Download as pdf or txt
Download as pdf or txt
You are on page 1of 129

QUALITY MANAGEMENT SYSETM

DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Disclaimer: This document is the proprietary property of Dosti Realty Ltd. and is meant for its intended
purposes only. No part of this document shall be disclosed, reproduced, published or shared privately with
any third party without the prior written consent of an authorized officer.

Page 1 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

INDEX
Ref No Method Statement / Work Instruction Revision Page No
- TITLE PAGE 00 1
- INDEX 00 2-3
MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9
MS/B SURVEYING WORK 00 10-13
MS/C WBM ROAD WORK 00 14-17
MS/D COMMON GUIDELINES FOR ALL ACTIVITIES 00 18-20
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE 00 21-27
WORKS
WORK BELOW PLINTH LEVEL 28-45
MS/01 PILING WORK 00 28-33
MS/02 EXCAVATION WORK 00 34-36
MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING 00 37-38
AND PCC WORK
MS/04 PRESSURE RELEASE PIPE GROUTING 00 39-39
MS/05 BACKFILLING WORK 00 40-43
MS/06 ANTI-TERMITE WORK 00 44-45
CONCRETE RELATED WORK 46-53
MS/07 RCC WORK 00 46-47
MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED 00 48-52
FLOORING WORK
MS/09 RCC REPAIRING WORK 00 53-57
WATER-PROOFING WORK 58-72
MS/10 WATER-PROOFING WORK – RAFT, R/WALL AND LIFT PIT 00 58-59
MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63
MS/12 WATER-PROOFING WORK – PLANTER, TERRACE, 00 64-67
LANDSCAPE, HARDSCAPE, SWIMMING POOL
MS/13 WATER-PROOFING WORK - UGT, STP, OHWT 00 68-70
MS/14 EXPANSION JOINT TREATMENT WORK 00 71-72
MASONRY WALL AND PLASTER WORK 73-81
MS/15 MASONRY WORK 00 73-75
MS/16 SAND MORTAR PLASTER WORK 00 76-78
MS/17 GYPSUM PLASTER WORK 00 79-81
BUILDING FINISHING WORK 82-97
MS/18 TILE / MARBLE AND CHINA CHIPS FLOORING WORK 00 82-84
MS/19 MARBLE & TILE CLADDING (DADO) WORK 00 85-86
MS/20 KITCHEN PLATFORM WORK 00 87-88
MS/21 DOOR AND WINDOW WORK 00 89-91
MS/22 SUSPENDED CEILING (FALSE CEILING ) WORK 00 92-93
MS/23 PUTTY WORK 00 94-95

Page 2 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Ref No Method Statement / Work Instruction Revision Page No


MS/24 PAINTING (INTERNAL AND EXTERNAL) WORK 00 96-97
MEP WORK 98-122
MS/25 EMBEDDED ELECTRICAL CONDUIT 00 98-99
MS/26 ELECTRICAL WIRING AND TESTING WORK 00 100-105
MS/27 FIRE FIGHTING WORK 00 106-110
MS/28 HVAC WORK 00 111-113
MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING 00 114-120
WORK
MS/30 SOLAR HEATER WORK 00 121-122
ELEVATION WORK 123-128
MS/31 GRILLS FABRICATION AND ELEVATION WORK 00 123-124
MS/32 HAND RAILING, BALLUSTER WORK 00 125-126
MS/33 FAÇADE WORK 00 127-128

Note: Additional activity based Method Statement will be added in next revision.

Page 3 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

1. INITIAL REQUIREMENTS

- Strata checking (Soil Investigation).


- Bore survey along plot boundary (N-E) corners, as per ‘VASTU’.
- Taking Boreholes for Geotech report which will require deciding SBC for structure design.
- Procurement and preparation of drawings from Consultant / Architect.
- Study and checking of drawing.
- Appointment of staff.
- Marking of the boundaries at site.
- Verification of actual boundaries at site.
- Demarcation and contour survey.
- Water/electricity arrangement in advance, also telephone & DG arrangements.
- Temporary labour toilet construction & drainage arrangements for the same.
- Approach roads, erection of temporary sheds ,
- Site office,
- Beans for stacking steels including permission for TMC /BMC to construct.
- Arrangement of labour huts & water supply of T.M.C. /B.M.C. for drinking.
- Tree cutting permission especially well in advance (which are coming in structure).
- Compound walls and security arrangements.
- Stock of materials and tools (ex. Dewatering Pump, 1+1 stand by) required at initial stage.
- Appointing the working agencies.
- Completion of the legal formalities.
- Keep one set of approved copy of IOD, CC, Tree cutting permission, excavation royalty
copy etc. on site.
- Bhoomi poojan and advertisement.
[Note: All the Activities & Work Instructions are exercise wherever applicable.]

2. PREPARATION ON SITE
a. CLEANING SITE AND LEVELLING

- Before starting any work on site, cleaning of land, cutting unwanted trees/bushes should
be carried out with permission from T.M.C. / B.M.C. with specialised agencies for taking
all required Measurements correctly, for demarcation and layout.
- If large trees are obstructing proposed buildings or structures then necessary written
permission from corporation authority should be obtained for transplanting / cutting the
trees.
(Application to do well in advance as it requires times to get permission.)
- If any undulations or soil heaps are in the premises, these should be levelled by JCB.

Page 4 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

b. BOUNDARIES MARKING

- Before starting any work on site, Engineer In charge should demand for security services
of reputed company.
- A shed using G.I. sheet to be erected near the entrance of project or at convenient area
within site.
- This shed can be used for storing and stacking of all initial required tools, reports, and
office files.
- Boundary marking should be done by using stones fixed in concrete on each corner/every
turning point after specific distance.
- This stone should be painted in red oil paint. While doing this initial marking, reference
should be taken from existing boundary stones, some trees on boundaries, nallah bunds,
and initial enquiries with local people, etc.
- While doing this initial boundary marking on sites reaction of adjacent plot owners should
also be judged.
- Any minor disputes regarding measurement should be settled with consent from the
directors.
- A rough sketch of fixed boundaries to be prepared.
- Permanent boundary marking work should be started by doing Total station survey.

c. DEMARCATION BY TOTAL STATION SURVEY

- Total station survey for actual demarcation should be done with reference to existing
boundaries.
- While doing this survey, all existing structures such as existing well, bore well, nearby
nallah, electric poles, high-tension line, trees, etc., should be shown on drawing.
- Demarcation drawing should be prepared in the office, which will be based on the field
survey.
- Comparisons of T.L.R.'s demarcation and architects drawings should be done by super
imposing the drawings.
- Major discrepancies should be reported to H. O.
- Architects will visit, inspect site and then finalize the revised demarcation.
- Based on this revised final demarked drawing, architect will prepare final layout of
buildings.

d. CONTOUR SURVEY

- Contour survey means to know the actual level i.e. ups and downs of the plot.
- Fix the permanent benchmark with reference to main road and approach road on the
existing main drainage chambers top, etc.

Page 5 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

- Engineer & Architect has to decide the grid interval 3 meter or 5 meter, as per the plot
condition.
- Grid interval depends on the plot conditions e.g. for plain ground, for sloping ground, for
steep ground, hilly areas.
- Then from collected data i.e. levels and interval distance. Surveyor will prepare the
contour map.

e. Importance of contour map -

- For quantity survey and estimation.


- Estimation for cutting and filling.
- To decide the height of compound wall.
- Fixing of plinth levels of all buildings, development work like drainage, nala, rain waters,
disposals, water lines, etc.
- For estimation of whole project.

PLANNING FOR APPROACH ROADS AND TEMPORARY STRUCTURES / WATER STORAGE AND
OTHER STRUCTURES

Approach roads and internal roads are very important for vehicular transport.
- Approach roadside boundaries should be marked with lime powder or guard stones and
internal roads side margin/boundaries should be marked with lime powder or steel rods.
- Internal road distribution should be same as per sanctioned layout plan.
- In rainy season, if there is possibility of formation and accumulation of mud on road, it is
very important to construct W.B.M. roads in earlier seasons only.
- So that it cannot disturb work activities and material can be stocked undisturbed.
- On approach road as well as on the main road hoardings as well as way to boards, tree
guards with plants should be provided.
- Planning of approach road and other structures should be done in advance as per
sanctioned buildings layout so that no structure / road should obstruct proposed
buildings.
- Planning for the location of material hoist & passenger hoist.
- Consider the material stacking space for each building with free vehicular movement
without obstructing any temporary structures.
- This is very important otherwise what is normally observed shifting of temporary sheds
from one place to another to accommodate proposed permanent structures. This may
lead to considerable increase in cost due to improper advance planning.

Page 6 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

3. WATCHMAN CABIN

- Location nearest to main gate, facing the road direction from where more vehicular flow
is expected.

4. SITE OFFICE AND STORE

- Temporary office and stores at site will remain as it is till completion of the project means
that should not be demolished earlier
- Processing & Non Processing area need to confirm by Architects & sanctioned by
management.

5. WATER ARRANGEMENT

- If sufficient water from open Well Corporation or other authorities is not available then
taking bore well is advisable.
- If there is a shortage or non-availability of water then it is necessary to get the tropical
geological
- survey to find out the maximum ground water table for bore well purposes.
- Number of bore wells depends upon the requirement of water for the completion of the
project. (asper VASTU, N-E corner should select. Bore should not disturb bldg. structure.)
- After completion of the bore well, pump installation with temporary GI / PVC line is to be
laid up to the central water storage tank.
- Water should be sent for testing to find out various impurities, PH value, so as to use the
potable water for construction.
- Engineer should be aware about the pump, which depends on horizontal and vertical
growth of the project.
- Another pump should be installed over the temporary water storage tank so that we can
use the water for construction curing purposes.
- Selection of pump capacity should be done in such a way that same pump could be
shifted to other project constructional activities.
- Minimum one water outlet with gate valve should be provided in front of each building
for temporary water arrangement for proper curing and construction activity.
- Also water tank or UG Tanks as per dwg should construct to store water for construction
use in case of bore failure. One line of bore must be also found various impurities and
suitability for construction.

Page 7 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

6. ELECTRICITY ARRANGEMENT

- For this normally a three-phase meter is required for operating pumps, polishing
machines etc.
- The following documents should be submitted to the Electricity Board for getting new
connection
a) Application on A-1 form, b) 7/12 Abstract.
c) Copy of commencement certificate from Municipal Corporation. d) Copy of power of
attorney. e) Copy of sanctioned drawings from the corporation. f) Property tax receipt.
- The above procedure should be followed up with Electricity Board by concerned electrical
contractor.
- The assistant Engineer or Sub Engineer of the service connection department then will
visit the site for study of location for supply point.
- As per Electricity Board rules, meter location should be nearest to the point of supply.
- A meter room should be construct as per convenient.

7. COMPOUND WALL / FENCING / SECURITY FENCING

- It is important to construct the compound wall at the beginning of the project; this
improves the overall security of the project. The construction of other structures like
watchman’s cabin, store,site offices, godowns, steel yards, etc.
- The compound wall boundary must be check as per T.L.R. & get approve from licence
dept.
- This activity can give ideas to the prospective customers and visitors
- For construction of the compound wall gate etc. proper drawing should be issued by the
Architect.
- After approval of this drawing the actual construction of compound wall begins.
- Provision for chain link fencing over M.S. angle should be made for security purposes.

8. GATE

- Only one entrance to the project or plot should be maintained to avoid theft, outgoing or
incoming materials, and site staff timing restrictions and to control the visitors or
customers entries to the site.
- If the main gate is not fixed at least a 'stop and start pole' should be used and which the
watchman will control.
- Once the compound wall and gate is complete, tree plantation should be done along the
fencing.
- This will result in a favourable impression in a perspective client's mind.

