based on such ground is improper. unilaterally notified the termination of the Subcontract, until Respondent’s
Accordingly, the Tribunal holds that Respondent must pay the above amount to full payment of the above sum.
Claimant.” Claimant’s claims under the Claim are granted to the extent described in the
foregoing Paragraph. The remainder of the Claim and the Counterclaim are,
e. Set-off against Overpayment by Respondent
respectively, dismissed for lack of merit.”
[9] “In connection with the Claimant’s requests for payment above, Respondent
argues … that even if any amount is due to Claimant from Respondent, such Implications
should be offset by the amount overpaid to Claimant for the construction work.
… [T]he Tribunal finds that Respondent has no claims for the overpayment I. NOTICE OF TERMINATION
against Claimant; accordingly, Respondent’s above argument is without merit.”
To terminate the Subcontract, the Respondent, which is contractor under the
2. Respondent’s Counterclaim Subcontract, bears the burden of proof first that a ground listed under the
Subcontract for termination was constituted and second that written notice was
[10] “Respondent claims that the total amount due to the Claimant for the
given as stipulated in the Subcontract. To terminate the Subcontract relying on the
construction work is US696,415.36 (inclusive of the additional construction
costs of US63,157.85), and that as Respondent has already paid Claimant Claimant’s failure to comply with the Respondent’s instructions, the Respondent
US$823,572.46 for the construction work, Claimant1) is actually owed the should give first written notice requesting the Claimant to cure the defaults within
difference between these amounts, which is US$127,157.10. time limit and expressing termination with its failure to do so and second written
notice to terminate the Subcontract only after the first written notice and the
[11] “Respondent’s above Counterclaim is based on Respondent’s Exhibits …. These Claimant’s failure to do so. Thus, attention should be brought to the point that the
documents, however, are documents unilaterally prepared by Respondent, giving of the first written notice, which was not sufficiently proved in the case, paves
and as such are insufficient to support a finding in favor of Respondent in the way for the termination of the Subcontract. With the Respondent’s successful
the absence of independent corroborating evidence. The record, however, is compliance with its burden of proof, the Arbitral Tribunal would have decided in its
devoid of any such evidence. Accordingly, the Tribunal finds that Respondent’s favor with regard to termination of the Subcontract.
Counterclaim is without merit.”

1) The arbitral award states “Respondent,” but this appears to be a clerical error for “Claimant.”

7 8
Korean Commercial Arbitration Board

products.

The Claimant initiated arbitration relying on the arbitration clause contained in


the “Supply-Contract” which provided for KCAB arbitration. The contract provided
KCAB case no.2 that the law applicable to the dispute was Korean law. The Claimant sought the
repayment of purchase price in part based on non-conformity of the products. In
Parties Claimant (Counter-Respondent): Construction Company (Korea) response, the Respondent 1 filed a counterclaim for the contract price against the
Respondent 1 (Counter-Claimant): Technology Company (USA) Claimant. The Arbitral Tribunal found that there was no binding guarantee between
Respondent 2: Energy Company (Korea) the parties as to output performance. In addition, the Claimant was considered to
Place of have waived any claims under the guarantee, even if otherwise binding, by issuing
Arbitration Seoul, Republic of Korea the “Certificate of Acceptance.” The Korean Commercial Code was applicable for
all the parties because they were merchants and the “Supply-Contract” was a
Language Original in English sales contract. According to the Code, the Claimant, a buyer, had the duty to inspect
Subject matters - applicable law to substance the delivered reactors and give the Respondent 1, a seller, notice of any defects
- non-conformity of goods immediately. The Claimant failed to notify the Respondent 1 and the Respondent 2
- breach of guarantee of any defects of the reactors within the time limit. Due to the explicit acceptance
- acceptance of goods and the failure of notification, the defects were deemed as accepted by the Claimant.
- examination of goods Without examining tortious acts by the Respondent 1 and the Respondent 2 through
- notice of non-conformity delivery of allegedly defective reactors, the Tribunal was of the opinion that a claim
- defense of concurrent performance for damages would anyway be barred by the Claimant’s “Certificate of Acceptance.”
- defense of set-off
Consequently, the Tribunal rejected the Claimant’s claims without calculating its
Facts damages. Also the Tribunal did not need to decide on the alleged joint and several
liability of the Respondent 2 on the ground that the Respondent 2 only guaranteed its
The Claimant contracted to purchase from the Respondent 1 ten reactors for the performance provided that proper performance was fulfilled by the Claimant and the
manufacture of its products. The Respondent 2 signed the “Supply-Contract” as a Respondent 1.
“Guarantor.” Already the Claimant’s parent company had concluded a “Technology
License Agreement” to use the Respondent 1’s process know-how for the The Tribunal found that the counterclaim by the Respondent 1 for the price of reactor
manufacture of the products. A few weeks after the contractual delivery date, the parts was acknowledged by the Claimant without any reservation and was not subject
parties signed an amendment to the “Supply-Contract” with respect to payment to the defense of concurrent performance due to the dismissal of the Claimant’s
modalities. After the delivery of the ten reactors, the Claimant began test runs to claims. The Claimant was ordered to pay the Respondent 1 the price of the parts. On
document manifold failures, excessive dust, water leakage and dendrites during the other hand, having found that the late delivery was neither agreed by the parties,
the test runs. After completing the test runs, the Claimant’s purchasing department nor was caused by the Claimant or by force majeure, the Tribunal awarded the
issued a “Certificate of Acceptance” in accordance with the “Supply-Contract,” Claimant a delay penalty for late delivery of the reactors and deducted this amount
stating that the reactors were proved satisfactory in specification and performance. from the above price of reactor parts. Also the Tribunal found that the Respondent
Then the Claimant requested from the Respondent 1 an invoice of payment for 1’s warranty period had elapsed without being extended and thus the Claimant
the delivered reactors deducting a delay penalty. Finding that the reactors were was obligated to make the payment for the last installment. The alleged defects
substantially short of performance stipulated under the “Supply-Contract” according of the reactors could also not be argued against the expiry of the warranty period
to the tests, the Claimant claimed damages against the Respondent 1 and the because the argument was excluded by the Claimant’s issuing of the “Certificate of
Respondent 2. Meanwhile, the prices of the products continued to drop substantially Acceptance.” Therefore, the Tribunal granted the counterclaim by the Respondent 1
and were unclear to rebound. Finally, the Claimant has ceased the production of the for the payment for the last installment as well.

9 10
Korean Commercial Arbitration Board

Excerpt polysilicon production. This TLA was replaced and partly changed by a License
Amendment signed on September 15, 2009 in view of a FBI search warrant
I. APPLICABLE LAW & JURISDICTION OF THE ARBITRAL TRIBUNAL
against Respondent 1 for alleged patent infringement. The license fee was
[1] “The Parties’ arbitration agreement is included in the Supply-Contract reduced ….
concluded on December 18, 2008 under Article 11 Miscellaneous. In Clause (….)
11.5, it provides:
[6] “On September 25, 2009, a few weeks after the contractual delivery date, the
‘‘Any disputes which may arise between the parties, in relation to this Parties signed an amendment to the Supply-Contract with regard to payment
CONTRACT, shall be finally settled by arbitration in Seoul, Korea in modalities. Actual delivery of the 10 CVD reactors to Claimant’s “P2” factory in
Daejuk, his second production facility for polysilicon besides his “P1” factory
accordance with the expedited procedures in arbitration rules of Korean
was completed on December 11, 2009.”
Commercial Arbitration Board and under the Law of Korea.’
2. Acceptance of the Goods
[2] “The jurisdiction of the Tribunal, Korean Law as governing law, and the
expedited procedure were agreed by the Parties in the Supply-Contract dated … [7] “Claimant began test runs of the reactors on December 19, 2009 and
and no objections have been brought forward until the end of the Hearing.” documented manifold failures, excessive dust, water leakage and dendrites
during these test runs.
II. NON-CONFORMITY OF THE GOODS
[8] “On March 19, 2010, after at least 6 test runs had been completed Claimant’s
1. Supply-Contract & Technology License Agreement between the Parties
Purchasing Department issued a Certificate of Acceptance in accordance with
[3] “The Parties entered into a contract (in the following “Supply-Contract”) signed … the Supply-Contract, stating that ‘…we certify that seller´s merchandise
December 18, 2008 whereby Respondent 1 would sell and deliver to Claimant supplied to us has been fully proven as satisfactory in all respects of the
10 silane based Chemical Vapor Deposition (CVD) Reactors for the production of guarantee of our purchase specification and performance.’ It further mentions
polysilicon usable for solar modules or semiconductors depending on the grade ‘B. Payable amount upon this acceptance certificate: 10% of total contract
of purity. The agreement provided for the reactors to be delivered to Claimant amount, USD 3,352,000.’ A warranty period of 12 months was to start with the
until July 15, 2009 with a grace period until end of August 2009 for a total price issuing of the Certificate of Acceptance.
of USD 33,520,000.

[9] “On April 20, 2010, Claimant wrote to Respondent 1 by mail, stating that ‘We
[4] “Co-Respondent Respondent 2 signed the Supply-Contract as a ‘Guarantor’
issue the Acceptance Certificate and we have plan to issue last payment
whose obligations were specified in an annex to the Supply-Contract signed
according to mutual contract’ and requested for this purpose an invoice for
by the President of Respondent 2 on December 18, 2008. The annex titled
‘Performance Certificate (Company Guarantee)’ stated that ‘in case your USD 4,424,640. This amount was calculated from the outstanding 10% of the
company (Claimant) and Respondent 1’ perform the terms of the contract purchase price (USD 3,352,000) and USD 1,407,840 for separate delivery of 2
without problems, the undersigned guarantees that our company will perform sets of CVD Reactor panel parts, minus a delay penalty of USD 335,200 (1% of
our role diligently.’ Dec. 18, 2008 contract amount) for delivery in December 2009 instead of August
2009. Claimant added that if ‘your invoice price do not match our request price,
[5] “… on January 22, 2007, Claimant’s parent company Claimant Corporation (in there will be some trouble for the last payment.”
the following ‘Claimant Corp.’) had concluded a Technology License Agreement
(TLA) to use Respondent 1’s process know-how for monosilane based 3. Examination of the Goods & Notice of Non-conformity

11 12
Korean Commercial Arbitration Board

[10] “On August 11, 2010, Claimant wrote to Respondent 2 that according to the tests [17] “Annex B to the Supply-Contract … refers to 180 MTY instead of 160 MTY
‘conducted to this date, it is found that the foregoing products are substantially and mentions several other different production figures which should be
short of the performance stipulated under the Contract’ and that it might have accomplished within 3 resp. 6 months from startup, though these tests have
no alternative but to claim damages against Respondent 1 and Respondent 2. never been required by Claimant nor have dates been chosen by a ‘Seller.’
Anyway, this Annex is not signed, but most probably, a copy from a purchase
[11] “Between September 30 and October 8, 2010 three test runs were performed by specification drafted by Hyundai Engineering Co., Ltd., the Annex refers to
Respondent 1 and Respondent 2 at Claimant’s premises using Respondent 1’s Claimant Corp. instead of Claimant as Buyer and does not name the Seller.
recipes which produced an estimated result of 93 / 257 / 278 (MTY) for the ten
reactors combined, as compared to 1600 (MTY) capacity claimed by Claimant to [18] “The Amendment as of September 15, 2009 to the TLA concluded Claimant
be guaranteed by Respondent 1 and Respondent 2.” Corp. and Respondent 1, however, which might contain in Exhibit A, … a
specified guarantee is not binding to the Parties of this arbitration. Also the
4. Claimant’s Claim for Repayment of Purchase Price of the Goods correspondence between the parties contains no explicit referral to the TLA or
the TLA Amendment as being incorporated in the contractual relation between
[12] “Claimant requests the repayment of USD 18,000,000 paid to Respondent 1 and
the parties to this arbitration.
Respondent 2 as part of the USD 33,520,000 purchase price for 10 CVD reactors,
of which 90% had been paid before delivery on December 11, 2009. Basis for [19] “Another indication that neither Claimant nor Respondent 1considered the 160
Claimant’s request are the alleged non-compliance of the delivered reactors MTY per reactor as being more than a theoretical capacity is the wording of
with an output-guarantee given by Respondent 1 and Respondent 2, of 160 MTY a mail exchange from February 19 – 21, 2009 … where Claimant’s Mr. … with
polysilicon per reactor, altogether 1600 MTY, as well as other defects of the explicit approval of Mr. … remarks as to the Respondent 1 guarantee: ‘I know
reactors. that all values are determined by Claimant Man-power’s skill’ and wishes to
have indications for values when highly-well-trained people (Respondent 1
[13] “Claimant refers to … of a proposal/quotation by Respondent 1 dated December people) operate the Siemens reactor as well as under ideal circumstances of
15, 2008 with the wording “one reactor can produce greater than 160 MTY of 330 days per year operation and all numbers assuming no extra downtime, no
solar grade polysilicon” and the Annex B, page 3 to the Supply-Contract with lost batch.”
identical wording but 180 MTY instead of 160 MTY.
6. Remedies Waived by Accepting the Goods
[14] “…, Claimant refers to Exhibit A “Process Performance Guarantees” … as a. Recovery of Price
attached to the Amendment dated September 15, 2009 to the TLA, concluded
between Claimant’s parent company Claimant Corp. and Respondent 1. [20] Even if a guarantee as to an output quantity were supposed to have been agreed
between the Parties, Claimant is deemed to have waived any rights thereof by
[15] “…, Claimant refers to the word “guarantee” in connection with an output per issuing the Certificate of Acceptance … early on March 19, 2010. This certificate
reactor of 160 MTY as repeatedly used in the correspondence between the was to be issued within 6.5 months after delivery on December 11, 2009, that is,
Parties.” at latest around end of June 2010 if no fault of the equipment would be found (5.2
5. Guarantee Liability D of Supply-Contract).

[16] “…, in the view of this Tribunal there is no explicit abstract guarantee as to the [21] “This early acceptance with a comprehensive wording ‘[the equipment] has
160 MTY which could be absolutely binding for Respondent 1 and Respondent been fully proven as satisfactory in all respects of the guarantee of our purchase
2 because important elements of an enforceable guarantee are missing. In specification and performance’ is in itself sufficient to negate any claims or
particular, there is no indication at or after which time this specific output complaints by Claimant as to defects known, discovered or detectable up to
performance should be measured.

13 14
Korean Commercial Arbitration Board

the date of the acceptance certificate. As evidenced through test protocols [25] “However, as evidenced the reactors did at no time between the first test runs
submitted by Claimant, there have been 6 – 7 production test runs of the in December 2009 and the issuance of the Certificate of Acceptance reach an
reactors between December 31, 2009 and February 19, 2010 thus confirming output which, if calculated for a complete year, would come even close to the
the statement ‘fully proven’ in the Certificate of Acceptance. allegedly guaranteed 160 MTY. Moreover, due to excessive dust development,
building of dendrites, water leakages and power failure all of the 6 – 7
[22] “Respondent 1 and Respondent 2 could rely on the validity of this acceptance production test runs completed before March 2010 could have been regarded
declaration all the more as they could not know the testing results because as failure. Due to the explicit acceptance and the lack of notification, however,
seemingly they had been excluded from directly conducting or supervising the these defects are deemed as accepted by Claimant, who - for unknown
tests. These have been conducted by Claimant despite the wording of Supply- reasons – did not notify Respondent 1 and Respondent 2 on any shortcomings
Contract … whereas ‘Seller’ shall perform the ‘Mechanical Performance of the reactors before August 2010, despite further production tests being
Test’ within one month after the first start-up and probably no jointly signed continuously conducted and the products being sold to the market.
report was made before the Certificate of Acceptance was issued by Claimant.
Furthermore, these tests have not been mere mechanical test with innocuous [26] “The contractual warranty period of one year after issuing of the acceptance
gases but fully fledged production test as evidenced by the test protocol and the certificate would only be relevant for defects alleged by Claimant to have
testimony of …. occurred after his acceptance certificate or those which were not detectable.
None of these two possibilities has been substantiated with facts to the
[23] “Article 69 of the Korean Commercial Code is applicable for all parties because conviction of the Tribunal.
they are merchants and the Supply-Contract states in its first sentence ‘Buyer
and Seller have agreed to the purchase and sale of Equipment.’ It was not a [27] “From documents supplied and witness testimony one could conclude possible
work contract, because general contractor for the new factory was Hyundai motives for Claimant’s early issuing of the Certificate of Acceptance and not
Engineering Co., Ltd. The undoubtedly important but somehow standardized formally complaining to Respondent 1 and Respondent 2 before August 2010
and substitutable ‘Siemens Type’ components delivered by Respondent 1 and despite alleged defects and insufficient productivity, namely a full order book
Respondent 2 were only one part of a complex installation. Any obligations in the requiring maximum production at full capacity without interruptions for repair
Supply-Contract refer only to the reactors, not the functioning or productivity of or improvements. Claimant’s witness … confirmed during the hearing that the
the whole factory, whose construction, set up and other components had been reactors were constantly producing since December 2009, that far more than
sourced by Claimant or Company A. 100 production runs were conducted and that the products were sold to the
market.
[24] “According to Article 69 Korean Commercial Code the buyer Claimant had
the duty to inspect the delivered goods and notify the seller of any defects and [28] “…, Claimant tried to optimize production by using other than Respondent
shortfall in quality or quantity immediately. If he failed to notify the seller, he 1’s recipes and, as evidenced by Claimant’s own public releases, Claimant
has no right to demand price cuts, rescind the agreement or claim damages. switched at least part of the production to the more lucrative higher purity
Claimant’s Certificate of Acceptance is a binding notification that after due semiconductor-grade polysilicon which, however, results in smaller
inspection no such defects existed. Therefore, only defects which were not quantities as the originally intended solar-grade polysilicon production.
detectable even for an experienced buyer – as Claimant following his own public These circumstances could have provided a motivation to keep, in particular,
statements and knowledge gained from the P 1 project certainly was– could be Respondent 1away from Claimant’s factory.”
claimed later within the warranty period. b. Tort Claim

15 16
Korean Commercial Arbitration Board

[29] “Tortious2) acts by Respondent 1 and Respondent 2 through delivery of alleged factual or legal objection has been made against the invoice for the two reactor
defective reactors are not seen by the Tribunal but a claim for damages panel parts. The amount is acknowledged by Claimant’s mail dated April 20,
would anyway be barred by Claimant’s Certificate of Acceptance, issued in full 2010 without any reservation and not subject to the submission of a warranty
knowledge of the condition and performance of the reactors from December bond. Therefore, the Tribunal has to award to Respondent 1 a payment of USD
2009 until early March 2010.” 1,407,840, evidenced by invoice … issued on December 29, 2009.

b. Counterclaim for Last Installment


7. Dismissal of Claimant’s Claims
[34] "Counterclaim for last installment of USD 3,352,000: The last 10% contractual
[30] “…, the Tribunal had to reject Claimant’s requests and need not verify Claimant’s installment was due 7 days after the issuance on March 19, 2010 of the
quantum calculation. Certificate of Acceptance by Claimant. Only on April 20, 2010 Claimant declared
its willingness to pay and demanded an invoice from Respondent 1 without
[31] “Given the dismissal of Claimant’s request it is not necessary to decide on the however referring to the submission of a warranty bond as required in … of the
alleged joint and several liability of Co-Respondent Respondent 2, but as obvious Supply-Contract dated December 18, 2008. Nevertheless the Tribunal finds that
from the wording … Respondent 2 only guaranteed for its own performance Claimant was not obliged to make the payment without prior submission by
provided proper performance by Claimant and Respondent 1.” Respondent 1 of a warranty bond, securing the 10% last installment of contract
price for the 12 months warranty period. Following the issuing of the acceptance
III. COUNTERCLAIM certificate, the warranty obligation and parallel the required duration of the
warranty bond was running until March 2011.
1. Contract Price & Defense of Concurrent Performance
[35] “…, in this arbitration in 2012 /13, after the warranty period has elapsed for at
[32] “Respondent 1’s Counterclaim refers to two different invoices namely USD least one and probably even two years, the Tribunal does not accept to require
3,352,000 for the remaining 10% of the contract price, payable 7 days after such warranty bond. There is no evidence that the warranty period has been
the March 19, 2010 issuance of the Certificate of Acceptance, as invoiced by extended by the Parties or by events triggering an extension as provided in
Respondent 1 on April 28, 2010 and an invoice with USD 1,407,840 already Clause … of the Supply-Contract. Even if the repair and maintenance work
issued on December 29, 2010 for polysilicon reactor parts. Both invoices have undertaken by Respondent 2 is regarded as an acknowledgement of faults,
admittedly not been paid by Claimant and due to the above dismissal of his those repairs in 2010 could not have prolonged the warranty period beyond
claims, there can be no holding back any payment to Respondent 1 based on the 2011. Finally, Claimant has referred to the warranty bond the first time in the
‘Defense of Concurrent Performance.’” course of this arbitration, long after the expiry of the warranty period.
(….)
a. Counterclaim for Part Delivery
[36] “The alleged initial faults and defects of the reactors delivered by Respondent
[33] “Counterclaim as to USD 1,407,840 for part delivery justified: Whilst Claimant 1 and Respondent 2 cannot be an argument against the expiry of the warranty
objects for several reasons to pay the last 10% contractual installment, no period because, as decided above, any such complaints are excluded by virtue
of the Certificate of Acceptance issued by Claimant after at least six real
production tests.

2) The arbitral award states “Tortuous,” but this appears to be a clerical error for “Tortious.” [37] “Counterclaim for USD 3,352,000 last installment justified: Therefore, the

17 18
Korean Commercial Arbitration Board

Tribunal accepts Respondent 1’s request as to payment of 10% outstanding last … referring to a reactor start from December 18, 2009, also make it doubtful if
installment, equivalent to USD 3,352,000. However, Tribunal does not award any an earlier delivery was expected by Claimant. Likewise an Amendment to the
interest thereon until the issuing of this award because “Respondent 1 failed Supply-Contract with a payment increase for Respondent 1 and Respondent 2
to submit the warranty bond required as a precondition for payment during the was concluded by the Parties on September 25, 2009 without referring to the
warranty period.” overdue delivery.

2. Claimant’s Set-off Defense [42] “Delay Penalty of USD 335,200 justified: Since no agreement by Claimant to
the undisputed late delivery or any other acceptable reason for the delay was
[38] “Tribunal noted that Claimant, by mail as of April 20, 2010, confirmed payments submitted by Respondent 1 and Respondent 2, the Tribunal has to award the
due to Respondent 1 for the final contractual installment and for the delivery 1% delay penalty to Claimant. This amount should be deducted from the USD
of two reactor panel parts but for first time claimed a delay penalty of USD 1,407,840 due from Claimant to Respondent 1 for the delivery of two reactor
335,200. Respondent 1 and Respondent 2 have referred to settlement talks panel parts, because both amounts were due from April 20. 2010, when
between the parties following the April 20, 2010 mail but no solution could respectively confirmed and claimed by Claimant.”
be reached. Claimant’s indication that ‘there will be some trouble for the last
payment,’ if Respondent were to challenge the delay penalty, could be regarded IV. CLAIMS FOR INTEREST
as threatening with an off-set of more than tenfold the amount allegedly due
to Claimant. Instead of deducting the alleged delay penalty from the promised [43] “Respondent 1– like Claimant – requested 6% interest on the amount awarded
payment, Claimant did not pay anything, claiming lack of performance of the in accordance with Article 54 of the Korean Commercial Code because there is
reactors only as late as on August 11, 2010. no other agreement between the Parties.

[39] “Claimant requested with mail dated April 20, 2010 from Respondent 1, a [44] “As decided above for the USD 3,352,000 final installment, there is no interest
delay penalty of USD 335,200, which is equivalent to 1% of contract price for payable except in case of post-award late payment.
late delivery of the 10 reactors. The actual delivery on December 11, 2009 and
the contractual delivery date, at latest, end of August 2009, are undisputed. [45] “The Tribunal finds it reasonable to fix the starting point of interest accrual
However, Respondent obviously refused to accept the delay penalty, but did not according to the specific circumstances for each component. For the two panel
prove that the late delivery was agreed by the parties or caused by the buyer or parts as invoiced on December 29, 2009, the interest is to be accrued from April
was caused by force majeure. 20, 2010, when Claimant confirmed USD 1,407,840. This amount after deduction
of USD 335,200 delay penalty decreases to USD 1,072,640 for which the 6%
[40] “As evident from Claimant’s undated mail which was answered by Respondent interest will be accrued up to the date of this Final Award.
1 on November 9, 2009 …, Claimant was still doing final works of construction
and had scheduled commissioning from mid-November to second week [46] “Post-award interest of 20% per annum shall be paid starting 14 calendar days
of December. There is no indication that Claimant urged earlier delivery or after the issuing day of this Final Award until the above referenced sum is fully
expressed disappointment with the late delivery at any time between the agreed paid.”
delivery date on July 15, 2009 and April 20, 2010.
V. COSTS
[41] “The reservation of a first testing time in January / February 2010 as indicated in
[47] “Claimant / Counter-Claimant in both arbitrations requested that all arbitration
Respondent 1’s letter dated December 2, 2009 and Claimant’s mail of same day
costs be borne by Respondent resp. Counter-Respondent.

19 20
Korean Commercial Arbitration Board

[48] “Pursuant to Article 61(2) of the KCAB Arbitration Rules, the Tribunal may at its the Claimant’s parent company concluded the agreement as an agent on behalf of
own discretion, taking into account the circumstances of the case, apportion the the Claimant, its binding effect could be extended to the Claimant. 3)
costs between the arbitration between the Parties.
II. ACCEPTANCE OF GOODS
[49] “If the amounts of Claim and Counterclaim are considered together in their The Claimant issued a “Certificate of Acceptance,” stating that the goods were
entirety of more than USD 23,000,000, then Claimant was successful only as to proved satisfactory in specification and performance. The Claimant, instead of
the USD 335,200 delay penalty, which is less than 2% of the combined amounts complaining non-conformity to the Respondents, was motivated to early issue
in dispute and less than 2% of Claimant’s request. Therefore, the Tribunal is the “Certificate of Acceptance” to satisfy high demand in the market without
of the view that Claimant should bear all Arbitration Costs. The Tribunal has in interruptions for repair or improvements. Unless the Claimant were otherwise
addition considered that according to KCAB domestic arbitration standards, the entitled to revoke acceptance, a claim for damages relying on non-conformity of
Parties has to bear all its legal costs and other expenses.” the goods would be barred by the Claimant’s “Certificate of Acceptance.” Accepting
the goods could lead to a waiver of the right to rely on a lack of conformity of the
VI. DECISION goods. If the buyer accepted the goods as conforming and were not entitled to
[50] “…, the Tribunal renders the following Final Award: revoke acceptance, it would be prevented from relying on the defects of the goods.
Even with the market condition demanding early acceptance, the buyer should give
(1) Claimant is ordered to pay to Respondent 1 the sum of USD 4,424,640; the seller notice of non-conformity to retain its remedies for the delivery of non-
(2)Claimant shall pay to Respondent 1 6% interest per annum on USD 1,072,640 conforming goods.
accruing from April 20, 2010 to the date of this Final Award;

(3) Claimant shall pay to Respondent 1 20% interest per annum on USD 4,424,640 III. TORT CLAIM
starting 14 calendar days after the issuing day of this Final Award until the The Arbitral Tribunal did not review whether delivery of allegedly defective goods
above referenced sum is fully paid.
by the Respondents constituted a tort but held that a claim for damages founded in
(4) Any other claims or defenses by the Parties are hereby dismissed with tort would be barred by the Claimant’s acceptance of goods. Korean law was chosen
prejudice.” for the contract by the parties. Meanwhile, the applicable law to a tort should be
determined. The Arbitral Tribunal may determine the law applicable to a tort by the
Implications conflict of laws rules which the Tribunal considered applicable.
Article 32(3) of the Korean Private International Law provides:
I. BINDING EFFECT OF CONTRACT ON THIRD PARTY “Notwithstanding the preceding paragraphs, if a tort violates an existing legal
The amendment to the “Technology License Agreement” concluded between the relationship between the tortfeasor and the injured party, the law applicable to
Claimant’s parent company and the Respondent 1, which might contain a specified that legal relationship shall govern.”
guarantee, is not binding the parties of this arbitration. The parties did not refer to the
“Technology License Agreement” or its amendment to incorporate it in the contracts Under the Korean conflict of laws rules which aim to create a uniform connection to
between them either. However, it is necessary to examine the possibility of a contract a single law, a claim founded in tort, if the tort violates an existing legal relationship
concluded between two parties also binding other parties. The corporate veil could between the tortfeasor and the injured party, should also be governed by Korean law
be pierced if the Claimant’s parent company exercised absolute control over the which is the law applicable to the contract.
Claimant or the Claimant’s parent company participated effectively and substantially
in the conclusion, performance, and termination of the contract concerned. Also if
3) Nigel Blackaby et al., Redfern and Hunter on International Arbitration (5th ed.) 99-103 (2009).

21 22
Korean Commercial Arbitration Board

shipment. However, the Claimant rejected this proposal. A quality inspection for the
third shipment was conducted in accordance with the contract to indicate that the
quality was lower than the guaranteed requirement but within the acceptable limit
of range as provided in the contract. The third shipment was delivered at an adjusted
KCAB case no.3
price based on the quality. The Respondent demanded that the price should be
adjusted in accordance with the difference between the loading port analysis and the
Parties Claimant: Resources Company (Singapore) discharging port analysis. Again the Claimant rejected this proposal, demanding full
Respondent: Power Company (Korea)
payment of purchase price for the third shipment. Despite the Claimant’s refusal,
Place of the Respondent unilaterally appointed a third party inspection agency to conduct
Arbitration Seoul, Republic of Korea a discharging port sample analysis for the remaining part of the second shipment
and the entire third shipment. The Claimant attended the inspection process on
Language Original in English
condition of ruling its admission out. Based on the analysis results showing the
Subject matters - applicable law to substance lower quality at the discharging port than that at the loading port, the Respondent
- application of KCAB International Rules requested the Claimant to reduce the purchase price for the second and third
- amendment of claim shipments in accordance with the difference in the quality at the two ports. Rather
- non-conformity of goods
than agreeing to reduce the purchase prices in accordance with the discharging port
- examination of goods
- breach of warranty analysis, the Claimant insisted the Respondent to appoint an independent agency
- hardship to analyze the loading port umpire samples of the second and third shipments.
- deposit by a provisional attachment Despite the Respondent’s refusal to appoint an agency, the Claimant appointed an
- defense of concurrent performance independent agency to analyze the shipments and to conclude that the coal in the
- applicable statutory interest rate shipments was within the parameters set forth in the contract. Another purchaser of
coal from the Claimant sought reduction of purchase price due to the lower quality
and damages due to delay in shipment and obtained a provisional attachment order
Facts
on the Claimant’s claim against the Respondent for purchase price of coal under
the contract. In accordance with the attachment order, the Respondent deposited
The Respondent contracted to purchase from the Claimant a quantity of coal mined
a certain amount out of the purchase price for the third shipment. The Respondent
from Indonesia to be delivered in four shipments. The contract provided for the final
notified to the Claimant that it would pay a reduced amount based on the discharging
determination of the quality of coal at the loading port and the adjustment of the
port analysis instead of paying the purchase price based on the loading port analysis.
purchase price in accordance with variation of quality. Also the contract provided
The Respondent partially paid for the third shipment.
that title and risk of loss or damages should pass to the Respondent as the coal
passed the ship’s rails at the loading port. The Claimant was a trader of coal and
The Claimant initiated arbitration relying on the arbitration clause contained in the
procured the contracted coal from its own suppliers. An independent inspection
contract providing for KCAB arbitration. The Claimant claimed an amount in payment
agency appointed by the parties in accordance with the contract conducted a
for the third shipment and interest. In response, the Respondent objected that the
quality inspection for the second shipment and certified the quality as satisfying
coal of substandard quality was delivered in the second and third shipments. As a
the guaranteed requirement under the contract. Around 20 days after the second
result, the Respondent was forced to use additional quantity of high calorific value
shipment was delivered, the Respondent notified a complaint about the quality of
coal, incurring excessive costs for which the Respondent claimed damages. Also the
coal based on its own analysis results and demanded price reduction for the second
Respondent was exempted from the payment obligation to the Claimant to the extent

23 24
Korean Commercial Arbitration Board

of the above deposit. The amount of overpayment for the second shipment and All disputes, controversies, or differences which may arise between the
damages was set off against the purchase price for the third shipment to leave no parties, out of, or in relation to or in connection with this contract, or for
payment obligation of the respondent to the claimant. Furthermore, the Respondent the breach thereof shall be finally settled by arbitration in Seoul, Korea
objected to the application of the statutory interest rate of 20% per annum under the in accordance with The Commercial Arbitration Rules of The Korean
Act on Special Cases Concerning Expedition, etc. of Legal Proceedings. Commercial Arbitration Board and under the laws of Korea. The award
rendered by the arbitrator(s) shall be final and binding upon both parties
concerned.’
Being of the opinion that the contract was read in its entirety to reflect the parties’
intent, the Arbitral Tribunal first held that the purchase price should be determined
[2] “Although Article 17 of the Agreement is silent as to which KCAB rules
on the basis of the loading port analysis of the quality. While the Respondent
(“Domestic” or “International”) apply, pursuant to Article 3 of the KCAB
was entitled to challenge the loading port analysis by appointing an independent
International Rules, such rules shall apply in case where “the parties have
laboratory to analyze the umpire sample, it failed to initiate the final challenge
agreed in writing to refer their disputes to arbitration before the KCAB, and
process despite the Claimant’s repeated invitation to do so. The reliability of the
the arbitration is an International Arbitration.” As Claimant, at the time of the
loading port analysis would remain unrefuted even with the discrepancy between conclusion of the Agreement, had its place of business outside of Korea, this
the loading port analysis and the discharging port analysis conducted by the matter falls under the definition of “International Arbitration” as stated in Article
Respondent. The Arbitral Tribunal granted the claim for the purchase price, rejecting 2 of the KCAB International Rules. Therefore, the KCAB International Rules …
the Respondent’s argument that the purchase price should be reduced on the basis shall apply to this arbitration.
of the discharging port analysis. The Arbitral Tribunal also found that the Claimant
did not breach a warranty obligation under the contract because it satisfied the [3] “According to Article 17 of the Agreement, the Parties agreed on the law of
minimum requirement under the contract on the basis of the loading port analysis Korea as governing law.”
as agreed by the parties. The Tribunal held that the Claimant’s refusal to enter into
good-faith negotiations with respect to hardship on account of technical difficulties in II. AMENDMENT OF CLAIM
using coal would not by itself lead to remedies for the Respondent. Accordingly, the
[4] “[I]n the Post-Hearing Brief …, for the first time, Claimant included, as a relief
Tribunal rejected the Respondent’s argument for set-off based on alleged breach
sought in this arbitration, the following:
of a warranty obligation and refusal to negotiations by the Claimant. With respect
‘‘b. declaring that Claimant is the beneficiary of the monies in the amount …
to applicable interest rate, the Tribunal denied, in light of the nature of the dispute
deposited by Respondent into the Seoul Central District Court dated 19 April
and all the circumstances of the case, the application of the statutory interest rate of
2013 (Deposit Number 2013geum8344) (‘Court Deposit Amount’)’
20% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal
Proceedings.
[5] “This relief sought seems to be in replacement of a relief sought in its Opening
Memorial …, namely, ‘declaring that the Provisional Attachment has no effect
Excerpt on any final award rendered by the Tribunal.’ This clearly is an amendment to its
original claim and is allowable only in accordance with Article 17 of the Rules,
I. APPLICABLE LAW & JURISDICTION OF THE ARBITRAL TRIBUNAL which states that the Tribunal shall not allow any amendments or supplements
[1] “… [T]he Parties entered into the coal-sales/purchase contract …, the content of to a claim or defense if the Tribunal ‘considers it inappropriate to allow such
which is summarized below …. Article 17 is the dispute resolution provision of amendment or supplement because of delay to the proceedings, prejudice to
the Agreement, which provides: the other parties or any other circumstances.’ In light of the timing, allowing
such an amendment to the original claim would be prejudicial to Respondent4) ,
‘17. Dispute and Arbitration

25 26
Korean Commercial Arbitration Board

as it has had no opportunity to rebut this new claim. Therefore, the Tribunal has [9] “Then, a question arises: What is the meaning of the above Article 5.01.1’s
determined not to allow this amendment to the original claim.” language, that is, “the determination of the quality at the loading port shall be
final”? To answer this question, in the view of the Tribunal, it is necessary to
III. NON-CONFORMITY OF THE GOODS answer a more preliminary question, that is, what is the purpose of that quality
1. Determination of Quality of Coal determination?

a. Loading Port Analysis v. Discharging Port Analysis [10] “This latter question should be answered on the basis of the relevant provisions
of the Agreement as well. In the first place, the immediate following provision,
[6] “Claimant alleges that, in accordance with the terms and conditions of the Article 5.02.1, provides that “the quality certified by such Agency shall be the
Agreement, it has performed its obligations and therefore is entitled to receiving basis for determination of the amount payable by the Buyer for the shipment.”
the full payment for the second and third Shipments of Coal. In response, In other words, the quality determination by the Agency at the loading port
Respondent contends that the quality of Coal delivered for the second and third shall be used for determining the amount of the purchase price for the relevant
Shipments fails to meet the contractual requirements, in particular, under shipment. In this case, what is disputed between the Parties is the proper
Article 4.01 of the Agreement. amount of the purchase prices of the second and third Shipments.
(….)
[11] “…, what is the meaning of “final” under Article 5.01.1? The plain meaning
[7] “The core subject of a dispute between the Parties is whether the quality of Coal of “final” in legal sense is “conclusive” or “allowing no further doubt or
… has satisfied the minimum requirement under Article 4.01 …. In this regard, dispute.” Therefore, according to its plain meaning, it appears that, unless
the Parties are sharply divided on how to determine whether the above Article other provisions of the Agreement indicate otherwise, the proper amount of
4.01 minimum quality requirement has been met. the purchase prices that should be paid by Respondent with respect to the
second and third Shipments must be based on the quality certified by … and …,
[8] “The answer to this question must be found from the provisions of the respectively, and their determination of the quality of Coal at the loading port
shall be conclusive and shall not be disputed again between the Parties. The
Agreement which finally reflect the Parties’ mutually shared intent. Therefore,
contractual amount invoiced by Claimant for the second and third Shipments
the Tribunal turns to examine all the relevant provisions of the Agreement. The
was calculated on the basis of the above loading port analysis of the quality, and
title of Article 5 of the Agreement is ‘Determination of Quantity and Quality.’
the accuracy of such calculation and adjustment pursuant to Articles 7 and 8 as
Hence, it is natural to examine this provision first. Article 5.01 provides that ‘[t]
such is not disputed by Respondent.
he determination of the . . . quantity at the loading port shall be final.’ Further,
its determination shall be made ‘by an International Independent Inspection [12] “The Tribunal also draws its attention to Article 5.03. This provision enables
Agency … which will be selected by the mutual agreement between the parties.’ the Buyer (Respondent) to challenge the result of a loading port analysis made
In this case, the Parties do not dispute that … and … are ‘the Agency’ selected by the Agency pursuant to the preceding paragraphs of the same Article 5.
by the mutual agreement of the Parties for the second and third Shipments, Namely, the Buyer may appoint an “Independent Laboratory” for the purpose of
respectively. In fact, … and … conducted the quality determination and issued analysing the umpire sample to challenge the loading port analysis conducted
the second and third Shipment Certificates, respectively, both of which indicate by the Agency. However, it should be noted that this challenge process must be
the quality of the Coal in terms of …, respectively, which satisfy at least the triggered by the Buyer (Respondent), but Respondent did not do so in this case.
minimum … requirement … under Article 4.01 of the Agreement. Rather, despite that Claimant repeatedly invited Respondent to initiate this
process by appointing the International Laboratory, Respondent has refused
to do so. Therefore, the fact that Respondent did not appoint the International
4) The arbitral award states “Claimant,” but this appears to be a clerical error for “Respondent.”

27 28
Korean Commercial Arbitration Board

Laboratory in this case alone cannot be used to deny the reliability of the loading [17] “The essence of Respondent’s argument here is that there is an exception
port analysis results. to, or a derogation from, the application of Article 5.01. That is, when the
quality of Coal is found to be lower than the minimum requirement …, it would
[13] “What is more important about this challenge process is that Article 5.03 clearly be a breach of the contractual obligations under Article 4 and thus a price
stipulates that this is the ‘final’ process as to the quality of Coal. It provides that calculation/adjustment method for a ‘normal’ case under Articles 5, 7, 8 and 9
‘[t]he results of the Independent Laboratory shall be final as to the quality of shall not apply.
the delivery in question.’ This strongly suggests that if the Buyer (Respondent)
wishes to challenge the loading port analysis of the quality of Coal, it would have
[18] “Even assuming that a price calculation/adjustment method under Articles 7,
to be through this Article 5.03 process (umpire sample analysis), and the results
8, and 9 cannot apply when the quality of Coal … is lower than [the minimum
of this umpire sample analysis shall become the “final” determination of the
quality requirement], a more fundamental and preliminary question still
quality at issue and therefore shall not be disputed again.
remains. That is, how should the Parties determine whether the [quality] at
issue is higher or lower than [the minimum quality requirement]? In the view
[14] “This interpretation is also reinforced by another provision of the Agreement,
of the Tribunal, Article 5.01.1 provides for this determination methodology:
Article 6 (Rejection), which immediately follows Article 5. Article 6.01 provides:
a loading port analysis by the Agency. No other provisions of the Agreement
‘6.01 If the quality of the loaded Coal as determined pursuant to the quality
provide otherwise.
analysis at the loading port … pursuant to Article 5 is outside the limits of
the range as specified in Article 4, the Buyer shall have…the right to reject
[19] “Respondent further contends that the discharging port analyses conducted
such inferior coal, and also the right to cancel or terminate this contract
by itself as well as an independent inspection agency … reveal that the [quality]
without further liability… Nevertheless, in the event that the quality is
of Coal for both the second and third Shipments was lower than the minimum
outside the limits of range as specified in Article 4, the Buyer will accept
quality requirement …, and hence the loading port analysis conducted by the
the Coal if the Buyer judges that Coal can be used by the Buyer and if both
Agency … is unreliable and thus cannot be used as the basis of the purchase
parties reach an agreement to a price adjustment thereof.’
price determination.

