DAILY PROGRESS REPORT

Project Name : AIM - Dorm Lobby Date : 04/15/2021


Location : Pasay Road, Legaspi Village, Report No. : 1
Makati City Philippines Weather : Cloudy

Week 1

Activities Manpower Count


Mobilization Project Manager 0
Board up at AIM Dorm Lobby Project in Charge 1
Dismantling of Ceiling Safety Officer 1
Chipping of Flooring Foreman 1
Dismantling of Wall Accent Mason 1
Carpenter 2
Electrician
Daily Project Challenges/Problems Encountered
Helper 1
Chipping of Flooring Total : 7

Toolbox Meeting Demolition Works

Board up Works
DAILY PROGRESS REPORT

Project Name : AIM - Dorm Lobby Date : 04/20/2021


Location : Pasay Road, Legaspi Village, Report No. : 3
Makati City Philippines Weather : Sunny

Week 1

Activities Manpower Count


Toolbox Meeting Project Manager 0
Clearing of Debris on Reception Area Project in Charge 1
Demolition / Chipping of Flooring Safety Officer 1
Preparing Dismantled Wood for Hauling Foreman 1
Mason 1
Carpenter 1
Electrician 2
Daily Project Challenges/Problems Encountered
Helper 1
Demolition / Chipping of Flooring Total : 8

Demolition Works

Board up Works