Page 8 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9

9. CHECKING OF LAYOUT WITH ACTUAL BOUNDARIES

- Before starting main building line out, the site engineer must confirm the actual
boundaries and check set back margins simultaneously in co ordination with Architect.
- Temporary makings of external building corners and other structures like under ground
water tank, swimming tank, etc. should be done with steel rods fixed with cement
concrete 15 cm above ground and painted with white oil paint.
- Cross check this marking with set back from actual plot boundaries.
- At this stage total buildings should be properly shown on layout with their set back as per
the given rule.
- This layout drawing should be approved by the architect and confirmed by the resident
architect.
- While checking this layout, mark open spaces and road portion on ground as per
approved layout drawings.

10. STORE/GODOWNS

- Store should be centrally located near all buildings and not obstruct any vehicular
movement as well as proposed permanent structure. Flooring of cement godown should
be raised 45 cm from existing ground level with smooth I.P.S. floor finishing.
- This being a temporary structure can be made from G.I. sheets or brick masonry to avoid
leakage in monsoon.
- It should be 100% water proof with two openings (so that old cement can be used first)
and perfect security.
- It should have sufficient capacity of storage.
- Sufficient light provision must be providing.
- Stock name board showing W M Y for each batch of material should be placed.

11. WATCHMAN TOWER

- Larger area can be under vision if one is at the highest point.


- Any trespassers can be easily located from higher point.
- It is therefore advisable for larger projects to have the watchman tower, centrally located
and an about 15 to 20 m above the ground level.
- Floodlights fitted at this tower are more advantageous from security point of view.
- Location of flood light should be such that it should not get disturb to other residence in
night.
- Proper control on switches for on & off operation should be maintained.

Page 9 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/B SURVEYING WORK 00 10-13

1. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications

2. Tools and Equipment:


Total Station, Dumpy Level, Surveying Tape, Measuring Tape, Surveyor's chain, Surveying Rods,
Surveying Poles, Marking Paint.
3. PROCEDURE:
- Ensure that all survey equipment will be recalibrated on or before the expiration of
calibration certificates.
- Elevation of Benchmarks; Elevation of benchmarks will be decided by direct leveling
survey. A leveling route for measuring benchmarks will be selected in such a way that the
route starts from existing benchmark, and return either to the original benchmark or
another existing benchmark in the area.
- The stations and benchmarks will be carefully constructed after approved by the
Engineer.
- The Stations and benchmarks will be provided with adequate protective fences to
preserve them during construction terms.
- The stations and benchmarks will be clearly marked with item number, elevation and / or
coordinate
- TOPOGRAPHICAL SURVEY The survey group shall ensure that a topographic survey shall
be done before the start of earthwork activities.Topographical survey will be include of
horizontal control survey, vertical control survey and survey the whole site using cross
section in every 10 meters.
- Beginning Point (BP), Intersection Point (IP) and Ending Point (EP) will be set out of each
cross section line from the nearby control point.
- Establishment of Horizontal and Vertical Controls All survey works shall be reference to
the existing survey control points within the project site. In cases where additional control
points are needed, traverse and leveling surveys shall be done.
- All visible features will be measured using ground measurement points for every feature
that needs to be shot. These points will be spread throughout the project area in
sufficient number to fully cover all features and the entire ground, and to ensure accurate
computation of the contour lines and elevations.
- Also, the gathered data shall be the basis for the earthworks (cut and fill) computations.
All man-made structures such as buildings, roads, culverts, drainages, bridges, walkways,
etc., within the project, site will also be measured in order to get their ground footprint.
-

Page 10 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/B SURVEYING WORK 00 10-13


- All other elements on the ground, such as plantations, trees (with a minimum diameter),
rivers, streams, etc. will also be included the measurements.
- Road Layout Horizontal road layouts shall be done at 10 meter interval (straight) and 5
meter interval (curves). Toe and embankment limit shall also be marked at the same
interval.
- Survey stakes shall be in the form of woods or rebars (preferably 10mm diameter).
Elevations shall be marked with the use of masking tapes to determine the required
elevations.
Survey control
Raft Foundation to Ground Level
- For the excavation, raft foundation and initial levels of construction, position and height
will be established by direct measurement from the permanent marks and temporary
control points established at each level. As soon as the slab is completed at each level
then the permanent grid points and grid lines will be set out.
Ground Level to Stilt Level
- At Ground level at least 4 permanent survey marks will be established within the
‘footprint’ of each tower. Block outs (150mm by 150mm) will be set in each slab vertically
above the survey marks so that the control can be transferred directly to each level above
using optical plumbing with the precision optical plumb.
- As soon as each section of the floor slab is cast, permanent grid points and grid lines will
be set out.
Vertical Control
- Traditional leveling techniques will be used to establish marks on the foundation slab.
- From the foundation slab to the top of the building the datum point for each floor will be
set by measurement from the floor below; traditional levelling can be used but where
more than one change point is required an alternative method will be used.
- The instruments are moved and a second set of readings taken. The mean value is used to
determine the datum at the upper level. This procedure will give an accuracy of ± 1mm
and as the errors are not cumulative over 10 or more floors.
Transfer of datum
Line and level datum will be progressively transference up the building at every 10–12
floors and survey points closed off behind.
As built surveys
1. As built surveys will be carried out as follows:
2. Lift shaft surveys
3. Core Wall verticality surveys
4. Column and shear wall position & verticality
5. Precast setting out / Edge of slab surveys
6. Slab level surveys

Page 11 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/B SURVEYING WORK 00 10-13


On site survey procedures
Primary survey control
- The 4 permanent marks established surrounding the site are considered to be the Primary
points and all precise work must be connected to these marks by closed traverse and/or
level run.
Secondary control
- Marks established by closed traverse and/or level run within or adjoining the structure
are considered secondary control and are used to establish control at all other levels of
the building. The traverse or level run miss-close must always be adjusted before the
secondary marks are used for the set out of further points.
Horizontal Position
- Horizontal control at another level is obtained by setting the precise optical plummet on
each secondary control mark and sighting vertically through the survey block-out, using
the angle eyepiece to mark a point / line over the block-out at the target floor.
- Two observations (180 deg. apart) are made to the target and the mid position adopted.
- The instrument is then transferred to the target level and observations made to the other
3 or 4 secondary control points.
- An initial accuracy of better than 1:10,000 should be achieved and a ‘best-fit’ solution is
the adopted for the marks and major grid points and grid lines are then set out.
Vertical Position
- Vertical datum for a new level is, in all cases, established directly from the level below.
- A suspended, tensioned tape should be used whenever the level transfer involves more
than one change point by traditional means.
- The level run must be closed and the miss-close must not exceed 2mm. If greater than
2mm – re-survey!
- When using the suspended, tensioned, tape the same tape and the same tension (about
3-4 Kg) must be used at all times.
- Two sets of readings must be taken and again the difference in the two vertical distances
must not exceed 2mm.
Core wall control
- Two different systems shall be used on site with some formwork being 3 or 4 levels above
the current slab and some formwork being on the slab and only rising to the next level.
- Control will be set out on the current slab and plumbed to the formwork system using the
laser plummet or the optical plummet.
- The shutter positions are then checked / set out from these marks. The verticality of lift
core walls shall be checked every floor, while form work moving up. But frequency of
results shall be generated and recorded every 5 floors including two diagonally opposite
corners of lift shafts.
- All shafts verticality will be monitored from the external wall co-ordinate results with the
thickness of wall.

Page 12 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/B SURVEYING WORK 00 10-13

Column control
- Three offset points or two lines are to be marked on the current slab defining the base of
the column.

Slab edge
- Survey points set out on the slab below each span are plumbed to the next level to
control the edge of slab form. Grid lines shall be established top of the slab prior to
casting and edges shall be marked and confirmed by representative of sub-contractors
precast department. Once slab been cast all grid lines to be marked by surveyor.

Accuracy
- At all times the aim is to achieve an accuracy of 5mm in relation to the secondary survey
control in setting the formwork at any one level. This applies to both horizontal and
vertical position.

Page 13 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/C WBM ROAD WORK 00 14-17

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Course Aggregate
 Screenings (filler material)
 Binding Material

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications

3. Tools and Equipment:


Roller, Mixing Machine, Spreader, Mud Pan,
4. PROCEDURE:
a. Course Aggregate :
- Unlike other course aggregates it consist of mixture of hard and durable crushed
aggregates and broken stones. The aggregates used for each layer of the WBM road
construction should be properly graded. Below table shows the standard gradation of the
aggregates that can be adopted.
- The course aggregates used in the construction of WBM road should hold the following
properties.
o It should be hard and durable.
o The course aggregate should be free from flaky and elongated particles.
o The course aggregate should be in acceptable shape and size.

- Physical requirements of course aggregates required for construction of WBM road in


terms of test values for different pavement layers is given below.

b. Screenings :
- The material which is used up to fill up the excess voids present in the compacted layer of
course aggregate is called as screenings.
- Screening material is nothing but the aggregates of smaller size than the course
aggregates. Below table shows the standard grading required of screening for
construction of WBM road.
- In order to reduce the overall cost of WBM road, IRC has recommended to use non-plastic
materials such as kankar nodules, murum or gravel.

Page 14 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/C WBM ROAD WORK 00 14-17
c. Binding Material :
- Binding material which is going to be used for the construction of WBM road should be
properly approved by engineer and it should have plasticity index value less than 6.
- Generally the binding materials are not required if screenings used for the construction of
WBM road is murum or gravel as they have crushable property.

Construction Procedure of WBM Road.


I. Preparation of Foundation for WBM Road :
- The subgrade or base course is properly prepared for the required grade and camber of
WBM road. The potholes and the depressions on the surface of the road are properly
filled up and compacted.

II. Provision for Lateral Confinement :


- Before laying of aggregates the shoulders having thickness as that of compacted WBM
layer should be constructed. They should be constructed with proper quality of murum or
earth.
- The main purpose of constructing shoulders is that the road surface to be constructed
retain in between them and it becomes easy for further laying of course aggregates.

III. Spreading of Course Aggregates :


- The course aggregates are uniformly spread on the prepared base after the construction
of the shoulders. Total number of layers and thickness of WBM road depends upon the
details of design pavement.
- In general for ordinary roads, single layer of compacted thickness 75 mm may be
sufficient. For special roads, 2 layers of 150 mm each compacted thickness may be
provided.
- If the course aggregate is used of number 1 grade as shown in above course aggregate
grading table then it is compacted to thickness of 100 mm.

IV. Rolling Operation :


- Rolling operation is carried out for compacting the course aggregates. Generally it is done
with the help of 3- wheeled power rollers weighing 6-10 tonnes or with the help of
vibratory rollers.
- Skilled operators should be used for driving the rollers as the fault rolling operations
causes formation of corrugations, unequal finish of road surface, wearing of road in few
months of construction.

Page 15 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/C WBM ROAD WORK 00 14-17

V. Application of Screenings :
- After the rolling operation is properly finished screenings is applied to properly fill the
voids remained after the compaction of aggregates. The screening may be applied in 3 or
more layers as per the site conditions.
- After uniformly spreading of screening compaction is carried out with the help of dry
rollers for each layer of screenings. After compaction brooming of the each layer should
be properly done to remove the uncompacted screening material.

VI. Sprinkling of Water and Grouting :


- After the application of screening the road surface is properly sprinkled with plenty of
water. After the water is sprinkled brooming is done to sweep the wet screening properly
into the voids.
- Rolling operation is further carried out for proper compaction. If the voids are still visible
then additional screenings can also be applied and properly compacted.