[15] “Article 6 provides for optional remedies for the Buyer (Respondent) in case of
[20] “…, the discrepancy between the loading port analysis and the discharging port
a breach of Article 4, that is, when the minimum requirement under Article 4
analysis as such cannot be a valid reason to cast doubt to the former in terms
has not been met. Such remedies include “rejection of the coal,” “cancelling or
of its reliability. There is no evidence to prove that the loading port analysis
terminating the contract,” or “price adjustment.” These remedies are available
deviates from the American Society for Testing and Materials (ASTM) Standards,
when there is a breach of Article 4, and more relevantly, whether such a breach
as required under Article 5.02.1. Even though Respondent expressed some
has occurred should be determined on the basis of the “quality analysis at the
suspicion about the objective nature of the loading port analysis or the possibility
loading port pursuant to Article 5.” This strongly suggests that the Parties
of manipulation while pointing out, for instance, that the umpire sample was
mutually intended (and agreed) to address an Article 4 breach situation on the
sealed within two, rather than one, working day, it is not sufficient to prove that a
basis of the results of the loading port analysis rather than any other extraneous
sampling for shipment analysis or its analysis itself was conducted in a manner
factors, if any.
that is contrary to the ASTM Standards and hence cannot be relied upon.
[16] “…, the Tribunal considers that Claimant has made the prima facie case that it
is entitled to receiving the full payment of the purchase prices as alleged in this [21] “The Tribunal is not in a proper position to make a judgment on which analysis
arbitration for second and third Shipments. (loading port analysis v. discharging port analysis) is more objective and
(….) reliable. Such discrepancy might have arisen for unknown reasons. In any

29 30
Korean Commercial Arbitration Board

event, the mission of the Tribunal in this arbitration is not to make that scientific seller in this case (Claimant) has not agreed to do so. Rather, it has consistently
or technical judgment. Rather, it is to determine whether Claimant is entitled refused to do so. Therefore, the two examples introduced by Respondent are
to receiving the full payment of the purchase price for the second and third not helpful for the resolution of the current dispute between the Parties.”
Shipments which was based on the quality of Coal certified by the Agency in
b. Warranty Obligation
its loading port analysis under Article 5.01.1. In this respect, the Tribunal has
accepted Claimant’s argument that the amount of the purchase prices as
[25] “[Further,] [r]espondent contends that Claimant breached a warranty obligation
claimed was calculated and adjusted in accordance with the relevant terms and
under Article 12.01(a) since the quality of Coal in question fails to meet the
conditions of the Agreement.
minimum requirement under Article 4 …. Therefore, according to Respondent,
Claimant must compensate Respondent for damages incurred by Respondent
[22] “…, the Tribunal rejects Respondent’s argument that the amount of the payment
due to Claimant’s breach, of which amount is …, and this amount must be set
for the second and third Shipments should be recalculated and reduced on the
off against Claimant’s claimed amount. In this regard, the Parties agree that,
basis of the discharging port analysis, not because its analysis is untrustworthy,
theoretically, Article 12.01(a) would be breached if the quality of Coal …is lower
but because there is no contractual basis to support this line of argument.
than [the minimum quality requirement]. However, Claimant denies that it
actually breached Article 12.01(a).
[23] “…, it is worth noting that, at an early stage of the bidding process for the Coal
transactions, Claimant gave options to Respondent with respect to the locus of
[26] “Once again, what is disputed between the Parties is whether the quality of Coal
the quality analysis which is inter-connected to the price adjustment and the
… is lower than [the minimum quality requirement] and, for this judgment, how
final payment amount of the purchase price. The first option was the loading
that quality should be determined.
port and the other was the discharging port. Claimant submitted an offer while
Article 12.01(a) provides:
choosing the former option in the bidding process, and Respondent accepted
‘12.01 The Seller shall supply the Coal of quality in accordance with the
it, which led to the conclusion of the Agreement including Article 5. In this light,
provisions of the Contract and warrants that:
it is reasonable to interpret the Parties’ intent as agreeing to the loading port
(a) Each shipment of Coal shall be of good grade meeting the requirements
analysis under Article 5 for the purpose of determining the quality of Coal even
referenced in Article 4 (Quality) ….’
under the circumstances at hand in this dispute.

[27] “Article 12 itself does not specifically address how to determine whether each
[24] “Respondent additionally alleges that use of methods other than loading port
shipment of Coal meets the Article 4 quality requirement …. Nevertheless, it is
analysis or umpire sample analysis is prevalent as an industry practice. To
also true that Article 12 does not exclude an application of Article 5.01 for this
show that it is an established industry practice, Respondent introduces at
determination. This logically means that a normal process for the determination
least two transactions involving the third parties … where the sellers of the
of the quality of Coal should apply for the purpose of whether the Seller
Indonesian bituminous coal agreed to reduce the purchase price when there
(Claimant) breached a warranty obligation under Article 12.01(a). As noted
was a discrepancy between the loading port analysis and the discharging port
above, Article 5.01.1 is the only contractual provision that explicitly provides for
analysis. Even assuming that the facts underlying the two examples of the coal
the methodology of determining the quality of Coal. It should also be noted that
sales transactions are true, it should be noted that there is a critical difference
Article 5.01.1 immediately follows Article 4. The title of Article 4 is “Quality” and
between the two examples, on the one hand, and the current transaction at
the same for Article 5 is “Determination of Quantity and Quality.” Unless other
issue, on the other hand. In the former, the sellers agreed to use the discharging
provisions of the Agreement provide otherwise, it is natural and contextually
port analysis as the basis of recalculating or readjusting the purchase price,
correct to interpret Article 5 as providing a methodology to check whether the
regardless of the timing of such agreement between the parties. In contrast, the

31 32
Korean Commercial Arbitration Board

quality requirement referenced in Article 4 has been met. No other provisions, [33] “First, there should be a substantial difficulty in using Coal due to the quality
including Article 12, of the Agreement provide otherwise. of Article 4 which arose for technical/environmental reasons. The Parties are
split on whether this situation includes Claimant’s breach of Article 4, that is,
[28] “As noted earlier, the quality determination properly made pursuant to Article an obligation to meet the minimum quality requirement …. Claimant denies this
5.01.1 against the Coal in question indicates that the Seller (Claimant) shipped provision covers contractual breach. On the other hand, Respondent appears
the Coal of which [quality] is above the minimum requirement under Article 4…. to argue that Article 15.02 applies to both contractual breach and non-breach
situations.
[29] “Therefore, the Tribunal finds that Respondent has failed to prove that Claimant
breached a warranty obligation under Article 12.01(a). Accordingly, Respondent’s [34] “The Tribunal considers that Article 15.02 applies to non-breach situations only
argument for set-off on the basis of Article 12 breach is rejected.” for the following reasons: First of all, Article 15.02 addresses ‘a substantial
difficulty in using Coal due to the quality of Article 4 for technical reasons.’
2. Hardship
Its language is not ‘due to a breach of Article 4’ or ‘due to failure to satisfy
the quality requirement under Article 4.’ Thus, a plain meaning of the above
[30] “…, Respondent contends that Claimant breached Article 15.02 since it failed
phrase suggests that Article 15.02 addresses a substantial difficulty in using
to enter into good-faith negotiations to rectify the situation that arose from
Coal which arises due to the quality requirements referenced in Article 4,
the technical difficulty in using Coal due to the quality of Article 4. Therefore,
that is, a substantial difficulty arising for technical reasons when the quality
according to Respondent, Claimant must compensate Respondent for damages
requirements under Article 4 have been met. This interpretation is justified in
incurred by Respondent due to Claimant’s breach, of which amount is …, and
light of the fact that there are other provisions of the Agreements (e.g., Articles
this amount must be set off against Claimant’s claimed amount. In response,
6 and 12) which specifically address breach of contractual obligations, including
Claimant argues that Article 15.025) is inapplicable to the current situation at
breach of Article 4. In addition, this right to good faith negotiations is subject to
hand.
two conditions: (i) that the buyer makes a request, and (ii) that such hardship on
buyer is recognized. Claimant argues that “[i]f Article 15 was intended to cover
[31] “Article 15.02 (Hardship) provides in relevant part that:
situations where the seller has breached the Agreement, why would recognition
‘‘In the event Buyer judges that there is a substantial difficulty in using Coal due
of such hardship by seller be a pre-requisite to good faith negotiations?” The
to the quality of Article 4 . . ., which may arise in future for technical . . . reasons,
Tribunal agrees.
both Parties shall, upon request by Buyer and under recognition of such
hardship on Buyer, enter into good-faith negotiations to rectify such situation.’
[35] “In any event, since the Tribunal has already found that Respondent has failed to
prove breach of Article 4 on the part of Claimant, it is of no practical use arguing
[32] “In order to determine whether Claimant breached Article 15.02, the Tribunal
that Article 15.02 applies to an Article 4 breach situation in this case.
considers it necessary to first define the scope of this provision. In other words,
what conditions should be met to trigger both Parties’ obligation to enter into
[36] “Given that Article 15.02 addresses a substantial difficulty arising for technical
good-faith negotiations under Article 15.02?
reasons when the quality requirements under Article 4 have been met, is the
current situation falling under this category? It is proven by Respondent that
it experienced some technical difficulties when actually burning the Coal in its
power plants and was required to use higher calorific value coals to meet the
target power output than expected at the time of entering into the Agreement.
The Tribunal understands that Claimant does not agree that such a situation
5) The arbitral award states “12.02,” but this appears to be a clerical error for “15.02.”

33 34
Korean Commercial Arbitration Board

falls under “a substantial difficulty arising for technical reasons.” However, to “enter into good-faith negotiations to rectify such situation.” Then, did
the language of Article 14.2 empowers the Buyer (Respondent) to “judge” that Claimant breach this obligation? Before answering this question, the Tribunal
there is a substantial difficulty arising for technical reasons. In Respondent’s considers it necessary to examine the legal nature of Article 15 obligations as a
judgment, the current situation at hand falls under that substantial difficulty, whole, which contains Article 15.02 as a subpart.
which, in the view of the Tribunal, is not meritless.
(….) [40] “First, the title of Article 15 is ‘Hardship.’ In addition, this provision is located
fairly at the last part of the Agreement and is preceded by all the other
[37] “The good-faith negotiation must be triggered ‘upon request by Buyer and under provisions addressing breach of contractual obligations. The Tribunal already
recognition of such hardship on Buyer.’ As to the Buyer’s request, it is proven found Article 15 covers non-breach situations only. Relevantly, the first sentence
that Respondent repeatedly requested for discussions of the then current of Article 15.01 expresses the underlying purpose of this provision, namely:
technical difficulties and proposed to jointly conduct a discharging port analysis ‘15.01 The Parties confirm the spirit of mutual cooperation and long-term
for the purpose of reducing the contract amount of the purchase prices for the goodwill which underlies this Contract and shall transact the business
second and third Shipments. For satisfying this ‘request’ condition, in the view contemplating the principles of mutual cooperation.’
of the Tribunal, it is not necessary for Respondent to explicitly refer to Article
15.02 in making such request. Thus, the Tribunal finds that this prior ‘request’ [41] “As Article 15.02 is also an integral part of Article 15 in its entirety, the legal
condition has been met. nature of the Parties’ obligations under Article 15.02 should be interpreted in
the context of the whole provisions of Article 15, including the first sentence
[38] “The Tribunal turns to the next condition, namely, “under recognition of of Article 15.01. In other words, the Parties’ obligation to enter into good-
such hardship on Buyer.” Claimant contends that it has never “recognized faith negotiations is also one way of realizing ‘the spirit or principles of mutual
such hardship on Buyer.” Nevertheless, to satisfy this requirement, it is not cooperation and long-term goodwill.’ Article 15.02, therefore, is not designed,
necessary for the Buyer (Respondent) to prove that the Seller (Claimant) made and cannot be used, to address any contractual breach and its resulting ‘legal
a statement in an explicit manner, namely, that “I as the Seller recognize such remedies.’ It is no more than a good-faith based provision, and thus even if it
hardship (i.e., technical difficulty) on you (Buyer).” In this regard, the Tribunal is assumed that Claimant refused to enter into good-faith negotiations and
draws its attention to the fact that, as soon as Respondent raised an issue with thereby breached this provision, such breach would not automatically end up
Claimant about the quality of Coal, the latter conveyed the former’s complaint with providing a legal tool to Respondent by which it can recover its loss or
to the original suppliers of the Coal. As a seller under the long-term contract, it damages arising from its hardship on account of technical difficulties in using
was natural that Claimant did not simply ignore Respondent’s complaint about Coal. …, the purpose of good-faith negotiations is to ‘rectify such situation.’
the quality of Coal. Although Claimant eventually did not agree to readjust the Nevertheless, such rectification could and should be achieved only through
final purchase price of Coal in accordance with the discharging port analysis, good-faith negotiations on the basis of the principles of mutual cooperation.
it appears that Claimant as a trader would have been willing to accommodate Even though Article 15.02 was designed to accommodate concerns of the Buyer,
Respondent’s concerns if the original Coal supplier also had been susceptible that Party (Respondent) may not unilaterally impose a certain rectification
to adjusting the original purchase price in light of the discharging port analysis method (e.g., reducing the purchase price or seeking damages) upon the other
results. This fact alone, in the view of the Tribunal, is sufficient to satisfy the Party (Claimant). Such rectification must be achieved only through good-faith
above “hardship recognition” condition. negotiations of which results are mutually acceptable to both Parties. To put
it differently, remedies from breach of Article 15.02, if any, should be obtained
[39] “…, the Tribunal finds that all the conditions for triggering Article 15.02 by ‘negotiations’ between the Parties, rather than through this arbitration
obligations have been met. Accordingly, both Parties were under the obligation procedure.

35 36
Korean Commercial Arbitration Board

performance of the obligation.’


[42] “…, in reliance on Article 15.02 breach, Respondent is trying to reduce the
purchase price by employing a discharge port analysis or recover damages. [48] “However, the Civil Execution Act provides for the right of the third-party
Then, it asserts that such amount of price reduction or damages must be set off debtor to deposit ‘the full amount related to the provisional attachment’ upon
against Claimant’s claimed amount in this arbitration. As stated above, these execution of the provisional attachment, for the exemption from the payment
legal remedies are not obtainable through Article 15.02 in the arbitration, and obligation which has been provisionally attached (Articles 248(1) and 297 of the
therefore the Tribunal rejects this set-off defense.” Civil Execution Act), and the amount to be deposited is not the full amount of
the third-party debtor’s payment obligation, but ‘the full amount of payment
IV. QUANTUM: THE REMAINING PURCHASE PRICE obligation related to the provisional attachment.’ Also, even if the third-party
[43] “For the foregoing reasons, the Tribunal concludes that Claimant is entitled debtor makes a deposit for execution (jiphaeng-gongtak) in form, such deposit
to receiving from Respondent the full payment of the purchase prices for the is construed as a deposit for repayment (byunjae-gongtak) in substance and
second and third Shipments which were calculated and adjusted on the basis of therefore, such deposit has the effect of repayment vis-à-vis the debtor and the
the loading port analysis in accordance with Article 5, 7, 8 and 9. debtor is exempted from the payment obligation to that extent.

[44] “For the third Shipment, as Claimant demanded in its third invoice, it is entitled [49] “In the present case, Respondent made a deposit for execution of the amount
to receive payment in the amount of USD …, which was calculated in accordance subject to provisional attachment, i.e. KRW … (= USD …), which is the full
with Article 5, 7, 8, and 9. The Parties do not dispute the payment due date, that amount of payment obligation related to the provisional attachment, as a third-
is, …. party debtor to the decision of provisional attachment. In light of the above
legal principles, Respondent has thereby paid USD … out of the purchase price
[45] “…obtained the Attachment order pursuant to which Respondent deposited KRW of the third Shipment to Claimant, and has been exempted from the payment
… out of the purchase price of the third Shipment on … payable to Claimant. The obligation to Claimant to the same extent.
Parties does not dispute that this KRW … is equivalent to USD … at the exchange
rate prevailing on the date of the deposit. [50] “…, on …, Respondent partially paid purchase price of USD … for the third
Shipment. Again, on …, which is three days later than the due date, Respondent
also partially paid the purchase price of USD … for the third Shipment.
[46] “Under the Korean law, a provisional attachment of a claim has the effect of
prohibiting the third party debtor’s payment of the claim to the debtor, and does
[51] “Therefore, Respondent shall pay to Claimant in the amount of …, which is the
not exempt the claim itself. Even if a claim has been provisionally attached,
unpaid portion out of the full payment for the third Shipment.”
the third party debtor is liable for any delay in payment thereof when the claim
becomes payable. In order to avoid being in such delay, the third party debtor V. INTEREST
may deposit the claim amount in accordance with Article 291 and Article 248,
1. The 6% Statutory Interest Rate under the Korean Commercial Code Not Disputed
paragraph 1 of the Civil Execution Act, and by making a deposit, Respondent
is exempted from an obligation to pay the provisionally attached amount to
[52] “The Claimant is claiming interest at the rate of 6% per annum be applied
Claimant.
for any amount due until the date of the filing of the Statement of Claim. On
the condition and to the extent that there remains any payable amount due,
[47] “On this matter, Claimant argues that ‘[u]nder Korean law, a debtor can only
Respondent does not dispute the applicability of the statutory interest rate at
be deemed to have performed its obligations by way of court deposit in lieu of
the above rate under the Korean Commercial Code.”
actual performance to the creditor in case of such deposit is equivalent to full

37 38
Korean Commercial Arbitration Board

2. Applicability of the 20% Statutory Interest Rate under the Expeditious Litigation [57] “In response, Respondent contends that the plain reading of these precedents
Proceeding Act merely suggests that “even if an arbitral tribunal renders an award applying
the statutory interest rate in accordance with Article 3(1) of the Expeditious
[53] “…, the Claimant is also claiming interest at the rate of 20% on any amount Litigation Proceedings Act, such fact does not amount to a reason for
due to be awarded by the Tribunal. According to Claimant, this claim is made cancellation of an arbitration award under Article 36(2)(ii) of the Arbitration
pursuant to the Expeditious Litigation Proceeding Act, and the 20% rate is to Act or refusal to the approve and execute an arbitration award under Article
apply from the next date of the filing of the Statement of Claim until the date 38 of the Arbitration Act.” The Tribunal agrees. Those precedents cannot be
on which payment is fully received. In response, Respondent contends that construed as holding that, in rendering an arbitration award, an arbitral tribunal
this 20% interest rate is not applicable to the current arbitration, and if there must apply the statutory interest rate in accordance with Article 3(1) of the
remains any amount due, only the 6% per annum rate would apply until the date Expeditious Litigation Proceedings Act.
on which payment is fully received.
[58] “In the view of the Tribunal, in light of the nature (e.g., international arbitration)
[54] “Article 3(1) of the Expeditious Litigation Proceedings Act provides that: of this dispute and its surrounding circumstances at hand, it is inappropriate
‘Where a judgment ordering performance of all or any monetary to apply this special 20% rate to this particular case. Therefore, the Tribunal
obligations (including ruling; hereinafter the same shall apply) is issued, dismisses this 20% special interest claim.
statutory interest rates constituting standards for computing the amount
of indemnification for damages resulting from the default of monetary 3. Defense of Concurrent Performance
obligations shall be in accordance with the interest rates prescribed by
Presidential Decree in consideration of economic conditions, such as the (….)
interest rate on delayed payments, and other relevant aspects applied by [59] “…, Claimant claims for the 6% per annum interest against the allegedly
banks under the Banking Act, etc., within the extent of 40/100 per year delayed payment of …. It is shown that Respondent paid … as a partial payment
from the day next to the day on which a written complaint demanding the of purchase price for the third Shipment on …, which is three days later than
performance of such monetary obligations or a document corresponding the due date. In this regard, it is not disputed between the Parties that Claimant
thereto was served on the obligor.’ delayed the second and third Shipments and hence assumed an obligation to
pay demurrage to Respondent pursuant to Article 10.08 of the Agreement, and
[55] “Nowhere in the Act is there any statutory provision which explicitly requires as directed by Respondent, the payment was made to the respective carriers on
that this delay penalty in the name of the 20% special interest rate must apply to ….
an arbitration award.
[60] “Under the Korean law’s simultaneous performance doctrine, until the
[56] “For this special interest claim, Claimant relies on the Supreme Court precedent demurrage was paid by Claimant, Respondent could resist payment of any
which states ‘ordering of the payment of the amount of indemnification for amount due by the same amount. Since Claimant paid demurrage on … and
damages with statutory interest rates in accordance with Article 3(1) for an the corresponding amount was paid by Respondent as a partial payment on
arbitration decision ordering the performance of monetary obligations may the next day, …, the Tribunal considers that Claimant is not entitled to recover
not be deemed to violate compulsory provisions or against the public policy’ interest against the delayed payment in the amount of …. Therefore, this claim
(Supreme Court Decision No. 2004Da67264 dated May 13, 2005; Supreme Court for interest is also denied.
Decision No. 99Da13577 dated April 10, 2001).

39 40
Korean Commercial Arbitration Board

[61] “In light of the foregoing, Respondent is under the obligation to pay to Claimant [64] “The issue to be determined here is which party will bear the arbitration costs
in the amount of … plus interest of 6% per annum from the next date of its due including the filing fee, the administrative fee, the arbitrator’s remuneration and
date … until Respondent pays the same amount to Claimant in full.” the necessary expenses incurred during the proceedings including reasonable
attorneys’ fees, and in what proportion.
VI. COSTS
[65] “First of all, the Tribunal notes that Claimant will be awarded the amount
[62] “With respect to the Parties’ cost-related claims, the Rules of the KCAB provide
of …, which is roughly one third of the whole amount claimed. Nonetheless,
in relevant part:
the Tribunal notes that, regardless of whether the Parties’ individual claims/
‘Article 47 (Apportionment of Arbitration Cost)
defences/arguments prevail in the end, both parties have put forward their
1. The Arbitration Costs including administrative fees shall in principle be
factual and legal cases in good faith throughout the arbitration proceedings.
borne by the unsuccessful party. However, the Arbitral Tribunal, taking into
account the circumstances of the case, may, at its discretion, apportion
[66] “In light of the above, the Tribunal hereby determines (i) Claimant shall bear the
each such cost between the parties.
filing fee; (ii) each party shall bear equally the administrative fee as well as the
2. When the Arbitral Tribunal issues any Award, it shall fix the costs of
cost of the arbitrator’s remuneration, and (iii) each party shall bear its own legal
arbitration provided that in case of interim, interlocutory or partial Awards,
costs and related expenses, including attorneys’ fees.
the Arbitral Tribunal may postpone such decision by the time of issue for
the final Award.
Implications
 ‘Article 48. Costs Incurred by a Party
I. APPLICABILITY OF THE 20% STATUTORY INTEREST RATE UNDER THE ACT ON
The necessary costs and expenses including but not limited to attorney SPECIAL CASES CONCERNING EXPEDITION, ETC. OF LEGAL PROCEEDINGS
fees and costs for experts, interpreters, witnesses incurred by a party
during the arbitration proceedings shall be borne by such party subject to The Korean Supreme Court has held that the 20% annual statutory interest rate
the allocation determined by the Arbitral Tribunal set forth in the Arbitral under the Korean Act on Special Cases Concerning Expedition, etc. of Legal
Award. Unless agreed otherwise by the parties, the Arbitral Tribunal shall, Proceedings, if the governing law is a foreign law, does not apply in ordering
taking into account the circumstances of the case, decide on allocation performance of monetary obligations because the provision stipulating the statutory
between the parties of the necessary expenses incurred during the interest rate is not only procedural to promote expeditious litigation but also in
arbitration proceedings.’ substance to delimitate the extent of damages due to delay in performing monetary
obligations (see Korean Supreme Court Decision No. 2009Da77754 dated Oct. 25,
[63] “In the Request for Arbitration, Claimant claimed for all expenses and costs 2012; Korean Supreme Court Decision No. 95Da34385 dated May 9, 1997). However,
Claimant has incurred in connection with this arbitration, including but not the applicable law in this case is Korean law. The Arbitral Tribunal is of the opinion
limited to all fees paid to the Tribunal or the KCAB, and all other arbitration that it is, even when Korean law is designated as the applicable law, not bound to
expenses including reasonable attorneys’ fees incurred due to the arbitral apply the 20% annual statutory interest rate in light of the nature of the dispute
proceedings. In response, Respondent sought the Tribunal’s ruling that the and all the circumstances of the case. Also the Arbitral Tribunal notes that the Act
costs of this arbitration (including the arbitration fee, arbitrator’s’ remuneration, does not expressly provide mandatory application of the statutory interest rate to an
Respondent’s legal costs and any other necessary expenses incurred during the arbitral award.
arbitral proceedings) should be borne by Claimant.
(….)

41 42
Korean Commercial Arbitration Board

The Act remains silent about but is interpreted not to exclude its application to an
arbitral award. Article 3(1) of the Act provides that the annual statutory interest rate
for measuring damages resulting from the default of monetary obligations should be
stipulated by Presidential Decree in consideration of economic conditions. The Act
KCAB case no.4
does not expressly confer on an Arbitral Tribunal any discretion to apply or not the
annual statutory interest rate so stipulated. Therefore, the Tribunal may be bound to
Parties Claimant: Wholesale Trade Company (Turkey)
apply the annual statutory interest rate when the applicable law of the case is Korean
Respondent: Component Manufacturing Company (Korea)
law. However, no doubt it may be open to qualifications and exceptions. It remains
therefore to be seen how the Arbitral Tribunals effectuate the basic objectives Place of
of the international arbitration to promote international trade by elaborating the Arbitration Seoul, Republic of Korea
appropriate interest rate in light of all the circumstances in individual cases.
Language Original in English

Subject matters - applicable law


- implicit choice of law
- application of CISG
- renewal of contract
- termination of contract
- calculation of damages
- statutory interest rate

Facts

The parties entered into a distribution agreement whereby the Claimant was granted
an exclusive distributorship right to sell the Respondent’s products in Country A. The
agreement contained an arbitral clause providing for KCAB arbitration but failed to
designate the applicable law to the contract. The Arbitral Tribunal determined that
the parties implicitly chose Korean law as the applicable law to the contract.

A dispute arose when the Claimant, without authorization, registered the


Respondent’s brand and logo as trademark under the Claimant’s name in Country
A. The trademark was transferred to the Respondent as a result of negotiations.
However, the Respondent gave a notice to the Claimant, terminating the contract
on the ground that the Respondent had lost its trust in the Claimant due to its
unauthorized registration of the trademark. The Respondent entered into another
exclusive distribution contract with Company E which was established by the

43 44
Korean Commercial Arbitration Board

Claimant’s former employees. The Claimant initiated arbitration against the rendered by the arbitrator(s) shall be final and binding upon parties.’
Respondent. The Claimant sought damages resulting from the Respondent’s
wrongful termination of the contract and unfair practice of soliciting the Claimant’s [2] “Article 8.1 is clear that Claimant and Respondent have agreed to refer any
employees and causing them to compete with the Claimant. Furthermore, the disputes arising from the Agreement to the Korean Commercial Arbitration
Claimant sought an order requiring the Respondent to purchase back the entire Board. However article 8.1 and other articles in the Agreement have specified
inventory of the products held by the Claimant. The Respondent objected that the neither substantive laws that will govern the disputes arising out of the
contract was not renewed and, even if renewed, was rightfully terminated. The Agreement, nor the language that will be used in conducting the arbitration
Respondent also argued that it did not induce or solicit the Claimant’s employees for proceedings to resolve such disputes. Upon request of the parties the Tribunal
the purpose of the unfair trade practice. Furthermore, the Respondent countered issued an interim ruling …, which is quoted as below:
that it was not obligated to purchase back the alleged inventory of the products.
‘(1) The language used in this arbitration case shall be the English
language. We have found that the parties have impliedly agreed upon the
The Arbitral Tribunal held that the contract had been renewed for another two year
English language as language to be used by entering into certain sole
term pursuant to the relevant provision of the contract. Furthermore, the Arbitral
distribution agreement in the English language, wherein an arbitration
Tribunal held that the Respondent’s termination of the contract on the ground of
clause was included and by using the English language during the parties’
the Claimant’s unauthorized registration of the trademark was unjustified and
communications not only for the commercial transactions but for the
wrongful. Consequently, the Respondent was liable for damages arising from its
subject matters that allegedly have led to initiation of this arbitration case;
wrongful termination of the contract. The Claimant was awarded damages for lost
and
profits. However, applying Korean law, the Arbitral Tribunal held that the Claimant

was not entitled to claim for goodwill compensation since it was not a commercial (2) The governing laws that will be applied to this arbitration case shall
agent. The Arbitral Tribunal also held that the Claimant’s claim with respect to the be the laws of the Republic of Korea, provided Country A laws may be
Respondent’s solicitation and inducement of employees was not substantiated with permitted to be introduced in form of experts’ opinion to the extent
evidence. Further, the Arbitral Tribunal denied the Claimant’s claim for damages in necessary and relevant. We have found that the parties have impliedly
respect of reputation. Having found that individual transactions under the contract agreed upon the Korean laws as governing laws to be applied by agreeing
were final and conclusive, the Tribunal denied the Claimant’s claim for an order of on Seoul, Korea as arbitral seat; by designating the Korean Commercial
repurchase of the inventory. Arbitration Board as arbitral institution; and by selecting the tribunal
members who are mostly familiar with the Korean laws.’
Excerpt
[3] “The Tribunal finds no reasons or logics to revise above rulings even after
I. APPLICABLE LAW hearing the entire case. Hence the language used in this arbitration case is the
English language and the governing laws applied to this arbitration case are the
[1] “Article 8.1 of the Agreement of October …, 2003 as referenced herein below laws of the Republic of Korea.
between Claimant and Respondent provides that:
‘8.1 All disputes, controversies or differences which may arise between [4] “Claimant has argued that the United Nations Convention on Contracts for the
Respondent (Supplier) and Claimant (Dealer) in relation to or in connection International Sale of Goods (CISG) also has to be applicable to this arbitration
with this Agreement, or for the breach thereof, shall be finally settled by case. However since core issue involved in this arbitration case is related to
arbitration in Seoul, Korea in accordance with the Commercial Arbitration a dispute on a distribution agreement, Claimant’s argument on this point is
Rules of the Korean Commercial Arbitration Board (edited). The award rejected.”

45 46
Korean Commercial Arbitration Board

II. WHETHER THE CONTRACTUAL RELATIONSHIP WAS DISSOLVED


conditions of the agreement and any other agreement entered into between
1. Renewal of the Contract the Supplier and Dealer, the parties hereto agree that this agreement shall
be renewed after mutual discussion and understanding for 2 year terms, It
[5] “On or about October …, 2003, Claimant and Respondent executed a sole is agreed and understood that any renewal term shall commence on the 1st
distribution agreement (hereinafter referred to as the ‘Agreement’), whereby day of after 2 year immediately following the proceeding term.
Respondent, as supplier of the Products, appointed Claimant as its exclusive
distributor (dealer) of the Products in Country A. Relevant provisions of the 6.2 In the event that the dealer exercises the Option to Renewal, the Dealer
agreement are quoted (without editing) as below: hereby agrees to purchase a minimum of USD 100,000. – value of ‘Product’s
 from the Supplier for each renewal team (should have been term).
‘‘2. TERM OF THE AGREEMENT:
6.3 The parties further agree that there shall be no renewal fee payable by
2.1 The Parties hereto agree that the term of this Agreement shall be a
period of 2 year which shall commence on the … October 2003 and shall the Dealer to the Supplier for the Dealer’s exercise of the renewal option
terminate on … September 2005. granted hereunder.’
Unless terminated sooner in accordance with the provisions of this (….)
Agreement. No change, modification and amendment of this Agreement are
binding up on Supplier or Dealer, unless made in writing and signed by both [6] “Respondent argues that:
parties. (1) The term of the Agreement has not been renewed in September 2013 and
hence has expired on September …, 2013 because unlike other occasions
Termination of this Agreement will not affect any right of either Supplier
for renewal previously there has been no mutual understanding for renewal
and Dealer in termination or other obligation of Supplier or Dealer under
between the parties in September 2013. Respondent argues that in order to
this Agreement.
have the Agreement renewed the parties have to share mutual understanding
for renewal. However in September 2013 there has been no mutual
‘3. MINIMUM REQUIREMENTS: understanding between the parties since Claimant has remained noncommittal

3.1 The Dealer will place the purchase order and place by the T/T from the to Respondent’s request for the price increase of the Products and Claimant’s
Supplier minimum USD 200,000. – per 2 year in order to distribute in the resistance to Respondent’s request for purchasing Respondent’s new line of the
Dealer – Territory. Products. Respondent further argues that, even assuming that there has been
mutual understanding for renewal between the parties in September 2013 and
 .2 It is understood and agreed that Dealer shall pay for each order of
3 that the Agreement has been renewed on September …, 2013, the Agreement
‘Product’ by way of placing Telegraphic transfer in order to deliver the should be terminated or the renewal of the Agreement has to be retrospectively
product. rescinded on October …, 2013 when Respondent became aware of Claimant’s
registration of the Trademark without Respondent’s consent since Claimant’s
 .3 If the customers don’t make orders over USD 100,000 – the exclusive
3
unauthorized registration of the Trademark not only destroyed mutual trust
right is invalidity (should have been in validity).
between the parties but also erased mutual understanding for renewal.

3.4 Dealer is supplier’s exclusive right agency in Country A for 2 year. (….)

‘6. OPTION TO RENEW: [7] “Whether renewal of the Agreement is premised upon explicit existence of
mutual understanding for renewal of the Agreement between the parties of the

6.1 Providing the Dealer shall have fully complied with all the terms and Agreement:

47 48
Korean Commercial Arbitration Board

Article 6 of the Agreement covers the subject of renewal. The heading of this [9] “Whether Claimant’s unauthorized registration of the Trademark could
article is ‘Option to Renew’; sub-article 6.1 states that the Agreement shall constitute one of grounds to terminate the Agreement by Respondent:
be renewed ‘after mutual discussion and understanding’ (Emphasis added) Intellectual property such as trademark is extremely important for business
for two years; and sub-articles 6.2 and 6.3 presuppose that Claimant-dealer entities generally. Therefore, Claimant’s unauthorized registration of the
in the Agreement could exercise the option to renew without paying any fees Trademark could have a potential to bring about serious consequences.
to Respondent-supplier in the Agreement. Judging from the structure of However, in the present case, Claimant has registered the Trademark with
this article 6, it is fair to interpret that the Agreement could be renewed by good intention of guarding both Respondent’s and Claimant’s interests in
Claimant’s exercise of the option to renew unless Claimant is in breach of the Country A from copycat products; eventually has caused the Trademark
Agreement or the parties have reached mutual understanding of not renewing assigned to Respondent without requiring any compensation from Respondent
the Agreement; and that Claimant’s exercise of the option for renewal does for such an assignment; and Claimant appears to have expected that the
not have to be explicit. Foregoing interpretation is in line with the parties’ past Agreement will remain effective as long as Claimant assigns the Trademark to
practice of renewing the Agreement in 2005, 2007, 2009 and 2011 without Respondent; and Respondent is already in breach of the exclusivity obligation
explicit mutual understanding to renew. As seen above, Respondent argues by shipping products that are covered in the Agreement to Company E on or
that the Agreement has not been renewed on September …, 2013 and instead about November …, 2013. The Tribunal therefore concludes that Respondent’s
the term of the Agreement has expired on September …, 2013, since it is hard termination of the Agreement as of December …, 2013 on the ground of
to expect on the part of Respondent to share mutual understanding to renew Claimant’s unauthorized registration of the Trademark in 2007 is unjustified
the Agreement while Claimant is less cooperative to Respondent’s request to and wrongful; and Respondent consequently is liable for damages that have
purchase new line of the Products and is opposed to Respondent’s request for been caused to Claimant arising from Respondent’s wrongful termination
the price increase of the Products. The Tribunal finds it to the contrary in that of the Agreement and subsequent cessation of the supply of the Products to
as per the operation of article 6 of the Agreement, where Claimant has not been Claimant.”
in breach of the Agreement and there appears to be no reasons for Claimant
not to exercise the option to renew that is vested in article 6 of the Agreement III. DAMAGES
and in line with the parties’ past practice for renewal, the Agreement has been
(….)
renewed for another two year term until September …, 2015.”
[10] “Claimant claims for damages in the aggregate amount of Euros …, comprised
of:
2. Termination of the Contract
(1) Euros …, which represents loss of profit amount suffered by Claimant
due to Respondent’s wrongful termination of the Agreement;
(….)
[8] “Respondent argues that: (2) Euros …, which represents so-called statutory good will compensation
(2) Even assuming for the sake of argument the Agreement has been renewed that Claimant is allegedly entitled to as per article 92-2 of the Korean
and continuously in effect after September … 2013, the Agreement has been Commercial Code;
rightfully terminated by Respondent on December …, 2013 on the ground of (3) Euros …, which represents marketing expenses that could not be
Claimant’s breach of good faith obligation exhibited by Claimant’s unauthorized recouped by Claimant due to Respondent’s wrongful termination of the
registration of the Trademark in 2007, thereby destroying fundamental mutual
Agreement; and
trust between the parties that otherwise is essential to the parties who have
committed to continuous transactional relationship such as an exclusive (4) Euros …, which represents damages arising from Claimant’s tainted
distribution agreement. reputation due to Respondent’s wrongful termination.”
(….) 1. Lost Profits

49 50
Korean Commercial Arbitration Board

(….) 
(ii) Respondent has raised the price of the Products rather moderately
[11] “Claimant’s expert Mr. F opined in his report of March …, 2016 that due to during the term of the Agreement;
Respondent’s wrongful termination of the Agreement Claimant has suffered a
(iii) Claimant could have communicated better to Respondent in 2007 when
loss of profit in the amount of Euros …. He has derived this amount based upon Claimant applied for the unauthorized registration of the Trademark;
his findings that Claimant’s annual average net profit arising out of the sale of
the Products prior to December …, 2013 is Euros …; Claimant’s loss of profit is (iv) During the term of the Agreement Claimant’s average purchase volume
prorated and expanded for a period from January …, 2014 until September …, of the Products remained stagnant;
2015, i.e. twenty-one months; and thereafter adjusted Claimant’s loss of profit
by considering Claimant’s profits that have been and would have been generated (v) Not insubstantial portion of Claimant’s business of the Products have
through sales of remaining inventory of the Products and the substituted been transacted in forms of factoring, whereby Claimant could generate
products supplied by third parties. The Tribunal finds with due respect that Mr. considerable profits by providing credit facilities to purchasers of the
F’s opinion has a value of reference in determining the quantum of damages Products, which cannot be reasonably anticipated by Respondent in the
but cannot be relied upon as conclusive guidance in defining the quantum of ordinary course of business;
damages, especially in light of the fact that raw data used in his report has not
(vi) In 2013, Claimant more or less acquiesced to Respondent’s request for
been verified objectively; different methodology of allocating overhead could
price increase at approximately fifty (50) percent level;
lead to different results; methodology of dividing Claimant’s business into the
sale of the Products and the sale of Claimant’s other products could be subject
(vii) Claimant was able to secure a steady source of supply of the products
to challenges; his report has failed to reflect that not insubstantial portion of that are comparable to the Products in March, 2015.”
Claimant’s business is transacted in forms of so-called factoring, where under
Claimant sells the Products and other products by offering credit terms to its 2. Goodwill
customers in exchange for higher sales price incorporating Claimant’s financial
cost. (….)
[14] “Respondent argues that:
[12] “Article 393 of the Korean Civil Code provides that a party that has breached (3) Claimant is not entitled to so-called goodwill compensation under article
a contract shall be responsible for ordinary damages that have been incurred 92-2 of the Korean Commercial Code, since Claimant is neither qualified as a
to the aggrieved party and the breaching party shall be held responsible for commercial agent nor as an entity comparable thereto under article 92-2 of the
damages arising out of special circumstances only if the breaching party has Korean Commercial Code.
known or should have known existence of such special circumstances. (….)

[13] “The Tribunal has been guided by above principles and searched for the [15] “Whether Claimant is entitled to so-called goodwill compensation under article
Claimant’s quantum of ordinary damages arising from Respondent’s wrongful 92-2 of the Korean Commercial Code:
termination of the Agreement and found … Euros … as appropriate and Article 92-2 of the Korean Commercial Code provides that:
reasonable. During this search the Tribunal has considered following factors,
among others: ‘(i) If a principal obtains new customers or its business transaction
volume increases substantially through the activities of its commercial
(i) Claimant’s average purchase volume of the Products is approximately
agent, and the principal gains thereby profits even after the contract is
Euros … per annum; terminated, the commercial agent may request reasonable compensation

51 52
Korean Commercial Arbitration Board

from the principal, except when the contract is terminated due to reasons contract was executed, the entity’s capital investment in the sales business
attributable to commercial agent. and the return on such investment and the status of the business, if
the entity is deemed to deserve a protection of a commercial agent as
(ii) The amount of compensation pursuant to paragraph (1) may not exceed stipulated in article 92-2 of the Korean Commercial Code, then above
the average annual remuneration for the last five years immediately prior article 92-2 will be applicable to such an entity.’
to the termination of the contract. If the term of the contract is less than five
years, it shall be based on the average annual remuneration for such lesser In the present case Claimant has built its transactional relationship with
period. Respondent under the Agreement, which clearly envisages that relationship
as one of distributor and supplier, not one of commercial agent and principal;
(iii) The amount of compensation pursuant to paragraph (1) may not exceed Claimant has purchased the Products on telegraphic transfer payment basis;
the average annual remuneration for the last five years immediately prior Claimant has acquired unrestricted title to the Products and structured the
to the termination of the contract. If the term of the contract is less than five
distribution system at its own cost and risk without guidance or instruction
years, it shall be based on the average annual remuneration for such lesser
from Respondent; took all the benefits of profits and assumed all the loss
period.
arising from the distribution system of its own creation. The Tribunal hence
concludes that Claimant is not entitled to claim for goodwill compensation since
(iv) A right to claim for compensation pursuant to paragraph (1) shall lapse
after six months has elapsed from the termination of the contract.’ Claimant is neither a commercial agent as defined in article 92-2 of the Korean
Commercial Code nor an entity that has to be protected in the same manner as
According to a decision issued by the Korean Supreme Court (Judgment for a commercial agent as per above judgment by the Supreme Court of Korea.”
2011Da28342, dated 14 February 2013), an entity that cannot be categorized
as commercial agent per se could also be entitled to claim for goodwill 3. Reputation
compensation under above article provided certain conditions are met. The
decision is summarized as below: (….)
[16] “Whether Claimant is entitled to claim for damages incurred to its reputation
‘(i) The entity has performed the same or similar activities to those of a due to Respondent’s wrongful termination of the Agreement as separate cause
commercial agent by virtually being incorporated into the sales force of action:
of a manufacturer or a vendor, as in the case, for example, where the In general, damages to reputation of certain distributor due to the supplier’s
purchaser is obligated not only to promote sales with the exclusive sale breach of a product supply agreement is encompassed as part of the lost profits
right in a specific area, but also to follow guidance or instructions from the suffered by the distributor. In the present case the Tribunal finds no special
manufacturer or the vendor regarding sales activities; situation or evidence that will lead the Tribunal to allow Claimant’s damages to
 its reputation as separate and distinct cause of an action.”
(ii) The entity is contractually obligated to transfer its customer connections
to the manufacturer or the vendor, such as by providing the manufacturer IV. UNFAIR TRADE PRACTICE
or the vendor with the information of those customers who were increased
substantially by its own efforts and thereby enabling the manufacturer (…)
or the vendor to immediately utilize such customer base even after the [17] “In addition Claimant claims for Euros …, which represents damages suffered
relevant contract is terminated; and by Claimant due to Respondent’s unfair practice of soliciting Claimant’s Two
Employees and causing them to engage in the business competing with
(iii) In light of all relevant circumstances, including how the relevant Claimant; ….