VII. Application of Binding Material :


- Same procedure is used for the application of binding material as that of screenings. Here
after each layer water is sprinkled and rolling operation is carried out.
- At the time of rolling operation the wheels of the roller should be constantly watered so
as to washout the binding material that gets stuck to the wheels of the rollers.

VIII. Setting and Drying of Surface :


- After the final rolling operation the road is allowed to cure or set over-night. The next day
if the depressions or voids are visible then again sufficient amount of screenings or
binding materials can be used and compaction is done.

IX. Preparation of Shoulders :


- At the time of Curing of road, shoulders are constructed alongside by filling earth to
specified cross slope. They are properly compacted.

X. Open for Traffic :


- After proper drying and without any depressions, the road is then made upon for traffic.
For few days the traffic should be well distributed over full width of road by placing
obstacles longitudinally in the form of drums, barricade etc.

Page 16 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/C WBM ROAD WORK 00 14-17

Maintenance of WBM Road :


- Whenever the potholes and ruts occur on the road by the period of time, they should be
be filled with adequate materials and proper compacting should be done.
- The corrugations occured on the roads should be removed by means of dragging. If not
could make the condition worse.
- Broken materials of the roads should be properly restored by fresh materials.
- The surface of the road should be renewed in 2-5 years or based according to the traffic
volume.
- The loose aggregates starts coming on the top of the surface of the road, they should be
removed and lavelled surface should be added by fresh binding material and it should be
properly watered and compacted.

Page 17 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/D COMMON GUIDELINES FOR ALL ACTIVITIES 00 18-20

A) Reference Documents:

Sr. No. Documents


1.1 Contract Documents
1.1.1 Agreement
1.1.2 Preamble
1.1.3 Special Condition of Contracts (SCC)
1.1.4 General Condition of Contracts (GCC)
1.1.5 Bill Of Quantity (BOQ)
1.1.6 Letter Of Award (LOA)
1.2 Codes & Standards
1.2.1 Technical Specifications
1.2.2 Code of Practice (Indian Standard , EN, BS, or other applicable Standards and Codes)
1.3 Engineering Documents
1.3.1 GFC Drawings
1.3.2 Good Engineering Practices
1.3.3 Consultant Instructions
1.3.4 Project Quality Management Plan
1.3.5 Method Statement (MS) / Work Instruction (WI)
1.3.6 Inspection and Test Plan (ITP)
1.3.7 Checklists
1.3.7 Approvals and Submittals – Submitted by Contractor / Manufacturer / Vendor /
Supplier

B) Roles and Responsibilities:

Contractor –
 As per work Order / BOQ, check the scope of the Contractor.
 Responsible to prepare schedule and submit to Dosti for Approval.
 At every inspection level, prior intimation to be given to Dosti for work inspection and
further approval.
 Responsible to maintain all inspection and sample report and one sample to be submitted
to the Dosti.
 Material Inspection should be done by contractor whether purchased by own or supplied
by the Dosti. Material inspection shall be witnessed by the Dosti.

Page 18 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/D COMMON GUIDELINES FOR ALL ACTIVITIES 00 18-20


Dosti Representative
 Responsible for work and material inspection and monitoring at every stage of the work.
 Responsible to maintain record for executed work.
 Responsible to follow Quality and Safety protocols set by Management.
 Timely and correct reporting to the Management / Site In-Charge
C) Datum / Survey Reference Point:
 Reference point i.e. bench mark will be given by surveyor at location wherever necessary.
 Site team to be cross verified with executed work.
D) Material Testing:
 Ensure Material Inspection should be done at the every delivery / receiving at site for
inspection and approval. Only after approval may allow unloading the material. Inspection
and Testing of material shall be done as per approved ITP or Approved Material
Specifications.
E) Records:

- Pre-Investigation Report
- Work Inspection Report
- Checklist for every inspection
- Concrete Log Sheet and Batch Sheet
- BBS
- Pour Plan
- Pour Card
- Area Marking Drawings
- Concrete Log sheet
- Batch Sheet
- Cube Test Register
- Material Samples
- In-House Material Test Report
- Non-Conformance / Observation Report
- 3rd Party Test Report
F) Quality Assurance and Quality Control:

- As per approved QUALITY PLAN / Inspection Testing Plan (ITP)


- Any non-conformity affecting the product Quality, Site / QA QC Engineer shall raise Non-
Conformance Report (NCR) and shall suggest and follow-up for Corrective and Preventive
Action.

Page 19 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/D COMMON GUIDELINES FOR ALL ACTIVITIES 00 18-20

G) Acceptance Criteria:

- Material –As per Approved ITP and Approved Material Specifications


- Workmanship – As per approved project specifications and Acceptance with Checklist and
Work Inspection Report
H) Safety:

- Use of PPE’s like safety shoes, dust masks, hand gloves, helmet, etc.
- Proper illumination to be provided for working during night.
- Material safety data sheet (MSDS) needs to be submitted prior start of work.
- Electrical equipment’s and machinery should have tag with month color code.
- Safety risk assessment shall be submitted separately for all work activities.
- Pile driving, Rebar cage lowering, concreting and casing extraction should be constantly
supervised.
- Rigs shall be moved on level and uniform ground.
- Welding and gas cutting activities must ensure safety compliance, like availability of
flash-back arrestor, double earthing for welding machine, separate identifications for
oxygen and DA hose etc.
- Proper housekeeping, Maintenance of piling rig is mandatory.
- Regular tool box meeting should be conducted.

Page 20 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27

A. Concrete Mix Design:


- Prior approval shall be taken for Source / brand of concrete ingredients, RMC Vendor,
Plant Location, etc.
- Workability at pouring point, retention period and temperature shall be decided based on
project specification, field requirements / conditions and standard documents.
- Slump of concrete for piling work shall range between 100 to 180 mm depending on the
manner of concreting. The table below gives the general guidance.
SLUMP (in MM)
PILING Typical conditions of use
Min. Max.
Poured into water-free unlined bore having widely spaced
reinforcement. Where reinforcement is not spaced widely
A 100 180 enough, cut-off level of pile is within the casing and
diameter of pile is less than or equal to 600mm, higher
order of slump within this range may be used.
Where concrete is to be placed under water or drilling
B 150 180
mud, by tremie or by placer.

- Concrete Mix shall be designed as per required grades and to ensure that the concrete
will fulfill all project requirements. Concrete Mix Design shall be undertaken as per the IS
10262.
- Preliminary Concrete Mix Designs and necessary test shall be carried out to achieve
controlled concrete of desired Quality, Density, Durability and Strength.
- If required, Concrete Mix Design trial to be taken before finalization of Mix Design to
check performance of the Mix.
- Concrete Mix Design shall be submitted by the RMC Vendor or Contractor for approval
along with all concrete ingredients test details, all in aggregates graph and detail Concrete
Mix Design calculation.
- For out-side RMC Supplier and Vendors following procedure shall be adopted
o Trial mix of proposed grade shall be witnessed by QC / Site Engineer and record
the results for final Concrete Mix Design approval.
o RMC Plant visit shall be done by QC Engineer / Manager to verify RMC QC process,
In-house testing of material, lab set-up, calibration of plant and lab equipment’s,
etc.
o Witness the fresh concrete sampling at RMC plant for carry out fresh concrete test
and also for cube casting.
o Witness and monitor cube casting and shall be marked for test witness.

Page 21 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
B. Clearance for Concreting:
The pour card shall be completed with approved pour plan, Work Inspection Report and
checklist of formwork and duly signed and certified by Site Engineer / QA QC Engineer
before starting of concrete.
C. Concrete Requisition:
- 24 hrs. Prior to the planned pour following detail / requirements to be submitted to the
concerned person or department.
- Location, Structure Details, Quantity, Grade of Concrete, Data and Time of Pour, Slump /
Flow requirements at field, Pouring Method, Name and Contact Number of responsible
person shall be mentioned in requisition request.
- If cement sand slurry required for pumping operation, mention separately.

D. Concrete Batching, Transportation, Placement and Inspection:


a. Batching:
- Production shall be started only after getting confirmation from Site Engineer in writing
only.
- Calibration of batching plant and all RMC plant equipment’s carried out and available on
demand.
- All the ingredients of the concrete shall be used by weight only.
- For Volume batching separate submission / approval to be taken form Dosti Quality
Department.
b. Mixing:
- The concrete shall be mixed only by mechanical mixer.
c. Transportation:
- Following details shall be provide during delivery of concrete and to be checked during
receiving of TM,
Delivery Challan, Date, Batch Report, Batch Time, Individual and Cumulative Quantity
of Concrete, Grade of Concrete, Slump / Flow, Temperature, Water Correction, etc.
- Batched concrete shall be conveyed by the transit mixer to the place of final deposit in
buckets, Concrete Pumps without segregation.
- During concrete transportation precaution to be taken to prevent loss of water by
evaporation in hot weather. No concrete will be transported and placed in open while it
rains. During rain proper covering /shade arrangements shall be provided.

Page 22 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27

- All equipment’s used for transportation and placing of concrete will be thoroughly
cleaned and maintained properly after each period of placement.
E. QAQC Inspection and Acceptance at Site:
- Once the concrete arrives at site the details of delivery challan shall be verified by
Engineer and then check for fresh concrete properties like slump / flow, temperature,
cohesiveness etc.
- On unloading of concrete Site Supervisor / Site Engineer shall sign the delivery challan for
acceptance of concrete with date and time.
- Pouring / Concrete Log Sheet shall be maintained during concreting and shall be
sign/certified by Site and QA QC Engineer.
- Re-dosing shall be as per Concrete Mix Design approval.
F. Placing:
- Pour sequence shall be approved before work commencement.
- While planning the pour depending upon the area and quantity the following points is to
be considered.
o Rate of Pour of concrete
o No. of Masons required
o No. of Vibrators Required
o Area Lighting
o Proper Access
o Concrete placement – Crane/Manual/Pump
- As per drawing/specification construction joint shall be provided and treated properly.
- The mix after discharging from the transit mixer shall be transported by wheel barrows,
buckets, pump’s, etc. without causing segregation and loss of cement slurry and without
altering its desired properties, with regards to water cement ratio, slump, cohesion and
homogeneity.
- Precaution shall be taken during raining season to avoid surface run-off or direct rain
water contaminations in the concrete pour. Plastic sheet / shade shall be provided.
- Concrete will be deposited in successive layers to its final position, as nearly as
practicable, to avoid segregation due to re-handling.
- The concrete shall be placed and compacted before initial setting of concrete commences
and each layer of concrete shall be compacted fully before the succeeding layer in placed.
- For locations where direct placement is not possible and in particular through narrow
forms, suitable drop chutes will be provided to confine the concrete in movement.
- To avoid cold joints casting is to be planned in such a manner to cover all the grids.

Page 23 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27

G. Compaction:
- Each layer of fresh concrete shall be thoroughly compacted by mechanical vibrators to
the minimum practicable consolidated volume.
- The concrete to be vibrated shall be placed in position in level layers of suitable thickness
not greater than the effective length of the vibrating needle.
- Vibrator needle shall be inserted vertically inside the Concrete and shall be allowed to
penetrate through by its own weight. Vibration shall not be stopped when needle is
immersed in concrete.
- The vibrator shall penetrate fully into the layer being placed and also penetrate about 100
to 200 mm or as required in the already consolidated lower layer for good bond and
homogeneity between the two layers and to prevent the formation of cold joints. The
vibrators shall be withdrawn slowly out of the concrete so as to allow the concrete to flow
back into the hole behind the vibrator.
- The specified spacing between the inserting positions shall be maintained uniformly
throughout the surface of concrete so that the concrete is uniformly vibrated.
- The spacing shall provide some overlapping of the area vibrated at each insertion. It is
better insert the vibrating head at a number of places than to leave it at one place for a
long time.
- Vibrator shall be prevented from coming into contact with the shuttering sides,
embedded parts, etc. under and over vibration shall be avoided.
H. Concrete Finishing:
- Finish concrete surface should be as per specified in the approved construction drawing
and specification. Recommended dip broom finish unless specified in specifications.
I. Curing Of Concrete:
- The curing shall be started immediately after initial setting start and same shall be
continued for a minimum of 7 days for OPC cement and 10 days for blended cement.
- Exposed surface of concrete shall be kept in a damp or wet condition by ponding or by
covering with a layer of hessian cloth, gunny bags or similar materials.
- The curing water shall be the same as that is used for construction purpose.
- At time of high ambient temperature cover with wet Hessian cloth and Commence
continuous curing in at regular interval to keep in wet condition.
- If wish to curing by Curing compound, then separate approval to be taken from Dosti
Quality Department.

Page 24 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
J. Sampling and Strength of Concrete:
- Sample from fresh concrete shall be taken as per IS 1199 & ITP, and cubes shall be cast,
cured and tested in accordance with IS 516 and IS 456.
- In order to get relatively quicker idea of the quality of concrete, optional test of
compressive strength at 7 and 14 days or as specified out in addition to the 28 days
compressive strength.
- Other Third Party Test shall be carried out as per ITP / QUALITY PLAN.

K. Reinforcement:
- Grade and make of reinforcement steel, coupler splices etc. shall be as per project
specification / approvals.
- Steel / coupler should be passed all in-house and third party test before cutting / bending
/ laying.
- Reinforcement shall be clean and free from rust, mud and oil.
- Reinforcement shall conform to the details given in the approved bar bending schedule
and as per approved drawings.
- Reinforcement shall be checked for correct position and for tying. Hooks and bends are
placed as specified by drawings. Lap length and lap zone is accurate & staggered and
anchorage checked.
- Reinforcement verticality / alignment shall be checked at regular interval / distance.
- Coupler fixed and tight for splicing and Coupler location are Staggered.
- Number, size and anchorage of stirrups as per drawing.
- Spacing and arrangement of stirrups and anchorage as per drawing.
- It shall also be checked for the size of bars, spacing between bars, welding or splicing (also
with coupler), binding wire bent inside, enough chairs and cover blocks kept in proper
position. Suitable good Quality binding wire shall be used.
- Treatment shall be done on dowels kept for further work.
- If required rebar grouting shall be done as per approved material and approved method.
- Reinforcement inspection record shall be maintained with Work Inspection Request (WIR)
& Checklist.
- Approved and same grade of cover block with correct size and spacing.

Page 25 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27

- For PT slab separate method statement to be submitted.


- Joint measurement to be taken for extra steel like Chairs, Spacer Pins, Used for Safety
Provision, extra suggested by consultant, extra consumption due to faulty work, etc.
L. Formwork:
- All formwork material shall be approved prior to work start.
- For Mivan Formwork, Hydraulic Jump form, climbing platform, Tunnel Formwork or
special formwork, separate method statement to be submitted by contractor /
manufacturer.
- All scheme / formwork drawing to be submitted by the contractor for Dosti approved and
ensure staging and formwork accordingly.
- Before staging work start housekeeping and clean that area and staging shall be checked
for its order.
- The staging will rest on firm ground or hard level surface of the concrete structure below
with lateral supports where necessary as per scheme drawings.
- Shuttering ply's free from holes, edges to be sharp and no gaps shall be observed at the
joint of ply and joints should be covered by masking tape.
- The formwork shall be to required size, line, level, diagonal land plumb. It will be free of
holes and gaps and shall remain sufficiently rigid during placing and compaction of
concrete.
- All openings, cut-outs, ducts shall be check for size, location and alignment.
- Approved shuttering oil shall be applied before placing of reinforcement or closing of
shutter.
- Ensure construction joint preparation has been completed. Check necessary
arrangements shall be made to prepare the formwork crack proof and to avoid slurry loss.
- Formwork inspection record shall be maintained with Work Inspection Request (WIR) &
Checklist.
M. Pre-checks/ Preparation:
- Prior to start any activity on site, the Site Engineer must be notified.
- Ensure that all workers are aware of the evacuation plan. Cordon off the work area.
- Discuss the method of working with all supervisors as per approved pour plan.
- All the related documents such as Concrete Mix Design, Shop Drawings, Method
Statement, Material Approval, Pour Plan etc. must be approved and available upon
request.

Page 26 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27

- Ensure the source of supply of ready mix and grade of concrete.


- Stand by mechanical equipment’s shall be checked for emergency break-down happened
like Concrete Pump, Mechanical Vibrator, Power Floater, etc.
- Cube Moulds, thermometer, Slump cone, flow table, etc. shall be arranged prior to the
concreting operation.
- Spacer / Cover block shall be provided with the same grade of concrete.
- Arrange the concrete testing area with proper shading and lighting.
- Polythene sheet, hessian cloths, water, etc. shall be arranged.
- Concrete check point / testing and casting place shall be checked and verified before start
of work.
N. Embedded Items:
- All Inserts of any kind like, sleeves, pipes, bolts and nuts, anchor bolts, MEP conduits, etc.
are to be accurately placed as per approved drawing and tied properly to avoid any
displacement during concreting, get clarification / confirmation from MEP / concerned
engineer.
- PVC/swell able water stoppers shall be provided in concrete joints confirming to IS-3370.
O. De-shuttering and Re-propping
- De-shuttering and Re-propping shall be as per project specification / QUALITY PLAN / ITP /
consultant approved documents.

P. Post-pour Inspection:

- Visual / measurable inspection of concrete member / structure shall be done after de-
shuttering for the checks of surface irregularities, honey-comb, cracks, etc. carried out as
per post pour inspection checklist.

- Observation / Snags to be handed over to the Contractor for their compliance with their
acceptance and projected compliance date.

- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer / Dosti Site Engineer. Repair shall be done as per approved methodology; not
following this protocol shall result in NCR being issued.

Page 27 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Concrete and Concrete Ingredients (Cement, Fly Ash, GGBS, Micro-silica, Fine and Coarse
Aggregate, Water, Admixtures, etc.)
 Concrete
 The grade of concrete shall not be less than M-30 with minimum cement content of
400 kg / m3.
 Steel
 Binding Wire
 Cover Block / Spacers
 Liner
 Bentonite

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following Specifications / Standards / Code and / or others as
applicable.
- IS 2911-1985 - Piling Works
- IS14893-2001- Pile Load Integrity Test on Piles
- IS 456-2000 - Plain and Reinforced Concrete
- IS 383-1970 - Specification for Coarse and Fine Aggregates from Natural Sources
for Concrete
- IS 2386-1963 - Methods of Test for Aggregates for Concrete
- IS 516-1959 - Methods of Tests for Strength of Concrete
- IS 1199-1959 - Methods of Sampling and Analysis of Concrete
- IS 3812-2003 - Specification for Fly Ash for Use as Pozzolana and Admixture
- IS 4926-2003 - Ready-Mixed Concrete – Code of Practice
- IS 10262-1982 - Concrete Mix Proportioning
- IS 9103-1999 - Concrete Admixtures – Specification
- IS: 2911 (Part 1 / Sec.2) – Indian Standard Code of Practice for Design and
Construction of pile foundations for Bored Cast-in-Situ Piles shall be referred to in
conjunction with these specifications during the entire design, construction and
installation work.
- Manufacturer Technical Specifications

Page 28 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33


3. Tools and Equipment:
- Site Equipment: MAIT Machine, Driller, Auger, Diamond Tooth Blade, Tremie Pipe, Steel
Cutting and Bending Machine, Chain / Measuring Equipment, etc.
The equipment and accessories for installation of bored cast-in-situ piles shall be selected giving
due consideration to the subsoil conditions and the method of installation etc., these shall be of
standard type and shall have the approval of the Dosti/Consultant.
 QA QC Equipment: Clean Pan, Trowel, Measuring Jar & Brush, Cube Moulds, Tamping
Rod, Slump Cone, Flow Table, Wheel Barrow, etc.

4. Work Procedure:
9.1 Pre-checks/ Preparation:
- Prior to start any activity on site, the consulting / responsible Dosti Engineer must be
notified.
- Ensure loose Soil compacted and compaction testing certified prior starting piling.
- Contractor - Discuss the method of working with all Dosti as well as Contractor Engineers
& Supervisors.
- All the related documents such as Work Order, Concrete Mix Design, GFC / Shop
Drawings, Method Statement, Material Approval, etc. must be approved and available
upon request.
- Ensure the approved source of ready mix Concrete and grade of concrete.
- Cube Mould, Thermometer, Slump Cone, Flow Table, etc. shall be arranged prior to the
concreting operation.
- Arrange the concrete testing area with proper shading and lighting.
9.2 Excavation of Pile Shaft:
- The capacity of the rig shall be adequate so as to reach the desired depth. Discuss with
Dosti Engineer before start of work.
- Provision shall be kept for chiseling within the borehole in case of any underground
obstruction / hard strata. However, chiseling shall be carried out only with the approval
of DOSTI/Consultant.
- In case pile is required to be socketed in medium or good quality rock strata, the
equipment mobilized shall have adequate capability to do so up to the required socket
length. From the purpose of classification of rock for the determination of length of
socketing, pilot drill holes shall be carried out in the areas to be piled.
- Rock drilling shall be carried out using double tube core barrel. Drilling and storing of rock
cores shall conform to relevant IS codes.
- The piles shall be installed as accurately as possible as per the designs and drawings. The
permissible positional deviations shall be governed by IS: 2911 (Part I /Sec.2). In case of
piles deviating beyond such permissible limits, the piles shall be replaced or
supplemented by additional piles, as directed by DOSTI/Consultant.

Page 29 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33


- Before excavation of each bored pile, identify any possible obstruction such as utility
services, gas / electric lines, water supply lines, etc. and confirming founding level by site
inspection.
- Set out the correct position of the bored pile on site as per pile layout drawing.
- Set up the vibrator in lifted with a crane.
- Install the bottom section of permanent or temporary casing into the ground by vibrating
motion exerted by the vibrator.
- In very soft soil a permanent liner shall be installed to ensure stability of borehole. A liner
shall be used to protect the green concrete where a high hydrostatic pressure exists in
the subsoil or where an underground flow of water exists and which is likely to damage
the concrete on withdrawal of casing.
- In very soft soil, if required use bentonite as per site engineer instruction.
- Use drilling machine i.e. mait/ soilmech, should have required torque to get drill into rock
as per standard or suggested by the consultant for auguring process.
- Excavate in soil using auguring method. The auger is lowered down by a telescopic boom
to excavate soil and retrieve the auger to the top after excavation.
- Move the auger with soil in it away from the excavated hole by swinging the machine.
Rotate the auger in the opposite direction to remove the soil from the auger.
- The auguring process is repeated until the required depth is reached or hard layer or rock
is reached.
- If necessary, use a bucket to clean the bored hole with the process similar to the auger.
However, for dumping of soil/spoils, the bucket needs to be released by pulling a pin
manually.
- For hard soils and solid rock, if necessary, rock auger head can be employed to grind into
hard soils and rock and subsequent removal of fragments by bucket.
- Verticality will be monitored by means of spirit level in bore drilling machine.
- Ensure Pile cut off level, concrete top level, top of steel and toe level.
- Casting diameter uniformity and alignment and Length of casing to be check in rock / hard
formation.
- Continue the above procedure until the tentative completed level / sound rock level has
reached. Soil samples & rock fragments will be collected for inspection as suggested by
the Consultant. Bore log sheet to be maintained.
- Pile termination shall be confirmed with the Consultant in writing only. Request to
consultant, for random checking of pile work and same shall be signed off by the
consultant for approval.
9.3 Cleaning of Pile Shaft:
- The pile shaft shall be cleaned by the bucket if there are suspected loose material at the
toe. The presence of water in the shaft (if any) is OK, provided there is no collapse of soil
in the bore hole. Bucket dia should be same as a pile dia unless otherwise mentioned.