53 54
Korean Commercial Arbitration Board

(….) purchase back the entire inventory of the Products at the current value:
[18] “Respondent argues that:
(4) Claimant’s claim on the ground of Respondent’s violation of the fair trade The Tribunal has found that the parties have intended individual transactions
practice should be dismissed, since Respondent6) has not induced or solicited consummated under the Agreement to be final and conclusive without
Two Employees to depart from Claimant; …. recourses, excepting in case of defects (if any), whereby Claimant has acquired
unrestricted titles to the Products having been delivered to Claimant. Therefore,
(….) the Tribunal decides that Claimant is not entitled to an order, whereby
[19] “Whether Respondent is liable for unfair trade practice in relation to Respondent is required to purchase back the entire inventory of the Products
establishment of transaction with Company E: from Claimant.”
Claimant claims that Respondent has induced and solicited Two Employees
to leave employment of Claimant, let Two Employees establish Company E VI. CONCLUSION
and engaged in sales transaction with Company E of the Products; Claimant
further claims that these activities constitute unfair trade practice, for which [23] “HENCE IT IS SO ORDERED THAT:
Respondent has to be held liable. (1) Respondent pay Claimant … Euros … together with interest at the rate of six
The Tribunal finds no evidence to support Claimant’s above claim especially in (6) percent per annum, which is prescribed in the Korean Commercial Code,
relation to Respondent’s solicitation and inducement of Two Employees from beginning September …, 2014, which is the day on the record immediately
Claimant.” following the day when the request for this arbitration was served upon
Respondent, until payment;
V. REPURCHASE OF THE INVENTORY
(2) Claimant’s claims in excess of above shall be dismissed;
(….)
[20] “In addition Claimant claims … for an order requiring Respondent purchase
(3) Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal
back from Claimant the entire inventory of the Products currently being held by
Proceedings will not be applied in this arbitration proceedings; and
Claimant.
(….)
(4) In accordance with article 61 of the Korean Commercial Arbitration Rules,
cost of this arbitration (KRW …) shall be borne equally between Claimant and
[21] “Respondent argues that:
Respondent.”
(4) … Claimant’s claim for an order requiring Respondent purchase back the
entire inventory of the Products at the current value also should be dismissed
since the existence of the inventory has not been proven factually and even Implications
assuming there exists the inventory, Respondent is not obligated to do so.
I. IMPLICIT CHOICE OF APPLICABLE LAW
(….)
[22] “Whether Claimant is entitled to claim for an order requiring Respondent In this case, the parties failed to expressly choose the applicable law to the
substance of the dispute. Accordingly, the Arbitral Tribunal held that the parties had

6) The arbitral award states “Claimant,” but this appears to be a clerical error for “Respondent.”

55 56
Korean Commercial Arbitration Board

implicitly agreed upon Korean law on the ground that they agreed on Seoul, Korea
as the seat of the arbitration, designated the Korean Commercial Arbitration Board II. APPLICATION OF CISG
as arbitral institution, and selected the tribunal members who were mostly familiar
with Korean law. As reviewed above, the Arbitral Tribunal held that the parties implicitly chose Korean
law as the applicable law in this case. While the Claimant argued for the application
It is not clear whether an implicit choice of applicable substantive law is to be of CISG, the Arbitral Tribunal rejected its argument on the ground that core issue
inferred from the parties’ selection of an arbitral seat. An arbitration clause is involved in this case was related to a dispute on a distribution agreement.
a presumptive indicator of a tacit choice of law which may be rebutted. Unless
there are other indications to the contrary in the terms of the contract and all the Article 30 of CISG requires the seller to deliver the goods and transfer the property in
circumstances of the case, the parties’ selection of the seat, coupled with other the goods. Distribution agreements fall outside the substantive sphere of application
pointers such as the arbitral institution, the language of the contract and the nature of CISG. They focus on how to organize distribution of goods rather than delivery of
of the contract, may legitimately infer the parties’ intention to choose the applicable goods and transfer of the property. If a distribution agreement specifies the sales
law.7) A choice of law can be inferred from an arbitration clause providing for the obligations of the parties and they intend the obligations to constitute the main part
seat of the arbitration and specifying arbitrators of nationality of the seat or carrying of the agreement, it may fall under CISG. Also CISG legitimately applies to sales
on business in the seat. But the inferred indication of a tacit choice of law would be contracts concluded in performance of the distribution agreement. The party who
weaker if the arbitration clause stipulates the seat of the arbitration but does not relies on Article 3(2) of CISG to exclude the application of CISG bears the burden of
provide for any method of identifying the arbitrators. A choice of law can be inferred proving that the supply of labor or other services constitutes the preponderant part
from the arbitration clause only if the arbitration clause contemplates clearly of the obligations.9)
localized arbitration proceedings in which the law of the seat would apply in the
absence of an express choice of law.8) The Arbitral Tribunal correctly rejected the Claimant’s argument for the application
of CISG on the ground that the contract in question was a distribution agreement.
In examining this case the parties chose Seoul, Korea as the seat of the arbitration However, finding CISG to best serve their contractual purpose, the parties may want
and KCAB as the arbitral institution, which would be the positive factors to be taken CISG to apply to their contractual relationship which is a distribution agreement.
into account in inferring tacit choice of Korean law as the applicable law to the Then CISG could apply to even the distribution agreement by the parties’ opting
substance of the contract. On the other hand, the language of the contract is English. in CISG. Because the Claimant argued for the application of CISG in this case, the
The tribunal members who were familiar with Korean law were selected by the Arbitral Tribunal, in the absence of the Respondent’s express indications to the
parties whose intention might be to choose Korean law as the applicable law. contrary, could have examined the parties’ opting in CISG.

7) Richard Plender & Michael Wilderspin, The European Private International Law of
Obligations (4th ed.) 151-152 (2015); Gary B. Born, International Commercial Arbitration (2nd
ed.) Vol. 2 2637-2642 (2014); Gralf-Peter Calliess, Rome Regulations 77-78 (2011); David 9) Stefan Kröll et al., UN Convention on Contracts for the International Sale of Goods (CISG),
Joseph Q.C., Jurisdiction and Arbitration Agreements and Their Enforcement (2nd ed.) 179- 30 (2011); Ingeborg Schwenzer, Commentary on the UN Convention on the International
180 (2010). Sale of Goods (CISG) (3rd ed.) 34 (2010); United Nations Commission on International
8) Lord Collins of Mapesbury et al., The Conflict of Laws (15th ed.) Vol. 2 1812-1813 (2012); Trade Law, Digest of Case Law on the United Nations Convention on Contracts for the
Calliess, supra note 7, at 78. International Sale of Goods (2012 ed.) 21 (2012).

57 58
Korean Commercial Arbitration Board

III. APPLICABLE INTEREST RATE

The Claimant argued in this case for the application of the 15% annual statutory KCAB case no.5
interest rate under the Korean Act on Special Cases Concerning Expedition, etc. of
Legal Proceedings. Rejecting this argument, the Arbitral Tribunal held that Article Parties Claimant (Counter-Respondent): Construction Company (Korea)
3(1) of the Act would not be applied in this arbitration proceedings. Respondent (Counter-Claimant): Power Company (France)

Place of
As reviewed above, the Arbitral Tribunal held that the applicable law to the
Arbitration Seoul, Republic of Korea
substance was Korean law in this case. The provision of the Act stipulating the
annual statutory interest rate regulates the substance of the dispute by delimitating Language Original in English
the extent of damages due to delay in performing monetary obligations (see Korean
Subject matters - applicable law to the substance
Supreme Court Decision No. 2009Da77754 dated Oct. 25, 2012; Korean Supreme - applicable law to the procedure
Court Decision No. 95Da34385 dated May 9, 1997). Where Korean law applies to - joinder
the substance of the dispute, the provision of the Act may apply in calculating delay - entire agreement clause
damages. Thus, the 15% annual statutory interest rate may apply in this case. - non-conformity of goods
- acceptance of goods
- examination of goods
- notice of non-conformity
- late delivery of goods
- termination of contract
- rescission of admission
- calculation of damages
- liquidated damages
- contributory negligence
- statutory interest rate
- summary dismissal
- power of arbitral tribunal to draw adverse inference
against party
from its failure to produce documents

Facts

The Claimant entered into a contract with Company A to construct the power plant
in a certain Middle Eastern country. The parties entered into a contract whereby
the Respondent was obligated to supply to the Claimant the goods which were
required for the construction of the power plant. A dispute arose between the

59 60
Korean Commercial Arbitration Board

parties regarding defects of the goods which were the bypass stacks and the contract and whether the assembly costs claimed by the Claimant were reasonable.
diverter dampers. The Claimant initiated arbitration relying on the arbitration clause Moreover, the Respondent argued that violating the Arbitral Tribunal’s procedural
contained in the contract which provided for KCAB arbitration. The contract provided order on document production, the Claimant concealed documentary evidence and
that the law applicable to the dispute was Korean law. It is undisputed that under thus the Arbitral Tribunal should sanction the Claimant by dismissing its claims or
the contract, the Respondent was obligated to supply the bypass stacks. While the draw adverse inferences against the Claimant. In response, the Claimant denied that
Claimant argued that the Respondent was also responsible for its subcontractor it violated the Arbitral Tribunal’s order or concealed evidence.
Company B’s supplying the diverter dampers under the contract, the Respondent
objected that the Respondent was not obligated to supply the diverter dampers Applying Korean law in examining the parties’ intention to make the Respondent a
under the contract between the parties and the Claimant entered into a separate party to the contract, the Arbitral Tribunal held that the Respondent was a party to
supply agreement for the diverter dampers with Company B. the contract and responsible for supplying both the bypass stacks and the diverter
dampers. A separate agreement was not concluded between the Claimant and
The Claimant terminated the contract because of the alleged defects of the Company B. The Arbitral Tribunal held that the Claimant properly terminated the
goods. The Claimant subsequently ordered a quantity of new diverter dampers contract. The Claimant did not accept the defects of the goods which would not
from Company Z as replacement. The Claimant sought the replacement cost or have been discovered upon inspection. The Claimant also relied on the documents
alternatively, repair cost, plus related indirect damages. The Claimant sought provided by the Respondent. The Arbitral Tribunal found that the Claimant did not
further liquidated damages relying on the Respondent’s failure to deliver the aggravate the damages by leaving the diverter dampers in the desert because the
goods by the delivery date. In response, the Respondent filed counterclaim seeking damages existed before they were replaced with new ones and left in the desert.
the payment of the balance of the contract price, of additional costs incurred by However, the Arbitral Tribunal held that damages with the diverter dampers were
changing the place of manufacture as a result of the Claimant’s request and of reduced due to the Claimant’s contributory negligence of starting gas turbines.
the costs associated with work performed by Company B as well as damages The Arbitral Tribunal denied in part damages resulting from the remedial work for
resulting from the Claimant’s wrongful termination of the contract. Meanwhile, the the diverter dampers. The Arbitral Tribunal found that the parties did not agree to
Claimant refused the Respondent’s request to join Company B as a third party to the extend the delivery dates under the contract. Consequently, the Arbitral Tribunal
arbitration. The Claimant also objected that the Respondent would not be entitled to denied in part the Claimant’s claim for damages in respect of the diverter dampers.
claim for any alleged work done by Company B if the Respondent were not an actual With respect to the bypass stacks, the Arbitral Tribunal granted in part the claim by
party to the contract with respect to the diverter dampers. the Claimant for damages. Then the Arbitral Tribunal calculated liquidated damages
for the Claimant based upon the contract price until the actual delivery dates,
The Respondent argued that the alleged defects were caused by the Claimant’s rejecting claims for additional damages resulting from delayed delivery. Moreover,
failure to comply with the Respondent’s instructions and its breach of the obligation the Arbitral Tribunal held that Korean fair trade laws did not apply to this arbitration.
to preserve the allegedly defective goods aggravated the damages. The Respondent On the other hand, the Arbitral Tribunal denied in its entirety the counterclaim
also objected that the alleged defects did not amount to material breach entitling filed by the Respondent on the grounds that it failed to complete performance of
the Claimant to terminate the contract. Furthermore, the Respondent argued that its obligations under the contract, was obligated to assume any additional costs
the Claimant, without the Respondent’s approval, made a manhole in the bypass incurred by changing place of manufacture, and the Claimant’s termination of
stacks, which constituted a major modification. The Respondent also countered that contract and initiation of the arbitration were justified. The Arbitral Tribunal held that
the parties agreed to postpone the delivery date, which changed the start date of the the Claimant did not violate Tribunal’s procedural order on document production,
liquidated damages. Again, the Respondent argued that the Claimant’s claim under and that there was insufficient evidence of bad faith on the part of the Claimant to
the contract violated Korean fair trade laws. Meanwhile, it was disputed between merit summary dismissal of its claims. The Arbitral Tribunal also declined to draw
the parties whether the Respondent was obligated to assemble the goods under the any adverse inferences against the Claimant on the ground that the evidence was

61 62
Korean Commercial Arbitration Board

produced by the parties prior to the hearing. II. JOINDER

Excerpt (….)
[3] “Also on 15 August 2014, the Claimant notified the Tribunal of a letter from
I. APPLICABLE LAW the Respondent dated 4 August 2014, in which the Respondent requested
[1] “This dispute concerns, inter alia, alleged defects in the construction of Bypass agreement from the Claimant for the joinder of Company B, the manufacturer
Stacks and Diverter Dampers at a power plant project in Saudi Arabia. … [O] of the Diverter Dampers. The Claimant stated in its email that it did not agree to
n 29 October 2011, the Claimant entered into a contract with the Company A have Company B join this case as an additional party, and asked the Tribunal to
to construct the Project I combined cycle power plant (the “Power Plant”). The consider its position in administering the arbitral proceedings. The Claimant did
Power Plant was constructed in order to solve the shortage of electric power not request the Tribunal to make any decision on joinder, and the Respondent
in southern Saudi Arabia, and is a large-scale project whose contract price did not ask the Tribunal to join Company B. … The Tribunal also noted that it had
amounts to approximately US$ 1.22 billion. In order to construct the Power
considered the Claimant’s position that it did not agree to have Company B join
Plant, the Claimant needed to procure Bypass Stacks and Diverter Dampers,
the case as an additional party.”
both of which are required for the construction of the Power Plant. On 30 March
2012, the Claimant entered into a contract (“Contract”) with the Respondent,
III. BREACH OF THE CONTRACT
consisting of, inter alia, a purchase order (“Purchase Order”) and the terms
and conditions to the Purchase Order (“Terms and Conditions”). It is undisputed 1. Non-conformity of the Diverter Dampers
that under the Contract, the Respondent was obligated to supply the Bypass
Stacks, although the Parties dispute whether the Respondent is responsible for a. Responsibility for the Diverter Dampers
supplying the Diverter Dampers under the Contract.
(….)
[2] “On 11 April 2014, the Claimant filed its Request for Arbitration with the Korean [4] “Under Korean law, the contracting party is determined by examining the
Commercial Arbitration Board (“KCAB”), pursuant to Article 33 of the Terms ‘intention of the party,’ which can be ascertained by looking at objective
and Conditions. expressions of such intention. If the objective expression of such intention is
Article 33 provides: recorded in a ‘disposal document,’ the objective wording of such intention must
 be followed if there is no clear evidence to the contrary.
‘All disputes, controversies, or differences, which may arise out of or in
relation to or in connection with the Contract, or for the breach thereof,
[5] “The Tribunal finds that there is sufficient objective evidence of the Parties’
shall be amicable settled between the Purchase and the Vendor.
intention to make the Respondent a party to the Purchase Order, for the

reasons discussed below.
In case no agreement is reached with [sic] reasonable period of time, such
disputes shall be finally referred to and settled by arbitration in Seoul,  irstly, the Purchase Order itself makes clear that the Respondent is party
F
Korea in accordance with the Commercial Arbitration Rules of the Korean to the Purchase Order and responsible for supplying both the Bypass Stacks
Commercial Arbitration Board and under the Laws of Korea. The award and the Diverter Dampers. Article 1 makes clear that the ‘Buyer or Purchaser’
rendered by the arbitrator(s) shall be final and binding upon both parties under the Purchase Order is the Claimant, while the ‘Seller or Vendor’ under
concerned.’” the Purchase Order is the Respondent. Conversely, Company B is not party to
the Purchase Order.
Furthermore, Article 13 makes clear that the Purchase Order encompasses

63 64
Korean Commercial Arbitration Board

both the Bypass Stacks and Diverter Dampers. [9] “First, the Tribunal regards the Respondent’s 3 May 2012 Confirmation
Letter as further persuasive evidence that the Respondent is party to the
 he Purchase Order is also signed by the Respondent, and the Respondent
T Purchase Order. In this letter, the Respondent stated that ‘[w]e hereby confirm
is the ‘Vendor’ that guarantees to repair or replace any defects in the Bypass that RESPONDENT will perform and guarantee all tasks for this project,
Stacks and Diverter Dampers under Article 9. including delivery of diverters and exhaust stacks as agreed on all previous
 correspondence.’ This language could not be significantly clearer: it provides
Therefore, the Purchase Order makes clear that the Respondent is responsible
in express terms that ‘RESPONDENT’ (and no other party) will ‘perform and
for any defects in both the Bypass Stacks and the Diverter Dampers.
guarantee all tasks for this project.’

[6] The Tribunal notes that the Purchase Order contains an entire agreement
[10] “Similarly persuasive is the fact that shortly after signing the Purchase Order
clause, which provides that ‘[t]he Purchase Order, the Terms and Conditions of
with the Claimant, the Respondent entered into a separate purchase order with
Purchase, and other documents constituting the Contract constitute the entire
Company B for the Diverter Dampers. The Tribunal considers this is decisive
agreement between the Purchaser and the Vendor and may not be modified
evidence that Respondent entered into a ‘back-to-back’ contract with Company
except in writing signed by the authorized representative of both parties.’ The
B (i.e. one where the subcontractor contracts out part of its work to a sub-
reference to ‘other documents constituting the Contract’ can admittedly be
vendor and includes the terms and conditions of its original contract with a
subject to interpretation, but the Tribunal is of the opinion that this is merely
contractor), whereby Company B would provide specified goods and services
a reference to the other attachments to the Purchase Order, which are listed
required by the Respondent in order for it to perform its obligations under the
in Article 3 of the Purchase Order. These attachments are limited to the
Purchase Order to the Claimant.
Terms and Conditions, Dispatch of Vendor’s Expatriate, Instruction for Vendor
Document, Packing & Marking Specification, Project Master Inspection and
[11] “The Tribunal also notes that it is undisputed between the Parties that the
Test Program for Project I CCPP, and General Instruction to Bidders.’ No other
Claimant made direct payments to the Respondent for both the Bypass Stacks
documents need be considered.
and Diverter Dampers. The Respondent asserts that it was merely acting
as a conduit for the payments, but there would have been no reason for the
[7] “Given the entire agreement clause and the clear and unambiguous language
Respondent to be acting as a conduit if the Claimant had a direct relationship
of the Purchase Order, the Tribunal considers it unnecessary to examine
with Company B on the Diverter Dampers. The Tribunal is therefore of the
other documents to ascertain the reasons why the Respondent entered into
opinion that these direct payments further confirm that the Claimant contracted
the Purchase Order (specifically, whether the Respondent was pressured
with the Respondent on the Diverter Dampers.
into signing the Purchase Order by the Claimant, who needed only COMPANY
A-approved vendors to appear on the Purchase Order in order to satisfy
[12] “The Respondent has argued that several items of evidence show that the
COMPANY A requirements).
Parties intended for Company B to be responsible for the Diverter Dampers.
However, the Tribunal finds these arguments unconvincing.
[8] “The Tribunal also considers it unnecessary to consider any of the other
evidence submitted by the Parties on this issue. Nonetheless, although it is not [13] “First, the Offer submitted by the Respondent does not clearly indicate that the
necessary to reach the conclusion set forth above, the Tribunal nevertheless Respondent and Company B submitted the Offer as a ‘joint venture.’ The cover
considers that there is other evidence which fully confirms its conclusion that page of the Offer clearly indicates that the Respondent is making the offer (not
the Respondent is party to the Purchase Order. Company B or a ‘joint venture’). The Offer is only signed by the Respondent (not
Company B or a ‘joint venture’). These are the decisive indications of the identity

65 66
Korean Commercial Arbitration Board

of the party making the Offer. contractual structure of the Purchase Order unchanged, confirms the Tribunal’s
conclusion that the Respondent was in principle obligated to perform all of the
The Tribunal considers that a single reference to RESPONDENT and Company obligations imposed by the Purchase Order.
B bidding as a joint venture on the project, contained in the technical part of the
Offer, does not clearly indicate that the offer was submitted by the Respondent [16] “The Tribunal takes note of the Commercial Court of Paris’s decision dated
and Company B on a joint basis. The fact that the technical specifications and 29 April 2014, but is satisfied that the decision can be distinguished from the
descriptions for the Diverter Dampers appear on Company B letterhead also current case. In that case, the Commercial Court considered the Claimant’s
does not show that the Offer was submitted by the Respondent and Company B attempt to call a guarantee provided by the Respondent for the Bypass Stacks,
on a joint basis. Rather, both of these references indicated how, as a technical and it believed that the Claimant’s claims only related to defects in the Diverter
matter, the Respondent planned to perform its (own) obligations to the Dampers. The Commercial Court therefore concluded that the Claimant had no
Claimant. grounds for calling the guarantee provided by the Respondent under Article 10
in respect of the Bypass Stacks, for defects in the Diverter Dampers supplied by
[14] “Second, the fact that the Respondent and Company B submitted separate Company B. The Commercial Court’s holding therefore related only to the scope
Manufacturer Responsibility Statements is, in the Tribunal’s view, irrelevant. of the guarantees under Article 10, rather than the respective responsibilities of
The Manufacturer Responsibility Statements are merely form documents the Respondent and Company B for the Bypass Stacks and Diverter Dampers
required by the COMPANY A, which were submitted by the Claimant as part of under the Purchase Order. While it is true that the Commercial Court also noted
its bid package to the COMPANY A for the Project. These supplemental bidding that ‘the provisions of the contract … makes a clear distinction between the two
documents cannot supersede the Purchase Order itself, which clearly indicates suppliers, and the amount of the order placed with each of them, as well as the
that the Respondent is responsible for both the Diverter Dampers and Bypass amount of the guarantees that each of them must provide,’ this statement was
Stacks (with no mention of Company B). not necessary to the Commercial Court’s holding and is not inconsistent with
a conclusion that the Respondent was contractually responsible for delivery of
[15] “Third, the Claimant, the Respondent and Company B agreed that the the Diverter Dampers.
Respondent and Company B would issue separate performance and payment
guarantees for the Bypass Stacks and Diverter Dampers, and that Article 10 [17] “Fourth, the Tribunal finds that the Transfer of Title Agreements do not
of the Purchase Order was revised to reflect that agreement. However, Article establish a separate agreement between Claimant and Company B for the
9 of the Purchase Order, which provides that the Vendor shall make repairs Diverter Dampers. The Tribunal agrees with the Claimant that the Transfer of
or provide replacements if required to remedy any defects, was not amended Title Agreements are essentially supplemental agreements required for the
to specify that Company B would be responsible for repairs/replacements administration of scheduled payments.
to defects in the Diverter Dampers. Thus, under the Purchase Order, the
Respondent is still the party responsible for repairing and/or replacing as [18] “Under the Purchase Order, payments were to be made in four tranches:
needed to remedy defects in both the Diverter Dampers and Bypass Stacks. The (1) Advance Payment, (2) Progress Payment, (3) Delivery Payment, and (4)
Tribunal therefore concludes that despite the separate issuance of performance Final Payment. To receive Advance Payment, the Respondent had to present
and payment guarantees, the Respondent is still the only party to the Purchase ‘Engineering Title (including G/A Drawing),’ and for the Progress Payment, it
Order who is responsible for defects in the Diverter Dampers. Indeed, the had to present ‘Material Title of Ownership.’ In the Tribunal’s view, the Transfer
fact that the Parties chose deliberately to amend only Article 10 to provide for of Title Agreements were entered into simply to satisfy these requirements,
Company B to directly perform limited obligations under the Purchase Order, so that the Respondent could receive the Advance Payment and Progress
while leaving the remainder of the Respondent’s obligations and the basic Payment under the Purchase Order. They therefore do not show that a separate

67 68
Korean Commercial Arbitration Board

agreement existed between the Claimant and Company B with respect to the or any breach of the above warranty, arises or is discovered within the less
Diverter Dampers. twenty four (24) months from the date on which the Goods are put into
commercial operation by the COMPANY or thirty six (36) months from the
[19] “Finally, the Tribunal considers that the existence of communications or date on which the last shipment of the Goods is delivered on-board on the
meetings between Claimant and Company B regarding the Diverter Dampers, carrier at the shipping port specified in the Purchase Order, the Vendor
even if conducted without the presence of the Respondent or without notifying shall, upon notice thereof, promptly make such repairs or provide such
the Respondent (and it is not making any determination on this issue), does not replacements as may be required to remedy such defect, error or omission
establish a direct contractual relationship between Claimant and Company B at its own expense. Should the Goods or any parts thereof be repaired,
for the Diverter Dampers. These communications and meetings did not alter replaced or fulfil the foregoing guarantee, the Vendor shall provide a
the contractual relationship between the Claimant and Respondent under the new guarantee on the same conditions for the repaired [sic] of replaced
Purchase Order.” materials for a period of twelve (12) months from the date of completion of
such remedial work.’
b. Defects of the Diverter Dampers

[24] “As set out in Article 9, the Respondent’s obligation to make repairs or provide
[20] “Having determined that the Respondent is responsible for the Diverter
replacements to cure defects only arises after the Claimant has notified the
Dampers, the Tribunal now considers each of the defects in the Diverter
Respondent of such defects. Therefore, in order to successfully establish a
Dampers alleged by the Claimant.
claim, the Claimant will have to show that the Respondent was notified.
(….)
[21] “As a preliminary matter, the Tribunal notes the testimony of Mr. CW1 regarding
the reliability of Field Change Notices, which were submitted as evidence of
[25] “The Tribunal finds that the blade on the Diverter Dampers was defective. The
both the existence of the alleged defects, as well as evidence of the cost of the
Tribunal notes in particular that Mr. CW1, a Claimant employee who worked on
remedial work necessary to cure the defects. The Tribunal considers the Field
the Project I since October 2012, testified that the blade did not fully open to a 90
Change Notices to be reliable pieces of evidence of both the existence of defects
degree angle and was unstable, thereby allowing the hot flue to escape to the
and the cost of remedial work.
outside. Mr. PH of Company B agreed that the blade only opened up to 85 or 88
degrees.
[22] “The Respondent argued that the Claimant accepted several of the alleged
defects by inspecting the Diverter Dampers and Bypass Stacks upon delivery
[26] “The Tribunal finds that most of the Diverter Dampers were not made of SS321,
and then issuing Inspection Release Notes without raising any objections
as required under the Purchase Order. This is shown by the Positive Material
or issuing any non-conformity reports. The Tribunal finds that this does not
Identification (‘PMI Test’) results, and was acknowledged by Company B itself.
establish that the Claimant accepted the defects in the products, because it is
not convinced that the defects were detectable upon inspection.
[27] “The Tribunal also finds that the Claimant did not approve the use of the
incorrect material for the Diverter Dampers. The Claimant did issue Inspection
[23] “The Respondent also denied responsibility for several of the alleged defects
Release Notes upon accepting delivery of the Diverter Dampers, but in doing so,
with the Diverter Dampers and Bypass Stacks on the grounds that it was not
the Claimant merely inspected the documents provided by the vendor (including
notified of such defects. Article 9 of the Purchase Order provides:
the PMI test result prepared by Axis Technologies, which was interpreted by the
‘If any defect, error or omission in the Goods, or any breach of warranty as to Claimant as saying that the Diverter Dampers were made of SS321), and relied
design, materials, workmanship, performance or operating characteristics, upon their contents. The Tribunal considers that the Claimant’s reliance on

69 70
Korean Commercial Arbitration Board

the documents provided by the vendor was reasonable, and that the use of the 2) Claimant’s Contributory Negligence: Gas Turbine Operation
incorrect material could not have been discovered by the Claimant upon closer
examination. [33] “The Tribunal finds the Claimant contributed to the damage caused by operating
the gas turbine and conducting the single cycle operation test. The Tribunal
[28] “Moreover, the Tribunal considers it unreasonable to expect that the Claimant considers the Claimant’s decision to conduct the single cycle operation test
should have tested the Diverter Dampers to see if they were made of the right imprudent in light of Company B’s warning not to do so. Company B warned the
material prior to releasing the Inspection Release Notes. As such, the Tribunal Claimant to wait to conduct the test until it had a chance to do a full overview of
concludes that the issuance of the Inspection Release Notes does not indicate the situation (including getting a metallurgical assessment), but the Claimant
that the Claimant approved the use of the wrong material for the Diverter ignored this and decided that the test could not wait.
Dampers.
[34] “The Tribunal also finds that the Claimant unreasonably relied on the Force
[29] “The Tribunal finds that the liner plates were not fixed to the blade, as was Technology Report in justifying the operation of the gas turbine. As Mr. JLA
required by the design. Mr. CW1 testified that the liner plate was ‘connected explained at some length in his witness statement, the Force Technology
in a way that was different from the drawing.’ He further explained that ‘[a] Report contains a number of qualifications regarding additional factors that
ccording to the drawing, a one-piece bolt should have been installed between needed to be considered before any decision can be made. Both Mr. PH and Mr.
the liner plate and the blade, but in actuality it turned out there was a two-piece, JLA testified that no reasonable engineer would interpret the Force Technology
namely the nut and the stud bolt that was installed between the liner plate and Report as giving an assurance that the gas turbine could be started.
the blade. And it is true that a two-piece is weaker than a one-piece.’ Mr. PH
did not dispute this – he argued only that using a nut and the stud bolt made no [35] “Nor did Company B ever assure the Claimant that it could start the gas
difference, because in his view, it is actually the same strength as a normal bolt. turbine safely. According to Mr. PH, during the 28 June 2013 meeting in which
Company B presented the Force Technology Report to the Claimant, Company
[30] “The Tribunal finds that there is sufficient evidence of some of the remaining B explained that the Force Technology Report evaluated the behaviour of
alleged defects with the Diverter Dampers.” different materials at different temperatures, but Company B never assured the
(…) Claimant that it could start the gas turbine.

c. Damages Caused by Defects of the Diverter Dampers


[36] “On the other hand, the 28 June 2013 meeting minutes relied upon by the
Claimant (which it claims show that Company B gave this assurance) were not
[31] “The Tribunal now assesses the damages arising out of the defects in the
signed by the attending parties. Mr. CW1, who stated in his witness statement
Diverter Dampers.”
that Company B confirmed during this meeting that it would be possible to
perform the test, later testified during the hearing that he did not personally
1) Aggravation
attend this meeting, and only heard this from others who attended the meeting.
The Tribunal therefore concludes that there is insufficient documentary and
[32] “The Tribunal finds that the Claimant did not aggravate the damage by leaving
witness evidence showing that Company B told the Claimant it could start the
the Diverter Dampers in the desert. The Tribunal agrees with the Claimant that
gas turbine safely.
its claimed damages all existed before the Diverter Dampers were replaced
with new diverter dampers, and the original Diverter Dampers were left in the
[37] “There was significant testimony during the hearing about the date on which
desert. The Respondent has not specifically pointed to any damage that was
the gas turbines were started, which is strongly disputed between the parties.
aggravated as a result of the Diverter Dampers being left in the desert.”

71 72
Korean Commercial Arbitration Board

However, the Tribunal considers it unnecessary to determine this issue, as in


any case, it has resolved that the Claimant’s reliance on the Force Technology [42] “The Tribunal therefore finds that as a result of the defects and the start of the
Report and/or the 28 June 2013 meeting with Company B was not justified, even gas turbine, the Diverter Dampers were severely damaged and ultimately had
if those events had taken place before the gas turbine was started or before the to be replaced. In particular, the Tribunal notes that the NEM Report, which
gas turbine began to produce hot exhaust gas. was completed after the single cycle operation test, found that the defects were
such that the Diverter Dampers had to be replaced by new ones.”
[38] “The Tribunal also finds that the deadline under the COMPANY A contract for 3) Quantum of Damages
performing the single-cycle operation test by 29 June 2013 does not justify
(….)
the Claimant’s actions. The Tribunal recognizes that the contract imposes
[43] “Article 9 of the Purchase Order provides that the Respondent shall, upon notice
significant liquidated damages per day of delay. However, the Tribunal considers
of the defect, ‘promptly make such repairs or provide such replacements as
that rather than starting the gas turbine and ignoring Company B’s (i.e. the
may be required to remedy such defect, error or omission at its own expense.’
manufacturer’s) warnings, a more reasonable course of action would have been
Moreover, Article 28.1 of the Terms and Conditions provides that in the event of
for the Claimant to incur these liquidated damages, give the Respondent and
termination, ‘the Purchaser may purchase similar supplies from other vendors,
Company B adequate time to investigate and remedy the situation, then seek
and the Vendor shall be liable to the Purchaser for any excess cost to the
to recover these liquidated damages later, through arbitration or otherwise.
Purchaser.’ The Tribunal therefore concludes that the Respondent is liable for
The threat of the liquidated damages therefore does not justify the Claimant
the cost of any repairs or replacements that were necessary to cure the defects,
operating the gas turbine.
including the excess cost of any supplies purchased by the Respondent after
termination.
[39] “The Tribunal therefore concludes that the Claimant imprudently started the
gas turbine.
[44] “The Claimant has sought to recover damages for the cost of purchasing
replacement dampers (including the purchase price and transportation cost),
[40] “The Tribunal also concludes that the start of the gas turbine was a contributory
as well as the labor costs associated with installing the replacement diverter
cause of the damage necessitating the replacement of the Diverter Dampers.
dampers. However, as discussed above …, the Tribunal finds that the operation
While it is true that the Diverter Dampers were made using the incorrect metal
of the gas turbine was a contributory cause of the damage necessitating the
alloy and the liner plate was not properly fixed to the blade, both issues were
replacement of the Diverter Dampers. The Tribunal is of the opinion that
exacerbated by the start of the gas turbines. Specifically, the Diverter Dampers
had the Claimant not operated the gas turbine, the Diverter Dampers could
are exposed to high temperatures (approximately 600 °C) and very high velocity
have been repaired, rather than replaced. In its post-hearing submission, the
exhaust gases (up to 300 km/h) once the gas turbine is started. This was a
Claimant submitted that if it had been possible to have the Diverter Dampers
problem given that the incorrect metal alloy used in the Diverter Dampers had
repaired instead of replacing them, ‘the estimated cost should at least be the
inferior heat resistance.
price quoted by Company B, which is €1,350,000 plus the related labor cost,
which would be at least be US$ 1,200,000, the labor cost associated with the
[41] “Moreover, during operation of the gas turbine, the liner plate broke off the
simpler work of installing the replacement diverter dampers.’ The estimated
blade and broke into several pieces during operation, causing damage to other
cost of repair is based on the quote received from Company B on 27 August
parts of the Diverter Dampers. Mr. PH testified that the gas turbine induced so
much force, pressure and suction that it caused the damage to the liner plate. 2013 for ten complete sets of damper blades and toggle arm systems, as well
The Claimant’s own documents also state that the liner plate was damaged as the cost of dismantling/installation of damper blades/shafts and transporting
during gas turbine operation. from the workshop to the Project site. The estimated labor costs are based

73 74
Korean Commercial Arbitration Board

on the invoices the Claimant received from SD and SC for the work they did in Field Change Notices to be reliable evidence of both the existence of defects
replacing the Diverter Dampers with the new diverter dampers. and the cost of remedial work. The Tribunal also considers that the Claimant
did not accept defects in the Bypass Stacks and Diverter Dampers by inspecting
[45] “The Tribunal therefore awards damages of … in relation to the repair of the them after delivery and then issuing the Inspection Release Notes. Finally,
Diverter Dampers. the Tribunal reiterates its finding that under Article 9 of the Purchase Order,
the Respondent’s obligation to make repairs or provide replacements to cure
[46] “The Claimant has also sought to recover US$ … for the cost of commissioning defects only arises after the Claimant has notified the Respondent of such
NEM [a major manufacturer of diverter dampers] to investigate the alleged defects. Therefore, in order to successfully establish a claim
defects in the Diverter Dampers. The Tribunal considers that this was a cost (….)
reasonably incurred by the Claimant, and therefore awards US$ … in damages.
(…) a. Admitted Defects

1) Admission
[47] “In support of these damages, the Claimant submitted Field Change Notices
that include cost breakdowns of the required remedial work. As explained above
[52] “The Respondent admitted liability and quantum with respect to certain defects
…, the Tribunal considers this sufficient evidence of reasonable costs incurred
in its Statement of Defense and Statement of Reply.”
by the Claimant. Moreover, the Tribunal does not consider that the Claimant’s
(….)
labor costs are overestimated (contrary to the Respondent’s contention). The
Tribunal acknowledges that the Claimant could have used lower-wage Saudi 2) Rescission of Admission
Arabian workers, but it is of the opinion that it was not unreasonable for the
Claimant to use more expensive Korean workers, if it felt they were better [53] “The Respondent subsequently sought to rescind its admission on the basis that
qualified to do the job. The Tribunal therefore finds the Claimant’s labor costs ‘new facts have come to light which have shown Claimant’s bad faith attempts
to be reasonable. to pass any and all costs to RESPONDENT.’ The Respondent did not explain
with any specificity what ‘new facts’ came to light or how the alleged bad faith
[48] “However, the Tribunal is also of the opinion that there may be some overlap conduct could justify its rescission of the admissions. As there is no reason
between this repair work and the repair work contemplated under the proposal justifying such rescission, the Tribunal finds that the rescission of admission
submitted by Company B …. The Tribunal therefore reduces the damages by was ineffective, and that the Respondent is liable for the admitted defects in its
50% and awards US$ … in damages. Statement of Reply.”

b. Defects Found & Defects Dismissed for Insufficient Evidence


[49] “The Tribunal finds that all the remaining damages alleged by the Claimant
relate to defects which the Tribunal did not find …, and therefore declines to
[54] “The Tribunal finds that there is sufficient evidence that certain defects existed
award those damages.”
and that the Respondent is liable for the resulting damages.
2. Non-conformity of the Bypass Stacks (….)

[50] “The Claimant alleged that a number of defects existed that were caused by the [55] “The Tribunal finds that the Claimant adduced insufficient evidence regarding
Respondent’s defective manufacturing of the Bypass Stacks. the below defects.”
(….)
[51] “Preliminarily, the Tribunal notes that, as discussed above …, it considers the
c. Defects Dismissed for Failure to Properly Follow Erection Procedure

75 76
Korean Commercial Arbitration Board

[56] “The Respondent submitted that certain defects were the result of the [61] “It is unclear to the Tribunal how this explanation renders it more likely that
Claimant’s failure to properly follow the erection manual. For example, there this defect was a result of the Respondent’s manufacturing than the Claimant’s
is evidence that the Claimant was following an outdated version of the erection faulty erection. The Tribunal therefore dismisses this claim.”
manual.
d. Quantum of Damages
(….)

(….)
[57] “However, the Tribunal is mindful that the incorrect erection manual may
[62] “Preliminarily, as discussed above …, the Tribunal finds the Field Change
have only been outdated by a couple of days, and the use of incorrect erection
Notices to be reliable evidence of both the existence of defects and the costs
drawings is likely to cause defects or aggravate defects only in relation to the
incurred in remedying those defects. The Tribunal also considers that the
liner plate.
Claimant’s claimed labor costs were reasonable because it was reasonable for
In addition, there is some evidence showing that the Claimant provided the
the Claimant to use more expensive Korean workers rather than lower-wage
wrong incentives to the assembly teams, as Mr. JLA stated in his witness
Saudi Arabian workers, if it felt that it was needed.
statement.
(….)
[63] “The Respondent admitted to certain defects with damages amounting to US$ ….
(….)
[58] “However, there is no other evidence corroborating Mr. JLA’s testimony.
The Claimant successfully established defects with damages amounting to US$
….”
[59] “Overall, the Tribunal concludes that there is some evidence that erection
(….)
procedures were not always adequately followed.
The Claimant’s failure to properly follow the erection procedures contributed to
3. Failure to Assemble the Diverter Dampers and Bypass Stacks
several of the alleged defects.
(….) a. Assembly Costs for the Diverter Dampers
Specifically, Mr. JLA suggested in his witness statement that failure to properly
follow the erection procedures caused a number of alleged defects. [64] “The Claimant asserts that the Respondent was responsible for delivering fully-
(….) assembled Diverter Dampers, but instead it delivered the Diverter Dampers in
two 180° parts, which the Claimant then had to assemble together at its own
[60] “To rebut the Respondent’s submission that the most likely cause of this cost. The Claimant now seeks to recover from the Respondent this assembly
error is that Claimant incorrectly paired the half stack sections, the Claimant cost, and it has submitted Field Change Notices and invoices in support of its
submitted that: claimed costs.
‘This issue is not related to pairing of the two half sections (180º). The issue
herein is not that the two half sections divided lengthwise did not match [65] “The Respondent did not dispute that it was liable for these costs; it only
challenged the quantum of the damages claimed on the basis that (1) the Field
with each other but that the joint areas of the upper stack shell and the
Change Notices are unilateral calculations by Claimant, and (2) the claimed
lower stack shell divided broad wise did not match with each other, thereby
labor costs are inflated.
resulting in a gap between them. As a result, the insulation material
installed in the joint area was exposed outside, and Claimant had to install
[66] “The Tribunal finds these objections unpersuasive. First, as discussed above …,
additional liner plate to cover it.’

77 78
Korean Commercial Arbitration Board

the Tribunal finds that the Field Change Notices are reliable pieces of evidence [71] “The Technical Clarification Record is part of the Material Requisition, which in
regarding the costs incurred by the Claimant. Second, the Tribunal has already turn was specifically incorporated into the Purchase Order through Article 3.2,
explained … above that it finds the labor costs incurred by the Claimant to be and is therefore part of the Contract between the Parties.
reasonable, notwithstanding that the cost of Korean workers may be higher (….)
than the cost of Saudi Arabian workers.
[72] “The Tribunal finds that the Technical Clarification Record makes clear that the
[67] “The Respondent also rejected the Claimant’s claimed costs for renting welding Respondent is responsible for delivering fully assembled, 360° sections of the
machines and undertaking NDE work on the grounds that the Claimant did Bypass Stacks (which means, for example, if the sections are delivered in 180°
not sufficiently prove why the equipment was rented. However, the evidence halves, then the Respondent is responsible for assembling those halves into
shows that the welding machines were rented as per Company B’s instruction, 360° sections).”
which the Tribunal considers as adequate reason for the renting of the welding
machines. 2) Procurement Specification

[68] “The Tribunal notes that Company B’s instruction only requested four welding [73] “The Respondent submitted that under section 2.4 of the Procurement
machines, while the Claimant rented five welding machines. With respect to the Specification, the Claimant is responsible for ‘uploading and field erection,’
costs of the welding machines, the Tribunal therefore finds that the Respondent which it submits includes assembling the Bypass Stacks. The Claimant,
is liable for only four-fifths (4 / 5) of the claimed costs, but it is liable for the total however, argued that this ‘refers to connecting the fully assembled Bypass
claimed amount for the NDE work.” Stacks with other equipment.’
(….)
[74] “The Tribunal finds that the Procurement Specification cannot be taken into
b. Assembly Costs for the Bypass Stacks account, given the entire agreement clause …. Unlike the Technical Clarification
Record, the Procurement Specification is not incorporated into the Purchase
[69] “In addition to the assembly costs for the Diverter Dampers, the Claimant also
Order under Article 3. There is therefore no need to determine the proper
seeks to recover costs associated with assembling the Bypass Stacks.
interpretation of ‘uploading and field erection.’

 he Parties dispute whether the Respondent is responsible for delivering fully


T
[75] “This notwithstanding, the Tribunal agrees with the Claimant’s interpretation.
assembled, 360º sections of the Bypass Stacks (and thus, as the Respondent
Section 2.4 provides that ‘[t]he following items will be provided by the
only delivered 180º sections, whether it is liable for the assembly costs to put
Purchaser’ including ‘[u]ploading and field erection.’ Reading this together with
the 180º sections together to form 360º sections).
the Technical Clarification Record, the Tribunal finds that the only plausible
interpretation of ‘uploading and field erection’ is that it refers to ‘connecting the
[70] “The Tribunal holds that it is the Respondent’s responsibility to supply the
fully assembled Bypass Stacks with other equipment.’ Any other interpretation
Bypass Stacks in 360º sections and thus it is liable for the assembly costs
would render the Technical Clarification Record and the Procurement
claimed by the Claimant. In reaching this conclusion, it considered the (1)
Specification incompatible, which is contrary to basic principles of contractual
Technical Clarification Record, (2) the Procurement Specification, and (3) the 14
interpretation.”
December 2012 meeting, each of which is discussed in detail below.”
3) 14 December 2012 Meeting
1) Technical Clarification Record
[76] “The Respondent submitted that although the Parties originally agreed to supply

79 80
Korean Commercial Arbitration Board

the Bypass Stacks in 360° sections (as shown by the Technical Clarification
‘All equipment and material shall be delivered on the basis of DDU Job-Site
Record), the Parties subsequently agreed that due to transportation and cost (ICC INCOTERMS 2010) not later than below schedule.
restrictions, the Respondent would transport the stacks in 180° form, and the
(#1,2 : by Oct. 30, 2012, #3,4,5 : by Nov. 15, 2012, #6,7,8 : by Nov. 30, 2012,
Claimant would be responsible for assembly.
#9,10 : by Dec. 15, 2012)’
(….)

[81] “The Respondent submitted that the delivery dates were extended through two
[77] “The Tribunal has already held at paragraph … that meeting minutes cannot be
separate extensions, one at the 14 December 2012 meeting, and the other at the
taken into account due to the entire agreement clause in the Purchase Order.
28 January 2013 meeting.
The Tribunal therefore declines to find that these meeting minutes constitute
any modification of the terms of the Contract.
[82] “The Tribunal finds that the delivery dates were not extended, for several
reasons.
[78] “Even if the meeting minutes could be taken into account, the Tribunal holds
First, as discussed above …, the Terms and Conditions include an entire
that the meeting minutes did not amend the original obligation under the
agreement clause in Article 31, which states that the Purchase Order, Terms
Purchase Order. The language in Item 3 is ambiguous as to who is responsible
and Conditions and other attachments to the Purchase comprise the entire
for assembling the 180° sections, once they are delivered. The underlined
agreement. Meeting minutes (such as the minutes for the 14 December 2012
language under Item 3.1 suggests that the Respondent’s obligation remains to
and 28 January 2013 meetings) therefore should not be taken into account.
deliver full (i.e. 360°) cylinders as specified in the Technical Clarification Record.
Second, even if these meeting minutes were to be taken into account, the
However, the underlined language under Item 3.2 seems to suggest that the
Tribunal still finds that they do not amend the delivery dates under the Contract,
Respondent’s obligation is now only to deliver half cylinders, and the cost of
as discussed below.”
assembling those half cylinders therefore now lies with the Claimant. Given this
conflicting language, the Tribunal finds that the Respondent has not satisfied 1) 14 December 2012 Meeting
its burden to show that the Contract was amended at the 14 December 2012
meeting. (….)
[83] “The majority of the Tribunal considers that this language reflects the parties’
[79] “The Tribunal thus finds that the obligation under the Technical Clarification agreement that the Respondent would deliver all materials by 15 February
Record to deliver 360º sections of Bypass Stacks remains, and therefore the 2013, but they did not intend to change the delivery dates set out in Article 6
Respondent is liable to the Claimant for the costs of assembling the 180º of the Purchase Order (and therefore, the date by which liquidated damages
sections into 360º sections. The Tribunal therefore awards US$ … in damages, begins to accrue). Although this decision is not unanimous, and the Tribunal
reflecting the costs incurred in assembling the Bypass Stacks.” recognizes that there is some ambiguity as to the meaning of the sentence ‘the
4. Late Delivery of the Diverter Dampers and Bypass Stacks extension of delivery date under this MOM shall be without prejudice to the
Article 6,’ the majority of the Tribunal is of the opinion that this language most
a. Contractual Delivery Date likely means the parties intended to extend the delivery dates (as set out in
the MOM) without prejudice to the delivery dates set out in Article 6. The next
[80] “The Parties disputed the delivery dates that the Respondent was obligated to sentence then further makes clear that the delivery conditions set out in Article
meet under the Contract. The Claimant argued that the delivery dates (along 6 shall also remain the same.
with the delivery conditions) are as set out in Article 6 of the Purchase Order:

81 82
Korean Commercial Arbitration Board

[84] “The Tribunal recognizes that another possible interpretation of this sentence orders made by Claimant up until at least October 2012; (iv) Claimant’s
could be that the extension in delivery dates shall be without prejudice only to many unilateral modifications to the products without RESPONDENT’s
the delivery conditions set out in Article 6. However, the majority of the Tribunal involvement; (v) Claimant’s onerous bureaucracy and interference; and (vi)
does not find this interpretation convincing because the delivery conditions set Claimant’s gross mismanagement of the Project.’
out in Article 6 (DDU Job-Site) concern the allocation of risk and transfer of title,
which would be unaffected by changes to the delivery schedule. There would [88] “The Tribunal first notes that even if certain delays were caused by the
therefore be no reason or need for the parties to specify that the extension in Claimant’s actions and the parties did agree to extend the deadlines to
delivery dates shall be without prejudice to the delivery conditions. In any case, accommodate these delays, this is not relevant to the issue of whether the
the majority of the Tribunal considers that the Respondent has not satisfied Parties intended during the 14 December 2012 meeting to amend the delivery
its burden of proving that it is more likely than not that the parties intended to schedule set out in Article 6 of the Purchase Order. The Tribunal finds that
extend the delivery dates under Article 6, because simply presenting another there is insufficient evidence to show that the Parties considered the Claimant’s
possible interpretation does not satisfy this burden. The majority of the Tribunal allegedly delay-inducing actions when the Parties met on 14 December 2012.
therefore concludes that the parties did not intend to extend the delivery dates
under the Contract, although the decision is not unanimous. [89] “Further, the Tribunal finds there is insufficient evidence of any of these
purported decisions:
[85] “The Respondent submitted that there was no reason for it to expedite
delivery if the delivery deadlines in Article 6 of the Purchase Order were not a. With respect to the first factor, the Respondent has not specified what
amended. Under Article 11, liquidated damages begin to accrue for each week these ‘ongoing technical discussions’ are, nor pointed to any evidence of
of delay ‘beyond the delivery time’ set out in Article 6. Thus, according to the these alleged discussions.
Respondent, there was no incentive for it to expedite delivery if the extension
to the delivery dates agreed during the 14 December 2012 meeting did not also  b. The Tribunal similarly disregards factor (ii) for lack of evidential support.
extend the date by which liquidated damages began to accrue. The only evidence seems to be from Mr. JLA’s testimony, however he did
not explain how much delay this caused nor did he give much context. He
[86] “The Tribunal cannot accept this argument. The Tribunal finds that it is equally only mentioned that there were instances where customs duties were not
plausible that there would be more incentive for the Respondent to deliver as paid. The Tribunal is not persuaded that this led to substantial delay.
early as possible if the date by which liquidated damages began to accrue was
left intact. The fact that the Respondent knew the liquidated damages started c. Factor (iii) is likewise disregarded for lack of evidentiary support. The
accruing would certainly incentivize the Respondent to deliver earlier so as to Tribunal does not see how the October 2012 order would cause delays in
avoid racking up the total liquidated damages. delivery of materials, and the Respondent has not explained how or why this
would be so. The Respondent has not pointed to any other additional late
[87] “The Respondent also submitted that the Parties agreed to extend the delivery orders.
dates set out in Article 6 to accommodate delays caused by the Claimant itself.
Specifically, the Claimant allegedly made several decisions which delayed d. The Tribunal also finds insufficient evidence of factors (iv) to (vi). The
delivery of the Bypass Stacks and Diverter Dampers: Respondent cited to the entirety of Mr. JLA’s witness statement for support;
‘These include, among others, (i) ongoing technical discussions with however, his witness statement does not provide clear support for these
Claimant related to design of the products up until at least December 2012; alleged factors.
(ii) Claimant’s failure to pay the customs duties on time; (iii) additional late

83 84
Korean Commercial Arbitration Board

[90] “Mr. JLA also testified that another reason delivery was delayed was because
the Parties spent almost 40 days discussing the terms of the Purchase Order, [96] “Thus, to calculate liquidated damages, it is necessary to determine (1)
before they finally signed the Purchase Order. The Tribunal finds that this the correct contract price under the Purchase Order, and (2) the liquidated
is irrelevant to whether the Parties agreed to extend the delivery date in the damages period.”
Purchase Order, because the influence of these pre-contractual discussions
1) Contract Price under the Purchase Order
would have been reflected in the original delivery date as set out in the Purchase
Order.
[97] “The Parties dispute the contract price under the Purchase Order. The
Respondent maintained that the price was €10 million as set out in the original
[91] “The Tribunal therefore finds that the Parties did not agree at the 14 December
Purchase Order, while the Claimant submitted that the price had been
2012 meeting to extend the delivery dates set out in Article 6 of the Purchase
subsequently amended by the Parties on 17 October 2012 and 16 April 2013.
Order.”

2) 28 January 2013 Meeting [98] “The Tribunal finds that the original price of €10 million was subsequently
modified to €10.3 million in a revised Purchase Order dated 17 October 2012,
[92] “The Tribunal also finds that the parties did not extend the delivery dates at the which was signed by both parties. However, the Tribunal holds that the contract
28 January 2013 meeting. The 28 January 2013 meeting minutes state: price was not modified again by the 16 April 2013 email between the Parties.
 As discussed above …, the entire agreement clause provides that the Purchase
‘PROJECT I DELIVERY ON SITE STACKS AND DIVERTER PROMISED DATES
Order, the Terms and Conditions and attachments to the Contract constitute
MOM 28.01.13 CLAIMANT/RESPONDENT/COMPANY B REV 2 29.01.13’3’
the entire agreement between the Purchaser and the Vendor, and may not
be modified except in writing signed by the authorized representative of both
[93] “The Tribunal finds that this language merely shows that the parties agreed on
parties. The Tribunal therefore finds that the 16 April 2013 email did not validly
some ‘promised dates’ for delivery, without amending the delivery dates set out
modify the Contract.”
in Article 6 of the Purchase Order.
(….)

[94] “ Thus, overall, the Tribunal holds that the delivery dates for the Bypass Stacks 2) End Date for the Liquidated Damages Period
and Diverter Dampers are as set out originally under Article 6 of the Purchase
Order.” [99] “The Parties also contest the appropriate end date for calculating liquidated
b. Calculation of Liquidated Damages damages. The Claimant calculated liquidated damages using the alleged
termination date of 3 October 2013 as the end date, while the Respondent
[95] “The Tribunal discusses next the calculation of liquidated damages under asserted that the correct end date should be 13 May 2013, when the
Article 11 of the Purchase Order. Article 11 provides: Respondent delivered the last component under the Purchase Order.
‘In the event of any delay beyond the delivery time, the Vendor shall pay
Liquidated Damage to the Purchaser at the rate of 3/1000 percent (0.3%) [100] “Using the actual delivery dates for each Diverter Damper and Bypass Stack
of contract price for each full calendar week of the delay, provided that the as the end date, the Respondent submitted two tables with its liquidated
cumulative sum of liquidated damages shall not exceed ten percent (10%) damages calculation for both the Diverter Dampers and Bypass Stacks. These
of the contract amount. Such liquidated damages shall be deduced from delivery dates were not challenged by the Claimant.
any payment due to the Vendor.’

85 86
Korean Commercial Arbitration Board

[101] “The Tribunal sees no basis for using the termination date as the end date for
the liquidated damages period. The Tribunal therefore calculates liquidated [106] “Article 18(c) of the Terms and Conditions makes clear that liquidated
damages on the basis of the actual delivery dates set out in the Respondent’s damages are for compensation of all damage arising out of any delay in
two tables.” delivery:
‘The liquidated damages shall not be deemed to represent a penalty and
3) Liquidated Damages Calculation shall constitute full and complete payment for such losses due to the
delay in delivery by the Vendor.’
[102] “Article 11 of the Purchase Order provides that liquidated damages shall be 0.3
percent of the contract price for each full calendar week of delay. [107] 
“Therefore, any claim for additional damages resulting from delayed delivery
(….) by the Respondent should be dismissed as excluded by the liquidated damages
clause in the Purchase Order.
[103] “The Respondent submitted that liquidated damages should be reduced after
considering the Claimant’s contributory negligence in the delay of delivery of [108] “The Respondent submitted that some of the items claimed by the Claimant
the products. The Tribunal considers it inappropriate to consider contributory relate to delays in the delivery of the materials. The Claimant disputed that
negligence as a basis for reducing this agreed sum. Liquidated damages these claims resulted from delayed delivery; instead, it submitted that these
reflect the Parties’ agreement as to the amount of compensation due in claims concerned defective materials supplied by the Respondent.
the event of contractual breach. The Respondent’s submission is therefore
dismissed.” [109] “The Tribunal agrees with the Respondent that some of the items claimed by
the Claimant relate to delivery delays.
 c. Other Damages Arising from Delayed Delivery (….)

[104] “The Tribunal now considers the Respondent’s argument that a number of [110] “The Tribunal therefore declines to award any of the damages listed above,
the Claimant’s asserted damages in relation to defects in the Bypass Stacks on the grounds that these damages are excluded by the liquidated damages
arise from delays in deliveries, and such damages are already included in the clause.”
liquidated damages. (….)
5. Other Costs
[105] “Under Korean law, when the parties to a contract agree on liquidated
damages in the event of a breach, those liquidated damages extinguish any [111] “The Tribunal denies the Claimant’s request for ‘other costs,’ including i)
claim for additional damages resulting from that breach. As the Korean business trips, ii) additional engineering manpower, iii) third party inspectors,
Supreme Court explained in a 27 September 1988 decision: iv) resident supervisor, and v) indirect costs for construction.


‘If an amount of damages is prearranged between parties regarding
[112] “Article 393(1) of the Korean Civil Code stipulates that the ‘compensation
default, the creditor can only claim for the previously fixed amount of
for damages arising from the non-performance of an obligation shall be
damages not only regarding general damage but also regarding damage
limited to ordinary damages.’ According to the Civil Code Commentaries,
that has occurred due to special circumstances, and cannot claim for
ordinary damages are defined as ‘damages which arise from a party’s non-
compensation that is in excess of such prefixed cost unless provided
performance of its obligation and have the cause-and-effect relationship at the
otherwise under special provisions.’
same time. In other words, the ordinary damages are understood to be within

87 88
Korean Commercial Arbitration Board

those which are deemed to usually arise if the same kind of non-performance might be necessary to investigate any suspected defects. However, it is
of an obligation occurs, unless there is any special reason, in accordance unclear whether these particular third party inspectors were conducting
with the general conception of society.’ By contrast, under Article 393(2) of inspections that are related to the alleged defects in this arbitration.
the Korean Civil Code, special damages may also be recovered only if the According to the Claimant, ‘[t]hird party inspectors were dispatched to
damages arise from the special circumstances that the obligor either knew or manufacturing shops in the Kingdom of Saudi Arabia due to delay of
could have known. manufacturing work and improper quality.’ However, the Tribunal agrees
with the Respondent that the underlying evidence suggests at least some
[113] “The Respondent cited two cases which it alleged presented similar factual of the inspections were conducted in locations ‘irrelevant to this Project,
circumstances. In the first case cited by the Respondent, the Seoul Central such as Hungary, India, Singapore, and Italy.’ The Tribunal therefore
District Court found that, inter alia, (1) business trip costs and (2) costs declines to award damages in relation to third party inspectors.
incurred to timely supply goods were not recoverable as ‘special damages’
because the court could not find that the plaintiff was aware of or could be d. Resident supervisors. The Claimant asserted that ‘to expedite
aware of the circumstances or events. In the second case, the Gwangju District manufacturing work, resident supervisors from Claimant were
Court found that, inter alia, costs and expenses allegedly paid by the plaintiff to dispatched,’ and sought to recover the costs associated with these
investigate damage caused by oil contamination were not recoverable because resident supervisors. However, it is unclear whether these resident
there was no causal relationship with the alleged breach. supervisors were dispatched to expedite manufacturing work related
to repairing or replacing the Bypass Stacks and Diverter Dampers, or
[114] “The Tribunal discusses each category of damages in turn below: manufacturing work related to other projects. The Tribunal therefore
declines to award costs relating to the Claimant’s resident supervisor.
 . Business trips. The Tribunal declines to award damages for the
a
Claimant’s ‘Business trips and Man Hours.’ The Seoul District Court
e. Indirect costs for construction. The Claimant has not explained why an
has held that business trips are not recoverable as ‘special damages.’
additional 20% in ‘indirect costs for the construction project carried out
Similarly, the Tribunal finds that is unclear whether these business trips
by SD and SC” is needed or justified. The Tribunal therefore declines to
were necessary as a result of the alleged breaches, as these business
award these damages.”
trips might have occurred anyway in the ordinary course of business.
(….)

b. Additional engineering manpower. The Claimant also sought to recover


IV. TERMINATION OF THE CONTRACT
costs ‘for additional engineering manpower was incurred due to late
submission of drawings (Vendor Print, VP). Furthermore, to prepare for
[115] “The Tribunal finds that the Claimant properly terminated the Contract
several meetings and to review drawings for new diverter dampers, more in accordance with Article 28.1 of the Terms and Conditions. Article 28.1
manpower was needed.’ There is no evidence that the ‘drawings (Vendor provides:
Print, VP)’ were submitted late. The Tribunal therefore declines to award
costs relating to additional engineering manpower. ‘‘28.1 Termination for Vendor’s Default
The Purchaser may terminate the contract in whole or in part, by giving
c. Third party inspectors. The Tribunal finds that the costs associated with ten (10) days prior notice of default to the Vendor in writing without
third party inspectors might constitute ‘special damages’ because the compensation to the Vendor under any of the following circumstances.
Respondent likely knew or could have known that third party inspections
a) if the Vendor fails to perform or deliver the goods within thirty (30)

89 90
Korean Commercial Arbitration Board

calendar days from the time(s) specified in the Purchase Order. interpretation.

b) if the Vendor fails to comply with other provisions of the Purchase [121] “The Tribunal declines to extend the FSA to apply to this arbitration. The
Order and does not cure any such failure within a period of ten (10) days Respondent is a multinational corporation, based in France, with significant
after receipt of notice from the Purchaser specifying such failure. experience in the global construction industry. Therefore, the Tribunal is of the
….’ opinion that it is inappropriate to extend the FSA to cover this dispute.

[116] “As discussed above …, the Respondent failed to deliver the goods within 30 [122] “The Tribunal also finds that the Standard Terms and Conditions Act (‘STCA’)
days of the deadlines specified in the Purchase Order. This delay in delivery does not apply. Significantly, Article 1 of the STCA states that its purpose is ‘to
alone is sufficient to justify termination of the Purchase Order. establish sound order in business transactions, and thus to protect consumers
and promote the balanced improvement of people’s lives by preventing
[117] “Moreover, as discussed above …, the Respondent has failed to cure the enterprises from preparing unfair terms and conditions and using them in
defects in the Diverter Dampers and Bypass Stacks, even though it was first business transactions by taking unfair advantage of their bargaining position
notified of certain of the defects as early as April and May 2013, and then again and regulating unfair terms and conditions.’ This makes clear that the purpose
in September 2013. The Respondent cited to several pieces of evidence that of the STCA is to protect consumers from an inferior bargaining position
purportedly showed its efforts to repair the alleged defects, but the Tribunal is against large enterprises. The Korean Supreme Court has never extended the
unconvinced that this evidence shows good-faith efforts to repair the defects STCA to situations like the present context. The Tribunal similarly declines to
notified by the Claimant. Moreover, there is no evidence that the Respondent do so. The Respondent is not a consumer suffering from an inferior bargaining
was not able to repair the alleged defects within the 10 day window set out in position vis-a-vis the Claimant—it is a multinational corporation with
Article 28.1. approximately equal bargaining power in relation to the Claimant. Therefore,
the Tribunal does not believe that the STCA applies to this dispute.
[118] “Furthermore, as discussed above …, the Respondent failed to assemble
the Bypass Stacks and Diverter Dampers as it was obligated to do under the [123] “Even if the STCA did apply to the current arbitration, the Tribunal does not
Contract. Instead, the Claimant hired subcontractors (at its own cost) to do believe that the Respondent has adequately explained how the Purchase
the assembly work. This too, by itself, is sufficient to justify termination of the Order violates the STCA. In its Reply, the Respondent only alleges that the
Purchase Order. Claimant has used a ‘pre-prepared boiler plate Purchase Order,’ and asserts
categorically that ‘any unreasonable and unfair provisions in the Purchase
[119] “The Tribunal therefore concludes that the Claimant properly terminated the Order that (a) exclude Claimant’s legal obligations arising from its intentional
Contract.” or gross negligence or (b) limit the scope of liability for damages of Claimant or
(….) shift the risk of the business to RESPONDENT should be invalidated (or should
be construed at least in favor of RESPONDENT).’ However, the Respondent
V. KOREAN FAIR TRADE LAWS fails to specify any particular provisions of the Purchase Order that are
[120] “The Tribunal finds that the Fair Subcontracting Act (‘FSA’) does not apply in unreasonable or unfair, or explain how such provisions are unreasonable
this case. Both parties agree that the FSA is not directly applicable in this case. or unfair. The Tribunal therefore declines to invalidate any provisions of the
The Claimant argues that the FSA is intended to protect small and medium Purchase Order as being in violation of the STCA.”
domestic businesses from known Korean conglomerates in order to further
develop the Korean economy, and the Respondent does not contest this

91 92
Korean Commercial Arbitration Board

VI. INTEREST claims. It is therefore not necessary for the Tribunal to determine whether
the non-disclosure of this evidence was a violation of the Tribunal’s Amended
[124] “The Tribunal does not believe that the default interest rate of 20% under the
Procedural Order on Document Requests.”
Expedition of Legal Proceedings Act (‘ELPA’) should apply in this arbitration.
b. Contract between COMPANY A and the Claimant
[125] “Firstly, and most importantly, the text of Article 3 of the ELPA provides
that the 20% per annum interest rate only applies to ‘court judgments.’ The [129] “The Claimant admits that it produced only a draft, incomplete version of the
Supreme Court of Korea has held that this provision should not be construed contract between COMPANY A and Claimant. However, the Respondent has
broadly, and thus should not be applied to proceedings other than ‘civil failed to adequately explain how the undisclosed portions of the COMPANY A
litigations.’ Moreover, there is insufficient evidence to conclude that it is contract were material pieces of evidence. The Respondent has not offered an
common practice among arbitrators in KCAB arbitration to order payment of explanation as to why disclosure of the excluded ‘price breakdowns,’ ‘contract
interest pursuant to the ELPA. price, bank details and signature blanks, and vastly more detailed schedules’
In light of the foregoing, the Tribunal is of the opinion that applying the ELPA to was necessary for determining whether the Claimant faced serious financial
the current arbitration would be improper. pressures from COMPANY A to fire the gas turbines, or to whether Claimant
was in fact liable for the alleged liquidated damage penalty from COMPANY
[126] “Therefore, the Tribunal holds that the 6% interest rate designated by the A. The Tribunal therefore finds that there was no material violation of the
Korean Commercial Code is the appropriate rate in this arbitration.” Tribunal’s Amended Procedural Order.

VII. DOCUMENT PRODUCTION [130] “The Respondent has also presented no evidence showing that the Claimant
intentionally concealed the full contract from the Tribunal. The Claimant
1. Violation of the Tribunal’s Procedural Order on Document Requests
understood the Tribunal’s Order to disclose the ‘full contract’ to mean ‘the
a. Alleged Agreement between the Claimant and Company B comprehensive schedules, and for Claimant’s Statement of Reply, only
relevant extracts from schedules A, B and C, without the main contract sheets’
[127] “The Respondent requested an order directing the Claimant to disclose, inter and denied that it had any intention to conceal any critical document or violate
alia, communications and documents between the Claimant and Company B in the Tribunal’s Order. The Tribunal therefore is of the view that there has been
July 2013. This request was withdrawn by the Respondent on the basis of the no deliberate non-compliance with the Tribunal’s order.”
Claimant’s assertion that it had never made an offer to purchase the Diverter
Dampers from Company B. The Tribunal therefore never made any order on c. Additional Documents Concealed
this request.
[131] “In addition to the documents outlined above, the Respondent also contends
[128] “The Tribunal recognizes that the Respondent has now produced evidence that the Claimant has possibly breached its obligations under the Tribunal’s
(including email exchanges between Company B and the Claimant) Order by failing to disclose ‘additional documents, contracts or other
that suggests that the Claimant’s assertion was incorrect. However, as evidences.’ The Respondent has not specified what these additional pieces
discussed below, even if the uncovered evidence falls within the scope of of evidence are, nor has it provided any evidence to support this allegation.
the Respondent’s request (which the parties dispute), the Tribunal finds The Tribunal therefore finds that there has been no violation of its Amended
in any case that the non-disclosure of this evidence does not support the Procedural Order with respect to additional documents concealed.”
drawing of adverse inferences or summary dismissal of the Claimant’s
2. Tribunal’s Authority to Dismiss Claims or Draw Adverse Inferences

93 94
Korean Commercial Arbitration Board

by the court, and promises and commitments by the plaintiffs.


a. Summary Dismissal of the Claimant’s Claims

[136] “The Ninth Circuit in Volcan v. Omnipoint Comm’n adopted the same approach
[132] “The Respondent argues that the Tribunal should adopt an approach similar to
and upheld a district court’s dismissal of a claim due to the plaintiff’s spoliation
that taken by U.S. courts under Rule 37(b)(2)(A) of the FRCP and sanction the
of evidence resulting from ‘willfulness, fault or bad faith.’ The district court
Claimant for its failure to comply with the Tribunal’s Order by dismissing its
found spoliation of evidence where the plaintiff had (1) knowingly permitted
claims.
its employees to destroy engineering notebooks that contained evidence
potentially relevant to the litigation; (2) destroyed and altered notes pertaining
[133] “While the Tribunal agrees that ‘arbitral tribunals possess the inherent
to its dealings with the defendant; and (3) falsified several documents and
authority to dismiss the claims of the non-obeying party in whole or in part,’
emails that were produced.
there is no basis on which the Tribunal can apply a procedural law which is
not the law chosen by the parties as applicable to the arbitration agreement.
[137] “Similarly, the Ninth Circuit in Leon v. IDX Systems held dismissal is an
Thus, contrary to the Respondent’s assertions, the Tribunal does not consider
available sanction only in circumstances where ‘a party has engaged
it within its power to apply a U.S.-style approach to non-disclosure and
deliberately in deceptive practices that undermine the integrity of judicial
summarily dismiss the claims.
proceedings,’ and held that ‘a finding of ‘willfulness, fault or bad faith’ is
required for dismissal to be proper.’ The district court found (and the Ninth
[134] “Even if U.S. procedural rules were applied, the Tribunal would not summarily
Circuit upheld) that the plaintiff’s behaviour amounted to willful spoliation
dismiss the Claimant’s claims. Rule 37(b)(2)(A) of the Federal Rules of Civil
because he knew he was under a duty to preserve all data on the laptop,
Procedure provides in pertinent part:
but intentionally deleted many files and then wrote a program to write over
‘If a party … fails to obey an order to provide or permit discovery … the deleted documents.
court where the action is pending may issue further just orders. They may
include the following: [138] “US courts have taken the same approach when considering an arbitrator’s
(iii) striking pleadings in whole or in part; authority to dismiss claims. In Americredit v. Oxford Mgmt., the district
 … court found that the arbitrator had the authority to dismiss the defendant’s
(v) dismissing the action or proceeding in whole or in part;’ counterclaim because the defendant had destroyed critical evidence that was
central to the analysis of the counterclaim on the merits, the absence of which
made it impossible for the defendant to meet its burden on its counterclaims.
[135] “U.S. courts have permitted dismissal of a claim when there has been
Specifically, the arbitrator found that the party had ‘knowingly destroyed
willfulness, fault or bad faith on the part of the claimant. For example, the
records necessary to resolve the disputes between the parties’ because it had
Supreme Court in NHL v. Metro Hockey Club held that dismissal of a claim
destroyed financial records of its activities.
should be permitted in exceptional circumstances, such as ‘flagrant bad
faith’ on the part of the respondents and counsel’s ‘callous disregard’ of
[139] “In light of the case law above, the Tribunal considers there is insufficient
their responsibilities pursuant to a disclosure order. The district court found
evidence of willfulness or bad faith on the part of the Claimant to merit
(and the Supreme Court upheld) that the respondents and their counsel
summary dismissal. There is no evidence of willful destruction of evidence, as
had demonstrated ‘flagrant bad faith’ and a ‘callous disregard’ of the
in Volcan, Leon or Americredit, nor has there been a willful refusal to respond
responsibilities owed to the court after they failed to answer interrogatories
despite repeated requests for evidence, as in NHL. As recognized by the
for seventeen months, despite numerous extensions and several admonitions
Supreme Court, the dismissal of a claim is ‘the most severe in the spectrum of

95 96
Korean Commercial Arbitration Board

sanctions’ and the Tribunal therefore considers that it would be inappropriate may be drawn. The Respondent asserts, relying on Professor Born, that
to dismiss the Claimant’s claims, in the absence of exceedingly clear evidence tribunals have broad authority to make adverse inferences where:
of willfulness or bad faith by the Claimant.”
a.the requesting party itself produced material evidence relating to the
disputed issue;
b. Adverse Inferences

b. the non-produced evidence could have been produced by the non-
[140] “The Tribunal recognizes that it has the authority to draw adverse inferences
producing party;
when documents have not been produced on time in response to a party
request or an order of the tribunal. For example, Article 29(3) of the KCAB
c. the requested inference to be drawn from the non-production of
Rules provide:
evidence is reasonable, supported by prima facie evidence and consistent
‘[i]f any of the parties, although duly invited to produce documentary with the evidentiary record; and
evidence, fails to do so within the established period of time, without valid
excuse, the Arbitral Tribunal may make the Award on the evidence before d. the non-producing party was aware of the possibilities of adverse
it.’ inferences.

[141] “In turn, Article 9(5) of the IBA Evidence Rules provides: [145] “The Respondent asserts that the first requirement is satisfied when the
 ‘If a Party fails without satisfactory explanation to produce any Document material evidence in question has been produced by the requesting party.
However, the Respondent has misunderstood this requirement, which actually
requested in a Request to Produce to which it has not objected in due time
places an obligation on the requesting party to provide evidence to support the
or fails to produce any Document ordered to be produced by the Arbitral
adverse inferences it seeks.
Tribunal, the Arbitral Tribunal may infer that such document would be
adverse to the interests of that Party.’
[146] “Here, the Respondent requests that the Tribunal draw the inferences that
‘a separate legal relationship existed directly between Company B and
[142] “Similarly, under Article 349 of the Korean Civil Procedure Act, a Korean court
Claimant, and that any liability for the Diverter Dampers does not concern
may accept the allegations of the other party when the party fails to comply
RESPONDENT’ or that ‘Claimant caused the alleged defects in the Diverter
with a specified order under the Act.
Dampers.’ However, the Respondent has failed to adduce evidence supporting
these inferences for multiple reasons.
[143] “However, the Tribunal considers that it is appropriate to draw adverse
inferences only in circumstances where the evidence is not produced or where
[147] “First, the allegedly concealed email exchanges between Company B and
evidence is not disclosed in due time. Here, the evidence was produced by the
Claimant do not show that a separate legal relationship existed directly
Parties prior to the hearing, and the evidence has been before the Tribunal for
between Company B and Claimant regarding the original Diverter Dampers,
many months. The Tribunal therefore believes it is unnecessary to draw any
or establish that the Respondent has no liability for the Diverter Dampers. At
adverse inferences and it is appropriate to proceed with the evidence on the
best, these emails show a separate legal relationship between the Claimant
record.
and Company B regarding the repairs of the existing Diverter Dampers. Even
if this relationship existed (and it is disputed whether an agreement was ever
[144] “Moreover, the Tribunal finds that the criteria required for the drawing of an
concluded, and the Tribunal makes no finding on that issue), this relationship
adverse inference have not been satisfied, and therefore no adverse inference

97 98
Korean Commercial Arbitration Board

does not establish that the Claimant and Company B had a separate legal
relationship for the purchase of the original Diverter Dampers. It is possible [152] “However, the Respondent has not requested that the Tribunal impose any
that Company B simply agreed to take over the repairs of the existing Diverter costs penalty nor proposed what a cost penalty should be. The Tribunal
Dampers, even though it never had primary contractual responsibility for the therefore does not impose any costs penalty.”
Diverter Dampers.
VIII. COUNTERCLAIMS
[148] “Second, the Respondent has failed to provide evidence to support an adverse 1. Payments pursuant to the Contract
inference in relation to the Claimant’s failure to disclose the full COMPANY
A contract. The Respondent alleges that ‘Dailem fully knew that it would [153] “Having considered all of the evidence before it and the submissions of
cause serious damages to the Diverter Dampers by starting the gas turbines the parties, the Tribunal finds that the Counterclaimant did not complete
prematurely’ and therefore it was ‘critical to receive the full contract between performance of its obligations under the Purchase Order and therefore is not
entitled to any payments that may be owed under the Contract. Specifically,
Claimant and COMPANY A in order to discern whether or not Claimant actually
the Counterclaimant has failed to demonstrate that it completed the following
faced this financial pressure.’ However, the Claimant does not explain the
obligations required under the Purchase Order:
significance of the undisclosed portions of the COMPANY A contract, or how
those undisclosed portions show that Company B is the party responsible for a. Failure to repair the defective goods, as required under the Vendor’s
the Diverter Dampers or that RESPONDENT is not responsible for the Diverter Guarantee in the Contract; and
Dampers. b. Failure to comply with the delivery schedule in the Contract.
(….)
[149] “Third, the Claimant alleges the Respondent has full access to Company B’s
records and should have been able to present the evidence in question (i.e., [154] “The Counterclaim Respondent also alleged two other breaches that should
the email exchange between Company B and the Claimant). This has not been be briefly mentioned. First, the Counterclaim Respondent argued that the
contested by the Respondent. In such circumstances, where the requesting Counterclaimant failed to submit all of the Final Documents required under
party itself has access to corroborating evidence but fails to present it or offer Article 5.4 of the Purchase Order prior to receiving the Final Payment. Article
any explanation as to its absence, no adverse inferences should be drawn. 5.4 of the Purchase Order provides:

‘‘Ten percent (10%) of total contract amount will be paid after submission
[150] “The Tribunal therefore declines to draw any adverse inferences.”
of Vendor’s final documents with presentation of following documents.
c. Costs Sanction
Original Commercial Invoice

[151] “The Respondent rightly noted in its submissions that a possible sanction for Copy of document transmittal of final documents signed by Purchaser’s
representative’
failure to comply with an order is a costs penalty, as set out in Article 9(7) of
the IBA Evidence Rules:
[155] “Article 5.4 therefore provides that payment of the contract price is conditional
If the Arbitral Tribunal determines that a Party has failed to conduct on receipt of particular Final Documents. The Parties do not dispute that the
itself in good faith in the taking of evidence, the Arbitral Tribunal may, in Respondent submitted the original commercial invoice, although they do
addition to any other measures available under these Rules, take such dispute whether the copy of document transmittal of final documents signed
failure into account in its assignment of the costs of the arbitration, by Purchaser’s representative was submitted.
including costs arising out of or in connection with evidence.

99 100
Korean Commercial Arbitration Board

[156] “Even if this copy of document transmittal documents signed by Purchaser’s [160] “The Tribunal therefore dismisses this counterclaim in its entirety.”
representative was not submitted, the requirement has been waived because
the Counterclaimant paid part of the Final Payment without raising any issues 2. Interference with RESPONDENT’s Performance of Its Obligations under the
related to the Final Documents requirement. The Claimant does not dispute Purchase Order
that it did make part of the Final Payment and has provided evidence of several
payments made to the Counterclaimant in the period between July 2012 and [161] “It is common ground between the Parties that there is no express provision
May 2013. in the Contract requiring the manufacture of the Bypass Stacks and Diverter
Dampers. Moreover, Article 4 of the Purchase Order provides that the
[157] “Second, the Counterclaim Respondent submitted that the Counterclaimant contract price is a ‘fixed price’ and no cost changes are permitted so long as
failed to fully perform on its obligations under the Purchase Order because ‘design conditions are not changed.’ The Tribunal finds that Article 4, on its
the ‘required guaranteed bond relating to €…of the purchase price was never terms, expressly limits any variation to the contract price to circumstances in
taken out.’ The Counterclaim Respondent does not specify, but the Tribunal which design conditions have varied, and it does not consider a change in the
believes that this is a reference to the guarantee bond that Company B, not place of manufacture to be a change to the design conditions. The Tribunal
RESPONDENT, was to procure (specifically, the Purchase Order was amended therefore concludes that no changes to the contract price are allowed in these
to specify that ‘one bond will be issued for RESPONDENT …’ and “one bond circumstances.
will be issued for Company B …’). RESPONDENT therefore has no obligation
[162] “The Counterclaimant submitted that Article 4 is ‘inherently unfair’ and
under the Purchase Order to procure the guarantee bond of €… for the
therefore should be ‘invalidated or otherwise be construed in a reasonable
Diverter Dampers.
and fair manner under the general principles of good faith under the Korean
Civil Code,’ the Fair Subcontracting Act (‘FSA’) and the Standard Terms and
[158] “In summary, the Tribunal concludes that the Counterclaimant breached
Conditions Act (‘STCA’).
the Contract by failing to repair the defective goods and failing to deliver
them in accordance with the delivery schedule, but it declines to find that the
[163] “As discussed above …, the Tribunal believes the FSA and STCA are not
Counterclaimant breached its obligations in relation to the guarantee and the
applicable in the present context.
Final Documents. Because the Counterclaimant has breached the Contract,
the Tribunal therefore finds that the Counterclaimant Respondent is not
[164] “As for the good faith principles under the Korean Civil Code, the Tribunal
obligated to pay the outstanding balance under the Contract.
declines to interpret Article 4 to mean that Claimant must ‘compensate any
and all additional costs incurred by RESPONDENT due to its deprivation of the
[159] “In relation to the Counterclaimant’s claim for €… in costs associated with
liberty to manufacture its products in its own plant in China.’ In the Tribunal’s
additional work performed by Company B, the Tribunal is of the view that these
view, an express contractual term which, on its terms, limits a price variation
costs are RESPONDENT’s responsibility under the Contract. As discussed
to changes in design conditions cannot, on any view, be read to require
above …, RESPONDENT is responsible for the Diverter Dampers and Bypass
Claimant to bear the burden of additional costs that the Counterclaimant
Stacks under the Purchase Order, and it is therefore also responsible for
made the autonomous decision to undertake when complying with Claimant’s
making any repairs or replacements necessary to remedy any defects found in
request. The Counterclaimant has failed to offer an adequate explanation as to
these products. Thus, any costs incurred in relation to repair or replacement
why Korean law would support such an interpretation.
work performed by Company B on the products are RESPONDENT’s sole
responsibility.

101 102
Korean Commercial Arbitration Board

[165] “In any event, the Tribunal considers that there is insufficient evidence that the after it discovered defects in the Bypass Stacks and Diverter Dampers, and
parties understood or agreed that the Bypass Stacks would be manufactured RESPONDENT failed to remedy defects as required by the Contract. As such,
in China: there is no basis, i.e., no wrongful actions on the part of Claimant, on which the
 . The Offer submitted by the Counterclaimant makes reference to
a Counterclaimant may claim any loss of business profits.
‘ex works KSA,’ which means that the products would be supplied at In light of the foregoing, the Tribunal dismisses this counterclaim.”
RESPONDENT’s place of business, which is in Saudi Arabia. While that
does not specify that the products were to be manufactured in Saudi IX. COSTS
Arabia, it would have been reasonable for Claimant to infer that the [168] “The Tribunal notes that according to the Claimant’s cost submission, it
products likely would be manufactured in Saudi Arabia. has incurred/will incur KRW 363,000,000 in legal fees, KRW 141,819,451 in
arbitration costs and KRW 26,233,498 in other expenses (including court
b. The 26 July 2012 meeting minutes submitted by the Counterclaimant reporter, interpreter and courier/photocopying fees).
do not clearly evidence a mutual agreement to manufacture in China.
While the invoices attached to the 26 July 2012 meeting minutes refer [169] “Under Article 47 of the KCAB Rules, arbitration costs (including administrative
to the supplier ‘Respondent Suzhou’ for 10 units of baffles, 3 units of fees) shall in principle be borne by the unsuccessful party. The Tribunal
silencer casing and 10 units of stack, these references, in the Tribunal’s therefore awards the Claimant KRW 141,819,451 in relation to its arbitration
opinion, are insufficient to show that the parties had an understanding costs.
that manufacture of the Bypass Stacks and Diverter Dampers would be
done solely in China. [170] “However, under Article 48 of the KCAB Rules, the Tribunal determines the
allocation of other expenses (including but not limited to attorney fees and
c. Moreover, it is also unclear why the Respondent would have requested costs for experts, interpreters, and witnesses incurred by a party during the
(as it did in an email dated 27 July 2013) Claimant’s consent for arbitration proceedings) between the parties. This Tribunal determines that
manufacture in China if such a mutual understanding already existed. the Claimant shall be awarded 35% of its legal fees and other expenses, i.e.,
(KRW 363,000,000 + KRW 26,233,498) * 0.35 = KRW 136,231,724. This allocation
d. Finally, the comments by Mr. CW3 about RESPONDENT’s factory in reflects the fact that the Claimant has prevailed on many (but not all) of its
China clearly is only an expression of praise of the factory, and, on any claims but its damages have been reduced due to its contributory negligence
view, does not show any agreement between the parties to manufacture by starting the gas turbines and that the Respondent did not prevail on its
in China. counterclaims.”