Page 30 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33


- This can be checked with when the withdrawal of bucket, there shall be no debris, soils or
rock fragments in the bucket after cleaning.
- The depth of the pile is checked using a weighted measuring tape or chain. And ensure
founding strata is as described in soil investigation report and hence approved pile design.
- Bore pile to design depth, ensuring no collapse takes place.
- Properties of bentonite used and quality control shall be as per IS: 2911 (Part I/Sec.2).
9.4 Preparation of Reinforcement:
- Grade and make of reinforcement steel, coupler splices etc. shall be as per project
specification / approvals.
- Reinforcement shall be clean and free from rust, mud and oil.
- Reinforcement shall conform to the details given in the bar bending schedule and as per
approved drawings. Check correct size mandrel using during bending the Steel to avoid
cracks.
- The reinforcement and links cage is prepared, prefabricated prior to the completion of
the bore pile.
- Place circular spacers onto the spiral link and at bottom of cage at regular intervals
required by the design & also as per site condition.
- Check reinforcement as per Bar bending schedule, also check for splicing, binding wire
bent inside, enough cover blocks kept in proper position. Suitable good Quality binding
wire shall be used.
- Proper Lapping of reinforcement is needed, a lap length of 40D or specified in drawing /
specification shall be used. The laps shall be tied with tie wires or U-bolts.
- Reinforcement inspection record shall be maintained with Work Inspection Report &
checklist.
9.5 Installation of Reinforcement:
- Borehole bottom shall be thoroughly cleaned to make it free from sludge or any foreign
matter before lowering the reinforcement cage. The full length of reinforcement cage
shall be in position before start of concreting.
- When the reinforcement cages are ready, they can be installed into the pile.
- The prefabricated cage shall be lowered down into the hole, segment by segment by
lifting the entire cage using a suitable crane.
- Welding:
Field welding of reinforcing bars will not be permitted without the written consent of the
DOSTI/Consultant. Where welding is permitted it must be at staggered locations. Tests
shall be made to prove that the joints are of the full strength of bars connected. Welding
of reinforcement shall be done in accordance with the recommendation of IS: 2751.
9.6 Concreting (Direct Pour or Tremie Method):
- Concrete should start as soon as possible after the driving is completed.

Page 31 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33


- Set up a working platform to the top of the temporary casing if the ground is soft using
steel plates.
- If there is less than 1m of water present in the hole (can use a tape measure and apiece of
timber/wood tied at the bottom), the hole is deemed to be dry and direct pour method
can be used.
- Otherwise, if the pile is flooded with water (>1m), the pile shaft shall be concreted by
“Tremie Technique". The tremie pipe sections will be inserted and be jointed until it
reaches the bottom of the pile shaft. The gap between the bottom of borehole & bottom
of the tremie pipe should be Max.300 mm.
- Concrete will be poured into the tremie pipe by using a concrete skip. Concreting will be
carried out in one continuous operation to a stop-off level (above the cutoff level) agreed
with the drawing / specifications.
- As concreting proceeds, the level of the concrete relative to the ground level can be
monitored by measuring with weighted tape after each skip of concrete is placed.
- The tremie pipe can then be extracted piece by piece as the concreting goes on. And
Check concrete level for lumping upon partially withdrawing the casing (top up if
needed).While withdrawal of tremie pipe care should be taken that bottom of the tremie
pipe should be always inside the concrete of pile shaft. One time of pouring of concrete
shall not exceed the 25% of pile length.
- The temporary casing can either be extracted simultaneously by the vibrator in course of
concreting, or after completion of concreting. A head of about 2 m(minimum) is always
maintained between the top of concrete and the bottom of steel casing.
- If a length of permanent casing is required, the extraction of casing shall be stopped after
the bottom of casing reaches the required level.
- Check the volume of concrete placed in the bore. Actual volume shall be more than
theoretical volume.
- Check the volume of concrete placed for initially cast piles and obtain average figure to
check for undue variation in concrete consumption for subsequent piles.
- Make a provision at ground level to flow water / muddy water coming from the pile
during concreting to avoid mixing in concrete at ground / cut-off level. Allow to concrete
over-flow.
9.7 Compaction:
- Fresh concrete shall be thoroughly compacted by tremie to the minimum practicable
consolidated volume.
9.8 Concrete Cut-off Level:
- Finish concrete surface up to cutoff level as per approved GFC drawing.
- The top of the pile shall be brought up above the cut off level minimum by 0.75 m so as to
permit removal of all laitance and weak concrete before capping and to ensure good and
sound concrete at the cut-off level for proper embedment into the pile cap. Any

Page 32 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/01 PILING WORK 00 28-33


defective concrete in the head of the completed piles shall be cut away and made good
with new concrete.

9.9 Sampling and Strength of Concrete:


- Sample from fresh concrete shall be taken as per IS 1199 & ITP, and cubes shall be cast,
cured and tested in accordance with IS 516 and IS 456.
- In order to get relatively quicker idea of the quality of concrete, optional test of
compressive strength at 7 and 14 days or as specified out in addition to the 28 days
compressive strength.
- Other third party test shall be carried out as per ITP / QUALITY PLAN.
9.10 Recording of Data / Details
A component supervisor shall be present to record the necessary information during the
installation of piles. The data to be recorded shall include:
- The dimensions of the piles, including the reinforcement detail and the mark of the pile.
- The boring method employed.
- The type of soil in which pile is terminated.
- The depth bored.
- The depth of water table.
- Rock Sampling and identifications
- Pile Penetration Rate
- When drilling mud is used, the specific gravity of the fresh supply and contaminated mud
in the borehole before concreting is taken up, in case of first few piles and subsequently
at suitable interval of piles.
- The time taken for concreting.
- The cut-off level / working level, and
- Any other important observations.
9.11 Testing
- The following tests and rates shall be carried out spread equally across the site as
suggested in Work Order / Consultant Instruction;
o Pile Integrity Test
o Dynamic load tests
o Static load tests
- Dynamic load testing of piles shall be carried out in accordance with ASTM D4945
Standard Test Method for High-Strain Dynamic Testing of Piles or other approved non-UK
national standards.
Static load testing of piles shall be carried out in accordance with BS EN 22477 Pile Load Test by
Static Axially Loaded Compression.

Page 33 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/02 EXCAVATION WORK 00 34-36

1. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 1200 (PART 1)-1992 - Methods of Measurement of Building and Civil
Engineering Works - Earthwork
- IS 2720 - Methods of Test for Soils
 PART 2: 1983 - Determination of Water Content.
 PART 7: 1980 - Determination of Water Content - Dry Density relation
using light compaction
 PART 8: 1983 - Determination of Water Content - Dry Density relation
using heavy compaction
 PART 28: 1974 - Determination of Dry Density of Soils in place by the Sand
Replacement Method.
 PART 29: 1975 - Determination of Dry Density of Soils in place by the Core
Cutters Method
- IS 3764- 1992 - Safety Code for Excavation Work.

2. Tools and Equipment:

The Contractor shall deploy any or all of the following resources as dictated by the volume and
nature of excavation.
2.1. Tools & tackles for manual Excavation
- Spade.
- Crow-bar
- Shovel
- Basket
2.2. Plant & Machinery for Mechanized Excavation
- Excavators / Rock Cutters
- Dumper
- Jack hammer
- De watering Pumps
2.3. Other
- Surveying equipment, trowel, etc.

3. Work Procedure:
All the material that can be easily excavated by mechanical equipment as described in
hereunder.

Page 34 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/02 EXCAVATION WORK 00 34-36

3.1. Soft/ Loose Soil:


It is understood that the soft soil/loose soil shall include sand, gravels, loam clay, mud, black
cotton soil, vegetable or organic soil, turf, peats, soft shale, loose moorums, mud concrete etc.,
which yields to the ordinary application of pick and shovel or to pick-axe, rake, or either ordinary
digging implements.
3.2. Hard/ Dense Soil:
Generally hard/dense soil shall include stiff heavy clay, hard-shale or compacted moorum, lime
concrete soft conglomerate or any such disintegrated rock formation requiring grafting tool, and/
or pick and shovel, shingle, river or rivulet bed boulders, soiling of roads, etc. It will be classified
as that which requires the close application of picks or jumpers or scarifiers and rippers to loosen
the same.
- Prior to commencement of any excavation, a detailed survey of the area shall be
conducted in order to establish the spot levels in a 5m-grid pattern and the results shall
be recorded in a protocol jointly with the DOSTI’s Engineer. Closer grid pattern shall be
adopted for survey where ground feature shows much variation in close distances.
- The Project Manager & Site Engineer shall check availability of GFC Drawings and
Specifications for any discrepancies. If any discrepancies are discovered, the Project
Manager shall be notified who will get the same clarified from the Architect / Consultant.
- All excavation legal / statutory permits are obtained for approval authorities before work
start.
- Check a report from Geotech Engg regarding landslide and technical plan to avoid
landslide.
- The Site Engineer shall supervise the clearing of existing vegetation and ensure that a
topographical survey of the site has been carried out prior to the commencement of
earthworks.
- Before start of the work an excavation plan shall be prepared & approved by site
engineer.
- After clearing the site, and preparing the site level plan, the Contractor will set out the
center lines of the building/columns or other involved works and get the same approved
from the Project Manager as per the approved check list.
- It will be the responsibility of the Contractor to install substantial reference marks; bench
marks etc. and maintain them as long as required by the Project Manager.
- Ensure any interruption to the existing utilities shall be permitted by the consultant in
writing before 48 hours to start of the work.
- Excavation Work permit should be received from safety officer before starting of
excavation.
- For major bulk earthworks, the Site Engineer shall propose the Cut / Fill Haulage plan for
the approval of the Project Manager.
- Sufficient light arrangements should be made for work in the night shift.

Page 35 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/02 EXCAVATION WORK 00 34-36


- The Site Engineer shall ensure that temporary drainage is provided or the
seepage/ground water is pumped out from the site to suitable drainage point and
maintained throughout the construction period in order that the site remains reasonably
dry. If Required maintain ground water table to a depth of at least 1 meter below the
excavation depth at all time and maintained.
- The Project Manager should choose correct type of Excavator having sufficient capacity to
execute specific job within budget & as per construction Master schedule.
- The Project Manager shall ensure that only suitable material from cut is used for
backfilling. Unsuitable material (Non-approved material of backfilling material) shall be
disposed off to dumping ground as per debris management plan or as instructed by the
Management.
- Where necessary, the Project Manager shall decide the method for protecting earthworks
on slope from soil erosion.
- Strata if very hard, Requires blasting or Rock Cutting, necessary permission to be taken
from authority.
- If dispute arises regarding strata classification, a sample to test in third party lab and
decision of structural engineer/geotechnical engineer shall be concluding.
- Check for any existing underground utility services through Electrical scanning and make a
full service survey before the start of Trial excavation.
- Check and ensure that the dimensions and depths of excavation completed as required to
allow for safe and proper construction work.
- Inspection shall be done by Site Engineer when the specified levels/limits of excavation
are reached.
- Site Engineer to be ensured that excavate to firm soil and not disturb the bottom of
excavation.
- Site Engineer shall check the earthworks process-using Checklist for Earthworks
- After completion of the work (cut/fill), the topographical survey is done under the
supervision of Site Engineer.
- Check that the approval taken for excavated material to be disposed of or to be reused
for back filling
- The Project Manager shall ensure that sufficient quantity of Machineries’, Material &
Manpower is available to execute specified job as per construction Master schedule &
Joint measurements to be taken for record purpose.
- Ensure records of levels are maintained at periodic interval of time. Separate level sheets
to be maintained for different strata like soft soil, hard soil, rock etc.
- Compaction value should be range from 97% to over 100% with moisture content 10 to
20%.