[166] “The Tribunal therefore finds that Claimant is not liable for any additional X. DISPOSITION
costs that may have been incurred by the Counterclaimant in relation to the
[171] “Based upon the foregoing, the Tribunal makes the following award:
manufacture of products in Saudi Arabia.”
 . Orders that the Respondent pay €1,350,000 plus US$ 1,238,750.63 in
a
3. Loss of Business Profits
relation to defects in the Diverter Dampers,

[167] “The Tribunal finds that the Counterclaim Respondent did not wrongfully b. Orders that the Respondent pay US$ 273,309.23 in relation to defects in
initiate the arbitration or terminate the Purchase Order. As discussed above …, the Bypass Stacks,
Claimant rightfully terminated the Purchase Order and initiated the arbitration

103 104
Korean Commercial Arbitration Board

c. Orders that the Respondent pay US$ 113,293.12 in relation to the or other services.” It appears in this case that the service part does not constitute
assembly costs for the Diverter Dampers, the preponderant part. Therefore, the contract would not fall outside the sphere of
application of CISG. As a result, the Arbitral Tribunal could have examined whether
d. Orders that the Respondent pay US$ 20,097.65 in relation to the CISG applies to the contract.
assembly costs for the Bypass Stacks,
Furthermore, Article 6 of CISG provides that “[t]he parties may exclude the
e. Orders that the Respondent pay €529,980 in relation to the delay in
application of this Convention or, subject to Article 12, derogate from or vary the
delivering the Diverter Dampers and Bypass Stacks,
effect of any of its provisions.” In this case the parties expressly chose Korean law
as the applicable to the substance in Article 33 of the contract. Meanwhile, it is
f. Declares that the Claimant properly terminated the Contract,
also clear that the parties just chose Korean law as the applicable law but they did

g. Rejects the Claimant’s request for “other costs” associated with not expressly derogate from CISG. Moreover, the contract stipulates “the Laws
business trips, additional engineering manpower, third party inspectors, of Korea” not “the Korean Civil Code” as the applicable law. A reference to the
resident supervisor and indirect costs for construction, Korean Civil Code rather than to Korean law would have higher possibility to exclude
CISG.10) Even a valid express reference to national law is not sufficient to exclude
h. Declines to apply the Fair Subcontracting Act or the Standard Terms the application of CISG since such an exclusion has to be made expressly.11) The
and Conditions Act in the present arbitration, contract also employs DDU, stipulating that “[a]ll equipment and material shall
be delivered on the basis of DDU Job-Site (ICC INCOTERMS 2010).” The parties’
i. Declares that a 6% interest rate per annum should be applied to the reference to the INCOTERMS is not considered sufficient to exclude the application
damages awarded above, from 4 October 2013 to the date of full payment of CISG either. It is decisive whether the parties have intended to derogate from
of damages, CISG.12) The Arbitral Tribunal therefore should have verified the parties’ intention to
exclude the application of CISG by choosing Korean law in this case.
j. Dismisses RESPONDENT’s counterclaims in their entirety,

II. INCOTERMS
k. Declines to draw adverse inferences or summarily dismiss the
Claimant’s claims on the basis of its alleged intentional concealment of
As reviewed above, the contract stipulates DDU term. The Arbitral Tribunal
evidence, and
held that “the delivery conditions set out in Article 6 (DDU Job-Site) concern the
allocation of risk and transfer of title.” The Incoterms are a set of rules established
l. Orders that the Respondent pay KRW 278,051,175 in relation to the
Claimant’s costs in this arbitration.” by the International Chamber of Commerce. The Incoterms certainly deal with

Implications

I. APPLICABLE LAW
10) Kröll et al., supra note 10, at 107.
The parties entered into a contract whereby the Respondent supplied to the 11) Oberster Gerichtshof, Austria, 28 April 2000, unilex 1 Ob 292/99v; Landgericht Ladnshut,
Germany, 5 April 1995, unilex 54 O 644/94; US Court of Appeals for the Fifth Circuit, 11
Claimant the goods in question and related services. Article 3(2) of CISG provides
June 2003, unilex 02-20166.
that “[t]his Convention does not apply to contracts in which the preponderant part of
12) United Nations Commission on International Trade Law, supra note 10, at 34; Schwenzer,
the obligations of the party who furnishes the goods consists in the supply of labor supra note 10, at 115.

105 106
Korean Commercial Arbitration Board

the allocation of risk but do not regulate transfer of title. Property rights may The requirement under CISG and Korean law has a dispositive character so that
coincidently be transferred at the time of passing of risk. However, risk and title the parties may derogate from or exclude its application. The parties therefore
are treated separately.13) The transfer of property in the goods is governed by the may derogate from the requirement by agreeing upon an entire agreement clause.
applicable law determined by the relevant private international law. The transfer of By doing this the parties bar recourse to any additional material for interpretation
property in movables is governed by the law of country where the goods are situated. beyond the four corners of the contract. An entire agreement clause must be
The lex situs at the time of transfer, as a general rule, governs the effect of the interpreted pursuant to the parties’ intent in the context of the contract embedding
transfer of the goods on the proprietary rights of the parties.14) it.16) For example, a court held that the merger clause contained in the sales
contract prevented the buyer from using extrinsic evidence such as the letter of
III. THE ENTIRE AGREEMENT CLAUSE credit, which is an instrument of payment that must be consistent with the contract
terms and cannot prevail over them. Further the court stated that the clause
contained in the letter of credit entitling the buyer to change the date of shipment
The Arbitral Tribunal finds in this case that the entire agreement clause provides
was to be considered an offer to modify the contract which was rejected by the seller
that the Purchase Order, the Terms and Conditions and attachments to the Contract
and therefore was not binding.17)
constitute the entire agreement between the Purchaser and the Vendor, and may not
be modified except in writing signed by the authorized representative of both parties.
The contract contains an entire agreement clause also called a merger clause, a
four corner clause, or an integration clause.15)

Under CISG and Korean law which is the applicable law to the contract, due
consideration is, in determining the intent of a party, to be given to all relevant
circumstances of the case including the negotiation, any practices which the parties
have established between themselves, usages and any subsequent conduct of the
parties. On the other hand, Article 2-202 UCC provides that “[t]erms with respect
to which the confirmatory memoranda of the parties agree or which are otherwise
set forth in a writing intended by the parties as a final expression of their agreement
with respect to such terms as are included therein may not be contradicted by
evidence of any prior agreement or of a contemporaneous oral agreement but may
be explained or supplemented (a) by course of dealing or usage of trade or by course
of performance; and (b) by evidence of consistent additional terms unless the court
finds the writing to have been intended also as a complete and exclusive statement
of the terms of the agreement.”

16) United Nations Commission on International Trade Law, supra note 10, at 57; Kröll et al.,
13) Ralph H. Folsom et al., International Business Transactions (2nd ed.) 49-50 (2001). supra note 10, at 150-151; Schwenzer, supra note 10, at 162-163.
14) Kröll et al., supra note 10, at 397-398; Collins et al., supra note 9, at 1336-1339. 17) People’s Supreme Court, Appeal Division in Ho Chi Minh City, Vietnam, 5 April 1996, unilex
15) Schwenzer, supra note 10, at 163. 74/VPPT.

107 108
Korean Commercial Arbitration Board

The Claimant initiated arbitration relying on the arbitration clause in the contract
which provided for KCAB arbitration. The contract provided that the law applicable to
the dispute was Korean law. Further, the parties agreed that the 1980 United Nations
KCAB case no.6
Convention on Contracts for the International Sale of Goods applied as part of
Korean law. The Claimant sought damages and interest relying on the Respondent’s
Parties Claimant (Counter-Respondent): Laboratories Ltd. (New Zealand)
failure to supply a system complying with the specifications of the contract and to
Respondent (Counter-Claimant): Softgel Ltd. (Korea)
correctly install the system. In response, the Respondent objected that it supplied
Place of and installed the system in accordance with the contract. Further, the Respondent
Arbitration Seoul, Republic of Korea sought the payment of the balance of the contract price and interest.

Language Original in English


The Arbitral Tribunal first found that the system failed to comply with the stipulated
Subject matters - applicable law contractual specifications in terms of speed and quality, rejecting the Respondent’s
- opting in CISG argument that the Claimant applied incorrect type and excessive quantity of oil to the
- mixed contract system and that the clarity level of reclaimed gel was not agreed by the parties in the
- non-conformity of goods contract. Further, the Arbitral Tribunal found that the Respondent failed to provide to
- change of condition of goods the Claimant the documents and information necessary to run the system in a proper
- burden of proof and effective manner. Having found that alterations by the Claimant to the system
- document production were not material and did not cause a problem, the Arbitral Tribunal also rejected
- calculation of damages the Respondent’s argument that the Claimant was barred due to the alterations
- duty to mitigate damages from any claim for damages. The Arbitral Tribunal rejected the Respondent’s
argument that the Claimant had failed to take appropriate measures to mitigate its
loss. Therefore, the Arbitral Tribunal denied the Respondent’s counterclaim, holding
Facts that the balance of the contract price sought by the Respondent was not due yet. As
a result, the Respondent was ordered to pay the Claimant for awarded damages.
The parties entered into a contract for the Claimant to purchase from the
Respondent the gelatin reclaim system which was to purify the remaining gelatin Excerpt
to be reused in the course of manufacturing soft gel capsules. The gelatin reclaim
system was delivered to the Claimant’s premises where the Respondent’s engineers I. APPLICABLE LAW
installed the system. Trial runs of the system produced cloudy reclaimed gel with
the oil residue exceeding the stipulated limit under the contract. However, the [1] “On 12 June 2013, the parties entered into a Sale and Purchase Contract …,
Respondent argued that the higher oil residue was attributable to the incorrect type pursuant to which the Claimant agreed to buy from the Respondent a Gelatin
and excessive quantity of lubricant oil used by the Claimant in manufacturing soft Reclaim System (…‘GRS’) for the price of ….
gel. In response, denying this, the Claimant instead altered the micro-filter in the
system but failed to obtain clear reclaimed gel. The Claimant also failed to produce [2] “Clause 2(10) of the Contract reads as follows:
clear reclaimed gel even with different lubricant oil. Consequently, the Claimant ‘Governing Law & Arbitration: The contract shall be governed as to all
refused to pay the remaining contract price. matters, including validity, construction and performance by and under

109 110
Korean Commercial Arbitration Board

the laws of Republic of Korea. All disputes arising out of or in connection from any of the parties present. The Respondent says it subsequently installed
with this contract shall be finally settled in Republic of Korea under the the GRS in the Claimant's factory in exactly the same condition as during the
Arbitration Rule of Korean Commercial Arbitration Board by one or more FAT.
arbitrators to be appointed in accordance with the said Rules.’
(….) [7] “The Respondent attributed the problems encountered by the Claimant to
the MCT [Medium Chain Triglyceride] oil used by the Claimant, which was
[3] “By consent, the parties agreed that the Tribunal may refer to the IBA Rules different from that used by the Respondent during the FAT. The Respondent
on the Taking of Evidence in International Arbitration 2010 in the conduct of also suggested that the Claimant had used excessive MCT oil in the reclamation
the arbitration. It was also agreed that Korean Law is the governing law of process.
the dispute and that the 1980 United Nations Convention on Contracts for the
International Sale of Goods (‘CISG’) applies as part of Korean Law.” [8] “I find that the Claimant had clearly established that the GRS did not meet the
stated contractual specifications of speed of 4000 kg/20 hours process speed
II. NON-CONFORMITY OF THE GOODS and quality of less than 20 ppm. As observed by the Claimant's expert witness,
Mr. F, the GRS reclaimed gel was ‘visually opaque and not clear enough for
1. Non-compliance with Contractual specifications reuse in commercial reclaimed gel capsules.’ In the Mr. E’s Report, Mr. F noted
that it was only possible to reclaim clear gel by reducing the flow rate of the
[4] “The Claimant argues that the Respondent expressly guaranteed that the GRS
GRS to 25-33% of the contractually agreed capacity. As such, the Claimant had
was able to reclaim clear gel from coloured and non-coloured gel net which
to sacrifice one of the contractual specifications stated above in order to achieve
would allow the Claimant to save a total of … per year. The Claimant submits
the other.
that it requested for the pilot model of the GRS to be customised to meet its
commercial needs and performance expectations.
[9] “The FAT did not establish anything related to compliance with the quality
or speed specifications. First, the Respondent did not run the GRS using the
[5] “The Claimant further argues that the Respondent had warranted that the GRS
Claimant's gel net, but with Korean gel net. The fillings and lubricants were also
would meet its contractual specifications under Clause 1. The Claimant alleges
different from those used by Laboratories LTD. (Claimant). In fact, it seemed
that the GRS failed in respect of the following two contractual specifications:
that no MCT oil was used. This was confirmed by the Respondent's Mr. H during
cross-examination. Secondly, the focus of a FAT, according to Mr. F, was the
Contractual Specifications Actual Result of GRS mechanical operations of the system to ensure that they were functioning
and operating the way they were supposed to. The FAT would not validate the
4000 kg/20 hours process speed 1,000 kg/20 hours process speed contractual warranties because this would be done on-site. There was no point
doing this at the FAT because the system had to be disassembled, shipped
Residue Oil < 20 ppm Residue Oil > 20 ppm (i.e. 440 ppm)
and then re-assembled on-site for the SAT (Site Acceptance Test). Thirdly,
there is evidence that the FAT was not properly conducted. No FAT report was
[6] “The Respondent submits that the GRS has the quality and performance issued. The Respondent provided no information on the characteristics of the
contractually accepted by the parties. According to the Respondent, the GRS gel net used, the oil used for fillings and lubricants, or any information that
produced clear gelatin solutions which could be used to manufacture gelatin one would expect on the parameters of the tests. Mr. E said he had expressed
capsules during the FAT [Factory Acceptance Test] in Korea, without objections dissatisfaction with the FAT to the Respondent because there was no proper
testing and the gelatin produced was not clear.

111 112
Korean Commercial Arbitration Board

[10] “I reject the Respondent's assertions that the cause of the problems the inventor of the GRS. He went on to explain how the testing was done in the
encountered on-site was the use of excessive MCT oil or the unsuitability of the laboratories of the Claimant, although he was not the one who did the testing
MCT oil used by the Claimant. There is no evidence that the Claimant applied himself.
excessive MCT oil to the GRS. On the contrary, Mr. E explained that MCT oil was
very expensive and machines supplied by Respondent limited its use to a low [13] “The Respondent's argument that the parties never agreed to the ppm level or
level. Furthermore, the Claimant was not using any peculiar or unusual MCT that it was not part of the Contract is untenable. It is clear that the Respondent
oil, but a type described as British Pharmacopeia grade that it had been using had expressly assured the Claimant in its pre-contract correspondence … that
all along, and obtaining from professional suppliers of MCT oil in Malaysia. I the GRS could achieve less than 20 ppm, and this was then expressly stipulated
would note also that the Respondent offered a GRS specifically for use by the in the Contract. It does not lie in the Respondent's mouth to now say that 20
Claimant, a company that it had been doing business with since 2007. There ppm was an arbitrary number or that parties never agreed to it. It did not matter
is no suggestion that the Respondent was taken by surprise by the type of gel that parties had not expressly agreed how it could be measured.
net used by the Claimant, which in any event was not of an unusual type. If the
Respondent was building a machine that could only be used with certain types [14] “I also find that the Respondent has failed to show that 20 ppm was not a
of gel net not used by the Claimant, for example the type that the Respondent measurable value. I accept the Claimant's position, as Mr. E maintained during
claimed it tested in Korea, this was a limitation that was not captured in the the hearing, that the ppm specification was a scientifically determinable value
Contract. Obviously, such a limitation, if it had been raised prior to the Contract, and thereby perfectly enforceable. Mr. F explained further how a chart could be
would not have been acceptable to the Claimant who was relying on the constructed for turbidity and ppm using carefully weighed amounts of oil.
Respondent to build a GRS to be used by the Claimant.
[15] “The Respondent referred to Korean case law and the CISG, neither of which
[11] “In addition, the Respondent argues that the ppm specification was not a provided any assistance to the Respondent where it was in breach of clearly
practical condition and therefore could not be recognised under the Korean defined contractual specifications as in this case. As the Claimant submits,
Civil Act which required a contract (legal act) to be determinable and feasible. Article 35(1) of the CISG, which applies to this Contract, reinforces the principle
It submitted that the stipulated level of ppm was not an industry standard and that the Respondent ‘must deliver goods which are of the quantity, quality and
could not be measured with any accuracy. The Respondent added that parties description required by the contract ….’”
never agreed to the level of 20 ppm, or how it could be determined and tested.
2. Failure to Correctly Install GRS

[12] “During the hearing, it was suggested by the Respondent's counsel to Mr.
[16] “The Claimant submits that the Respondent had breached its obligations under
E that the clearness of the gel net solution was the most important aspect.
Clause 1 of the Contract by failing to correctly install the GRS at the Claimant's
Mr. E answered that the GRS should achieve whatever was specified in the
premises. In the Statement of Claim and the Opening Statement, the Claimant
specifications, and gave the example of gel strength and viscosity as well as the
alleges that the Respondent had failed in three aspects: first, failing to plan
requirement of less than 20 ppm. Mr. E was challenged on the origin of the 20
ahead and properly organise the installation; second, lacking the necessary
ppm requirement as well as how it could be calculated. According to Mr. E, the
skills and expertise to properly carry out the installation; and third, failing to
Claimant needed to work regulatory standards in Australia and New Zealand.
provide the information that would have allowed the Claimant to independently
The 20 ppm was the lowest level that the Claimant could test and the Claimant
run the GRS. The List of Agreed Issues, however, put the second and third
needed to meet this level to avoid challenge by the regulatory authorities on
grounds as separate issues from the failure to correctly install and commission
whether the Claimant had done enough to prevent cross-contamination and
the GRS.
impurities in the batches it produced. This was a level introduced by Company B,

113 114
Korean Commercial Arbitration Board

(….) suffered delays. The Claimant emphasises that the Respondent's engineers
[17] “The Respondent argued in its Closing Argument that the GRS was installed forgot to clean the GRS after the FAT in December 2013, which resulted in the
correctly. It referred to the statement of the Respondent's Mr. F that the GRS first batch of reclaimed gel being wasted.
was well installed and that all parts of the machinery were in good working
order, but unfortunately does not point to where Mr. F made such comments. [21] “The Claimant asserts that it had to explain to the Respondent's engineers as to
The Respondent might have meant the following passage in the Transcripts what was required, even though the Respondent had the task of doing so as the
where Mr. F was asked if the product was installed well and there was nothing manufacturer and seller of the GRS. The Claimant further asserts that although
wrong with the actual working and operation of the machine. He answered in the Respondent initially indicated that it would cooperate with Company B and
the affirmative as follows: obtain its technical support, the Respondent subsequently dispensed itself
of useful guidance. The Claimant suggests that this was to the Claimant's
‘Yes. In fact, I thought the quality of the workmanship was very good and I
detriment as the Respondent failed to obtain valuable training from Company B..
thought overall there was nothing that I saw that said the system itself was
(….)
poorly manufactured from a workmanship perspective.’

[22] “I find that the Claimant has established that the Respondent's engineers
[18] “The Respondent also pointed out that the Contract did not provide any
lacked the skills and expertise to properly install and commission the GRS
installation timeline or schedule. It pointed out that the complaint about
only to the limited extent that they did not know how to make the GRS perform
failure to plan or organize installation, and for that matter, the lack of skills
according to contractual specifications.”
or expertise, was irrelevant to the operation and functioning of the GRS. It
maintained that the installation was well done. 3. Failure to Provide Information and Documents

[19] “As I have found that the GRS did not comply with contractual specifications (….)
in terms of speed and quality above, the question of installation and [23] “The Claimant submits that (1) the Respondent provided Claimant with a
commissioning is a peripheral one. I agree with the Respondent that the wrong and/or incomplete operating protocol to operate the GRS; and (2) the
question of the poor planning or lack of skills in the installation of the GRS was Respondent failed to provide Claimant with the functional description of the
not material, and the Claimant did not seem to pursue this point in its Closing GRS, despite requests. The Claimant relies on Article 30 of the CISG which
Statement. For avoidance of doubt, it can be said that, factually, there was no provides that: "The seller must deliver the goods, hand over any documents
evidence of any mechanical problem with the GRS and no evidence of physical relating to them and transfer the property in the goods, as required by the
poor workmanship. Nor was there any suggestion that it had been wrongly contract and this Convention."
installed in the sense that the parts were not where they were supposed to be. (….)
This is not to say that the system had been correctly installed and commissioned
to perform according to the Contract. Indeed, it obviously could not perform [24] “During the hearing, Mr. F explained the purpose of the functional description of
according to contractual specifications. In this sense, I find that it had not been components of the GRS which the Respondent did not produce. It is a document
correctly installed and commissioned as per the Contract. prepared by the process engineer in the project and details every step of
(….) the entire project. It is needed if there is a major disruption in the process. It
is customary for the manufacturer and seller of a GRS to give a copy to the
[20] “[Furthermore], the Claimant argues that the Respondent's engineers were customer.
inexperienced and insufficiently skilled such that the installation process

115 116
Korean Commercial Arbitration Board

[25] “The Respondent denies the allegations and argues that it had provided all III. CHANGE OF CONDITION OF THE GOODS
information regarding the regular operation of the GRS to the Claimant as well (….)
as all reasonable cooperation and assistance. The Respondent argues that it [27] “Another defence raised by the Respondent is based on a clause in Clause 2(6)
was entitled to protect confidential information relating to the GRS protocol and of the Contract which provides as follows:
operating principle. The Respondent asserts that it had provided the Claimant 
 ‘In no event may buyer assert a claim for any reason whatsoever after
with all the necessary documents, training and assistance necessary to run
the goods are sold, cut, proceed or otherwise altered. In no event shall
the GRS properly and in an effective manner. The Respondent alleges that
Seller be liable for the prospective profits, or indirect, special, incidental or
there was ample opportunity at the FAT and the SAT for the Claimant to ask
consequential damages.’
any question if there was any uncertainty. The Respondent further asserts
that due to the Claimant's modification of the GRS, the Claimant consistently
[28] “The Respondent argues that the Claimant had made alterations to the GRS and
demanded for documents which the Respondent expresses to be unnecessary
was thereby in breach, as a result of which it was prohibited from any claim for
for the operation of the GRS and of a confidential nature. The Respondent adds
damage on any basis whatsoever.
that the requested information, if given, would have been ineffective and would
require further re-examination due to the Claimant's customisation. It further
[29] “The alterations in question were the addition of a diaphragm valve on the
argues that the additional information that Mr. F mentioned as necessary to
permeate valve on the permeate flow pipe on 8 May 2014 to control the flow-
correctly operate the GRS was a change in the operating specifications due to
rate and the addition of a flow meter to the return flow-pipe on 9 May 2014.
the Claimant using excessive oil and the wrong type of oil.
These were part of the troubleshooting steps that the Claimant undertook after
the GRS had already been failed. As Mr. F explained, the flow meter was the
[26] “The Respondent's arguments are not convincing and fail on the evidence. I find
same diameter as the pipe that was originally there and did not affect the flow
that it has failed to provide both the categories of documents that the Claimant
of the fluid. The valve controlled the flow but when it was open, it would not
says it was obliged to provide. Indeed, it was established during the hearing that
change the parameters of the flow through the pipe.
the Respondent's witnesses had little knowledge about either the operating
protocol or the functional description of the GRS. Mr. H tried to explain that a
[30] “Clause 2(6) cannot be read in an absurd, literal way. For instance, it says that
person with less proficiency should only use the automatic operation setting but
the buyer has no claim after the goods are ‘sold,’ or after ‘proceed’ (whatever
admitted, however, that the Respondent never gave the Claimant any manual
that means). In the circumstances here, the buyer was trying to figure out a
with numbers for setting the parameters of the GRS. It was up to the Claimant,
way to solve a problem that had already arisen, for which notice had been given
by its own investigation, to figure out that flow rate and pressure settings were
to the seller, without any solution forthcoming from the seller. The alterations
important settings in the micro-filtration process. The Respondent had no
it made did not cause the problem that had already been complained of, nor
immediate answers to the Claimant's queries on the filter that the Respondent
were the alterations so invasive that it could be said the machine was materially
obtained from P. The Respondent promised to visit the site with P but never
altered. Clause 2(6) does not prohibit attempts to rectify a defect after the seller
did so. Curiously, Mr. G said the Respondent did not proceed with the visit
has failed to rectify it.”
because the Claimant was asking for data continuously. As for the functional
description, Mr. H admitted that since P refused to deliver it to the Respondent,
IV. DAMAGES
the Respondent could not deliver it to the Claimant. On further examination, he
displayed some confusion over whether he had the functional description but
1. Calculating Damages
eventually admitted that he did not have it. Consequently, I find in favour of the
Claimant on this issue.”

117 118
Korean Commercial Arbitration Board

[31] “As the GRS failed to comply with contractual specifications, the Claimant is It bears noting that the Respondent had requested for production of, amongst
entitled to damages. other documents, evidence of the quantum claimed by the Claimant but
(….) withdrew it at the hearing by telephone conference on … after the Claimant
insisted that it had produced sufficient evidence to support its monetary claim.
[32] “It appeared from Mr. F's testimony that the numbers provided up to then were The Claimant's position was it had no further documents to produce at that
indeed very rough estimates. He only obtained a ballpark figure orally over the time.
phone from P USA as he ‘was in a hurry to put these numbers together’ and P
USA gave him a quote for six units. When questioned whether it was essential [35] “Although the Claimant produced further documents on quantum after the
to change the existing feed and return manifold, he said it was because of the hearing with the agreement of the Respondent, the Respondent objects to
additional housings. At the moment there were only two housings, but if four the Claimant attempting to substantiate and add additional components to its
were to be added, there would be many more connections. Mr. F had not done estimation other than those already contained and set out in the Statement of
any engineering drawings so he and the stainless steel fabricators he spoke to Claim and the Mr. F’s Report, in particular paragraph … of the technical report.
were working off ‘kind of a rough idea.’ He guessed that they probably gave him The Respondent pointed out that the purpose of the statement of quantum
a ballpark estimate that would cover themselves a bit, which I take to mean with was to substantiate the components and work envisaged as contained in the
some margin built in. He seemed to accept that the costs could be lower but Statement of Claim and the Mr. F’s Report. The agreement and liberty to
when it was suggested it could be half the price, he replied: ‘Probably not half submit further documents on quantum were for the purpose of firming up
the price, no.’ the quotations and cost estimates that the Claimant had not done up to the
conclusion of the oral hearing. I agree with the Respondent. It cannot be right
[33] “After the hearing, the claimed quantum was revised on quotations received that, after the close of the oral hearing, the Claimant submits claim amounts
from suppliers selected by the Claimant who responded to two formal Requests based on specifications that neither the Claimant nor Mr. F had previously
for Quotes (‘RFQs’) sent by the Claimant on …. One RFQ was in relation to submitted for the purpose of examination or clarifications during the oral
stainless steel piping and component installation of the sub-system of the hearing.
micro-filter … (for brevity, I will refer to this as ‘the Piping RFQ’) and the other
RFQ was for the automated control, operation and graphics of the sub-system of [36] “The Claimant has not produced much information on the result of the post-
the micro-filter … (I will refer to this as ‘the Automation RFQ’). Mr. F provided a hearing work done at Laboratories LTD. (Claimant) or the design specifications
GRS MF Remediation Project Cost Summary … (‘Project Cost Summary’) which that would clearly show that the proposed work had not expanded beyond what
explains and summarises the breakdown of the costs based on quotations the Mr. F’s Report originally envisaged.
received. He said that, after the hearing, ‘work was done at Laboratories LTD.
(Claimant) to determine the operating envelope of the GRS MF system. The [37] “In particular, the Respondent highlighted the omission of a Piping and
result of that work was provided to management at Laboratories LTD. (Claimant) Instrumentation Diagram (‘P&ID’) to demonstrate that the work proposed dealt
along with the new design specifications and equipment components required with the micro-filtration system only and that it was in line with what was set out
to get the systems operating at warranted design performance.’” in the Statement of Claim and the Mr. F’s Report. The Respondent offered two
P&IDs - one depicting the current state of the GRS … and the other depicting the
2. Burden of Proof & Document Production additions proposed in the Mr. F’s Report …. In addition, the Respondent submits
a quotation received from Company J that it says sets out the reasonable fees
[34] “As the Respondent submits, the burden of proving the necessity of the for the modifications envisaged by the Claimant …. According to the Respondent,
proposed modification works and the quantum of damages lies on the Claimant. the total amount of the costs to bring about the modifications in the P&ID … are

119 120
Korean Commercial Arbitration Board

Korean Won 326,800,000 (USD 281,724.14). the Respondent could assert that it was "normally installed" given that it was
not part of the contractual design of the Respondent. The Respondent did not
[38] “The Respondent mounted numerous specific challenges to the Claimant's two furnish evidence addressing the specific points that Mr. E had testified on, nor
RFQs and the Project Cost Summary. Both parties have agreed that I should was Mr. E's testimony on these points discredited in cross-examination.
proceed to a decision based on the materials and submissions before me. I
do so taking into account the parties' submissions and the principle that the [42] “The Respondent has failed to show how the Claimant had failed to take
Claimant has the burden of proof, but without the benefit of specific explanation appropriate steps to mitigate its loss and damage.
of the items from any witness on either of the parties' closing submissions on (….)
quantum.”
[43] “…, I repeat that I do not accept the Respondent's argument that its suggested
2. Duty to Mitigate Damages
pre-washing was a solution that should have been accepted by the Claimant.”

(….)
V. INTEREST
[39] “There was no submission on mitigation other than the argument of the
Respondent that it had offered to install a pre-washing tank free of charge for
[44] “The Claimant seeks interest on any amount to be awarded at the rate of 6% per
the Claimant but was refused.
annum from the day following the day on which the Request for Arbitration was
served on the Respondent until full payment. In … its Statement of Claim, the
[40] “Mr. E explained the reasons for the Claimant's refusal to accept the pre-
Claimant relies on Article 54 of the Korean Commercial Code which provides as
washing tank solution as follows: first, the Claimant would not have purchased
follows:
the GRS if the pre-washing tank had been included in the original quotation;
‘The legal rate of interest on obligations resulting from commercial
second, pre-washing the gel net is not a scientific solution guaranteed to
activities shall be six percent per annum.’
generate consistent results; third, the result of the pre-washing demonstration
by the Respondent at the Claimant’s premises did not comply with the ppm
[45] “In … its Statement of Defence and Counterclaim, the Respondent denied the
specifications; fourth, pre-washing the gel was not a fully automatic process
Claimant's claim to interest on the basis that the Respondent is not liable for
and is labour-intensive as it required at least one operator to load and unload
any amount whatsoever.
200 kg of gel net 20 times a day in order to meet the contractually agreed
speed of 4,000 kg/20 hours; fifth, adding a pre-washing step to the GRS would
[46] “I decline to award interest on the damages awarded because the Claimant has
require the Claimant to add another water purification system and increase
not yet paid its suppliers for the proposed modification works.”
its consumption of city water by 60,000 litres resulting in US$ 1,000,000.00 of
Infrastructure Growth Charge to the … Water Supply Network; and sixth, the
VI. COUNTERCLAIM FOR THE PURCHASE PRICE
Claimant did not have space at its premises for another water purification
system and a pre-washing tank.
(….)
[47] “The Respondent claims under the Contract which provides for the following
[41] “The Respondent's argument that the pre-washing tank was a reasonable and
payments:
normal solution to the GRS, and that it functioned automatically with minimum
labour, was not supported by cogent or persuasive evidence. There were mainly • USD 200,000 2 months after installment
bare general assertions that it would have solved the problem. I do not see how • USD 120,000 9 months after installment

121 122
Korean Commercial Arbitration Board

[48] “The Respondent cited Article 59 of the CISG which provides that: between the parties of the necessary expenses incurred during the
‘The buyer must pay the price on the date fixed by or determinable from the arbitration proceedings.’
contract and this Convention without the need for any request or compliance
with any formality on the part of the seller.’ [52] “The Respondent submits that Clause 7 of the Contract which excludes liability
for ‘loss of profit or for any indirect, special, incidental or consequential losses
[49] “As I have found that the GRS had not been properly installed yet, … in the sense or damages which may be suffered by the other party’ means that the party in
that it was able to perform according to contractual specifications, the payments breach will not be able for the legal costs of the successful party. This argument
are not due yet. …, the Respondent is not precluded from claiming these sums is clearly unmeritorious.
in the future.”
[53] “The Respondent asked the Tribunal to take into account a number of factors,
VII. COSTS none of which really impact the Claimant's right to costs. In its reply to the
Claimant's costs submissions, the Respondent submitted that it would be fair
(….) and reasonable for the Claimant to produce documents to substantiate its
[50] “The Claimant claims costs in the sum of USD … and NZD …. claim to costs. As the bulk of the Claimant's claim for costs is the legal fees of
(….) its lawyers, there is no reason to believe that its lawyers are submitting false
numbers of the legal fees incurred and I do not see a need for the Claimant to
[51] “The Claimant cites several provisions of the KCAB Rules in support. produce the invoices of its lawyers.
Article 45 of the KCAB Rules provides that the Arbitration Costs pursuant to
the above article shall include ‘the filing fees, the administrative fees, the fees [54] “There is a component which relates to the expert's costs. I will not allow
and expenses of the arbitrators incurred during the arbitration proceedings
costs claimed for the expert's expenses and fees in relation to conducting trial
in accordance with the Regulations on Filing Fees and Administrative Fees
runs, troubleshooting and investigations. These are not costs incurred in the
(APPENDIX I) and Regulations on Arbitrators Fees and Expenses (APPENDIX II)
arbitration. Furthermore, the Claimant is being compensated for much of the
and other expenses.’
engineering and consulting work of the expert. The Claimant is entitled to a
Article 47(1) of the KCAB Rules which relates to the apportionment of the
Arbitration Costs, provides that: reasonable sum for the expert's fees of preparing his reports and attendance
at the hearing, including his travel expenses. No explanation was given of the
‘The Arbitration Costs including administrative fees shall in principle be invoices said to be issued by the expert, so I am unable to work out any specific
borne by the unsuccessful party. However, the Arbitral Tribunal, taking into allocation of his costs. I would allow the sums of … as these were the sums
account the circumstances of the case, may, at its discretion, apportion of his invoices dated … which could be surmised as invoices for work done in
each such costs between the parties.’ connection with the hearing.
Article 48 of the KCAB Rules provides that: (….)

‘The necessary costs and expenses including but not limited to attorney
[55] “With regard to … legal fees, however, I will allow a sum of … taking into account
fees and costs for experts, interpreters, witnesses incurred by a party
the following:
during the arbitration proceedings shall be borne by such party subject to
the allocation determined by the Arbitral Tribunal set forth in the Arbitral 
(a) The costs awarded should be proportionate to the amount in dispute,
Award. Unless agreed otherwise by the parties, the Arbitral Tribunal shall, although the issues and work required to be done should be considered as
taking into account the circumstances of the case, decide on allocation well.

123 124
Korean Commercial Arbitration Board

(b) The Claimant made a number of submissions in its Statement of The parties entered into a sales contract whereby the Respondent was to deliver a
Claim and Opening Statement which it did not follow through in its gelatin reclaim system to Claimant, to install the system on the Claimant’s premises,
closing arguments, for example, issues relating to the proper installation and to provide the information and documents for the Claimant to independently
of the GRS, the lack of skills of the Respondent's engineers and the run the system. The contract between the parties is a mixed contract stipulating
documentation. obligations to supply goods and to provide services. Article 3(2) of CISG clearly
provides that contracts which include an obligation to supply services alongside the
(c) The Claimant has not succeeded entirely in the quantum of its claim. delivery of the goods are excluded from the scope of application of CISG, provided
that the service obligation constitutes the preponderant part of the obligations.23)
(d) Although the Respondent's Counterclaim has not succeeded, the
Claimant was wrong to initially argue that the Respondent was not entitled The Arbitral Tribunal could first have determined whether the obligation to supply
to payment at all. The Respondent was not entitled to payment yet, but that services is a preponderant part of the obligations in this contract. Meanwhile, it
does not mean it will never be entitled to payment.” appears in this case that the preponderant part of the obligations does not consist
in the supply of services. On the other hand, an alternative option would be to sever
VIII. DECISION the services part and to have this part governed by applicable domestic law, Korean
law in this case, while applying CISG to the sales part of the contract. However, this
[56] “Accordingly I hereby award and direct in full and final determination of all option, having two laws applied to one contract, would be contrary to the ordinary
claims in this arbitration that: intent of the parties. Therefore, as long as the parties are considered to have
 concluded one contract, CISG, tailored to the international sale of goods, would apply
1. The micro-filtration system of the GRS supplied by Respondent has failed to to the whole contract with necessary adjustment to fit mixed contracts.24) Even if the
conform to the specifications of the Contract; services portion of the contract constitutes the preponderant part of the obligations,
the parties may opt into CISG which would most appropriately fit the contract. In this
2. The Respondent shall pay the Claimant damages in the sums of NZD … and
case by the parties’ opting in CISG, the contract is governed primarily by CISG and
USD …;
supplementarily by Korean law.

3. The Respondent’s counterclaims are dismissed;

4. The Respondent shall pay the Claimant’s legal fees and arbitration costs
relating to this dispute, fixed at USD … and NZD ….

Implications

I. OPTING IN CISG

In this case the parties have agreed that Korean law is the applicable law to
the dispute, and that the 1980 United Nations Convention on Contracts for the
International Sale of Goods (CISG) applies as part of Korean law. Therefore, it is 22) United Nations Commission on International Trade Law, supra note 10, at 34; Schwenzer,
supra note 10, at 117.
evident that Korean law applies to the matters not governed by CISG, and that the
23) Kröll et al., supra note 10, at, 57-58.
mandatory provisions of Korean law apply.22) 24) Schwenzer, supra note 10, at 69-70.

125 126
Korean Commercial Arbitration Board

Respondent shipped a lesser quantity of the goods, the Arbitral Tribunal, based upon
the shipping documents, first found that the Respondent shipped the quantity of the
goods for which it obtained payment from the bank by presenting the documents.
Having found that the contract stipulated the CFR term, the Arbitral Tribunal further
KCAB case no.7
held that the Respondent was responsible for loading the correct quantity of the
goods on board the vessel, and that once the goods were on board the risk of loss
Parties Claimant (Counter-Respondent): Energy Company (Korea) passed to the Claimant. Consequently, the Arbitral Tribunal denied the Claimant’s
Respondent (Counter-Claimant): Seller Company (Vietnam) claim for damages and interest.
Place of
Arbitration Seoul, Republic of Korea Excerpt
Language Original in English
I. JURISDICTION
Subject matters - applicable law
- seller’s delivery obligation [1] “Each of the Contracts contains the following arbitration agreement under
- non-conformity of goods Article 10 of its General Terms and Conditions:
- risk of loss under the CFR term  ‘Any dispute arising out of or in connection with this contract, including any
question regarding its existence, validity or termination shall be referred to
and any [sic] finally resolved by arbitration in Korea in accordance with the
Arbitration Rules of the Korea International Arbitration Centre (KIAC Rules)
Facts for the time being in force, which rules are deemed to be incorporated by
reference in this clause. This tribunal shall consist of one/three arbitrator(s)
The parties entered into a contract for the Claimant to purchase from the to be appointed by the Chairman of the KIAC.’
Respondent a quantity of goods. The goods were delivered at the delivery port. The
Claimant carried out inspections to verify the quantity of the goods shipped by the [2] “Notwithstanding the reference to ‘Korea International Arbitration Centre’ in the
Respondent, which revealed an alleged shortfall in weight compared to the certified Arbitration Agreement, the Tribunal understands the Parties to have intended
weight by the Respondent. The Claimant subsequently filed a claim with its cargo to submit this dispute to the ‘Korean Commercial Arbitration Board,’ as that
insurer. However, the insurer rejected the claim on the ground that the insurer was institution was clearly stated in paragraph 4.2 of Procedural Order No. 1 and not
not liable for the quantity never loaded on the ship. subsequently objected to by either Party.

A dispute arose between the parties regarding the quantity of the good loaded at [3] “Under Article 17(2) of the Korean Arbitration Act, an objection to the Tribunal’s
the loading port. The Claimant commenced KCAB arbitration as provided for in jurisdiction must be raised no later than the submission of the Statement of
the contract. The contract provided that the law applicable to the dispute was the Defense on the merits; and under Article 17(3), an objection that the Tribunal
law of Vietnam. The Claimant sought damages in respect of an alleged shortfall has exceeded the scope of its authority must be raised as soon as grounds for
of the goods and interest. In response, the Respondent denied any liability for the such an objection exist. Both Parties have fully participated in these proceedings
Claimant’s alleged losses. without raising any jurisdictional objections or challenges to the jurisdiction of
the Tribunal or the competence of the Sole Arbitrator. Accordingly, the Tribunal
Rejecting the Claimant’s argument, not supported by sufficient evidence, that the

127 128
Korean Commercial Arbitration Board

finds that it has been properly constituted in accordance with the Rules, and [7] “The current dispute concerns a shipment of wood pellets which was loaded
decides that it has jurisdiction over the Arbitration and is competent to decide onto the MV ST OLGA at the loading port in Vietnam between 14 August and 18
the Parties’ dispute.” August 2014. According to the ‘Certificate of Quantity by Draft Survey’ prepared
at the loading port in Vietnam by A Inspection Company, the shipment contained
II. APPLICABLE LAW a total quantity of 4,665.78 MT of wood pellets. The Parties are not in agreement
as to the accuracy of the draft survey performed by A Inspection Company.
[4] “Each of the Amended Contracts provides, in Article 10, that ‘[t]his agreement
shall be governed by and construed in accordance with the law of Vietnam, [8] “It is not disputed, however, that Respondent (i) received bills of lading from
without reference to any conflicts of law provisions.’ It is not disputed, however, the carrier in which the weight of the cargo was stated as 4,665.78 MT in the
that the transaction at issue in this Arbitration falls within the scope of freedom aggregate, and (ii) negotiated irrevocable letters of credit with the relevant bank
of contract permitted under Vietnamese law, and neither Party has alleged to receive USD 402,600 on 21 August 2014 and USD 451,237.74 on 25 August
the existence of any mandatory rule of Vietnamese law having relevance to the 2014, for a total price of USD 853,837.74. The USD 853,837.74 received by
merits of this dispute. In practice, the Tribunal has found it possible to decide Respondent assumes a total cargo of 4,665.78 MT of wood pellets at a unit price
this dispute on the basis of the Amended Contracts, and is not aware of any of USD 183/MT.
relevant issue in regard to which the application of other rules of Vietnamese
law would dictate a different outcome.” [9] “The MV ST OLGA reportedly left the port in Vietnam on 18 August 2014.
According to the Sealing Record prepared as of the same date by A Inspection
III. NON-CONFORMITY OF THE GOODS Company, all hatch covers and manholes for Hold #1 and Hold #2 had been
sealed prior to the ship’s departure. The Parties are in agreement that such
1. Contracts between the Parties seals remained intact upon arrival of the MV ST OLGA at the delivery port, and
no particular issues have been raised concerning Respondent’s compliance
[5] “[T]he Parties entered into two separate ‘Wood Pellet Sale and Purchase with the packing terms of the Amended Contracts in other respects.
Contracts.’ … Each of the Contracts provided for the sale and purchase of 3,000
metric tons … of wood pellets at a unit price of USD 173/MT, for a total price of [10] “The MV ST OLGA arrived at the delivery port, Pyeongtaek Port in Korea, on 29
USD 519,000 per Contract. Among the various terms and conditions specified August 2014, whereupon Claimant proceeded to weigh the cargo to verify the
in the Contracts, the terms pertaining to packing, shipment and delivery are of quantity of wood pellets shipped by Respondent. To that end, a series of draft
particular relevance to this dispute. Each of the Contracts initially provided for surveys was carried out at the discharge port by B Inspection Company. The
‘Packing Type: In accordance with Export standard’ and ‘Terms of delivery’ of final draft survey conducted by B Inspection Company reportedly indicated that
‘CFR KWANGYANG PORT KOREA in accordance with INCOTERMS 2010.’ a total of only 4,246.22 MT of wood pellets had been unloaded from the ship’s
cargo holds, resulting in an alleged discrepancy of 419.56 MT from the amount
[6] “Each of the Contracts was subsequently amended on 21 July 2014. Under stated in the draft survey conducted by A Inspection Company and subsequently
‘AMEND No. 1,’ the Contract dated 27 June 2014 was amended so as to increase recorded in the bills of lading (i.e., 4,665.78 MT).
the unit price to USD 183/MT for a total price of USD 549,000. The ‘Packing Type’
term was also amended to read ‘Bulk Ship In accordance with Export standard,’ [11] “The weight of the wood pellets unloaded from the cargo holds of the MV ST
and the ‘Terms of delivery’ were amended to read ‘CFR PYEONGTAEK PORT OLGA was subsequently measured by the weigh-bridge of Pyeongtaek-Dangjin
KOREA in accordance with INCOTERMS 2010.’ All other terms and conditions Port Logistics Co., Ltd., whereupon the weight was found to be only 4,203.11
remained unchanged. MT, resulting in a discrepancy of 462.67 MT from the amount stated in the draft

129 130
Korean Commercial Arbitration Board

survey conducted by A Inspection Company and recorded in the bills of lading (not [16] “At the hearing, Respondent’s counsel presented a demonstrative exhibit
to mention a discrepancy of 43.11 MT from the final draft survey carried out by B titled ‘The Process of Loading/Discharging the Wood Pellet of M/V ST. OLGA’
Inspection Company). (copies of which were provided to Claimant and the Tribunal) which included the
following explanation:
[12] “Claimant subsequently filed a claim with its cargo insurer, G Insurance According to article A4, A5 of the term CFR of Incoterm 2010. The seller
Company in the amount of USD 84,668.61, corresponding to an alleged fulfils its obligation to deliver when it hands the goods by placing them on
insufficiency of 462.67 MT. Having engaged K Insurance Adjusters Ltd. to board and the seller (Respondent) have transferred all risks of loss of or
prepare a report on the extent and possible causes of the alleged insufficiency damage to the buyer (Claimant) at point (B).
…, G Insurance Company ultimately rejected the claim on the following stated
ground: ‘Considering specific gravity of wood pellets shipped by the obligor [17] “In the accompanying illustration, the ‘point (B)’ referred to in the quoted
and area of the ship, only 4141.8 tons of pellets could have been loaded on the passage indicates a point at which the goods have already been loaded onto
corresponding ST OLGA ship. As the amount of original shipment was 4,203.11 the ship. With respect to subsequent points in time (e.g., transit to discharge
tons instead of 4,665.78 tons, the insurance company cannot make payment port, unloading of cargo, etc.), Respondent goes on to state in the same
on insurance benefit because the quantity, that never loaded on the ship is not demonstrative exhibit that ‘the seller is no obligation about all risks of loss of
subject to cargo insurance.’ or damage in this stage. That is dispute among carrier, consignee, insurer and
(….) others.’

[13] “The main claim before this Tribunal is Claimant’s claim for damages in the [18] “The foregoing submissions by Respondent are consistent with its earlier
amount of USD 84,668.61 in respect of an alleged shortfall of 462.67 MT of wood written submissions, where it had averred that it is ‘absolutely not responsible
pellets based on a unit price of USD 183 per MT, plus pre- and post-award for the cargo quantity were loaded on board when the ship left the loading port.’
interest on the claimed amount.
[19] “Claimant, by contrast, has not addressed the legal implications of the CFR
[14] “Article 22(3) of the Rules provides that ‘[e]ach party shall have the burden of term directly but has argued that ‘[e]ven if the [Respondent] actually shipped
proving the facts relied upon to support any claim, counterclaim or defense.’ accurate quantity, it violated the contract which requires an obligation to
Accordingly, Claimant bears the burden of proving the facts underlying its claim guarantee that the exact quantity arrives at the Republic of Korea.’ Thus,
for damages in this case. For the reasons set out below, the Tribunal finds that Claimant appears to be arguing in effect that Respondent bears the risk of cargo
Claimant has not satisfied its burden in this case.” loss up to the discharge port. If that is Claimant’s position, it is not supported by
the CFR term in the Amended Contracts.
2. Respondent’s Obligations under the CFR Terms in the Amended Contracts
[20] “Under the CFR term, the seller is responsible for delivering the goods on board
[15] “The first issue to be decided in regard to this claim is the nature and scope of the vessel and must pay the costs and freight necessary to bring the goods to
Respondent’s relevant delivery obligations under the Amended Contracts. the named port of destination. However, once the goods are on board the vessel,
Each of the Amended Contracts contained the following delivery term: ‘CFR the risk of loss or damage to the goods passes to the buyer. In other words, the
PYEONGTAEK PORT KOREA in accordance with INCOTERMS 2010.’ It is a seller’s obligation under a CFR term is to ship goods of the agreed type and
matter of common knowledge that ‘CFR’ under INCOTERMS 2010 stands for quantity; the seller is not responsible for ensuring that the goods so shipped
‘Cost and Freight (named port of destination).’ The existence or validity of the arrive at the delivery port in the same condition and quantity.
CFR delivery term in this case is not disputed by either Party.

131 132
Korean Commercial Arbitration Board

[21] “In view of the foregoing, the Tribunal finds that, under the operative CFR [25] “The cargo quantities listed in the bills of lading, commercial invoices and
delivery term in the Amended Contracts, Respondent was responsible for packing lists were based on the draft survey results taken at the loading port by
loading the proper quantity of wood pellets – i.e., the quantity for which it was A Inspection Company. The various draft survey records submitted into evidence
paid – on board the MV ST OLGA. The risk of any loss or damage occurring bear all required signatures including that of the Master/Chief Officer of the MV
thereafter must be borne by Claimant.” ST OLGA … and consistently evidence that 4,665.78 MT of wood pellets were
shipped.
3. Whether Respondent Shipped the Quantity of Wood Pellets for Which It Was
Paid [26] “On the basis of the bills of lading (and other required shipping documents
including commercial invoices and packing lists), Respondent negotiated
[22] “The second issue to be decided is whether evidence from the loading port – i.e., irrevocable letter of credit no. M07M81407NU00025 in the amount of USD
the bills of lading and related shipping documents – indicates that Respondent 451,237.74, and irrevocable letter of credit no. M07M81407NU00018 in the
shipped the quantity of wood pellets for which it was paid. amount of USD 402,600.00, for total payment of USD 853,837.74. As Claimant
has acknowledged in the Request for Arbitration, the foregoing documents
[23] “It should first be noted that the present dispute concerns the quantity of wood evidence that a total of 4,665.78 MT of wood pellets were shipped against a
pellets shipped by Respondent. It has not been suggested that the wood pellets purchase price of USD 853,837.74.
failed to comply with the requirements of the Amended Contracts other than
in quantity. Accordingly, the outcome of the present dispute necessarily turns [27] “While Claimant contests the accuracy of the results of the draft survey
on the question of whether Respondent shipped the quantity of wood pellets conducted by A Inspection Company on the basis that such results allegedly
for which it received payment – i.e., 4,665.78 MT – irrespective of the quantity of conflict with draft survey results taken at the discharge port, Claimant does not
wood pellets that was ultimately unloaded at the discharge port. appear to dispute the fact that the draft survey results reported by A Inspection
Company, as well as the bills of lading, commercial invoices, and packing lists
[24] “Under the payment terms set out in the Contracts, payment to Respondent tendered by Respondent in exchange for payment, all indicate that Respondent
was to be made against presentation of certain documents including ‘clean shipped 4,665.78 MT of wood pellets.
on board’ bills of lading marked ‘Freight Prepaid,’ commercial invoices,
packing lists, certificates of fumigation, certificates of origin, and certificates of [28] “Claimant has not established that any of the foregoing documents fail to
phytosanitary. Among these, the following key shipping documents have been conform to any applicable requirements of form or content. Rather, Claimant
submitted into evidence in this Arbitration: (i) Bill of Lading no. STOG-RQPT01, merely alleges that ‘the initial draft survey at loading port had something
Commercial Invoice No. 11082014, and Packing List No. 11082014, each of wrong due to the unknown reason.’ In the view of the Tribunal, such vague and
which indicates a quantity of wood pellets of 2,465.78 MT, and (ii) Bill of Lading unsubstantiated allegations do not constitute sufficient grounds for rejecting the
no. STOG-RQPT02, Commercial Invoice No. 12082014, and Packing List No. validity of the shipping documents – i.e., bills of lading, commercial invoices and
12082014, each of which indicates a quantity of wood pellets of 2,200 MT. When packing lists – and the underlying draft survey records, all of which (i) appear
the figures in the two sets of shipping documents are combined, they amount to have been prepared in the ordinary course of business, (ii) comply with
to a total quantity of 4,665.78 MT of wood pellets. It is undisputed that these applicable requirements of form and content, and (iii) are clear and consistent
basic shipping documents all indicate that a total quantity of 4,665.78 MT of on their face.
wood pellets was, in fact, shipped. Furthermore, as noted by Respondent, both
of the bills of lading contained the notation ‘clean on board,’ indicating that no [29] “In light of the foregoing considerations, the Tribunal accepts that the shipping
irregularities had been identified in the cargo by the carrier. documents clearly and consistently indicate that Respondent shipped 4,665.78

133 134
Korean Commercial Arbitration Board

MT of wood pellets, which is the quantity for which it was paid. On that basis, cargo holds, resulting in a discrepancy of 419.56 MT from the results of the
the Tribunal finds, as a prima facie matter, that Respondent has satisfied its draft survey conducted by A Inspection Company and subsequently recorded
obligations under the operative CFR deliver term by shipping the quantity of in the bills of lading (i.e., 4,665.78 MT). Thereafter, the wood pellets unloaded
wood pellets for which it was paid.” from the cargo holds of the MV ST OLGA were weighed by the weigh-bridge of
Pyeongtaek-Dangjin Port Logistics Co., Ltd. According to Claimant, the weight
4. Whether Evidence from the Discharge Port Proves that Respondent Actually was found to be only 4,203.11 MT, resulting in a discrepancy of 462.67 MT
Shipped a Lesser Quantity of Wood Pellets from the results of the draft survey conducted by A Inspection Company and
subsequently recorded in the bills of lading.
[30] “Notwithstanding the foregoing, Claimant has alleged that a lesser quantity
of wood pellets was actually received at the discharge port. Thus, a third [34] “To be sure, the foregoing allegations are troubling, and the Tribunal has no
issue to be decided in regard to this claim is whether the evidence from the particular reason to doubt that some extent of shortfall could have occurred.
discharge port on which Claimant’s allegations rest is sufficient to overcome Claimant has not, however, established that the claimed shortfall – in the
the Tribunal’s prima facie finding that Respondent shipped the quantity of wood amount of 462.67 MT – actually occurred. On the contrary, the final draft
pellets for which it was paid. survey conducted by B Inspection Company indicated a shortfall of only 419.56
MT, a discrepancy of 43.11 MT from the weigh-bridge results. In view of this
[31] “As a preliminary matter, the Tribunal has already decided above that under the inconsistency between the final draft survey and the weigh bridge results, the
CFR terms in the Amended Contracts, Claimant bears the risk of any loss of or Tribunal can only conclude that the extent of shortfall, if any, is unproven.
damage to the cargo after it is on board the shipping vessel. Hence, to the extent
that the bills of lading and other shipping documents establish that the correct [35] “There are other problems with Claimant’s evidence. First, the ‘Certificate of
quantity of cargo was placed on board the vessel, there is arguably no need in Weighing Results’ issued by B Inspection Company as of 29 August 2014 was
this case to examine evidence relating to events occurring after the MV ST OLGA not certified by the MCO of the MV ST OLGA on behalf of the carrier. In this
left the loading port in Vietnam since Claimant, as buyer, would ultimately be regard, Respondent has argued that the results of the weigh-bridge process
responsible for any cargo shortfall identified at the discharge port. cannot be accepted because they were conducted unilaterally by Claimant,
without the involvement of any witness or supervision from the carrier’s
[32] “Nevertheless, certain of Claimant’s allegations could, if proven, potentially side. While certain related documents, including the operation daily report,
call into question the Tribunal’s prima facie finding that Respondent shipped convention and voucher, were apparently signed by the MCO, none of these is
the quantity of wood pellets for which it was paid. Accordingly, the Tribunal an official certificate. Nor is it clear what facts are being certified by the MCO in
has carefully considered the evidence presented in support of Claimant’s these documents as each contains handwritten notes stating that ‘1. Ship not
allegations, and has briefly summarized its findings in regard to such evidence responsible for Qtty of cargo. 2. Cargo delivered in seal holds and discharged in
below. Ultimately, the Tribunal has found the evidence presented by Claimant full. 3. Cargo absolutely is empty in holds.’
to be insufficient to prove that Respondent actually shipped a lesser quantity of
wood pellets than the quantity for which it was paid.” [36] “There is also reason to doubt the reliability as evidence of the draft survey
5. Claimant’s Allegations of Cargo Shortfall at the Discharge Port results obtained by B Inspection Company at the discharging port. First, the
Draft Survey Report issued by B Inspection Company as of 29 August 2014 is
[33] “As explained in paragraphs … above, Claimant alleges that the final draft not signed or certified by the MCO. Furthermore, according to the K Insurance
survey conducted at the discharge port by B Inspection Company found that Adjusters Ltd.’s Report …, B Inspection Company performed the draft survey
a total of only 4,246.22 MT of wood pellets had been unloaded from the ship’s twice, first at 0400 on 30 August 2014 and again at 0530 the same day ‘after

135 136
Korean Commercial Arbitration Board

adjust[ing] the ship’s trim from 3.45 meters to 2.08 to obtain more accurate Insurance Adjusters Ltd.’s calculations are based in part on the draft survey
figure’ …. While Claimant confirms that the draft survey was performed twice, results taken at the discharge port. In light of the problems with that evidence
there does not appear to be any evidence in the record concerning the results discussed above, the Tribunal cannot accept K Insurance Adjusters Ltd.’s
of the draft survey performed at 0400 on 30 August 2014. It is not clear whether finding as conclusive.
the results of that draft survey differed from the subsequent draft survey and,
if so, to what extent. In any event, as the report of the draft survey performed [41] “Second, Claimant alleges that photos of the cargo taken at the loading port
at 0530 on 30 August 2014 does not contain the MCO’s signature, its reliability and discharge port indicate ‘no quantity change during shipping,’ and on that
as evidence is questionable. By contrast, the draft survey results taken by A basis endorses K Insurance Adjusters Ltd.’s earlier conclusion that ‘the initial
Inspection Company at the loading port appear to have been certified by the draft survey at loading port had something wrong due to the unknown reason.’
MCO without comment or exception. However, the Tribunal does not find this photographic evidence to be conclusive
on any relevant point. In particular, the Tribunal does not believe that the
[37] “Therefore, the Tribunal finds that the evidence pertaining to the weigh- photographs in evidence depict the quantity of wood pellets contained in the
bridge and draft survey results at the discharge port is inconclusive and does holds at the loading port and discharge port in sufficient detail as to be capable
not provide a sound and sufficient basis for disregarding the cargo quantity of proving that there was ‘no quantity change during shipping.’
indicated in the shipping documents, which were based on the certified draft
survey results taken at the loading port. [42] “Third, Claimant argues that the quantity of wood pellets that Respondent
claims to have shipped is more than the MV ST OLGA could have carried in
[38] “Furthermore, in light of the manifest inconsistencies between the weigh- light of the alleged ‘stowage factor’ of the wood pellets in question. It will be
bridge and draft survey results at the discharge port, the Tribunal must recalled, in this connection, that G Insurance Company’s rejection of Claimant’s
conclude that even if a cargo shortfall of some magnitude existed, Claimant has insurance claim was reportedly based on the same theory:
not proven the extent of such shortfall. That is an entirely separate reason why Considering specific gravity of wood pellets shipped by the obligor and
the Claimant’s claim for damages cannot be accepted.” area of the ship, only 4141.8 tons of pellets could have been loaded on
the corresponding ST OLGA ship. As the amount of original shipment was
6. Alleged “Suspicion” regarding the Draft Survey at Loading Port 4,203.11 tons instead of 4,665.78 tons, the insurance company cannot make
payment on insurance benefit because the quantity, that never loaded on
[39] “Claimant has also raised various issues and allegations concerning the draft the ship is not subject to cargo insurance.
survey performed by A Inspection Company at the loading port. Certain of these
allegations and the evidence presented in support of them are briefly addressed [43] “It should first be noted that the insurer’s conclusion that the MV ST OLGA
below. could only have held 4,141.8 tons of pellets appears to be based on a number of
assumptions, including that the stowage factor of the wood pellets as shipped
[40] “First, Claimant points to a finding set out in the K Insurance Adjusters Ltd. was actually 1.5, and that their specific gravity was actually 0.6. Neither of these
Report to the effect that the ballast condition of the draft surveys taken at the assumptions has been proven. More importantly, the insurer’s conclusion is
loading and discharge ports differed by approximately 455 tons, which is similar contradicted by the results of the weigh-bridge survey, which found that 4,203.11
to the amount of cargo shortfall being claimed by Claimant in this Arbitration, MT of wood pellets had been unloaded from the MV ST OLGA, not to mention
and endorses the opinion of K Insurance Adjusters Ltd. that ‘this discrepancy the results of the draft survey taken by B Inspection Company, which found
would be too much high to be considered as human error.’ While the alleged that 4,246.22 MT of wood pellets had been unloaded from the ship. If either of
similarity in figures is superficially intriguing, it must be emphasized that K those figures is accurate – and it appears that K Insurance Adjusters Ltd. (the

137 138
Korean Commercial Arbitration Board

insurer’s appointed insurance adjuster) accepts the validity of the weigh-bridge which has been challenged by Claimant.
survey’s findings at the very least – then the insurer’s conclusion that only 4,148.8
tons of pellets could have been loaded on the MV ST OLGA is necessarily wrong. [47] “The Tribunal agrees with Claimant that the survey report prepared by A
Inspection Company would, if accepted, constitute ‘important evidence’ that
[44] “Notwithstanding the foregoing, Claimant argues that the ‘general stowage the quantity of wood pellets that Respondent claims to have shipped – 4,665.78
factor of wood pellet is 1.6 to 1.8,’ and that the stowage factor of the wood MT – could actually have been loaded on the MV ST OLGA. For that reason, the
pellets at issue in this dispute was approximately 1.6. According to Claimant, Tribunal also finds it curious that Respondent did not seek to rely on it before
this means that the MV ST OLGA – which has a grain capacity of 6,903CBM – submitting it into evidence with its submission dated 9 January 2015. On the
could not possibly have held the quantity of wood pellets, 4,665.78 MT, which other hand, there could be any number of legitimate reasons why Respondent
Respondent claims to have shipped. In support of its argument, Claimant failed to rely on the A Inspection Company survey report prior to the start of
relies on various data including the K Insurance Adjusters Ltd.’s Report and this Arbitration. In light of that fact, the Tribunal is not prepared to conclude,
a Certificate of Analysis from Analysis Company, in which the stowage factor based on the timing of Respondent’s reliance on the survey report alone, that
of a wood pellet sample was found to be 1.64. While the Analysis Company the A Inspection Company survey report lacks credibility as evidence. Rather, in
Certificate of Analysis states that the sample was from ‘August 2014,’ no other the absence of credible reasons to believe that the report itself is a fabrication,
information is available concerning the source of the sample or the sampling materially inaccurate or otherwise deficient – and no such reasons have
methodology. In the view of the Tribunal, these omissions reduce the evidentiary been presented by Claimant – the Tribunal is of the view that the A Inspection
value of the Analysis Company Certificate of Analysis. Company survey report and the findings stated therein deserve to be accepted
at face value. Accordingly, the Tribunal does not accept Claimant’s argument
[45] “By contrast, Respondent has put forward a letter dated 24 December 2014 that 4,665.78 MT of wood pellets could not have been loaded on the MV ST
from the shipping company, A Shipping Company Pte., Ltd., stating that the OLGA.
storage factor of the wood pellets at issue here was 1.3~1.4. Respondent also
relies on the record of a survey allegedly conducted by A Inspection Company [48] “As to Claimant’s suggestion that the A Inspection Company survey report
on or around 11 August 2014. According to that survey, which was reportedly ‘cannot be effective as an evidence’ because A Inspection Company has
conducted by means of random sampling of the wood pellets to be shipped to accepted responsibility for damage to Respondent resulting from its draft
Claimant, the stowage factor of the wood pellets at issue was found to be 1.47. survey, the Tribunal would only note that the same logic could easily be applied
to the K Insurance Adjusters Ltd.’s Report, on which Claimant has relied
[46] “Claimant admits that if the stowage factor of the wood pellets at issue was 1.47, for various purposes in this Arbitration. After all, the K Insurance Adjusters
‘this would be the important evidence to determine that 4665ton of wood pellet Ltd.’s Report was reportedly prepared at the request of Claimant’s insurer, G
can be loaded on ST OLGA.’ However, Claimant argues that the A Inspection Insurance Company, which is the party against whom cargo insurance claims
Company survey report cannot be accepted as credible evidence because it have already been filed by Claimant, and to whom Claimant will presumably
was allegedly never relied upon by Respondent until it was submitted into look again for satisfaction to the extent that its claims against Respondent
the record of this Arbitration with Respondent’s Amendment to Self-Defense in this Arbitration do not succeed. In the circumstances, the Tribunal is not
Statement for Arbitration dated 9 January 2015. In light of the relatively late prepared to draw the conclusions suggested by Claimant regarding the motives
appearance of this document, Claimant suggests that it was ‘just made up underlying the A Inspection Company survey report.
retroactively.’ Furthermore, Claimant denies the credibility of the survey report
on the basis that A Inspection Company had, in a separate document, agreed to
be responsible for its own draft survey figure and calculation, the accuracy of

139 140
Korean Commercial Arbitration Board

[49] “In short, the Tribunal does not find the various allegations and evidence [53] “The Rules define ‘arbitration costs’ to include ‘filing fees, the administrative
presented by Claimant25) under the heading “Suspicion of the draft survey at fees [and] the fees and expenses of the arbitrators incurred during the
loading port” to be sufficiently credible and compelling as to overcome the arbitration proceedings…’ (‘Arbitration Costs’). Under Article 48 of the Rules, the
Tribunal’s earlier findings based on the shipping documents.” Tribunal also has full discretion to apportion the costs of ‘other necessary costs
and expenses’ (such as fees for attorneys and interpreters) between the Parties.
7. Tribunal’s Conclusion
[54] “As Claimant commenced this Arbitration but has not succeeded in proving its
[50] “For the reasons set out above, the Tribunal finds that the evidence presented claims, the Tribunal is of the view that the Arbitration Costs should be borne by
by Claimant in support of its allegations of a shortfall at the destination port is Claimant.
inconclusive and/or insufficient to prove that Respondent actually shipped a However, with regard to all other ‘necessary costs and expenses’ incurred by
lesser quantity of wood pellets than the quantity for which it was paid. Thus, the the Parties in connection with this Arbitration, the Tribunal is of the view that
Tribunal remains of the view that the shipping documents – namely, the bills each Party should bear its own costs.”
of lading, commercial invoices and packing lists – constitute the most reliable
evidence of what was actually shipped in this case. That evidence clearly and Implications
consistently indicates that Respondent shipped 4,665.78 MT of wood pellets,
which is the quantity for which it received payment. Claimant has not proven I. EXCLUSION OF THE CONFLICT OF LAWS RULES
otherwise.

The contract between the parties stipulates that “[t]his agreement shall be governed
[51] “Accordingly, Claimant’s claim for damages in the amount of USD 84,668.61 is
by and construed in accordance with the law of Vietnam, without reference to any
hereby dismissed.
conflicts of law provisions.” The purpose of the parties appears to designate the
In light of the foregoing, the final two issues to be decided by the Tribunal in
applicable law as Vietnamese law, ruling out any possibility that the choice of the
regard to this claim – whether Claimant has proven the quantum of damages
applicable law may be affected by reference to a conflict of laws rule. However,
claimed and whether Claimant is entitled to pre- or post-award interest thereon
the Korean court has held that the private international law, which determines
– have become moot.”
the applicable law to legal relationships including a foreign element, cannot be
derogated by the parties’ agreement (see Seoul Administrative Court Decision No.
IV. COSTS
2007Guhap26322 dated June 19, 2008). It remains to be seen in arbitration whether
the conflict of laws rules can be excluded by the parties’ agreement.
(….)
[52] “Under Article 47(1) of the Rules, arbitration costs, including administrative II. BURDEN OF PROOF
fees, are to be borne by the unsuccessful party in principle. However, the
One of the issues decided by the Arbitral Tribunal is whether the Respondent
Tribunal retains discretion to apportion the costs between the Parties as it sees
shipped the quantity of the goods for which it obtained payment from the bank. In
fit, taking into account all circumstances of the case.
doing so, the Arbitral Tribunal could have clarified which party carries the burden of
proof in this respect. The Arbitral Tribunal holds that “neither Party has alleged the
existence of any mandatory rule of Vietnamese law having relevance to the merits
of this dispute,” and that “the Tribunal has found it possible to decide this dispute on
25) The arbitral award states “Respondent,” but this appears to be a clerical error for the basis of the Amended Contracts, and is not aware of any relevant issue in regard
“Claimant.”

141 142
Korean Commercial Arbitration Board

to which the application of other rules of Vietnamese law would dictate a different
outcome.”

It is necessary to identify the applicable law to the burden of proof. In general,


KCAB case no.8
the law governing the contract applies with respect to the burden of proof. For
example, Article 18 of Rome I Regulation provides that “[t]he law governing a
Parties Claimant (Counter-Respondent): Engineering Company (Korea)
contractual obligation under this Regulation shall apply to the extent that, in
Respondent (Counter-Claimant): Manufacturer (Italy)
matters of contractual obligations, it contains rules which raise presumptions of
law or determine the burden of proof.” The burden of proof is to be decided by the Place of
applicable law to the substance. The parties expressly chose Vietnamese law as Arbitration Seoul, Republic of Korea
the applicable law in this case. The Arbitral Tribunal therefore could have reviewed
Language Original in English
Vietnamese law in regard to the burden of proof.
Subject matters - applicable law
- opting in CISG
- jurisdiction
- non-conformity of goods
- fitness for a particular purpose
- public law standards
- consequences of seller’s knowledge of defects
- fundamental breach
- notice requirement
- duty to mitigate damages

Facts

The parties entered into a contract for the Respondent to purchase from the
Claimant a quantity of goods. The Respondent also contracted to purchase from
the Claimant a quantity of another goods. The goods under the first contract were
delivered to the Respondent which found the delivered goods were materially
different from the goods it ordered. Respondent informed the Claimant of the
alleged non-conformity. Various inspections and tests were carried out. The goods
under the second contract were delivered in four shipments. Following the issuance
of several inspection or test reports, the Respondent gave notice of termination for
the first and second contracts. Furthermore, the Respondent filed an application
seeking attachment of the bills of exchange issued in favor of the Claimant to the

143 144
Korean Commercial Arbitration Board

Italian court of first instance which seized the four bills. Again the Respondent gave breach thereof, shall be finally settled by arbitration in Seoul in accordance
the second notice of termination for the second contract. An independent expert, with the Arbitration Rules of the Korean Commercial Arbitration Board.’
appointed by the court in accordance with the Respondent’s request, conducted an
inspection and issued a report on the defects of the goods. The Claimant challenged [2] “The Parties agree that the substantive contract is governed by the United
the court’s jurisdiction over the second contract relying on the arbitration clause Nations Convention on Contracts for the International Sale of Goods (CISG). The
stipulated therein. Tribunal understands that the Parties are in agreement that, to the extent that
the CISG does not address an issue, the law of the substantive contract shall be
The Claimant initiated arbitration relying on the arbitration clause contained in governed by the laws of the Republic of Korea pursuant to Article 10 of the Sales
the second contract which provided for KCAB arbitration. The parties agreed that Contract.
the dispute was governed by the United Nations Convention on Contracts for the (….)
International Sale of Goods (CISG) and matters not governed by CISG were governed
by Korean law. The Claimant sought an amount in payment for the bills of lading, [3] “… [T]he Tribunal notes that both Parties’ pleadings refer to case law of various
interest and costs and expenses of the arbitration. The Respondent objected that the jurisdictions other than the Republic of Korea (e.g., Germany and Switzerland).
Claimant’s delivery of the non-conforming goods amounted to a fundamental breach As stated above …, however, it has been agreed between the Parties that the
of contract. The Respondent also counterclaimed its deposit allegedly paid under the substantive laws to be applied are the CISG and, where appropriate, Korean law.
first contract and damages resulting from the Claimant’s breach. As the Parties have failed to establish the relevance of case law that fall outside
the applicable scope, the Tribunal has not given weight to such jurisprudence.”
The Arbitral Tribunal found that the Claimant had committed a fundamental breach
of the second contract by delivering non-conforming goods, and that the Respondent II. JURISDICTION OF THE ARBITRAL TRIBUNAL
gave notice thereof in accordance with CISG. Therefore, the Arbitral Tribunal denied
the claim by the Claimant for purchase price and interest. The Arbitral Tribunal 1. Sales Contracts between the Parties
denied the counterclaim filed by the Respondent. In particular, the Arbitral Tribunal
held that it had no jurisdiction over the Respondent’s counterclaim to recover the [4] “… [P]rior to the Claimant’s involvement, the Respondent had an agreement
deposit under the first contract. Also the Arbitral Tribunal held that the Respondent with Trading Company A whereby Trading Company A would supply 2,080
failed to satisfy its burden of proof in respect of damages resulting from the metric tons (MT) of electrolytic tin plate (ETP) and tin free steel (TFS) to the
Claimant’s breach. Respondent for a total of USD 2,048,550.00. From 24 January 2014 through 6
March 2014, the Respondent paid a total of USD 204,855.00 to Trading Company
Excerpt A as a 10% advance deposit.

I. APPLICABLE LAW [5] “Trading Company A's tin materials were to be purchased from Steel Company
A. However, it is understood that the deal between the Respondent and Trading
[1] “This arbitration is brought under the dispute resolution and arbitration clause Company A was cut short when certain restrictions imposed by Steel Company
contained in the Sales Contract dated 14 May 2014 between Claimant and A against Trading Company A effectively made it commercially impossible
Respondent (Sales Contract). Article 8 of the Sales Contract states as follows: or impractical for Trading Company A to supply the tin materials to the
‘All disputes, controversies, or differences which may arise between the Respondent.
Parties, out of or in relation to or in connection with this Contract, or for the

145 146
Korean Commercial Arbitration Board

[6] “Due to these restrictions, the Respondent became in need of another supplier. [10] “As an initial matter, the Tribunal notes that the Parties' submissions do not
The Parties were acquainted through a broker by the name of Mr. B and entered clearly indicate their respective positions in respect of the law governing
into an arrangement whereby the Claimant would supply quantities of ETP and the arbitration agreement stipulated in the Sales Contract. The Tribunal
TFS to the Respondent. understands the Respondent's position to be that Korean law applies and that
the Claimant has not disputed this.
[7] “… [T]he Parties entered into (1) a contract dated 14 May 2014 for the sale and
purchase of 208 MT of ETP by way of pro forma invoice … in consideration of [11] “… [T]he Parties have chosen the law of the Republic of Korea to govern the
USD 204,855.00 (representing the 10% deposit the Respondent originally paid substance of their dispute pursuant to Article 10 of the Sales Contract and have
to Trading Company A, which would transfer the amount to the Claimant), plus designated Seoul as the seat of the arbitration pursuant to Article 8. Therefore,
any balance amount (First Contract); and (2) the Sales Contract – which was the law applicable to determine the scope of the arbitration agreement
entered for the sale and purchase of 500 MT of ETP and 400 MT of TFS (the contained in the Sales Contract should be the law of the Republic of Korea.
Goods) in consideration of USD ….”
[12] “In this connection, the Respondent seeks support of its position from the
2. Objection to Jurisdiction over the First Contract Korean Supreme Court’s judgment in Case No. 99Da13577. Specifically, the
Respondent directs the Tribunal to the following passage:
[8] “The Claimant objects to the Tribunal’s jurisdiction over the dispute arising ‘The arbitration agreement applies not only to the contract in which the
from the First Contract. The Claimant asserts that the KCAB does not have arbitration clause is written, but also to disputes directly related to or
jurisdiction over such dispute as it contains no arbitration clause and that closely related to formation, performance, and validity of the contract.’
the arbitration clause under Article 8 of the Sales Contract does not extend
its scope to disputes under the First Contract because there is no factual or [13] “On this basis, the Respondent submits that it is clear from the Supreme
legal connection between the two agreements. The Claimant argues that the Court's ruling that under Korean law ‘an arbitration clause is interpreted to
similarities in names, execution date and purpose of the two agreements are apply to a broader range of disputes in relation to the contract, and not limited
mere coincidence and bear no legal significance. to disputes strictly arising from the contract itself.’

[9] “The Respondent asserts that the language of the arbitration clause in the [14] “The Tribunal has difficulty reaching the same conclusion. On reading the above
Sales Contract is very broad, and that its wide coverage was meant to apply excerpt, the scope of the arbitration agreement in that context simply dealt with
to not only disputes arising directly from the Sales Contract, but also to any the ‘formation, performance, and validity of the contract.’ This is distinguishable
disputes arising in relation thereto or in connection therewith. The Respondent from the present case, which concerns whether the arbitration agreement
thus contends that the arbitration clause under Article 8 of the Sales Contract extends to a transaction arising out of a separate contract.
applies to the First Contract. The Respondent asserts that it was the Parties’
intention to subject the First Contract to the general terms of the Sales [15] “The Parties have not advanced further Korean law in respect of this issue.
Contract. Highlighting that the names of the invoices are almost identical, that The Tribunal notes that the Respondent has advanced English case law, but
they were entered into on the same day and that the purpose of the agreements analysis thereof is limited and, more importantly, their relevance has not been
were the same, the Respondent contends that the First Contract does not established.
contain an arbitration clause because it was already well provided in the Sales
Contract, and that the two agreements were intended to be read together. [16] “Against that background, the Tribunal has carefully examined the arbitration
clause set out in Article 8 of the Sales Contract, which in pertinent part reads, ‘[a]

147 148
Korean Commercial Arbitration Board

ll disputes, controversies, or differences which may arise between the Parties, III. NON-CONFORMITY OF THE GOODS
out of or in relation to or in connection with this Contract . . . .’ (emphasis
added). Based on a plain and ordinary reading of the clause, the starting point 1. Specificity Requirement of Notice
in determining the scope of the arbitration agreement is therefore the Sales
Contract. [21] “The Claimant asserts that the Respondent breached the Sales Contract by
way of failing to make payment for the 900 MT of ETP and TFS delivered to the
[17] “As such, matters relating to the 900 MT of tin materials under the Sales Respondent pursuant to the Sales Contract. The Respondent disagrees, arguing
Contract naturally fall within the scope of the arbitration agreement. Based on that non-payment was justified as the Goods were not in conformity with the
the arguments and evidence advanced by the Parties, however, the Tribunal specifications stipulated in the Sales Contract.
is not convinced that the same can be said for a separate quantity of similar
goods under a different contract (i.e., the First Contract). Although the Tribunal [22] “It is undisputed that the Goods were actually delivered to the Respondent, that
appreciates that the two agreements bear similar names as well as the same they were not in accordance with the agreed specifications and that payment
execution date and serve similar purposes, it is of the view that this is not was refused by the Respondent. However, the Parties do dispute as to whether
dispositive of the issue – especially so because no relevant jurisprudence in this the standard of sample testing adopted by … (CBL) – a company which was
regard has been established by the Respondent. tasked to verify the conformity of goods – and the court-appointed expert, Mr.
E, were objective and reliable and whether the right standard that should have
[18] “Further, the Tribunal is not convinced by the Respondent's argument that the been adopted was the European Standard, EN 10202.
general terms, including the arbitration clause, of the Sales Contract should
be implied into the First Contract. If the Parties intended the arbitration clause [23] “In light of the above, the Tribunal understands that the main issues in dispute
to also apply to the First Contract, it could have easily said so, for example, by are whether the Respondent gave sufficient notice in respect of the defects and
way of incorporation by reference. In this connection, the Tribunal notes that the whether such defects amounted to a fundamental breach.
Respondent has not advanced any jurisprudence in support of its implied term (….)
argument.

[24] “The Claimant submits that the Respondent failed to comply with the notice
[19] “In light of the above, the Tribunal finds that it lacks jurisdiction over the Parties' requirements set out in Article 39(1) of the CISG. The Claimant asserts that
dispute arising from the First Contract. the Respondent was required to provide notice specifying the nature of the
non-conformity within a reasonable time of discovery. Further, the Claimant
[20] “The Tribunal notes that the parties have advanced further arguments in contends that, if more than one type of non-conformity or defect is found, the
respect of the First Contract (e.g., the validity of the contract, the Claimant's role Respondent was required to duly notify the Claimant of each non-conformity or
thereunder and damages suffered). For the aforementioned reasons, however, defect.
the Tribunal leaves these issues to be dealt with by the appropriate authorities.
Accordingly, all claims and/or counterclaims arising out of the First Contract [25] “In addition, the Claimant argues that the First Termination Letter and the
are dismissed without prejudice. Second Termination Letter were deficient. With respect to the First Termination
Letter, the Claimant asserts that it did not specifically indicate the shipment
which contained the non-conforming products and that there was no mention
of the delivery date in the Respondent’s notice. In addition, the Claimant asserts

149 150
Korean Commercial Arbitration Board

that while three types of ETP (Type A, B, and C) were delivered under the Sales participated in the examination of the goods.
Contract, only Type A was specified in the First Termination Letter. Type A, the
Claimant says, was delivered in two shipments under the Sales Contract alone. [31] “The Respondent contends that, given the Claimant’s participation in multiple
The Claimant asserts that in the circumstances, it believed that the Respondent tests of the goods and having been provided with multiple notices of the goods'
had accepted the other two types of ETP that had been delivered. non-conformity, it was impossible for the Claimant to not have been unaware
of the non-conformity of the ETP and TFS delivered. The Respondent asserts
[26] “As to the Second Termination Letter, the Claimant contends that the that the Claimant was aware of the non-conformity by 30 September 2014 at the
Respondent did not specifically indicate which packages of TFS were affected latest, when Mr. CW2 [a representative of the Claimant’s company] emailed Mr.
by oxidation. The Claimant argues that, because the type of TFS specified in B acknowledging the defects in the products delivered pursuant to the Sales
the Second Termination Letter were delivered in two shipments, with each Contract.
shipment consisting of more than twenty packages, it was difficult for the (….)
Claimant to identify the defective packages.
[32] “Having duly considered the Parties' arguments, the Tribunal is of the view that
[27] “In addition, the Claimant contends that the Second Termination Letter did the Respondent did give sufficient notice as to the non-conformity of the goods.
not specify the extent of oxidation that was detected on the TFS. The Claimant
argues that it could not have been aware of the defects, as no personnel from [33] “Article 39(1) of the CISG prescribes that ‘[t]he buyer loses the right to rely on a
the Claimant participated in the examination of TFS, and as the Claimant was lack of conformity of the goods if he does not give notice to the seller specifying
not provided information regarding the methods used for TFS sampling. The the nature of the lack of conformity within a reasonable time after he has
Claimant contends that the Respondent, as a manufacturer of fabricated metal discovered it or ought to have discovered it.’
products and an expert on ETP and TFS, was in a position to provide more
information but failed to do so. [34] “The Tribunal finds that the Respondent gave sufficient notice as to the non-
conformity observed in the three types of ETP as well as TFS Type E by way of
[28] “The Claimant thus submits that the Respondent has forfeited its right to rely the Respondent's First and Second Termination Letter and, effectively, through
on the defects of the unspecified ETP and the entire TFS. the various inspections and tests conducted in relation to those goods. The
(….) notice required under Article 39(1) is as to the ‘nature’ of the non-conformity for
which the reasons discussed below were identified.
[29] “The Respondent denies the Claimant’s assertion that the Respondent’s notice
of non-conformity did not satisfy the requirements set out in Article 39(1) of the [35] “On 22 August 2014, Dr. C of CBL performed the verification process for the
CISG. three types of ETP under the Sales Contract at the Respondent’s plant. As
recorded in the CBL Operation Report dated 22 August 2014, Mr. B, Mr. CW2,
[30] “The Respondent relies on Article 40 of the CISG which provides that ‘the and Dr. RR (the Respondent’s representative) were present for the sampling
seller is not entitled to rely on the provisions of Articles 38 and 39 if the lack of process. The report states that Mr. CW2, after checking that all packages and
conformity relates to facts of which he knew or could not have been unaware seals were intact, personally selected one package from each specification of
and which he did not disclose to the buyer.’ The Respondent submits that the products as samples to be assessed. As recorded in the Operation Report dated
Claimant knew or could not have been unaware of the defects in both ETP 23 August 2014, the same individuals underwent a similar process for the three
and TFS. The Respondent asserts that the Claimant must have been exactly types of ETP that arrived at the Dome Box.
aware of the non-conformity as a representative of the Claimant personally

151 152
Korean Commercial Arbitration Board

[36] “On 28 August 2014, Dr. C conducted tests on the ETP samples collected. defect) is required.
The test was performed at CBL in the presence of Mr. CW2 and Mr. B. On the
same day, Dr. C issued his report, which concluded that ‘no tinplate sample [43] “In view of the above, the Tribunal finds that the Respondent provided sufficient
is compliant … with the contract and the labels glued on each page,’ and that notice as to the non-conformity of the goods pursuant to Article 39(1) of the
the ‘entire consignment … is not suitable to be used for tomato products.’ It is CISG.”
significant to note that all parties confirmed the contents of the report, which as
recorded therein was ‘Read and Accepted’ by among others Mr. CW2. 2. Fundamental Breach

[37] “The Tribunal further notes that the Claimant in its Post-Hearing Brief asserts (….)
that Mr. CW2 was forced to sign off on the Operation Reports as well as the test [44] “The Claimant submits that it has not committed a fundamental breach of
results of 28 August 2014 under duress and undue influence. Having carefully contract.
considered all of the evidence and submissions of the Parties, the Tribunal finds
that there is no clear and persuasive evidence that Mr. CW2 signed off on the [45] “The Claimant contends that, under Article 49(1)(a) of the CISG, avoidance of
said reports and test results in the circumstances alleged by the Claimant. contract is only available where the non-conformity of goods can be regarded as
a fundamental breach of contract. In the case of partial non-performance, the
[38] “On 3 September 2014, Dr. C issued a chemical analysis report in respect of the Clamant argues that pursuant to Article 51(2) of the CISG, the entire contract
three types of ETP. The report specified the non-compliant items on the basis can only be declared avoided if the non-performance amounts to a fundamental
of the chemical results and concluded that the goods under the Sales Contract breach; otherwise, the Claimant says, Article 51(1) permits the buyer's remedy,
were ‘not suitable to be used for tomato products.’ including avoidance of contract, to be applied only to the non-conforming
portion of the goods. In turn, the Claimant refers to Article 25 of the CISG,
[39] “On 16 September 2014, CBL issued a report concerning the TFS Type E that which according to the Claimant defines fundamental breach as a detriment
was delivered under the Sales Contract. Based on the samples taken by CBL, so significant that it substantially deprives the aggrieved party of what it was
it specified the nature of the defects (i.e., oxidation) and concluded that the TFS entitled to expect under the contract.
was ‘not suitable to be used for food products being affected by rust.’
[46] “The Claimant’s position is that the above requirements have not been satisfied.
[40] “Against the above background, the First Termination Letter was issued on 8 In the Claimant's view, issues of non-conformity are not a fundamental breach
September 2014 in respect of the ETP. Through Mr. CW2, the Claimant was or as long as the buyer can use the goods or resell them even at a discount.
should have been aware of the specific issues in respect of these goods. Further, the Claimant argues that the buyer should not be entitled to avoid the
contract so long as the goods are not bought for a particular purpose, they can
[41] “Further, the Second Termination Letter was issued a couple weeks later in be reasonably used in the normal course of business and there is no need to
respect of the TFS Type E delivered by the Claimant. The letter specified that buy replaced goods.
‘oxide was detected on the wide supply and on the entire coils' surface,’ thereby
informing the Claimant that it sought to terminate the Sales Contract. [47] “In this connection, the Claimant contends that the Respondent could have
mitigated its damages as the types of ETP and TFS that were delivered could
[42] “Based on the evidence submitted and submissions made by the Parties, the have been used. For example, the Claimant asserts that the ETP delivered was
Tribunal is not convinced by the Claimant’s argument that a greater level of still of a quality which was still usable for light metal packaging such as cans
specificity (e.g., identification of each package of the shipment affected by the for food, beverage, and general line products. Further, the Claimant argues that

153 154
Korean Commercial Arbitration Board

the Respondent's business uses a wide range of ETP and could have made use [52] “The Respondent submits that, as it could not produce tin cans as it planned
of some of the delivered ETP for Company S, a company which the Claimant and expected, the situation could not be resolved by a price reduction or any
alleges is affiliated with the Respondent. Therefore, the Claimant says, the other means of remedy other than avoidance of the Sales Contract. According to
Respondent could make reasonable use of goods within its normal course of the Respondent, it could not reasonably use the goods within the Respondent’s
business. normal course of business, as conformity of quality is critical in the production
of tomato cans and their derivatives. Tomatoes, according to the Respondent,
[48] “The Claimant denies that the Respondent’s purpose of purchasing the goods are acid in nature, and require stricter tinplate and steel specifications
should negate the usability of the goods. Further, the Claimant argues that it compared to cans that store other foodstuffs.
was not aware of the purpose behind the Respondent’s purchase – according
to the Claimant, it was neither expressly stipulated in the Sales Contract nor [53] “The Respondent further argues that Italy maintains strict regulations
discussed in the course of the negotiation thereof. According to the Claimant, regarding the technical requirements of tinplates and steel which prevent non-
the Respondent bears the burden of proof that both the ETP and TFS in question compliant products from entering the market. The Respondent asserts that it
were difficult for the Respondent to resell, that it could only have done so at a could not possibly manufacture and sell cans that could be transacted in the
lower price or that such an attempt of disposal could not have been expected Italian market, and that reselling the non-compliant goods would also have
from the Respondent at all. been arduous.
(….) (….)