Page 36 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING AND PCC WORK 00 37-38
1. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
- IS 12269- 1987 - OPC cement
- IS 1489 - 1991 - PPC cement
- IS 383-1970 - Specification for Coarse and Fine Aggregates from Natural Sources
for Concrete
- IS 2386 - 1963 - Methods of Test for Aggregates for Concrete
(Part 1 – 8)
- IS 516-1959- Methods of Tests for Strength of Concrete
- IS 1199-1959 - Methods of Sampling and Analysis of Concrete
- IS 3812-2003 - Specification for Fly Ash for use as Pozzolana and Admixture
- IS 4926-2003- Ready-Mixed Concrete — Code of Practice
- IS 4990 - 1993 - Plywood for Concrete Shuttering Work - Specification
- IS 10262 - 1982- Concrete Mix Proportioning - Guidelines
- IS 2502-1963- Code of Practice for Bending and Fixing of Bars for Concrete
Reinforcement
- IS 9103 – 1999 - Concrete Admixtures – Specification

2. Tools and Equipment:


 Site Equipment: Air Compressor, Concrete Pump, Mechanical Vibrator, Rubber / Wooden
Mallet, Measuring Tape, Right Angle, Plumb Bob, Concrete Spreader, Power Floater, Hand
Float, Surveying Equipment’s, etc.
 QA QC Equipment: Clean Pan, Trowel, Measuring Jar & Brush, Cube Moulds, Tamping
Rod, Slump cone, Flow Table, Wheel Barrow, etc.

3. Work Procedure:
9.1 Pre-checks/ Preparation:
- Prior to start any activity on site, the Site Engineer must be notified.
- Ensure that all workers are aware of the evacuation plan. Cordon off the work area.
- Discuss the method of working with all supervisors as per approved pour plan.
- Ensure soil compaction test certificate before Soling / Plum Concrete / PCC work, if
required.
- Anti-termite treatment should be done before concreting.
- Stand by mechanical equipment’s shall be checked for emergency break-down happened
like Concrete Pump, Mechanical Vibrator, Power Floater, etc.

Page 37 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING AND PCC WORK 00 37-38
- All the related documents such as Concrete Mix Design, Shop Drawings, Method
Statement, Material Approval, Pour Plan, Pour Card and Inspection Checklists, etc. must
be approved and available upon request.
- Cube Moulds, Thermometer, Slump Cone, Flow Table, etc. shall be arranged prior to the
concreting operation.
- Any accumulated rainwater shall be pumped from the spill collection sump or bailed out
only under controlled circumstances and if contaminated, should be disposed of in
accordance with legislation.
- Clean the Excavation formation and remove the loose materials. Leveling & proper
dimension should be checked as per the approved drawings.
9.2 Rubble Soling Work Procedure
- Fix the 10mm or 12mm bar at 5m or 10m interval and mark all levels on it like Footing
PCC Top, Bottom Level of PCC, Top Level of Rubble Soling, Bottom Level of Rubble Soling,
etc.
- Start laying of stone as per your given standards, generally, all are preferred “Rubble
Soling” Where we need to keep all the stone should be dense, and minimum gaps are
kept between them and fix the small stone chips in the gaps of stones.
- Fix Line Dori to the marked bar at the top level of Rubble soling. And lay all the area as per
the marking, if any stone height is more than your desired height then it should be cut by
the hammer.
9.3 Plum Concrete Work Procedure
- The volume of the plum from the concrete will not exceed 40% (percent) of overall
volume.
- Plum will comprise of black trap basalt of crushing strength of minimum 100 Kg /Sq.cm.
- Plum concrete density 1650 kg/Cubic.meter
- Each layer plum concert maximum height 900mm did not exceed more hight in one layer
- NO two stones are closer than 150mm to each other either sideway or bottom to the top
layer.
9.4 Work Procedure for Rock Anchoring for Raft Foundation:
- Ensure design received from consultant for rock anchoring.
- Achieve depth of anchor hole and check depth, location, alignment of Anchor whole as
per GFC / Design.
- Place reinforcement in anchor hole and grout with approved material.
- Pull-out test to be carried out to check the designed load.
9.1 PCC Work Procedure
- Wherever necessary, Fix Shuttering where PCC to be laid.
- Surface should be saturated and free from foreign particles.
- Provide proper level pads for level before starting PCC.
Place the PCC, spread it by panja or spade & Compact by rammers/wooden batten with handle in
both ends & Level it.

Page 38 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/04 PRESSURE RELEASE PIPE GROUTING 00 39-


1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
a) Cement (PPC/OPC) b) Sand (River / Crushed / Silpoze)
c) G.I/MS pipe d) Water-proofing Grout Compound

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others
as applicable.

- IS 1489 - 1991-PPC cement


- IS 2645 - 2003 - Specification for Integral Waterproofing Compounds for Cement
- Mortar and Concrete Specification
- IS2062-Codeof Practice for MS Steel Specifications
- IS 2629 – 1985 - Hot-dip Galvanizing of Iron and Steel
- IS 3203 - 1982 - Method for Testing Local Thickness of Electroplated Coating
- IS 2633 – 1986- Method for Testing of coating on Zink coated articles
- Manufacturer Technical Specifications
3. Tools and Equipment:
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Bucket, Measuring Jar, Blower, Pressure Grouting Machine, Weigh Balance, etc.
4. Work Procedure for Pressure Release Pipe:
a. Pre-Check:
- RCC and Civil work complete in all respect.
- Clearance from Structural Consultant taken before work commencement.
- Ensure all Materials available for Pressure Grouting.
b. Work Procedure:
- Prior to start any activity on site, the consulting engineer must be notified.
- Inserting G.I. C class pipe (Or Approved Make) in to pressure release pipe / Location.
- Fill gaps between two pipes using micro concrete.
- Seal the RCC top near pipe by using approved material (Polymer modified mortar) and
quartz sand.
- Inner 60mm diameter pipe to be extended up to 4 meters or as specified by Consultant.
- Dewater shall be done till the required level.
- Install 40mm diameter inflatable packers for subsequent grouting or as specified by the
Consultant.
- Inject Cementitious / PU / Alternate approved type grout using high pressure hand
operated or electrically operated grouting.
- Cut the pressure release pipe flush with the concrete and sealing the same with epoxy
mortar.

Page 39 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/05 BACKFILLING WORK 00 40-43

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Murum / Soil
 Controlled Low Strength Material (CLSM)
A controlled low-strength material (CLSM) is a self-consolidating, cementing material
used primarily as a backfill as an alternative to compacted fill. Many terms have been
used to describe this material, including flow-able fill, un-shrink-able fill, controlled
density fill, flow-able mortar, plastic soil-cement, and soil-cement slurry; however, the
correct terminology is controlled low-strength material.

2. Technical Specifications and Applicable Standards:

Work shall be carried out as per following specifications / standards / code and / or others
as applicable.
- IS 1200 (PART 1)-1992 - Methods of Measurement of Building and Civil
Engineering Works - Earthwork
- IS 2720 - Methods of Test for Soils
 PART 2: 1983 - Determination of Water Content.
 PART 7: 1980 - Determination of Water Content - Dry Density relation
using light compaction
 PART 8: 1983 - Determination of Water Content - Dry Density relation
using heavy compaction
 PART 28: 1974 - Determination of Dry Density of Soils in place by the Sand
Replacement Method.
 PART 29: 1975- Determination of Dry Density of Soils in place by the Core
Cutters Method
- IS 3764 - 1992 - Safety Code for Excavation Work.
- ACI 229R-99 - Controlled low strength materials

3. Tools and Equipment:


Trowel, Plant and Machineries, Mud Pan, Compaction Machine & Testing Equipment etc.

4. Work Procedure:
- The Site Engineer shall ensure that the material to be used for backfilling is in accordance
with the relevant Specification.

Page 40 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/05 BACKFILLING WORK 00 40-43


- The Project Manager & Site Engineer shall check availability of GFC drawings and
specifications for any discrepancies. If any discrepancies are discovered, the Project
Manager shall be notified who will get the same clarified from the Architect / Consulting.
- The Site Engineer shall supervise the clearing of existing vegetation and ensure that a
topographical survey of the site has been carried out prior to the commencement of
earthworks.
- Ensure any interruption to the existing utilities shall be permitted by the consultant in
writing before 48 hours to start of the work.
- Ensure structural water-proofing done and protected at the outer side of the structure
before start of backfilling work.
- Sufficient light arrangements should be made for work in the night shift. Temporary
supports shall be given to shear wall less than 250 mm thick to avoid bending of
structure.
- The Site Engineer shall ensure that temporary drainage is provided or the
seepage/ground water is pumped out from the site to suitable drainage point and
maintained throughout the construction period in order that the site remains reasonably
dry. If Required maintain ground water table to a depth of at least 1 meter below the
excavation depth at all time and maintained.
- The Project Manager shall ensure that only suitable / approved material from cut is used
for backfilling. Unsuitable material shall be disposed off to dumping ground as per debris
management plan.
- The material shall be free from rubbish, roots, hard lumps and any other foreign organic
material. The compaction of filling shall be carried out as specified in drawings or as
directed by Project Manager / Site Engineer.
- Where necessary, the Project Manager shall decide the method for protecting earthworks
on slope from soil erosion.
- Check for any existing underground utility services through Electrical scanning and make a
full service survey before the start.
- All operations for structural fill & backfill which will support footings & slabs shall be
conducted in the dry with suitable on - site taken from excavated stock piles designated
for such use.
- Back filling shall be done in layers and ensure each layer is properly compacted to achieve
desired level of compaction as specified by consultant. Compaction shall be done with
approval methodology.
- Backfilling of foundation pits and trenches will be carried out after adequate strength
has reached for foundations and structural work.
- Area will be stripped for a depth of 200mm and will be compacted to 95% of the
Maximum density.

Page 41 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/05 BACKFILLING WORK 00 40-43


- Care to be taken during backfilling, to avoid damage to waterproofing layer or RCC
member. Ensure or if required provide protection coat to water-proofing layer to avoid
damages.
- Compaction shall be done by as per approval.
- Loose layer thickness will be 200 to 400 mm thick before compaction.
- Next backfill layer will be placed within 24 hours of moisture treatment and compaction.
- After spreading of Back fill material, it will be watered and compacted in layer not
exceeding 150 mm in depth or directed by the site Engineer, when compacted to achieve
95% of the Maximum dry density & moisture content within 2% of OMC.
- Check and ensure that the dimensions and depths of backfilling completed as required to
allow for safe and proper construction work. Backfilling work shall be done in layer wise.
- For Compaction, plate compactors and any other suitable compactors will be used for
achieving desired compaction.
- To prevent ponding of water, a system of temporary drainage will be provided
- Backfilling shall not be proceeded with following conditions
1. In case of heavy rain
2. Water logging

- Inspection shall be done by Site Engineer when the specified levels/limits of backfilling are
reached.
- Site Engineer shall check the backfilling process-using Checklist for backfilling.
- The Project Manager shall ensure that sufficient quantity of Machineries’, Material &
Manpower is available to execute specified job as per construction Master schedule &
Joint measurements to be taken for record purpose
Quality Control of Backfill
- Prior to carrying out filling Project Team shall carry out sufficient laboratory moisture -
density tests to evaluate compaction. From these tests, the maximum dry density and
optimum moisture content for the approved fill material shall be determined.
- The laboratory tests shall be in accordance with Indian Standards IS:2720 - Parts 2, 7 and
8. Based on the type of soil, suitable test shall be adopted.
- When earth filling is being carried out field tests shall be carried out at various stages to
ensure that adequate compaction is being achieved. The field tests shall be in accordance
with IS:2720, Part 28 and 29.
- The compacted surface shall be carried out to the dimensions and levels as indicated on
the drawing within a tolerance of ± 25 mm.
- Frequency of Field Density Tests to ensure adequate Quality Control on compaction of
earth fill, the following minimum number of field density tests or directed by the Site
Engineer / instructed by the consultant shall be performed.
o One test for every 500 cubic meters of fill material placed for fill construction in
site grading.