[49] “The Respondent submits that the Claimant’s delivery of the non-conforming [54] “Article 49(1) of the CISG prescribes in pertinent part as follows:
goods amounts to a fundamental breach under Article 25 of the CISG and thus ‘The buyer may declare the contract avoided:
the Sales Contract has been successfully avoided by the Respondent through
(a) if the failure by the seller to perform any of his obligations under the
the First and Second Termination Letter pursuant to Article 49 of the CISG. The
contract or this Convention amounts to a fundamental breach of contract …’
Respondent submits that in the circumstances the Claimant is not entitled to
receive the claim amount. In turn, Article 25 defines a fundamental breach as:

‘[a] breach of contract committed by one of the parties is fundamental if


[50] “The Respondent denies that the delivered goods could have been of some use
it results in such detriment to the other party as substantially to deprive
to the Respondent. According to the Respondent, the sole purpose of entering
him of what he is entitled to expect under the contract, unless the party in
into the Sales Contract was to purchase raw materials to produce tin cans for
breach did not foresee and a reasonable person of the same kind in the
storage of tomatoes. This purpose, the Respondent says, was known to the
same circumstances would not have foreseen such a result.’
Claimant.

[55] “As discussed above, it was found based on the examination reports and test
[51] “According to the Respondent, it has been firmly established throughout
results that at least all three types of ETP as well as TFS Type E were not
multiple investigations and tests by SST, CBL and SSICA that the delivered
in conformity with the contractual specifications. Those category of goods
goods did not conform with the specifications of the Sales Contract. Further,
comprised of around 700 MT of the total 900 MT delivered – i.e., nearly 80
the Respondent asserts that the reports from CBL and SSICA, as well as from
per cent of the shipments. Based on the arguments raised by the Parties,
Mr. E, conclude that the goods cannot be used to produce cans to store food for
the Tribunal is of the view that such circumstance amounts to substantial
human consumption as they are affected by rust and oxidation.
deprivation of what the Respondent would have expected under the Sales

155 156
Korean Commercial Arbitration Board

Contract. Accordingly, the Tribunal finds that a fundamental breach was [61] “With respect to the 10 per cent deposit allegedly paid under the First Contract,
committed by the Claimant. the Tribunal has no jurisdiction to decide this issue for the reasons mentioned
above ….
[56] ‘As to the Claimant's submission on the possibility of resale of the Goods or
the particular purpose behind the Respondent's purchase of the Goods, the [62] “Turning to the Respondent's claims for loss of profit and goodwill, as well as
Tribunal finds that the Claimant has failed to establish their relevance based on for incidental damages, the Tribunal notes that it has carefully reviewed the
the evidence submitted. For instance, the Tribunal notes that the Claimant in Parties' arguments and the evidence submitted. However, the Tribunal remains
its Memorial on the Merits refers to Supreme Court decisions from Switzerland unconvinced that the Respondent has satisfied its burden of proof in this
and Germany as well as a CIETAC arbitration award - none of which on their regard. In particular, the Tribunal has found it difficult to award such damages
face fall within the scope of the governing law. due to the Respondent's failure to clearly and adequately set out relevant
jurisprudence in support of its damage theory. For instance, the Respondent in
[57] “As to the reliability of the reports and test results, the Tribunal, having duly its Reply to Claimant’s Defense Memorial states what it views to be the ‘norm
considered the Claimant's arguments and the evidence it has advanced, fails under Korean law’ in respect of lost profits but then fails to provide any evidence
to see any clear and persuasive evidence that they were unreliable or partial. in support of its position on the law. The same goes for the Respondent's case
Further, the Tribunal is not convinced by the evidence and arguments submitted for reputational and incidental damages. The Respondent makes some (albeit
by the Parties that the European Standard, EN 10202, should have applied minimal) reference to Article 74 of the CISG throughout its pleadings, but such
mandatorily or that the sampling method adopted was unsuitable. article is discussed in the context of the alleged damages suffered under the
First Contract (which as discussed the Tribunal is not in a position to entertain);
[58] “For the aforementioned reasons, the Tribunal finds that it was the Claimant otherwise the article is only referenced in a broad statement in respect of the
who had committed a fundamental breach of the Sales Contract in the first Claimant's alleged obligations to compensate the Respondent.
place. Accordingly, the Claimant's claims for the contract price26) under the
Sales Contract are dismissed.” [63] “For the aforementioned reasons, the Respondent's counterclaims for damages
are dismissed.”
IV. COUNTERCLAIM
V. INTEREST

[59] “The Respondent asserts that, as a result of the Claimant’s breach, it has
suffered damages in the form of incidental damages, reputational damages and [64] “The Tribunal notes that the Parties dispute as to whether the interest rate
lost profit. It also seeks the return of the deposit allegedly paid under the First set out in Article 3(2) of the Special Act should apply. The Respondent seeks
Contract. application thereof whereas the Claimant opposes.

[60] “The Claimant denies that the Respondent is entitled to such damages, arguing [65] “The Tribunal has carefully reviewed the Parties’ submissions in this regard.
among other things that it is not justified, that the calculations are erroneous However, given that neither party has succeeded with regards to its respective
and that Respondent has failed to mitigate its losses. damages claims, the Tribunal sees no need to render a decision as to the
interest rate.”

26) The arbitral award states “claims for damages,” but this appears to be a clerical error for
“claims for the contract price.”

157 158
Korean Commercial Arbitration Board

VI. COSTS Cost Submission can be claimed under this head. In particular, the Respondent
fails to explain the relevance of item nos. …, which on its face do not appear to
[66] “The Respondent in its Cost Submission directs the Tribunal's attention to correspond to the costs of the experts appointed by the Respondent in these
Article 47(1) of the KCAB Rules, which prescribes that ‘the Arbitration Costs proceedings …. Further, the Tribunal has difficulty understanding the nature of
including administrative fees shall in principle be borne by the unsuccessful item no. 10, an "Expert Opinion" by Mr. E, as the Tribunal understands that Mr.
party.’ The Tribunal finds no reason to depart from this general principle and E has only submitted a fact witness statement in these proceedings.
thus accepts this approach.
[72] “In the circumstances, the Tribunal in its assessment finds that the only
[67] “The Tribunal notes that the Claimant did not succeed in any of its claims. claimable item under this head is item no. 9 (claimed in the sum of EUR …),
Respondent therefore has succeeded in its defense against the Claimant's which according to the Tribunal's understanding represents the costs associated
claims but did not succeed in respect of its counterclaims. Therefore, on with the expert report issued by Mr. RE. Similar to the invoices observed above,
balance, the Tribunal is of the view that the Respondent shall be deemed to be however, the Respondent has failed to show any supporting detail such as the
the (partially) successful party when assessing costs. rate charged, time spent or description of the work performed, thereby making
(….) it difficult for the Tribunal to assess the reasonableness of the costs claimed.
On this basis, the Tribunal assesses that a 40 percent reduction is appropriate.”
1. Translation Costs
3. Costs of Legal Experts
[68] “The Respondent submits that it has incurred EUR … in translation costs and
has submitted what appears to be invoices issued by the translation service [73] “The Respondent submits that it has incurred EUR … in legal costs, which the
provider. Tribunal understands includes fees and disbursements of legal counsel.

[69] “The Tribunal appreciates that a significant portion of the documents exhibited [74] “In … the Respondent's Cost Submission, the Respondent has identified
have required translation. However, the Tribunal notes that the Respondent fails sums corresponding to various ‘Contractor[s],’ namely ‘Studio Legale A,’
to provide any details required to verify the extent of work performed. On the ‘Studio Legale B,’ ‘Studio C’ and ‘Studio D,’ of which the Respondent has
face of the invoices, there appears to be no indication as to how these figures failed to explain their role in these proceedings. The invoices attached to the
have been calculated and, in any case, they are recorded in a foreign language Respondent's Cost Submission do not help in this regard. On this basis, the
not comprehensible to the Tribunal. In the circumstances, the Tribunal in its Tribunal is not able to assess the relevance of these items and therefore is not
assessment does not find it appropriate to award the entire sum; rather it views in a position to award their corresponding figures.
that a deduction of 40 per cent would be suitable and within reason.”
[75] “The Tribunal does recognize those items corresponding to Law Firm,
2. Expert Costs the Respondent's counsel on record …. But again, having reviewed the
corresponding invoices, there appears to be no submission with regards
[70] “The Respondent submits that it has incurred EUR … in expert costs during this to hourly rates, time spent or descriptions of the work performed. For this
arbitration. reason, the Tribunal finds it difficult to assess the reasonableness of the sums
pertaining to the attorney’s fees and therefore assesses that a 40 per cent
[71] “Based on the evidences submitted by the Respondent, the Tribunal is not reduction is appropriate.
convinced that the entirety of these items set out under … the Respondent's

159 160
Korean Commercial Arbitration Board

[76] “Further, the Tribunal notes that the Respondent's counterclaims in respect II. CONSEQUENCES OF SELLER’S KNOWLEDGE OF DEFECTS
of the First Contract has proved unsuccessful. As it was the Respondent that
invoked the First Contract, which as a result led to extensive arguments by both With respect to the Respondent’s notice of defects, the arbitral award stated that
Parties in relation thereto, the Tribunal assesses that the Respondent bears “[t]hrough Mr. CW2, the Claimant was or should have been aware of the specific
some responsibility in the extra time and costs spent. The Tribunal therefore issues in respect of these goods.” On the other hand, Article 40 of CISG provides
assesses that an additional 40 per cent reduction to the sum claimed for the that “the seller is not entitled to rely on the provisions of Articles 38 and 39 if the
costs of the Respondent's counsel is appropriate.” lack of conformity relates to facts of which he knew or could not have been unaware
and which he did not disclose to the buyer.” “Should have been aware” stated in
4. Arbitration Costs the arbitral award needs to be distinguished from “could not have been unaware”
provided in Article 40 of CISG. The facts of which the seller “should have been aware”
[77] “The Respondent submits that it is entitled to its payment of the ‘KCAB fees’ in include those facts that would be disclosed by an investigation that he should make.
the sum of EUR …. The Tribunal notes that the total amount of the arbitration On the other hand, the facts of which the seller “could not have been unaware” are
costs fixed by the Secretariat of KCAB is KRW …. the facts that are before his eyes and reach his mind even without fulfilling a duty
of investigation. By employing “could not have been unaware,” Article 40 does not
[78] “As provided under Article 47(1) of the KCAB Rules, the Tribunal, ‘taking into differentiate “could not have been unaware” from “knew” in practice.27) Furthermore,
account the circumstances of the case, may, at its discretion,’ apportion the the relevant time when the seller could not have been unaware of the defects, in
arbitration costs between the Parties. Applying the same principle in paragraph light of the purpose of Article 39, is the expiry of the reasonable time within which
… above, the Tribunal finds it appropriate to apportion such costs in the the buyer should give notice under Article 39.28)
following manner: the Claimant and the Respondent will bear KRW … and KRW
…, respectively.” III. FITNESS FOR A PARTICULAR PURPOSE: PUBLIC LAW STANDARDS

Implications
In this case, the Respondent argues that the sole purpose of entering into the
contract was to purchase raw materials to produce tin cans for storage of tomatoes
I. APPLICABLE LAW TO OBJECTIONS TO JURISDICTION
and the purpose was made known to the claimant. In addition, the Respondent
argues that Italy, the intended place of use in this case, maintains strict regulations
The parties agreed upon the application of CISG to the contract and of Korean law regarding the technical requirements of tin plates and steel which prevent non-
to matters not governed by CISG. The parties did not clearly indicate the applicable complying products from entering the market, and that it could not possibly
law to the arbitration agreement contained in the contract. While the Respondent manufacture and sell cans that could be transacted in the Italian market. Meanwhile,
appears to be of the opinion that Korean law applies to the arbitration agreement, the parties dispute whether the inspection standard for the goods is European
the Claimant has not contested this. While ruling on objections to its jurisdiction, the Standard, EN 10202.
Arbitral Tribunal needs to identify the applicable law to the arbitration agreement.
Having found that the parties chose Korean law to govern the substance of the
dispute and designated Seoul as the seat of the arbitration, the Arbitral Tribunal
correctly determined that the applicable law in delimitating the scope of the
arbitration agreement should be Korean law. The Arbitral Tribunal’s determination
could be sustained because Korean law is not only lex causae but also lex arbitri. 27) John O. Honnold, Uniform Law for International Sales (3rd ed.), 229-230 (1999).
28) Kröll et al., supra note 10, at 632; Schwenzer, supra note 10, at 646.

161 162
Korean Commercial Arbitration Board

have perceived the purpose. It would therefore serve for implicit information if the
Article 35 of CISG provides: buyer provides to the seller brochures describing his activities or products. However,
“Article 35 for evidentiary reasons, it is advisable that the buyer clarifies any particular purpose
(1) The seller must deliver goods which are of the quantity, quality and when concluding the contract. The relevant time for the purpose to be made known
description required by the contract and which are contained or packaged to the seller is the time of contract conclusion.29) The Arbitral Tribunal could have
in the manner required by the contract. drawn attention to whether a particular purpose of the Respondent was made known
to the Claimant and thus the Claimant was responsible for the fitness of the goods in
(2) Except where the parties have agreed otherwise, the goods do not this case.
conform with the contract unless they:

(a) are fit for the purposes for which goods of the same description would
ordinarily be used;
(b) are fit for any particular purpose expressly or impliedly made known to
the seller at the time of the conclusion of the contract, except where the
circumstances show that the buyer did not rely, or that it was unreasonable
for him to rely, on the seller's skill and judgement;

(c) possess the qualities of goods which the seller has held out to the buyer
as a sample or model;

(d) are contained or packaged in the manner usual for such goods or, where
there is no such manner, in a manner adequate to preserve and protect the
goods.

(3) The seller is not liable under subparagraphs (a) to (d) of the preceding
paragraph for any lack of conformity of the goods if at the time of the
conclusion of the contract the buyer knew or could not have been unaware
of such lack of conformity.”

Article 35(2)(b) requires the seller to supply goods that are fit for any particular
purpose expressly or impliedly made known to him. The particular purpose includes
climate conditions, cultural traditions, religious beliefs, and public law standards. The
particular purpose is only required to be made known to the seller but not required
to be contractually agreed upon. The particular purpose may not only be expressly
made known to the seller but it would also be sufficient if a reasonable seller could

29) United Nations Commission on International Trade Law, supra note 10, at 146; Kröll et al.,
supra note 10, at 513-515, 518-520; Schwenzer, supra note 10, at 580-582.

163 164
Korean Commercial Arbitration Board

interest as well.

Excerpt
KCAB case no.9
I. JURISDICTION AND APPLICABLE LAW

Parties Claimant (Counter-Respondent): John Doe (Korea)


Respondent (Counter-Claimant): Electronic Company (Vietnam) 1. Jurisdiction

Place of
[1] “Article 14 of the Installation Contract I and … contain the Parties’ arbitration
Arbitration Seoul, Republic of Korea
agreement:
Language Original in English Any dispute arising out of or in connection with this Contract shall be finally
settled by arbitration in Seoul in accordance with the Arbitration Rules of
Subject matters - capacity of a party to the arbitration agreement
the Korean Commercial Arbitration Board.
- applicable law to the procedure
- lex arbitri
[2] “The present dispute concerns Claimant’s claim for payments allegedly due
- correction of a party
under the Installation Contract I and thus arises out of the Installation Contract I.
- termination of contract by agreement
Therefore, said dispute is within the scope of the Parties’ arbitration agreement,
which designates the KCAB as the administrative institution and the KCAB’
arbitration rules as the rules to govern the resolution of said dispute.

Facts [3] “Also, under Article 17(2) of the Korean Arbitration Act (‘KAA’), an objection
to the Tribunal’s jurisdiction must be raised no later than the submission of
The parties entered into four contracts whereby the Respondent purchased the Statement of Defense on the merits; and under Article 17(3) of the KAA,
manufacturing equipment from the Claimant and the Claimant also installed the an objection that the Tribunal has exceed the scope of its authority must be
equipment. The equipment were delivered to the Respondent and the Claimant was raised as soon as grounds for such an objection exist. Both Parties have fully
paid for them. A dispute arose between the parties regarding the installation of the participated in these proceedings without raising any jurisdictional objections
equipment and the payment therefor under the installation contract. The Claimant or challenges to the jurisdiction of the Tribunal or the competence of the Sole
initiated arbitration relying on the arbitration clause contained in the installation Arbitrator.
contract which provided for KCAB arbitration. The contract provided that the law
applicable to the dispute was Korean law. The Claimant sought damages in the [4] “Accordingly, the Tribunal finds that it has been properly constituted in
amount of 70% of the outstanding payment and interest because it completed 70% accordance with the Rules, and decides that it has jurisdiction over the
of its performance under the contract. In response, the Respondent objected that it Arbitration and is competent to decide the Parties’ dispute.”
was not liable for the outstanding payment under the contract because the parties
terminated the contract by executing the “Liquidation Agreement.” Having found 2. The Applicable Law
that the “Liquidation Agreement” terminated the installation contract, the Arbitral
Tribunal held that the Respondent was not obligated to make any remaining payment [5] “… and Article 13 of the Installation Contract I contain the governing law clause:
to the Claimant under the contract. Accordingly, the Claimant was not awarded This Contract shall be governed under the laws of Korea.”

165 166
Korean Commercial Arbitration Board

II. BREACH OF CONTRACT [10] “Claimant filed separate arbitrations i.e. one arbitration on the basis of the
Installation Contract I and the other on the Installation Contract J. This Final
Award concerns the former.”
1. Contract between the Parties
(….)

[6] “In early …, Respondent sought to set up a manufacturing facility in Vietnam for
the production of printed circuit boards (‘PCBs’). Towards that end, Respondent 2. Suspension of Installation
executed four contracts with Claimant which provided for Claimant’s sale of
[11] “On …, Claimant commenced installation pursuant to the Installation Contract I.
PCB-manufacturing equipment as well as the installation of such equipment at
Company D was contracted by Claimant to carry out said installation work.
Respondent’s facility. The contracts at issue are as follows:

[12] “On …, Claimant informed Respondent that installation pursuant to the


(1) Contract No. ADPS-01 dated … for the supply of a PCB Full Automatic
Installation Contract I could not continue because certain utility work (such as
Through-Hole Plating System (‘Sales Contract I’).
air compressor, waste water system, etc.) which was an essential prerequisite
for Claimant’s installation had not been completed or purchased. The Parties
(2) Contract No. ADPT-01-3 dated … for the Tear Down & Setup of Plating
do not dispute that installation pursuant to the Installation Contract I was to
System (‘Installation Contract I’).
be completed by …, as well as do not dispute that as at … installation was not
completed.
(3) Contract No. ADP26-01 dated … for the supply of “J” PCB Production
Machine List (‘Sales Contract J’).
Meanwhile, installation pursuant to the Installation Contract J commenced on
…. Company D was contracted by Claimant to carry out said installation work
(4) Contract No. ADT26-02 dated … for the Tear Down & Setup of the “J”
as well. The Parties do not dispute that installation pursuant to the Installation
PCB Production Machine List (‘Installation Contract J’).
Contract was also to be completed by …, as well as do not dispute that as at …
installation was not completed. And it is common ground between the Parties
[7] “The Parties do not dispute that the equipment that are the subject of the Sales
that installation pursuant to the Installation Contract J was completed on ….
Contract I and the Sales Contract J were duly delivered to Respondent and that
Claimant was duly paid for them.
[13] “On …, to discuss installation progress under both the Installation Contract I
and the Installation Contract J, Mr. John Doe met with Respondent’s Mr. B at
[8] “The Parties’ dispute rather arises from Claimant’s performance of, and
a meeting at which Company D’s Mr. C and six other people attended. At the
Respondent’s payment obligation under, the Installation Contract I and the
meeting, Respondent took the position that Claimant had failed to complete
Installation Contract J. Claimant contends that Respondent owes Claimant
performance of both the Installation Contract I and the Installation Contract J on
monies under both the Installation Contract I and the Installation Contract J.
time, and thus, that Respondent would not pay Claimant the amounts due under
either the Installation Contract I or the Installation Contract J unless installation
[9] “Under both the Installation Contract J and the Installation Contract I,
pursuant to both such contracts was completed within 40 days.
Respondent was obligated to pay amounts due thereunder in installments. The
Parties agree that all installments under both Installation Contracts were paid
[14] “Mr. John Doe took the position that the two contracts were separate and
save for the final payment of USD 21,000 under the Installation Contract J and
independent, and thus, that Respondent should not condition payment under
the final payment of USD 36,600 under the Installation Contract I.
one contract on the completion of both contracts. Specifically, Claimant was of

167 168
Korean Commercial Arbitration Board

the view that performance of the Installation Contract J could be finalized by 36,600 under the Installation Contract I —plus interest at the rate of 18% per
the end of …, so Respondent was obligated to pay for corresponding amounts year accruing from … until completion.
regardless of whether the Installation Contract I had been completed.
Claimant’s position is that it is owed 70% of the final outstanding installment of
[15] “However, Respondent disagreed. In response, Claimant counter-offered, USD 36,600 under the Installation Contract I because Claimant completed 70%
proposing that, Respondent, irrespective of the payment terms under the of its performance under the Installation Contract I.
Installation Contracts, pay USD 15,000 in addition to USD 5,000 as part of the
Installation Contract J’s final installment payment of USD 21,000—a total of [18] “However, Respondent’s position is that: (i) Respondent is not obligated to pay
USD 20,000—to resolve the matter. Respondent, however, rejected the counter- the final outstanding installment of USD 36,600 under the Installation Contract
offer. I unless Claimant’s performance thereunder is completed; (ii) Respondent
is not obligated to pay the final outstanding installment of USD 36,600 under
On …, Respondent insisted that Claimant choose, within one hour, either the Installation Contract I unless Claimant provides acceptable documents
to terminate the Installation Contracts or complete performance of both confirming Claimant completed its performance; and (iii) Respondent is not
Installation Contracts within 40 days. Claimant consulted Company D, which obligated to pay the final outstanding installment of USD 36,600 under the
furnished its view that completion of the Installation Contract I would require Installation Contract I because the Parties terminated the Installation Contract I
at least 2 months, which was more than the 40 days Respondent offered. by executing the Liquidation Agreement.
In addition, Claimant had previously visited the site a couple of days earlier
and had seen that only 3 out of 26 components of the equipment J had been [19] “Based on the facts alleged by the Parties, the critical issue in the Arbitration is
installed.” determining the scope and terms of the Liquidation Agreement. And although
Claimant raised contentions concerning whose fault it was that performance of
3. Execution of Liquidation Agreement the Installation Contract I and the Installation Contract J was not completed on
time, due to the Tribunal’s decision on the effect of the Liquidation Agreement
[16] “On the same day … Claimant and Respondent, under such circumstances, the Tribunal finds that Claimant’s such contentions are moot.
signed the Liquidation Agreement (‘Liquidation Agreement’). (….)

Then, also on the same day … Claimant instructed Company D to discontinue its
[20] “The intent of the Liquidation Agreement is clear and unambiguous.
installation work and withdraw from the site.
Thereunder, the purpose of the Liquidation Agreement was to terminate two
On …, Company D issued a Construction Completion Certificate to Respondent contracts specifically identified in the Liquidation Agreement and to release the
stating that construction corresponding to the Installation Contract J was Parties from any obligations under those two contracts. That said, while ‘ADT26-
completed on …, as well as a Construction Completion Certificate to Respondent 02 date …’ referred to the Installation Contract J, ‘ADPS-01 – Date …’ referred to
stating that construction corresponding to the Installation Contract I was about the Sales Contract I, not the Installation Contract I.
70% complete as at ….”
[21] “The fact that the Liquidation Agreement referred to the Installation Contract
4. Claim for Damages J was understandable, because the Sales Contract J was not at issue since
the equipment to be supplied thereunder delivered and payments owed paid.
[17] “The main claim before this Tribunal is Claimant’s claim for damages in the Rather, it was the installation of that equipment, pursuant to the Installation
amount of USD 25,620—i.e. 70% of the final outstanding installment of USD Contract J, that was thus at issue and outstanding at the time the Liquidation

169 170
Korean Commercial Arbitration Board

Agreement was executed, so it made sense for the Liquidation Agreement Liquidation Agreement, instructed Company D to withdraw from the site.
to terminate the Installation Contract J. On the other hand, however, it is odd Indeed, at the hearing, Mr. John Doe testified that he instructed Company
that the Liquidation Agreement referred to the Sales Contract I instead of D to withdraw from the site because his understanding at the time was that
the Installation Contract I because while the former had been fulfilled at the installation pursuant to both the Installation Contract I and the Installation
time the Liquidation Agreement was executed, it was the latter that was at Contract J had been terminated.
issue. Therefore, the point was explored during the course of the Arbitration, (….)
particularly at the evidentiary hearing. And Company D’s understanding was the same, as Mr. C testified at the hearing.
(….)
[22] “The Parties agree that the Liquidation Agreement contains typographical Consistently, Ms. H’s and Mr. B’s testimony is that the Liquidation Agreement
errors. While Claimant contends that the scope of the Liquidation Agreement was executed against the backdrop of discussions with Mr. John Doe of … that
extends to the Sales Contract I and the Sales Contract J, not the Installation if the Liquidation Agreement is signed Claimant would not have to install the
Contract J, Respondent contends that the scope of the Liquidation Agreement machines and Respondent would not have to pay.
extends to the Installation Contract J and the Installation Contract I, not the (….)
Sales Contract I. Fourth, the Tribunal is of the view that if Claimant’s position is to be entertained,
it would mean that Claimant continued to be bound to complete both Installation
[23] “Having reviewed and evaluated all submissions and evidence including witness Contracts. In such case, Claimant would have been exposed to the risk of
testimony presented during the course of the Arbitration, the Tribunal finds that incurring substantial unexpected costs and expenses. Such burden would have
Respondent’s contention is more probable. been substantial for Claimant, and thus, would have been reason for Claimant
First, it is common ground between the Parties that their intent in executing the to discontinue performance under the Installation Contracts, not to continue
Liquidation Agreement was to terminate two contracts effective at the time the them.
Liquidation Agreement was executed and to release the Parties from obligations Fifth, the Tribunal cannot find any evidence showing Claimant made any effort
owed under those two contracts. However, as noted, at the time the Liquidation to correct the mistakes in the Liquidation Agreement so that it would conform to
Agreement was executed the Sales Contract I and the Sales Contract J had Claimant’s understanding of the Liquidation Agreement. If it was not Claimant’s
both been fulfilled. The equipment that were to be supplied under those intention to terminate the Installation Contract J but to terminate the Sales
two contracts had been delivered and paid for. Consequently, the two Sales Contract J instead, it would have been in Claimant’s interest to correct the
Contracts could not be terminated. It is illogical and contrary to the evidence to Liquidation Agreement accordingly. The Tribunal however is unaware of any
construe the Liquidation Agreement as having been executed to terminate two follow-up communication between the Parties to that effect, or of any instance
contracts had already been fulfilled and thus could not be terminated. where Claimant reserved its rights to receive any amounts outstanding under
Second, factually, the evidence shows that Claimant’s contemporaneous the Installation Contracts.
understanding about the progress of installation under either the Installation
Contract I or the Installation Contract J was that they could not be both [24] “In sum, the Tribunal finds that the Liquidation Agreement terminated the
completed within 40 days of … i.e. the timeline Respondent afforded. Thus, at Installation Contract I and that consequently there are no legal obligations
the time the Liquidation Agreement was executed, Claimant was aware that it thereunder remaining between Claimant and Respondent. Therefore,
was performance of the Installation Contracts that was at issue and that the Respondent is under no obligation to make any remaining payment to Claimant.
Liquidation Agreement was being executed to resolve issues concerning the
incomplete performance of the Installation Contracts. [25] “In closing, as noted above, Claimant raised contentions concerning whose
Third, the Tribunal finds dispositive the fact that Claimant, after signing the fault it was that performance of the Installation Contract I and the Installation

171 172
Korean Commercial Arbitration Board

Contract J was not completed on time. Having reviewed and evaluated those is of the view that the Arbitration Costs should be borne by Claimant. However,
contentions, the Tribunal concludes that the issues so raised only matter if with regard to all other ‘necessary costs and expenses’ incurred by the Parties
the Liquidation Agreement was not legitimately entered into between the in connection with this Arbitration, the Tribunal is of the view that each Party
Parties. At the hearing, the Tribunal clarified the issues before both Parties, and should bear its own costs.”
advised that these were only to be reviewed and/or evaluated if the Liquidation
Agreement was not effectively entered into. Therefore, the Tribunal refrains Implications
from making any decisions in this regard.”
I. CAPACITY OF A PARTY TO THE ARBITRATION AGREEMENT
III. INTEREST

In this case, the Arbitration Tribunal finds that the arbitration was initiated by the
[26] “For the reasons set out above, the Tribunal finds that the evidence presented Claimant under the name of Company A which was not an independent legal entity.
by Claimant in support of its allegations is inconclusive and/or insufficient In the absence of the parties’ objections, the Arbitral Tribunal names Mr. John Doe,
to prove that Claimant is entitled to the amount it claims pursuant to the the sole proprietor of the company, as the Claimant.
Installation Contract I. The Tribunal finds that the Liquidation Agreement was
legitimately entered into and that its scope extended to, and thus terminated, A party to the arbitration agreement must have legal capacity to enter into that
the Installation Contract I. Accordingly, Respondent is under no obligation to pay agreement. If the arbitration agreement is entered into by a party who lacks the
any amounts to Claimant under the Installation Contract I, so the principal that capacity to do so, the arbitral process could be challenged on the basis that the
is the basis of Claimant’s claim for interest cannot be sustained. Consequently, arbitration agreement is void, inoperative, or incapable of being performed.30)
with no principal, Claimant cannot be awarded interest.”
Without objections from the parties, the Arbitral Tribunal correctly names Mr. John
IV. COSTS Doe as the Claimant. However, the Arbitral Tribunal could have examined whether
Company A is a party to the arbitration agreement and determined whether the
arbitration agreement is void, inoperative, or incapable of being performed due to
[27] “Under Article 47.1 of the KCAB International Rules, the Arbitration Costs,
the incapacity of Company A.
including administrative fees, are to be borne by the unsuccessful party in
principle. However, the Tribunal retains discretion to apportion the costs
II. CORRECTION OF A PARTY AND THE LAW APPLICABLE TO THE PROCEDURE
between the Parties as it sees fit, taking into account all circumstances of the
case.
In naming Mr. John Doe as the Claimant, the Arbitral Tribunal holds that the Tribunal
[28] “The KCAB International Rules define ‘Arbitration Costs’ to include ‘filing fees, has the authority to identify and designate the parties to the arbitral proceedings.
the administrative fees [and] the fees and expenses of the arbitrators incurred The Arbitral Tribunal relies on the Korean courts’ practice to do so under Korean
during the arbitration proceedings…’ (‘Arbitration Costs’). Under Article 48 of procedural law. A distinction is made between the rectification of a defendant and
the KCAB International Rules, the Tribunal also has full discretion to apportion
the costs of ‘other necessary costs and expenses’ (such as fees for attorneys
and interpreters) between the Parties.
30) Articles II(3), V(1)(a) of United Nations Convention on the Recognition and Enforcement of
[29] “Since Claimant commenced the Arbitration but failed to prevail, the Tribunal Foreign Arbitral Awards; Articles 8(1), 34(2)(a), 36(1)(a)(i) of the Model Law on International
Commercial Arbitration; Blackaby et al., supra note 3, at 95.

173 174
Korean Commercial Arbitration Board

the correction of a party. Article 260(1) of the Korean Civil Procedure Act expressly
provides that “[w]here it is obvious that a plaintiff has mistakenly designated a
KCAB case no.10
defendant, the court of first instance may, upon request of the plaintiff, permit by its
ruling the plaintiff to rectify the defendant, by the close of the pleadings.” However, Parties Claimant: Aircraft Manufacturing Company (Indonesia)
the Korean Civil Procedure Act does not expressly stipulate the correction of a party. Respondent: The Republic of Korea (Korea)
But the Korean Supreme Court has held that the court should, at the request of one Place of
of the parties, mandate the correction of the incorrect description of a party, provided Arbitration Seoul, Republic of Korea
that it retains the identity of the proper party identified by the court (see Supreme
Court Decision No. 2010Da99040 dated Mar. 10, 2011; Supreme Court Decision No. Language Original in Korean
2005Ma425 dated July 4, 2006; Supreme Court Decision No. 96Da3852 dated Oct. 11, Subject matters - applicable law
1996). - late delivery of goods
- force majeure
Article 20(1) of the Korean Arbitration Act provides that “[s]ubject to the mandatory - exemption of liability
provisions of this Act, the parties are free to agree on the arbitral proceedings.” - liquidated damages
Paragraph (2) provides that “[f]ailing such agreement referred to in paragraph (1), - statutory interest rate
the arbitral tribunal may, subject to the provisions of this Act, conduct the arbitration
in such manner, as it considers appropriate.” The parties chose the Arbitration Rules
of KCAB. The parties’ adoption of procedural rules does not amount to a derogation
from the lex arbitri. The parties’ autonomy in determining the rules of procedure
is subject to the mandatory provisions in the Korean Arbitration Act. This strikes
the balance between the parties’ autonomy and the overriding requirements of the
lex arbitri. Therefore, the procedure of the arbitration is generally regulated by the Facts
Rules chosen by the parties. The Korean Arbitration Act, the lex arbitri, to the extent
The Respondent contracted to purchase from the Claimant four patrol airplanes,
that it contains mandatory provisions, is binding the parties.31)
in two installments, installed with search radar made by Company C and forward
looking infrared system made by Company L. The engineers of Company C
It is natural that the Arbitral Tribunal should look into the Korean Arbitration Act,
established in Country I were scheduled to visit the Claimant in Country B to conduct
the lex arbitri. In this case the Arbitral Tribunal further refers to “Korean procedural
lab integration test between the two components to be mounted on the airplanes.
law.” However, it is ambiguous whether it indicates the Korean Civil Procedure
Meanwhile, several civilians were killed by a military raid by Country I’s naval
Act. The Arbitral Tribunal could have ascertained whether and why the Korean Civil
commandos on the MV Mavi Marmara carrying humanitarian aid in international
Procedure Act extends to the arbitral proceedings. It remains to be seen whether the
waters. Because of Country B’s refusal of the engineers’ entry triggered by the
Korean Civil Procedure Act is encompassed into the lex arbitri and thus extends to
raid, the test was not conducted as planned. Later the engineers managed to enter
the arbitral proceedings in respect of correcting a party.
Country B and to conduct integration test with help of Company L. As a result, the
Claimant failed to deliver the airplanes in accordance with the contractual schedule.
In response, the Respondent paid the remaining amount deducting the liquidated
damages from the purchase price.
31) United Nations Commission on International Trade Law, supra note 4, at 100-101;
Blackaby et al., supra note 3, at 179-180.

175 176
Korean Commercial Arbitration Board

The Claimant initiated arbitration relying on the arbitration clause contained in [3] “Article 79 of CISG provides:
the contract which provided for KCAB arbitration. The contract provided that the ‘(1) A party is not liable for a failure to perform any of his obligations if he proves
law applicable to the dispute was Korean law. Even though the United Nations that the failure was due to an impediment beyond his control and that he could
Convention on Contracts for the International Sale of Goods (CISG) did not apply, the not reasonably be expected to have taken the impediment into account at the
Arbitral Tribunal decided to take it into account. Arguing that the delay in delivery time of the conclusion of the contract or to have avoided or overcome it or its
was due to a force majeure, the Claimant sought the payment of the amount consequences.
equivalent to the liquidated damages deducted from the purchase price and interest.
In response, the Respondent objected that Claimant was not exempted because it (2) If the party's failure is due to the failure by a third person whom he has
failed to satisfy the requirements for exemption due to a force majeure. engaged to perform the whole or a part of the contract, that party is exempt
from liability only if:
Having found that the delay in delivery was due to a force majeure, the Arbitral
(a) he is exempt under the preceding paragraph; and
Tribunal examined the duration of the force majeure and the amount of the
liquidated damages. The Claimant was awarded the remainder exceeding the part (b) the person whom he has so engaged would be so exempt if the
granted by the Arbitral Tribunal at the daily rate for, and subject to a maximum of provisions of that paragraph were applied to him.
ten percent of, the purchase price of the delayed part out of the amount suspended
by the Respondent as the alleged liquidated damages. Further, the Arbitral Tribunal (3) The exemption provided by this article has effect for the period during which
denied in part the Claimant’s claim for interest. the impediment exists..

(4) The party who fails to perform must give notice to the other party of the
Excerpt
impediment and its effect on his ability to perform. If the notice is not received
by the other party within a reasonable time after the party who fails to perform
I. APPLICABLE LAW
knew or ought to have known of the impediment, he is liable for damages
resulting from such non-receipt.’
[1] “The formation, validity and the performance of this Contract shall be
governed by the laws of the Republic of Korea. Nothing in this Contract shall be [4] “Article 29 of the General Terms of this contract provides:
interpreted against the ‘Act on Contract to which the State is a Party.’ ‘All disputes, controversies, or differences which may arise between the Seller
and the Buyer in relation to this Contract shall be finally settled by arbitration
[2] “Article 2(f) of the United Nations Convention on Contracts for the International in Seoul, the Republic of Korea, in accordance with the Commercial Arbitration
Sale of Goods (CISG) provides that it does not apply to sales of aircraft. If the Rules of the Korean Commercial Arbitration Board.’”
subject matter of this contract were goods to which CISG applies, CISG would
apply to this contract by Article 1(1) (b) of CISG because the parties chose II. EXEMPTION DUE TO A FORCE MAJEURE
Korean law as the applicable law to the contract. Furthermore, CISG is an
international standard to be relied on for international trade in general as
[5] “Article 21 of the General Terms of this contract provides:
well as for international sales. Therefore, the arbitral tribunal takes CISG into
account in examining the claimant’s prerequisites of exemption from paying the ‘a. The Seller shall not be responsible for any delay or failure of Delivery
liquidated damages resulting from the delay in delivery. of Commodity which may arise from acts of God, fires, explosions, strikes,
lockouts, riots, civil commotions, mobilizations, threat or existence of war,

177 178
Korean Commercial Arbitration Board

blockades, embargoes, requisition of vessels, epidemics, changes in the be difficult to consider the attachments to be unlawful. Even if the attachments
relevant laws and regulations made after this Contract became effective, were groundless, they would not constitute a force majeure beyond the
or other causes beyond the Seller’s reasonable control (the ‘Force Majeure claimant’s control because they resulted from the dispute between the claimant
Event’). and its agent Company E. Therefore, the arbitral tribunal rejects the claimant’s
argument.”
b. Upon occurrence of the Force Majeure Event, the Seller shall notify the Buyer
by teletransmission and subsequent airmail within ten (10) days from such 2. Was the Delay in Delivery due to the Delay in Payment of the Purchase Price?
occurrence of the Force Majeure Event. The notification shall be attached by a
written certificate issued by the authorized governmental organization of the [9] “The claimant argues that even upon the delivery of the first and second
applicable country. The certificate shall indicate: airplanes the respondent paid the remaining amount deducting the amount
subject to the attachment orders from the purchase price for the two airplanes
(i) that the Seller could not reasonably foresee occurrence of the Force
in two installments three months later and five months and ten days later
Majeure Event at the time of execution of the Contract, and
respectively. The claimant therefore asserts that it is not responsible for the

(ii) that the Seller could not control the failure of or the delay in Delivery of delay in delivery of the third and fourth airplanes.
Commodity due to such Force Majeure Event.’
[10] “The arbitral tribunal is of the opinion that the seller to supply the goods to be
[6] “In accordance with the above provision of the contract, the claimant is entitled manufactured or produced is responsible to procure parts necessary for the
to be exempted from liability if it can prove cumulatively the following: manufacture of the goods, and that the buyer’s failure to pay in part does not
relieve the seller of the obligation to deliver the goods or the liability for the
(i) that the delay in delivery was due to a force majeure beyond its control; delay in delivery thereof. It appears that the delay in payment in part for the first
(ii) that the force majeure was not foreseeable at the time of the conclusion of installment was resulted from remedying the documents stipulated in the letter
the contract; and of credit or the dispute with respect to the payment of the liquidated damages
to be borne by the claimant. Therefore, the respondent is not liable for the delay
(iii) that it gave notice to the respondent of the force majeure.” in payment in part for the first installment. The arbitral tribunal rejects the
claimant’s argument because the claimant is not entitled to rely, based on the
1. Did the Alleged Unlawful Attachment Constitute a Force Majeure? respondent’s delay, on the exemption of liability for the delay in delivery of the
third and fourth airplanes.”
[7] “The claimant argues that the delay in delivery of the patrol airplanes was
due to a force majeure under Article 21 of the General Terms of this contract 3. Did the Failure for the Engineers to Access the Goods Constitute a Force
because it was unable to purchase major parts on time as a result of the Majeure?
unlawful attachments by Company E on the contract price.
a. Prerequisites of Exemption
[8] “While Company E had been an agent for the claimant’s business in Korea,
the claimant terminated the agency agreement on …. In response, Company E [11] “The claimant argues that the delay in delivery of the patrol airplanes was due
obtained the attachments order on the claim for the purchase price which the to Country B’s refusal of the engineers’ entry with the computer equipment
claimant held against the respondent. Furthermore, the arbitrator rendered triggered by the MV Mavi Marmara incident, which constitutes a force majeure.
an arbitral award ordering the claimant to pay US $ … to Company E. It would As reviewed above, the claimant is entitled to be exempted from liability if it can

179 180
Korean Commercial Arbitration Board

prove cumulatively the following: engineers entered Country B;


(i) that the delay in delivery was due to a force majeure beyond its control; (iii) that the integration between search radar and forward looking infrared
system was scheduled in the 19th and 20th flight tests;
(ii) that the force majeure was not foreseeable at the time of the conclusion
of the contract; and
(iv) that the technical data necessary for the installation of search radar was
(iii) that it gave notice to the respondent of the force majeure. procured barely on …;
Therefore, the arbitral tribunal examines the requirements.”
(v) that the independent navigation system provided by U.S. Company K
b. Whether the Delay in Delivery was due to a Force Majeure beyond Control had not been procured by the time of the pre-inspection of the Korea Coast
Guard; and
[12] “The arbitral tribunal finds that the integration between search radar and
forward looking infrared system manufactured by different producers is (vi) that even if the engineers had entered Country B in June …, they could
essential. The integration test consists of lab integration test, ground integration not have conducted the integration test because the bench integration test
test and flight integration test in the three phases. The lab integration test may tool sent by Company C arrived on December 22, …
be conducted with bench integration test tool which is a computer equipped
with necessary software. The lab integration test conducted before the ground [15] “However, the respondent’s above arguments are groundless on the following
integration test may be skipped. If, however, the lab integration test identified grounds:
any problem in integration, the claimant could resolve the problem in the
(i) that the incorrect version of the software, which was alleged as the cause
course of manufacturing the airplanes and deliver them on time.
of the failure of integration test, could result in the delay in delivery;

[13] “The arbitral tribunal finds that the engineers of Company C were unable to
(ii) that the flight test is separate from the integration test;
enter Country B and to conduct the lab integration test as scheduled, and that
they later conducted the unsuccessful ground integration test. The claimant’s
(iii) that as reviewed above the lab integration test was scheduled to be
remedying the failure resulted in the delay in delivery of the airplanes. Because
followed by the flight integration test;
of Country B’s refusal to issue visas triggered by the MV Mavi Marmara incident,
the engineers were unable to enter Country B. State’s refusal to issue visas
(iv) that the technical data necessary for the installation of search radar is
constitutes a force majeure beyond the claimant’s control.
not necessary in the phase of the lab integration test;

[14] “On the following grounds the respondent objected that the failure to conduct
(v) that as reviewed above the lab integration test requires only the bench
the lab integration test resulting from the delayed entry of the engineers did not
integration test tool and forward looking infrared system, not all of search
have a causal link to the delay in delivery of the airplanes:
radar, forward looking infrared system, independent navigation system,
etc.; and
(i) that the cause of the failure of integration test was the incorrect version
of the software installed in forward looking infrared system made by
(vi) that the delay of the lab integration test is not attributable to the delay
Company L;
of arrival of the bench integration test tool because the engineers were, in
entering Country B, supposed to take the tool.
(ii) that three flight tests had already been conducted by the day when the

181 182
Korean Commercial Arbitration Board

approval under the US Arms Export Control Act which takes a considerable
[16] “The respondent further argues that the delivery of the airplanes was delayed time. Thus, the claimant attempted to conduct the integration test at the US
not because the engineers were unable to enter Country B but because the parent company of Company L, but it was unable to conduct the integration test
supply of parts necessary for the manufacture of the airplanes was delayed by because the system retained by Company L was sent for the Farnborough Air
upstream suppliers, for which the claimant is responsible. However, the arbitral Show in the U.K.
tribunal finds that the delay in supply of parts necessary for the manufacture
of the airplanes resulted in the delay production rate of 3% to 14%, and that [20] “The respondent argues that under the US International Traffic in Arms
the extended working hours pushed up the process completion rate of the first Regulations the relocation of a defense article without transfer of ownership
airplane to 99.63% and that of the second to 98.62% in January, …. Therefore, is not subject to the approval by the US government. However, “reselling,
the arbitral tribunal rejects the respondent’s argument that the delay in delivery transferring, reexporting, retransferring, transshipping, or disposing” provided
of all the airplanes resulted from the delay of the supply of parts.” in the Regulations is not necessarily interpreted to mean the cases in which the
ownership is transferred. A temporary export is also subject to the Regulations.
c. Whether the Claimant Could not Reasonably Foresee the Cause of the Delay The arms trading control is not limited to the cases in which the ownership is
in Delivery transferred in light of the purpose to regulate exports to a third country. In light
of the foregoing, the arbitral tribunal is of the opinion that the relocation to a
[17] “A reasonable person is not expected foresee that Country I would raid a foreign third country is subject to the approval by the US government.
ship, that crew members would be killed by the raid, and that people of Country
B would be among them. The claimant could not reasonably have foreseen at [21] “As such, the claimant did a reasonable effort to avoid or overcome the force
the time of the conclusion of the contract that the MV Mavi Marmara incident majeure, i.e., the failure of the engineers to enter Country B and to conduct the
would arise and as a result the engineers would be unable to enter Country B. integration test, or its consequences by trying to let the engineers enter Country
Therefore, the second pre-requisite of exemption is satisfied for the claimant. B and to conduct the lab integration test in a third country Country S or at the
US parent company of Company L. Therefore, the arbitral tribunal rejects the
[18] “The respondent further argues that the claimant could have avoided or respondent’s argument that the claimant could have avoided the delay in the
overcome the force majeure by a reasonable effort of trying reentry of the integration test.”
engineers and conducting the integration test in a third country. The claimant
would not be liable if it could not reasonably foresee the force majeure and also d. Whether the Claimant Gave Notice to the Respondent of the Cause of the
avoid or overcome it or its consequences. Delay in Delivery

[19] “The arbitral tribunal finds that the claimant made an effort to contact the [22] “The claimant argues that because since July, … the respondent was aware that
government authorities of Country B for the entry of the engineers and as a the delivery of the airplanes would be delayed the claimant did not have to give
result the engineers were, with unofficial visas issued by Country B’s consulate notice to the respondent of the delay. However, there is no evidence to prove the
office in Singapore, able to enter Country B on December 20, …. argument. The arbitral tribunal therefore rejects this argument.

The arbitral tribunal also finds that the claimant considered the option to [23] “The arbitral tribunal finds that in the midterm checkup meeting held in Country
conduct the lab integration test in a third country Country S, not in Country B October 12 – 15, …, the claimant gave notice to the respondent of the possible
B, and that it turned out to be infeasible because handing over of the forward delay in delivery due to the failure of the engineers to enter Country B and to
looking infrared system of Company L to a third country was subject to the conduct the integration test.

183 184
Korean Commercial Arbitration Board

(…) bidder.
Therefore, the arbitral tribunal finds that the claimant gave notice to the The reply letter by the Korea Defense Acquisition Program Administration to the
respondent of the cause of the delay in delivery by October 15, … when the Korea Coast Guard expresses its opinion that the delay in supply of the search
meeting was closed. radar by Company C was due to the disruption of the diplomatic relations
between Country B and Country I, and that this constitutes a force majeure
[24] “In response, the respondent objects that the claimant failed to give notice to the beyond the claimant’s control and as a result it is entitled to the exemption of
respondent pursuant to Article 21(b) of the General Terms. The Article provides the liquidated damages.
that ‘[u]pon occurrence of the Force Majeure Event, the Seller shall notify the
Buyer by teletransmission and subsequent airmail within ten (10) days from In light of the foregoing, the arbitral tribunal is of the opinion that the delay
such occurrence of the Force Majeure Event. The notification shall be attached in delivery of the airplanes was due to the failure of the engineers to enter
by a written certificate issued by the authorized governmental organization of Country B and to conduct the integration test on time, that this constitutes a
the applicable country.’ The respondent therefore argues that the claimant was force majeure beyond the claimant’s control which it could not reasonably be
not entitled to rely on the force majeure. expected to foresee and to avoid or overcome, and that the claimant gave notice
to the respondent thereof. Therefore, the claimant is entitled to rely on the
[25] “The arbitral tribunal finds that the claimant failed to give notice in accordance exemption of liability based upon the force majeure.
with Article 21 of the General Terms. However, the arbitral tribunal is of the
opinion that the notice is a procedural requirement to prove the force majeure, [27] “The respondent objects that because the claimant is responsible for conducting
that the exemption remains unaffected in case of the failure to notify, and that the integration between the search radar and the forward looking infrared
the party who fails to notify is liable to compensate the damages which have system the claimant must not be exempted from liability due to the failure of
arisen from the failure (Article 79(1), (4) of CISG). Therefore, the claimant is the engineers to enter Country B. If, however, the party’s failure to perform
entitled to rely on the exemption because it gave notice to the respondent of its obligations is due to the failure by a third person whom it has engaged to
the force majeure. However, the claimant would not be exempted from liability perform a part of the contract, that party is exempted from liability by relying
during the period when it failed to perform its duty to notify. The arbitral tribunal on the person’s force majeure under certain requirements (Article 79(2)). The
grants the respondent’s argument to that extent.” arbitral tribunal therefore rejects the respondent’s argument.”

e. Conclusion on the Force Majeure f. Claimant’s Other Arguments for Exemption

[26] “The arbitral tribunal recognizes that the respondent’s decision to purchase the [28] “The claimant argues that the delivery date for the first and second airplanes
airplanes from the claimant was based on diplomatic and political consideration was extended to April, … by the respondent’s consent at the meeting in January,
rather than business and technical consideration because the contract was …. However, the arbitral tribunal is unpersuaded by Exhibit 4 on which the
in tandem with the other contract whereby Country B purchased T50 practice claimant relied. There is no evidence that the delivery date was extended.
planes from Korea.
[29] “The claimant further asserts that the respondent admitted the force majeure
Also due consideration is to be given to the respondent’s request to replace the in delivering the first and second airplanes by paying on October 28, … US $...
US search radar to be installed in the airplanes with another made by Company whose payment had been suspended by it. However, Exhibits 1 and 2 show that
C in Country I while the specifications in the bidding did not require the search the respondent expressed its intent not to waive the liquidated damages when
radar made by Company C when the claimant was chosen as the preferred paying the above suspended payment. Therefore, the arbitral tribunal rejects

185 186
Korean Commercial Arbitration Board

the claimant’s argument.” following the day of its notice of the force majeure until the day when the force
majeure ends. As reviewed above, the claimant gave notice of the force majeure
to the respondent on October 15, … and the engineers of Company C entered
III. LIQUIDATED DAMAGES
Country B and conducted the integration test on December 22, …. Therefore,
the claimant could be exempted from liability for the delay in delivery during the
[30] “In light of the foregoing, the arbitral tribunal finds that the delay in delivery of period of 68 days. If the claimant was able to perform earlier, it would be liable
the airplanes was due to the force majeure and thus the claimant is entitled from the following day.
to be exempted from liability. The arbitral tribunal examines next the extent to
which the claimant is exempted from liability.” [34] “As reviewed above, the process completion rate of the first and second
airplanes was well over 98% in January, … and on February 10, …. The claimant,
1. Whether the Liquidated Damages Are Excessive succeeding in the integration test, promised to deliver the first and second
airplanes by April, …. At the hearing held in Country B, the claimant stated that
[31] “The claimant argues that the liquidated damages should be reduced in the delivery would take about 53 days upon the completion of the integration
accordance with Article 398 of the Korean Civil Code because they are test. The witness Mr. BS testified that if the lab integration test had been
unreasonably excessive even if it is obliged for them. Article 20 of the General conducted before December, … the first and second airplanes could have been
Terms provides that the claimant is obligated to pay liquidated damages to the delivered by the delivery date, February 17, …. In light of the foregoing, the
respondent at the rate of 0.15% of the contract price of the delayed part for each arbitral tribunal finds that the claimant was able to deliver the first and second
day of delay with the cumulative total not exceeding 10% of the total contract airplanes to the respondent at latest by mid-April, …. Therefore, the claimant is
amount. The arbitral tribunal is of the opinion that the liquidated damages liable to the respondent for the delay in delivery of the first and second airplanes
agreed upon by the parties are a kind of calculation of damages in advance to after April 15, ….
which Article 398 of the Korean Civil Code applies.

Meanwhile, as reviewed above, the integration test for the third and fourth
[32] “The arbitral tribunal recognizes that the liquidated damages at the rate of 0.15% airplanes was conducted in December, … and they were able to be delivered
of the contract price of the delayed part for each day of delay are ordinary in without difficulties by the delivery date, June 17, …. Therefore, the delay in
domestic and international contracts and are not excessive in amount. However, delivery of the third and fourth airplanes has no causal link to the force majeure
the cumulative total of the liquidated damages set at 10% of the total contract on which the claimant relies.”
amount instead of the delayed part only is unreasonably excessive because
the delay in trivial part could amount to 10% of the total contract amount. … 3. Calculation of the Liquidated Damages
Therefore, the arbitral tribunal, pursuant to Article 398(2) of the Korean Civil
Code, reduces the cumulative total of the liquidated damages to 10% of the a. Calculation of the Liquidated Damages for the First and Second Airplanes
contract price of the delayed part, not of the total contract price.”

[35] “The claimant should have delivered the first and second airplanes by April 15,
2. Period during which Liability is Exempted …. However, the first airplane was delivered on May 10, and the second was
delivered on May 14, … respectively. Therefore, the claimant is liable for the
[33] “In general the exemption due to a force majeure has effect for the period delay of 25 days for the first airplane and of 29 days for the second respectively.”
during which the force majeure exists (Article 79(3) of CISG). Therefore, the (….)
claimant is exempted from liability for the delay in delivery from the day

187 188
Korean Commercial Arbitration Board

b. Calculation of the Liquidated Damages for the Third and Fourth Airplanes Implications

[36] “The claimant should have delivered the third and fourth airplanes by June I. APPLICABLE LAW
17, …. However, the third airplane was delivered on January 17, and the fourth
was delivered on March 11, … respectively. Therefore, the claimant is liable The parties chose Korean law as the applicable law to the contract in this case. The
for the delay of 201 days for the third airplane and of 255 days for the fourth sales of aircraft is excluded from the CISG’s sphere of application. Furthermore, the
respectively. As reviewed above, the cumulative total of the liquidated damages parties did not opt into CISG. However, the Arbitral Tribunal takes CISG into account
is limited to 10% of the contract price of the delayed part.” in examining the Claimant’s exemption of liability on the ground that CISG is an
international standard for international trade.
c. Calculation of Suspended Payment Exceeding the Liquidated Damages
II. EXEMPTION OF LIABILITY DUE TO A FORCE MAJEURE
[37] “The respondent paid the remaining contract price deducting the liquidated
damages of US $ … from the total contract price. Therefore, the respondent
is obligated to pay the amount of US $ …, the remainder exceeding the part 1. Exemption from Liability for the Conduct of Third Persons
granted by the arbitral tribunal out of the amount suspended by the respondent
Article 79(2) of CISG provides that:
as the alleged liquidated damages.”
“If the party’s failure is due to the failure by a third person whom he has
engaged to perform the whole or a part of the contract, that party is exempt
IV. INTEREST
from liability only if:
(a) he is exempt under the preceding paragraph; and
[38] “The respondent is obligated to pay to the claimant US $ … of the unlawfully (b) the person whom he has so engaged would be so exempt if the
deducted part of the contract price and 20% per annum interest, as provided provisions of that paragraph were applied to him.”
in the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings,
thereupon from the date following the date of the delivery of the arbitral award Article 79(2) of CISG intends to cover not the third persons under the party’s
to the date of full payment. organizational structure and sphere of control but those acting independently
under its responsibility. An upstream supplier of the seller is not considered to be
Meanwhile, the claimant seeks 5% per annum interest from the date following a third person the seller has engaged to perform a part of the seller’s contract. The
the date of delivery of the fourth airplane to the date of the arbitral award. supplier may supply to the seller manufactured parts necessary for the manufacture
However, the arbitral tribunal is of the opinion that it is reasonable for the of the goods. The failure of the supplier to provide the seller with the parts does
respondent to contest the existence and extent of the obligation to pay the not constitute an impediment under Article 79(2). This falls under the seller’s
remaining part of the contract price. Therefore, the arbitral tribunal dismisses procurement risk for the parts. The seller has the duty to procure the parts from
the claimant’s claim for 5% per annum interest.” some other source. However, the seller may be exempted with respect to the failure
(….) of the supplier if the seller successfully meets the requirements under Article
79(1).36)

36) United Nations Commission on International Trade Law, supra note 10, at 392-393; Kröll
et al., supra note 10, at 1080-1081, 1083-1084; Schwenzer, supra note 10, at 1077-1079.

189 190
Korean Commercial Arbitration Board

Referring to Article 79(2) of CISG, the Arbitral Tribunal holds that the Claimant is to be exempted from paying damages caused by the late delivery.38) The extent of
entitled to be exempted from liability. The Arbitral Tribunal finds that the Claimant exemption from paying damages in respect of late delivery should be determined
has engaged a third person Company C to perform a part of its contract, and that the by the duration of the impediment. The period during which the impediment exists
failure of Company C to perform was due to an impediment and the seller’s failure and accordingly the extent of exemption in respect of late delivery would not be
was due to the failure of Company C’s failure. It is clear that Company C is a supplier influenced by a notice of the impediment. Even with the failure to give notice of
of parts necessary for the manufacture of the airplanes by the Claimant. the impediment as provided in Article 79(4), the exemption of liability may remain
unaffected. However, the other party has the right to claim damages which have
2. Exemption from Liability for Liquidated Damages arisen from the non-receipt, imprecise or untimely receipt of notice. 39)The period
during which the Claimant is entitled to be exempted from liability in this case
In this case the Arbitral Tribunal calculated the liquidated damages under the starts, irrespective of the timeliness of the notice, upon the occurrence of the
premise that the exemption due to an impediment extends to the contractually impediment, not upon the notice of the impediment. The untimeliness of the notice
agreed sums, that is, the liquidated damages. Article 79(5) provides that “[n]othing by the Claimant may give rise to only the Respondent’s right to claim damages with a
in this article prevents either party from exercising any right other than to claim causal relation with it.
damages under this Convention.” Therefore, it is not expressly regulated in CISG
whether the exemption due to an impediment extends to the contractual obligation III. INTEREST
to pay liquidated damages or penalties. The impact of an impediment on such a
While the Claimant seeks 5% per annum interest from the date following the date
contractual agreement must be decided according to the purpose of the parties
of delivery of the fourth airplane to the date of the Arbitral Award, the Arbitral
found by interpreting the agreement – i.e., whether they have stipulated payment
Tribunal dismisses the Claimant’s claim on the ground that it is reasonable for
of liquidated damages or penalties instead of a damages claim. In case of doubt, a
the Respondent to contest the existence and extent of the obligation to pay the
claim for damages under CISG should be deemed to be replaced by a contractual
remaining part of the contract price. Once, however, the Arbitral Tribunal finds that
claim. Therefore, the exemption of liability extends to the liquidated damages by
the Respondent is obligated to pay the contract price to the Claimant, the Arbitral
directly or at least indirectly applying Article 79.37) The Arbitral Tribunal first could
Tribunal could have ordered the Respondent to pay the contract price and interest
have examined whether the exemption of liability extends to the liquidated damages.
thereon. No legal effects could be imputed to the starting point of interest accrual by
whether it is reasonable for the Respondent to contest the existence and extent of
3. Temporary Force Majeure and Extent of Exemption
the obligation to pay.

Under the premise that the exemption due to a force majeure has effect for the
period during which the force majeure exists, the Arbitral Tribunal is of the opinion
in this case that the Claimant is exempted from liability for the delay in delivery
from the day following the day of its notice of the force majeure until the day when
the force majeure ends. The extent of the exemption from paying damages due to
an impediment must be determined by the effect of the impediment. In this case
the impediment caused the delay in delivery. As a result, the Claimant is entitled

38) Schwenzer, supra note 10, at 1082; Kröll et al., supra note 10, at 1060-1061.
37) Kröll et al., supra note 10, at 1060-1061; Schwenzer, supra note 10, at 1082-1083 39) Kröll et al., supra note 10, at 1094-1095; Schwenzer, supra note 10, at 1081.

191 192
Korean Commercial Arbitration Board

Claimant’s products.

The Claimant initiated arbitration relying on the arbitration clause contained in


the agreement providing for KCAB arbitration. The agreement provided that the
KCAB case no.11
applicable law to the dispute was Korean law. The Claimant sought damages resulting
from the breach of the agreement, the infringement of the trademark rights, unfair
Parties Claimant: Cosmetic Company A (Israel)
competition, or torts and interest. In response, the Respondent objected that it
Respondent: Cosmetic Company B (Korea)
used for its products colors not listed negatively in the agreement. The Respondent
Place of further argued that the allegedly similar products were not confirmed to be
Arbitration Seoul, Republic of Korea manufactured after the conclusion of the agreement.

Language Original in Korean


The Arbitral Tribunal first held that the Respondent breached the agreement
Subject matters - applicable law to the substance unless it persuasively proved the similar products were manufactured prior to the
- applicable law to the arbitration agreement conclusion of the agreement. The Arbitral Tribunal then found that the Respondent
- scope of the arbitration agreement was liable to pay damages resulting from the infringement of the trademark rights
- entire agreement clause by manufacturing and selling its products with similar trademark on them. However,
- infringement of trademark rights the Arbitral Tribunal dismissed the Claimant’s argument for unfair competition on
- unfair competition the ground that the Claimant failed to prove that its trademark was widely known
- tort claim in Korea. But the Tribunal held that the Respondent’s manufacturing and selling its
- calculation of damages products with similar trademark on them were sufficient to constitute a tort, and the
- statutory interest rate Respondent was liable for the Claimant’s damages.

Excerpt

Facts I. APPLICABLE LAW

1. Applicable Law to the Substance


The Respondent displayed its hair treatment products with trademark “A oil” on
them in a trade show. The trademark has been registered for the Claimant at the
[1] “Article 15 of the Settlement Agreement provides that ‘[t]his agreement is to be
Korean Intellectual Property Office. The Claimant sought an injunction against
construed under Korean law.’ Article 12 also provides that ‘[i]n the event that
the Respondent to bar the infringement of the trademark rights and the unfair
any future dispute arises between Company A and Company B concerning the
competition at the Central Court in the State of California. In the course of the
terms, conditions, or enforceability of this Agreement, the Parties agree that
litigation, the parties concluded the “Settlement Agreement” to resolve their dispute.
proper and exclusive venue for such dispute shall be the Korean Commercial
The Respondent was obligated not to use for its products similar packaging to the
Arbitration Board (KCAB). Company A and Company B hereby consent to
Claimant’s packaging and a prominent capital letter “M.” The Respondent also
personal jurisdiction in the KCAB and waive any objection to the KCAB based on
agreed not to challenge or contest the Claimant’s trademark rights worldwide. After
improper or inconvenient venue.
the conclusion of the agreement, the Respondent manufactured and sold allegedly
similar products on line as well as in Korea, which caused confusion with the
[2] “The arbitral tribunal determines the law applicable to the dispute and to the

193 194
Korean Commercial Arbitration Board

arbitration agreement in accordance with the Arbitration Act and the Private was violated by the infringement of the trademark rights, unfair competition
International Law of Korea, the seat of the arbitration. or a tort. Therefore, Korean law, the applicable law to the agreement, is the
applicable law to the infringement of the trademark rights, unfair competition
First, Article 29(1) of the Arbitration Act provides that ‘[t]he arbitral tribunal or the tort. In conclusion, the applicable law to the dispute in this case is Korean
shall decide the dispute in accordance with such rules of law as are chosen by law which the parties chose
the parties as applicable to the substance of the dispute.’ Article 25(1) of the
Private International Law also provides that ‘[a] contract shall be governed by 2. Applicable Law to the Arbitration Agreement
the law expressly or implicitly chosen by the parties.’ As such, party autonomy
is respected for the choice of law. Because the parties agreed to interpret the [3] “Both the Korean Arbitration Act and the Korean Private International Law
Settlement Agreement in accordance with Korean law, the applicable law to the remain silent on the applicable law to the arbitration agreement. With respect
alleged breach of the agreement is Korean law. to this, the Supreme Court of Korea has held that ‘[t]he validity and effect of the
arbitration agreement is determined by the law of the seat of the arbitration or
Furthermore, the arbitral tribunal examines the applicable law to the the applicable law to the arbitration clause’ (see Supreme Court Decision No.
infringement of the trademark rights, unfair competition and a tort. Article 88Daca23735 dated Feb. 13, 1990). Therefore, the applicable law to the effect
29(2) of the Arbitration Act provides that ‘[f]ailing the designation referred to in of the arbitration agreement is Korean law which is the applicable law to the
paragraph (1), the arbitral tribunal shall apply the law of the State with which Settlement Agreement or the law of the seat of the arbitration.”
the subject matter of the dispute is most closely connected.’ However, the
Arbitration Act fails to provide for any standard in determining the law of the II. SCOPE OF THE ARBITRATION AGREEMENT
state with which the subject matter of the dispute is most closely connected.
Referring to the Private International Law, the arbitral tribunal therefore [4] “With respect to whether the arbitration agreement on disputes arising out
determines the law of the state with which the subject matter of the dispute of a contract extends to a tort, the Supreme Court of Korea has held that ‘[t]
is most closely connected. Article 24 of the Private International Law provides he arbitration agreement covers not only the contract itself containing the
that ‘[t]he protection of an intellectual property right shall be governed by the agreement but also disputes directly related to or closely connected with the
law of the state where the right was infringed.’ Therefore, the applicable law to existence, the performance and the effect of the contract (see Supreme Court
the infringement of the trademark rights and the violation of unfair competition Decision No. 2004Da67264 dated May 13, 2005); the arbitration agreement
law, closely related to the former, is the law of Korea with which the subject extends to a claim for damages founded in tort with which the contract is closely
matter of the dispute is most closely connected and where the infringement connected (see Supreme Court Decision No. 91Da17146 dated Apr. 14, 1992);
is prevailing in scope. Article 32(1) of the Private International Law provides and it is reasonable to deem that the arbitration agreement, absent special
that ‘[a] tort shall be governed by the law of the state where in which the event circumstances, covers all disputes arising between the parties in respect of a
giving rise to the damage occurred.’ The applicable law to the alleged tort by the defined legal relationship (see Supreme Court Decision No. 2005Da74344 dated
respondent is the law of Korea with which the subject matter of the dispute is May 31, 2007).’
most closely connected and where the tort was mostly committed.
In light of the foregoing decisions of the Supreme Court of Korea, the arbitral
Meanwhile, Article 32(3) provides that ‘[n]otwithstanding the preceding tribunal is of the opinion that the arbitration agreement extends to the disputes
paragraphs, if a tort violates an existing legal relationship between the in respect of the infringement of the trademark rights, unfair competition
tortfeasor and the injured party, it shall be governed by the law applicable to that and the tort with which the breach of the Settlement Agreement is closely
legal relationship.’ Between the parties exists the Settlement Agreement which connected.”

195 196
Korean Commercial Arbitration Board

III. BREACH OF THE SETTLEMENT AGREEMENT reviewed above, the respondent admitted that no representation or promise
not expressly contained in the Agreement has been made and the parties are
not entering into the Agreement on the basis of any promise, representation or
[5] “As reviewed above, the respondent agreed not to adopt confusingly similar
statement, express or implied, which is not specifically set forth therein (Article
trade dress to that currently used by the claimant for its own products (Article
16 of the Settlement Agreement). The respondent is not entitled to rely on the
6 of the Settlement Agreement), and, to enforce this, to discontinue use of the
transcripts as a part of the Settlement Agreement.
amber color and glass bottle similar to the ones being used by the claimant and
to change the packaging for its products to incorporate design elements which
Also the respondent argues that there is no evidence produced by the claimant
are not substantially similar to the packaging on the claimant’s product (Article
to corroborate its claim that the respondent’s products have been manufactured
1 of the Settlement Agreement).
after the conclusion of the Settlement Agreement. However, the products are
presumed to have been manufactured after the conclusion of the agreement
In comparing the respondent’s products to the claimant’s product, the arbitral
as long as they are being marketed. The respondent bears the onus of
tribunal finds that the respondent’s products have changed in part design
demonstrating that the products were manufactured prior to the conclusion of
elements of the previous ones but use orange colored trademark ‘B oil’ on
the agreement. Notwithstanding the respondent’s argument to the contrary, the
the packaging and labelling, similar light blue packaging and labelling, and
arbitral tribunal finds that the products marketed in Korea were manufactured
amber color and glass bottle. The arbitral tribunal therefore notes that the
on July 31, … which is after the conclusion of the agreement. The respondent
respondent’s products cause confusing with the claimant’s product.
is not entitled to argue that it has not breached the agreement unless it
satisfies the burden of proving that the products marketed abroad were also
As such, the respondent’s manufacture and sales of its products breached the
manufactured prior to the conclusion of the agreement.
agreement to discontinue use of the amber color and glass bottle and not to
adopt confusingly similar trade dress. Therefore, the arbitral tribunal holds that
Therefore, the arbitral tribunal dismisses the respondent’s argument that the
the respondent breached the Settlement Agreement.
products have not breached the agreement.

[6] “The respondent argues that it did not agree not to use light blue packaging for
[7] “The arbitral tribunal holds that the respondent’s manufacture and sales of the
its own products but agreed not to use a total of 12 colors, including Pantone
products breached Articles 1 and 6 of the Settlement Agreement, and that the
color 305C, exhaustively listed in the Settlement Agreement. The respondent
respondent is obligated to pay damages thereof for the claimant.”
further objects that its products used Pantone color 310C not listed in the
agreement and thus did not breach the agreement.
IV. INFRINGEMENT OF THE TRADEMARK RIGHTS
As reviewed above, however, the respondent agreed not to manufacture and
sell products confusingly similar to the claimant’s product. Considering that 1. Identicalness and Similarity to the Registered Trademark and the Designated
the parties have agreed that the packaging shown in Exhibit C is acceptable Goods
and non-infringing, it cannot be deemed that the Settlement Agreement
exhaustively lists a total of 12 colors as the colors for the respondent not to use [8] “Under the Korean Trademark Act, the identicalness and similarity to the
and the respondent is allowed to freely use the other colors. In this respect, registered trademark and the designated goods are required to constitute the
submitting transcripts (Exhibit 12), the respondent argues that the parties made infringement of the trademark rights.”
an agreement different in the contents from the Settlement Agreement. As
a. Identicalness and Similarity to the Designated Goods

197 198
Korean Commercial Arbitration Board

[9] “The designated goods of the trademark for the claimant in Korea are hair oil’ on them constitute the infringement of the claimant’s trademark rights.
lotion, hair oil, etc. The respondent’s products are hair oil which is identical to Therefore, the respondent is obligated to pay damages the claimant suffered
the hair oil, one of the designated goods. Therefore, this satisfies the requirement from the infringement.”
of the identicalness of the designated goods to constitute the infringement of
the trademark rights.” V. UNFAIR COMPETITION

1. The Prerequisites of Unfair Competition


b. Similarity to the Registered Trademark
[13] “Article 2(1)(a) of the Korean Unfair Competition Prevention and Trade Secret
[10] “The similarities of the trademarks are determined by examining them in their Protection Act provides that ‘[a]n act of unfair competition is constituted by an
entireties as to their appearance, sound and meaning. The trademark of the act of causing confusion with another person’s goods by using marks identical
claimant, ‘A oil’ and the trademark of the respondent, ‘B oil’ are similar in their or similar to, another person’s name, trade name, trademark, or container or
appearance. … Also the two trademarks are similar in their sound. … Lastly, package of goods, or any other mark indicating another person’s goods, which
the two trademarks are similar in their meaning because the marks mean oil is widely known in Korea; or by selling, distributing, importing or exporting
originating from the Mediterranean countries. Therefore, the arbitral tribunal goods bearing such marks.’ The manufacture and sales of the respondent’s
finds that the two trademarks are similar as to their appearance, sound and products constitute an act of unfair competition if the following requirements
meaning.” are met: (i) that the claimant’s trademark, container or package of the products
is widely known in Korea; (ii) that the respondent’s mark is identical or similar
2. Extent of Effect of the Registered Trademark to the claimant’s mark; and (iii) that the respondent’s manufacture and export
of its products cause confusion with the claimant’s products.”
[11] “The respondent argues that the effect of the claimant’s trademark rights does
not extend to the respondent’s trademark because it is ‘a trademark indicating 2. The Claimant’ Mark
the common name, place of production, quality, raw materials, efficacy, uses,
quantity, shape, price, or methods of production, methods of processing, [14] “The arbitral tribunal first examines whether the claimant’s trademark,
methods of use and time of goods identical or similar to the designated goods container and package of its products constitute the mark indicating its products
of the registered trademark according to methods in common use.’ ‘B’ is a under the Act. The arbitral tribunal finds that the claimant’s trademark, ‘A oil’ is
geographical name and … means oil originating in the above area. Therefore, no doubt the mark indicating its products and further finds that the claimant’s
they are common names. However, the arbitral tribunal is of the opinion that ‘A products can be differentiated from other products with light blue packaging
oil’ combining ‘B oil’ and … is not a trademark indicating the common name or and labelling symbolizing the color of the Mediterranean Sea, the amber color
place of production according to methods in common use. The arbitral tribunal and glass bottle effectively showing their functionality, and orange colored
therefore dismisses the respondent’s argument.” letters on the packaging. The arbitral tribunal recognizes that the claimant has
continued to advertise its products in Korea and abroad and thus they have
3. Tribunal’s Conclusion been individualized enough for the traders or consumers to associate their
color and shape with them due to the differentiating characteristics. Therefore,
[12] “Finding that the trademark of the claimant, ‘A oil’ and the trademark of the the arbitral tribunal holds that the claimant’s products are unique in their
respondent, ‘B oil’ are similar as to their appearance, sound and meaning packaging, labelling, the color of the container, and the combination thereof and
and their designated goods are identical, the arbitral tribunal holds that the thus the container and packaging of the products, along with the trademark,
respondent manufacturing and selling the products with the trademark ‘B also constitute a mark indicating its products.”

199 200
Korean Commercial Arbitration Board

3. Confusing Similarity VI. TORT CLAIM

1. The Prerequisites of a Tort


[15] “As reviewed above, the trademark of the respondent ‘B oil’ is similar to
that of the claimant ‘A oil.’ The respondent uses similar lettering in orange [18] “Even if it does not constitute an infringement of the intellectual property rights
colored type for its trademark, the amber color and glass bottle, and light blue or an act of unfair competition, an act to gain undue interests at the expense of a
packaging and labelling. The arbitral tribunal therefore is of the opinion that competitor’s legally protected legitimate interests by using the achievements of
the respondent’s products are similar to the claimant’s product. Furthermore, the competitor’s substantial efforts and investment without authorization, which
the respondent advertises its products with a capital letter ‘M’ and ‘Korea OEM’ is contrary to good commercial morals or the fair competition order, would
on them, which gives rise to misunderstanding that the products have been constitute a tort under the Korean Civil Code (see Supreme Court Decision No.
manufactured by the respondent according to the order of the claimant. In 2010Da20044 dated Mar. 29, 2012; Supreme Court Decision No. 2008Ma1541
practice some consumers mistook the respondent’s products for the claimant’s dated Aug. 25, 2010). The arbitral tribunal examines whether the respondent’s
products and thus purchased them. Based upon the foregoing, the arbitral manufacturing and selling the products constitute a tort.”
tribunal is of the opinion that the respondent’s products cause confusing with
the claimant’s product by using similar trademark, container, packaging, etc.” 2. Unlawful Competition

4. Wide Knowledge [19] “The arbitral tribunal finds that the claimant chose ‘A oil’ for its trademark,
differentiated its products from others in terms of the packaging and container
[16] “In addition, the arbitral tribunal examines whether the claimant’s mark shape, continued to advertise its products in Korea and abroad, gained
indicating its products is widely known in Korea. substantial reputation from the consumers, and thus the products are its
(….) achievements with its substantial efforts and investment. Taking advantage
With the above facts, the arbitral tribunal is not persuaded that the claimant’s of the reputation for the claimant’s products achieved by its efforts and
mark indicating its products is widely known in Korea. There is no evidence investment, the respondent manufactures, sells and exports similar products in
sufficient to prove this.” Korea and abroad, and gains substantial profits. As a consequence of this, the
claimant suffers damages. The arbitral tribunal therefore is of the opinion that
5. Tribunal’s Conclusion the act of the respondent constitutes an act of unlawful competition contrary to
good commercial morals or the fair competition order.”
[17] “The respondent’s selling its products would constitute an act of unfair
competition under the Korean Unfair Competition Prevention and Trade Secret 3. Tribunal’s Conclusion
Protection Act if the claimant satisfied its burden of proof proving that the
claimant’s mark indicating its products is widely known in Korea. In light of [20] “The respondent’s manufacturing and selling its products would not constitute
the foregoing, the arbitral tribunal dismisses the claimant’s claim for unfair an act of unfair competition under the Korean Unfair Competition Prevention
competition on the ground that the claimant failed to discharge the burden.” and Trade Secret Protection Act because it was not sufficiently proved that the
claimant’s products are widely known in Korea. However, the respondent’s
manufacturing and selling its products are an act of unlawful competition
and are considered sufficient to constitute a tort under the Korean Civil Code.
The arbitral tribunal therefore holds that the respondent is obligated to pay
damages suffered by the claimant.”

201 202
Korean Commercial Arbitration Board

VII. QUANTUM OF DAMAGES Implications


[21] “It is sufficiently found in accordance with the rules of logic and experience that
I. APPLICABLE LAW
the claimant suffered damages due to the respondent’s manufacturing and
selling its products which constituted the breach of the Settlement Agreement, 1. Applicable Law to the Substance
the infringement of the trademark rights, and a tort. The arbitral tribunal now
considers the quantum of damages suffered by the claimant. It is an evident It is clear that the applicable law to the breach of the “Settlement Agreement” is
fact that the margin of the cosmetics manufacturing industry is more than 10% Korean law expressly chosen by the parties. However, certain categories of claim
of the total sales. The arbitral tribunal finds that the increase in the claimant’s cannot be subject to the applicable law chosen by the parties.40) The Arbitral Tribunal,
sales in Korea remarkably dropped due to the respondent’s manufacturing referring to the Korean Private International Law, determines the applicable law
and selling its products in …. The arbitral tribunal is of the opinion that the to the infringement of trademark rights, unfair competition and a tort. It is correct
reduction of the claimant’s sales due to the respondent’s manufacturing that the Arbitral Tribunal determines the applicable law to those issues instead of
and selling its products amounts to at least KRW 500,000,000 and as a result applying the parties’ chosen law. Article 29(2) of the Korean Arbitration Act provides
the claimant suffered loss of profit in the amount of KRW 50,000,000. In the that “[f]ailing the designation referred to in paragraph (1), the arbitral tribunal shall
infringement of a trademark right where damages have been suffered but it apply the law of the State with which the subject matter of the dispute is most closely
is difficult, because of their nature, to verify the facts necessary to prove the connected.” Article 25(1) of the International Arbitration Rules of the KCAB provides
quantum thereof, reasonable quantum of damages may be awarded based on that “[i]n the absence of any such agreement, the Arbitral Tribunal shall apply the
the evidence and the tenor of all the pleadings. This also applies by analogy in substantive laws or rules of law which it determines to be appropriate.” Neither the
calculating damages resulting from the breach of a contract or a tort. In light Korean Arbitration Act nor the Rule stipulates the application of any conflict of laws
of all the circumstances including the total sales and advertising costs of the rule. If the Arbitral Tribunal had referred to the relevant provisions of the Rule and
claimant’s products in Korea and abroad, the arbitral tribunal is of the opinion stated why the Tribunal referred to the Korean Private International Law even when
that damages suffered by the claimant are reasonably calculated in the amount it is not stipulated to do so, it might have been better. Also, if the Arbitral Tribunal,
of KRW 50,000,000.” where it considers it proper to refer to any conflict of laws rule, had stated why it
considers the Korean Private International Law applicable, it might have been better.

VIII. INTEREST
In addition, the Arbitral Tribunal holds that the applicable law to the infringement
[22] “The respondent is obligated to pay to the claimant KRW 50,000,000 and of trademark rights and the violation of unfair competition law, closely related
20% per annum interest, as provided in the Act on Special Cases Concerning to the former, is the law of Korea with which the subject matter of the dispute
Expedition, etc. of Legal Proceedings, thereupon from the date following is most closely connected and where the infringement is prevailing in scope.
the date of the closing of the proceedings to the date of full payment. The Unlike the Rome II Regulation which provides a separate conflict of laws rule for
arbitral tribunal grants the claim for damages to this extent and dismisses the unfair competition, the Korean Private International Law remains silent for unfair
remainder of the claim.” competition. Unless and until the Korean Private International Law sets forth a
separate conflict of laws rule for unfair competition, it would be reasonable to
resort to the conflict of laws rule for a tort rather than that for an infringement of an
intellectual property right.

40) Born, supra note 8, at 2721-2722.

203 204
Korean Commercial Arbitration Board

2. Applicable Law to the Arbitration Agreement In this case the parties agreed on an entire agreement clause. Article 16 of the
“Settlement Agreement” stipulates that “[e]ach Party represents and warrants
The Arbitral Tribunal holds that the applicable law to the arbitration agreement is that no representation or promise not expressly contained in the Agreement has
Korean law which is the applicable law to the “Settlement Agreement” or the law been made and the parties are not entering into the Agreement on the basis of any
of the seat of the arbitration. In doing so, the Arbitral Tribunal relies on Korean promise, representation or statement, express or implied, which is not specifically
Supreme Court’s decision which is ambiguous with respect to whether the decision set forth herein.” Submitting transcripts, the Respondent argues that the parties
pointed the applicable law to the arbitration clause or to the main contract. However, made an agreement different in the contents from the “Settlement Agreement.”
a distinction is made between the applicable law to the substance and the applicable Rejecting the Respondent’s argument, the Arbitration Tribunal, based on the entire
law to the arbitration agreement. If the Arbitral Tribunal had ascertained whether the agreement clause, correctly holds that the Respondent is not entitled to rely on the
parties had chosen the applicable law to the arbitration agreement and, failing any transcripts as a part of the “Settlement Agreement.”
designation by the parties, explained how to determine the applicable law, it might
have been better. In particular, if the Arbitral Tribunal had first examined whether IV. STATUTORY INTEREST RATE
the parties implicitly had chosen the applicable law to the arbitration agreement, it The Arbitral Tribunal grants in part of the claim for damages and orders the
might have been better. Respondent to pay to the Claimant 20% per annum interest, as provided in the Act
on Special Cases Concerning Expedition, etc. of Legal Proceedings, thereupon
II. SCOPE OF THE ARBITRATION AGREEMENT from the date following the date of the closing of the proceedings to the date of
full payment. Article 3(2) of the Act provides that “[w]here it is deemed reasonable
The Arbitral Tribunal correctly holds that the arbitration agreement extends to the for an obligor to contest whether he or she is responsible for the performance of
disputes in respect of the infringement of trademark rights, unfair competition and obligations or the extent thereof not later than a ruling that the obligor is responsible
the tort with which the breach of the “Settlement Agreement” is closely connected. for the performance of such obligations at a fact-finding proceeding is adjudicated,
In determining the scope of the arbitration agreement, the arbitration agreement paragraph (1) shall not apply to the reasonable extent.” In this case it is deemed
itself, other relevant contractual provisions, the notice of request for arbitration, reasonable for the Respondent to contest the existence or extent of its obligation.
and the pleadings exchanged between the parties are taken into account. A broad The Arbitral Tribunal holds that 20% per annum interest starts to accrue from the
interpretation is adopted for the arbitration agreement.41) The arbitration agreement date following the date of the closing of the proceedings. In light of Article 3(2) of the
is broadly drafted to encompass all disputes arising out of or in relations to or in Act, it would, however, be reasonable to hold that 20% per annum interest starts to
connection with the “Settlement Agreement.” accrue from the date following the date of the delivery of the arbitral award, not the
date of the closing of the proceedings. If the Arbitral Tribunal had examined the date
when 20% per annum interest starts to accrue and had stated its opinion regarding
III. ENTIRE AGREEMENT CLAUSE
why 20% per annum interest starts to accrue from the date following the date of the
Under Korean law, the applicable law to the “Settlement Agreement,” due closing of the proceedings, not of the delivery of the arbitral award, it might have
consideration is to be given to all relevant circumstances of the case including the been better.
negotiations and any subsequent conduct of the parties. However, the parties are
free, by agreeing upon an entire agreement clause, to bar an interpretation beyond
the four corners of the contract.

41) United Nations Commission on International Trade Law, supra note 4, at 151-152.

205 206

You might also like