Page 42 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/05 BACKFILLING WORK 00 40-43


o One test for every 250 cubic meters of fill material placed for fill construction in
plinth filling.
- The Supervisor shall verify that fill material shall be suitably placed and compacted in
accordance with method statement and that the tests identified on method statement
are carried out. The Site Engineer shall verify that these tests confirm compliance with the
Outline Construction Specification & relevant codes.
- The Surveyor shall check that backfilling is completed to the correct lines and levels.
- The Site Engineer shall verify that all requirements identified on method statement have
been accomplished and any non-conformance raised has been closed out prior to signing
off the work.

Page 43 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/06 ANTI-TERMITE WORK 00 44-45


1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Anti-Termite Chemical / Material

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications

3. Tools and Equipment:


Spraying / Penetrating Equipment
4. PROCEDURE:
a. Treatment for Basement Structure Bldg.
- The treatment shall start after the excavation is complete and before laying soaling and
PCC.
- The treatment shall carry out as below.
1) Treatment of Basement Floor
- The top surface of the basement floor & sides upto a height of 300 mm shall be treated
before PCC with chemical emulsion.
2) Treatment of Soil along the Retaining Walls
- The filled soil in contact with the Retaining Wall shall be treated with chemical emulsion
of vertical surface. As the back filling done in layers, treatment is also carried out in layers.
3) Treatment of soil along the External perimeter of Bldg.
- After the bldg. is completed the soil along the external perimeter of the structure shall be
treated by digging holes upto a depth of 300 mm and 150 mm centers. The chemical shall
be sprayed Of the vertical surface.
4) Treatment of soil surrounding Pipe Wastes & Conduits
- When pipes, wastes and conduits enter the soil inside the area of the foundation the soil
surrounding the point of entry shall be loosened around each pipe, wastes or conduits for
a distance of 150 mm and to a depth of 75 mm and loosened soil shall be treated with
chemical emulsion.
5) Treatment for Expansion Joints
- Expansion joints at ground level are one of the biggest hazards for termite infestation to
the bldg. The soil around these joints to be treated @ 2.0 Ltr. per linear meter after the
sub-grade has been laid.
E) Treatments for Plinth Structure Bldg. without Basement.

Page 44 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- This treatment will start after the foundation and the plinth beam work is over. The
treatment shall be carried out as below.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/06 ANTI-TERMITE WORK 00 44-45

b. Treatment of plinth Filling:


- In the plinth filling holes upto 500 mm deep and 150mm centres will be made along the
all beams & columns.
- The chemical emulsion will be poured / sprayed of the vertical surface into these holes.
- The Top surface of consolidated earth in plinth filling new soil level below ground floor
slab shall be treated with chemical emulsion.
- If the filled earth , and surface does not allow the chemical emulsion to go through zig zag
will be made to loosen the soil to facilitate saturation of the soil with the chemical
emulsion.

Page 45 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/07 RCC WORK 00 46-47


1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Concrete and Concrete Ingredients (Cement, Fly Ash, GGBS, Micro-silica, Fine and Coarse
Aggregate, Water, Admixtures, etc.)
 Steel Reinforcement
 Shuttering Ply / Shuttering Scheme
 Scaffolding
 Binding Wire
 Shuttering Oil
 Curing Compound
 Mechanical Coupler
 Cover Block / Spacers
 RMC Material Source / Brand, Concrete Mix Design, RMC Vendors / Suppliers shall be
approved.

2. Technical Specifications and Applicable Standards:


Structural Concreting Work shall be carried out as per following specifications / standards / code
and / or others as applicable.
 IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
 IS 12269 - 1987 - OPC cement
 IS 1489 - 1991 - PPC cement
 IS 383–197 - Specification for Coarse and Fine Aggregates from Natural Sources for
Concrete
 IS 2386-1963 - Methods of Test for Aggregates for Concrete (Part 1 – 8)
 IS 516 – 1959 - Methods of Tests for Strength of Concrete
 IS 1199-1959 - Methods of Sampling and Analysis of Concrete
 IS 1786-1985- High Strength Deformed Steel Bars and Wires for Concrete Reinforcement
 IS 2750-1964- Specification for Steel Scaffoldings
 IS 3812-2003 - Specification for Fly Ash for use as Pozzolana and Admixture
 IS 4926-2003- Ready-Mixed Concrete — Code of Practice
 IS 4990-1993 - Plywood for Concrete Shuttering Work - Specification
 IS 10262-1982- Concrete Mix Proportioning - Guidelines
 IS 2502-1963 - Code of Practice for Bending and Fixing of Bars for Concrete Reinforcement

Page 46 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

 IS 9103-1999- Concrete Admixtures – Specification

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/07 RCC WORK 00 46-47


3. Tools and Equipment:
 Site Equipment: Air Compressor / Air Blower, Concrete Pump, Mechanical Vibrator,
Rubber / Wooden Mallet, Measuring Tape, Right Angle, Plumb Bob, Concrete Spreader,
Power Floater, Hand Float, etc.
 QA QC Equipment: Clean Pan, Trowel, Measuring Jar & Brush, Cube Moulds, Tamping
Rod, Slump cone, Flow Table, Wheel Barrow, etc.

4. Work Procedure:
- Ensure all guidelines listed in above for concrete activities. (Page NO 18-27)
- Recommended only one RMC manufacturer / supplier for individual casting.
- Level to be ensured before start of pouring of concrete.
- Ensure pouring sequence and monitor concrete pouring rate.
- Height of pouring concrete should not exceed 1.5 m.
- Construction joint should be avoided in the column.
- Proper cover as per structural drawings to be maintained.

Page 47 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED FLOORING WORK 00 48-52

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Concrete and Concrete Ingredients (Cement, Fly Ash, GGBS, Micro-silica, Fine and Coarse
Aggregate, Water, Admixtures, etc.)
 Shuttering / MS Channels
 Shuttering Oil
 Curing Compound
 Construction / Joint filler
 RMC Material Source / Brand, Concrete Mix Design, RMC Vendors / Suppliers shall be
approved.
 Sealant
 Bonding Agent
 PP Fibers
 Floor Hardener
 Isolation Sheet

2. Technical Specifications and Applicable Standards:


Structural Concreting Work shall be carried out as per following specifications / standards / code
and / or others as applicable.
 IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
 IS 12269:1987 - OPC cement
 IS 1489:1991 - PPC cement
 IS 383-1970 - Specification for Coarse and Fine Aggregates from Natural Sources for
Concrete
 IS 2386-1963 (Part 1 – 8) - Methods of Test for Aggregates for Concrete
 IS 516-1959 - Methods of Tests for Strength of Concrete
 IS 1199-1959 - Methods of Sampling and Analysis of Concrete
 IS 3812-2003 - Specification for Fly Ash for use as Pozzolana and Admixture
 IS 4926-2003 - Ready-Mixed Concrete — Code of Practice
 IS 10262-1982- Concrete Mix Proportioning - Guidelines
 IS 9103-1999 - Concrete Admixtures – Specification
 IS 4971 – Code for Industrial Floor Finish

Page 48 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED FLOORING WORK 00 48-52
3. Tools and Equipment:
 Site Equipment:-Air Compressor, Water Jet Spray, Concrete Pump, Vibrator with high
frequency preferably 335hz, dia.25 to 38cm., Poker Vibrator with combination of surface
vibrator. Suction mat 100% made from air tight plastic material, width of the mat shall be
same as bay, Filter pad 1200mm length, width shall be less than the bay width by about
20mm, Vacuum pump, Skim floater with disc, Power Trowel, Rubber / Wooden Mallet,
Measuring Tape, Concrete Spreader, , Hand Float, etc.
 QA QC Equipment: -Clean Pan, Trowel, Measuring Jar & Brush, Cube Moulds, Tamping
Rod, Slump cone, Flow Table, Wheel Barrow, etc.

4. Work Procedure:

9.1 Formwork:-
- Initial suitable layout of construction joints and isolation joints shall be decided prior to
start of vacuum dewatering flooring work. (As per approved ridge line drawings)
- Approved Pour sequence, Treatment of construction joint etc. will be followed as per GFC
Drawing /Engineer In-Charge.
- All formwork material shall be approved prior to work start.
- Two side track rails (mild steel arrangement) to be provided with required level and
gradient on which the leveling beam and surface vibrator would be erected. The surface
of the MS channels guides (on which the surface vibrator is supported) shall be cleaned
from concrete. Align the guide channels to true line and level. Panel casting layout shall
be strictly followed as per layout of construction joint.
- While fixing shutter space of at least 1 feet shall be left from walls. This will help to facility
the movement of person operating the machine.
- Stop ends to be provided for both ends with MS arrangement or equivalent. Area of pour
will be decided as per site condition and direction of client engineer.
9.2 Embedded Items:-
- All Inserts of any kind like, sleeves, pipes, bolts and nuts, anchor bolts, MEP conduits, etc.
are to be accurately placed as per approved drawing and tied properly to avoid any
displacement during concreting, get clarification / confirmation from MEP / concerned
engineer.
9.3 Pre-checks/ Preparation:-
- Prior to start any activity on site, the Site Engineer must be notified.
- The base concrete surface shall be thoroughly cleaned and dusted off by water Jet Spray
or Air Compressor. All dead mortar, loose concrete, dust, dirt, scales smoke splashes,
mortar droppings and grease shall be thoroughly removed before started the work.

Page 49 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- All major honey comb, damaged surfaces and cracks of main RCC structure should be
repaired.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED FLOORING WORK 00 48-52


- Mark the layout as per the GFC, MEP and architectural layout.
- Check for slopes and drainage.
- Check the structural section drawings.
- MEP clearance is mandatory prior to commencement of Work.
- Level Pads /Bull Marks should be prepared before fixing of channels.
- Discuss the method of working with all supervisors and engineers as per approved pour
plan.
- All the related documents such as Concrete Mix Design, Shop Drawings, Method
Statement, Material Approval, Pour Plan etc. must be approved and should be available
upon request.
- Ensure the source of supply of ready mix and grade of concrete.
- Stand by mechanical equipment’s shall be checked for emergency break-down happened
like Concrete Pump, Mechanical Vibrator, Power Floater, etc.
- Cube Moulds, thermometer, Slump cone, flow table, etc. shall be arranged prior to the
concreting operation.
- Arrange the concrete testing area with proper illumination.
- Polythene sheet, hessian cloths, water, etc. shall be arranged.
9.4 Bonding Agent (Chemical) Application:
- Bonding Agent / Chemical application to be done as per manufacturer technical
specification.
- Bonding agent should be shaking well to have homogenous mix and colour.
- Always add powder to Liquid (e.g. polymer) under constant mixing using slow speed
paddle mixer to achieve smooth and homo generous slurry.
- Allow to stand about 5 minutes to release entrapped air.
A. Placing:
- Pour sequence shall be approved before work commencement.
- Isolation sheet to be provided at Old RCC structure / joint.
- While planning the pour depending upon the area and quantity the following points are
to consider.
o Rate of Pour of concrete
o No. of Masons required
o No. of Vibrators Required
o Area Lighting
o Proper Access
o Concrete placement – Crane/Manual/Pump
- As per drawing/specification construction joint shall be provided and treated properly.

Page 50 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- The mix after discharging from the transit mixer shall be transported by wheel barrows,
buckets, pump’s, etc. without causing segregation and loss of cement slurry and without

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED FLOORING WORK 00 48-52


altering its desired properties, with regards to water cement ratio, slump, cohesion and
homogeneity.
- Before placing of the concrete visual checks shall be done for all embedded parts, water
stops, expansion boards shall be correctly placed, aligned and securely held in position.
- Precaution shall be taken during raining season to avoid surface run-off or direct rain
water contaminations in the concrete pour. Plastic sheet / shade shall be provided.
- Concrete will be deposited in successive layers to its final position, as nearly as
practicable, to avoid segregation due to re-handling.
- The concrete shall be placed and compacted before initial setting of concrete commences
and each layer of concrete shall be compacted fully before the succeeding layer in placed.
- For locations where direct placement is not possible and in particular through narrow
forms, suitable drop chutes will be provided to confine the concrete in movement.
- Concrete shall be placed carefully to avoid displacement of embedded parts, water
stoppers, etc.
- To avoid cold joints casting is to be planned in such a manner to cover all the grids.
B. Compaction:
- Each layer of fresh concrete shall be thoroughly compacted by mechanical vibrators to
the minimum practicable consolidated volume.
- Placing of specified grade of concrete shall begin at starting point and continued in a
horizontal manner.
- Vibration to be done with needle vibrator of minimum 40mm /60mm dia. The concrete to
be vibrated shall be placed in position in level layers of suitable thickness not greater than
the effective length of the vibrating needle.
- The spacing shall provide some overlapping of the area vibrated at each insertion. It is
better insert the vibrating head at a number of places than to leave it at one place for a
long time.
- Vibrator shall be prevented from coming into contact with the shuttering sides,
embedded parts, etc. under and over vibration shall be avoided.
- Ensure that the areas close to channels and stop ends are carefully vibrated
- Ensure not distribute the concrete with the poker vibrator as it would create a risk of over
vibration and segregation.
- After completing the laying for 5 to 6 sq.mt, the surface vibrator shall be run over the
concrete surface.
- The vibrating screed shall be moved forward as rapidly as proper consolidation allows.
The proper surcharge of concrete must be maintained in front of the leading edge of the
screed.

Page 51 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Continuing the above process the surface vibrator to be run for the second time along
with leveling on the finished concrete surface.
- Immediately after leveling, the concrete shall be compacted / treated with truss vibrator
or immediate start dewatering by vacuum sheet to dewater excess water.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED FLOORING WORK 00 48-52


- Start the engine and slowly increase the throttle.
- Engage or turn winch handles simultaneously to keep the screed even.
- DO NOT adjust the throttle on the engine to slow down or speed up the hydraulic
winches, use the flow controls instead.
- NEVER let the concrete build up on the front blade, this causes the screed to be stressed
and is strenuous on the operators controlling the manual winches. The concrete should
not go above the bolts attaching the blades. If this happens, stop the screed and let the
vibration do its job.
- If the concrete is not being added at the appropriate rate, slow the screed down to
compensate.
- The speed at which the screed should be operated depends on the slump of the concrete.
Pay close attention to the aggregates, slump and concrete modifying agents so that can
compensate for them. REMINDER! – DO NOT OVER – VIBRATE THE CONCRETE
- Non Color Floor Hardener of approved make @ 3.5 KG/Sq.mt shall be sprinkled over
green concrete .1/3 rd of dry shake shall be broad-casted in first pass and same is floated
with power floater, remaining 2/3rd of dry shake is sprinkled in next pass thus the floor
laid is floated and toweled to acquire smooth finish.1M X 1M Grid shall be marked on
Floor to check 3.5 KG/Sq.mt consumption of floor hardener.
9.5 Concrete Finishing:-
- Finish concrete surface as specified in the approved construction drawing and
specification.
- The second finishing operation shall be power troweling with skim floater attached with
the troweling blades. Normally, troweling is to be continued till the smooth surface finish
is achieved without floater marks.
- Final finishing shall be as per approved by project specification or instructed by Site In-
charge. If stamped concrete, stamping design approved prior to start of work.
9.6 Curing Of Concrete:
- Floor has to be protected from rapid drying because of dewatering chemical reaction is
faster, which may result cracking.
- The hessian cloth curing shall be started immediately after initial setting start and same
shall be continued for a minimum of 7 days.
- The curing water shall be the same as that is used for construction purpose.
9.7 Groove and bitumen filling:
- Making groove at locations not more than 11-12 sqmt or as per Site In-charge instruction.
- Thickness and depth of groves 4mmx20mm respectively or as per project specification.

Page 52 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Groove shall be cut by mechanical saw within 72hrs or as soon as concrete is ready to
accept the saw cut.
- Fill the grooves with approved bitumen or bitumen sealant/Polysulphide sealant or as per
project specification.
- Groove cleaning and drying needs to be ensured.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/09 RCC REPAIRING WORK 00 53-57

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Repairing Material
 Shuttering Ply / Shuttering Scheme
 Shuttering Oil
 Curing Compound
 Bonding Agent

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
 IS 12269 - 1987 - OPC cement
 IS 1489 - 1991 - PPC cement
 IS 516 – 1959 - Methods of Tests for Strength of Concrete
 IS 13311 – 1992 – Non Destructive Testing of Concrete – Method of Test

3. Tools and Equipment:


 Site Equipment: Air Blower, Electrical Chisel, Chisel, Hammer, Rubber / Wooden Mallet,
Measuring Tape, Right Angle, Plumb Bob, Hand Float, Brush, Mechanical Mixer, Pressure
Grouting Machine, Measuring Jar, etc.
 QA QC Equipment: Clean Pan, Trowel, Measuring Jar & Brush, Cube Moulds, Tamping
Rod, etc.

4. Work Procedure:
- Ensure Corrective Action (CA) and Preventive Action (PA) Should be submitted to the
Dosti Site Team / Quality team for their approval. Only after approval of CAPA repairing
work can start
- The surface preparation of the concrete to be repaired and the mixing, application and
curing of the repair mortars/ micro-Concrete/Cementitious grout/epoxy grout/PU grout

Page 53 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

shall be as per manufacturer’s requirements/recommendations and /or the specifications


applicable for concrete shall be followed if specific requirements are not given by the
manufacturer(e.g. curing).
- All repair areas shall be covered from direct sunlight.
- The repair shall only be carried out after the curing has been completed of structure.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/09 RCC REPAIRING WORK 00 53-57

9.12 Repair of Cracks:


9.12.1 Crack within 0.3 mm in width
- Open the crack, by chiseling a V-cut, to a depth where the crack visually seems to stop;
however the maximum depth for chiseling is 20mm.
- The crack shall be cleaned with compressed air and shall be washed out by clean water.
- Fill the crack up with water and observe whether or not the crack continues by looking for
air bubbles in the water due to air escaping out of the crack.
- Approved low viscosity fillers / repairing material shall be poured into the crack as per
manufactures recommendation until the crack is fully saturated with therein.
- Where detection of a possible continuation of the crack with water filling is not possible
(on vertical faces) the crack repair shall be discussed between DOSTI and the Contractor,
looking for similarities with horizontal cracks in the same area.
- Where similarities are not found and/or agreed the crack shall be deemed to be deep and
injected with epoxy and the V-cut further repaired/sealed as per above.
9.12.2 Crack more than 0.3 mm in width
- Open the crack, by chiseling a V-cut, to a depth where the crack visually seems to stop;
however the maximum depth for chiseling is 20mm. If crack seems as a structural crack
(same pattern observed from both sides), the issue to be raised to the Consultant for
further clarification / action.
- The crack shall be cleaned with compressed air and shall be washed out by clean water.
- Fill the crack up with water and observe whether or not the crack continues by looking for
air bubbles in the water due to air escaping out of the crack.
- Approved low viscosity fillers / repairing material shall be poured into the crack as per
manufactures recommendation until the crack is fully saturated with therein. Repair / seal
the V-cut of the crack, Fix the nozzles for injection grouting. Injection grouting shall be
done with an approved shrinkage controlled structural grade Cementitious/ epoxy/PU
repair mortar system.

Page 54 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Where detection of a possible continuation of the crack with water filling is not possible
(on vertical faces) the crack repair shall be discussed between DOSTI and the Contractor,
looking for similarities with horizontal cracks in the same area.
- Where similarities are not found and/or agreed the crack shall be deemed to be deep and
injected with epoxy and the V-cut further repaired/sealed as per above.
- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/09 RCC REPAIRING WORK 00 53-57

9.13 Repair of Honey-comb:


9.13.1 Repair of Minor surface deficiencies in the concrete (air voids, etc.)
- Surface defects that can be enclosed by a 50mm circle and in which circle the concrete
cover is not reduced by more than 10mm are defined as minor surface deficiencies.
- The affected defective area shall be hammered or chiseled, cleaned,
brushed, to remove all the loose concrete and small particles such as sand.
- These minor voids shall be filled with approved fine / micro mortar as per manufacturer
specification by brush or by trowel application.
9.13.2 Honey-combing within Cover Zone
- Honey-comb surfaces deficiencies are deficiencies that cannot be enclosed by a circle of
50mm and / or where the concrete cover has been reduced by more than 10mm and up
to the rebar zone (no rebar exposed).
- Identify the loose concrete and honey combs areas of the defective areas.
- The affected defective area shall be hammered or chiseled, cleaned,
brushed, to remove all the loose concrete and small particles such as sand.
- Defective concrete shall be removed up to sound concrete.
- The area shall be cleaned with compressed air and shall be washed out by clean water.
- All the concrete dust that left over is then washed away with water or blown away using
compressed air. This is to ensure good bonding between the concrete and there pair
material.

- These honeycombing shall be repaired by an approved shrinkage controlled structural


grade cementitious mortar system as per manufacturer technical specifications.

Page 55 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.

9.13.3 Honey-combing Exposing Reinforcement

- Areas where after removal of the defective concrete the rebar becomes exposed and/or
where the extend of the repair is such that formwork has to be used are defined as Major
honeycomb.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/09 RCC REPAIRING WORK 00 53-57

- Identify the loose concrete and honey combs areas of the defective areas.

- The affected defective area shall be hammered or chiseled, cleaned,


brushed, to remove all the loose concrete and small particles such as sand.

- Defective concrete shall be removed up to sound concrete.

- The area shall be cleaned with compressed air and shall be washed out by clean water.

- If the defective concrete extends to the rebar a clear gap of at least 20mm shall be
created behind the rear face of the rebar, such that a gloved hand can comfortably reach
behind the main bars.

- All exposed rebar shall be carefully cleaned by wire brushing before the repair and the
concrete faces to be scrabbled and wetted as per requirement/recommendation of the
manufacturer of the repair micro concrete.

- All the concrete dust that left over is then washed away with water or blown away using
compressed air. This is to ensure good bonding between the concrete and there repair
material.

- Ensure that the surface is free from oil, grease or any loose material.

- These honeycombing shall be repaired by an approved shrinkage controlled structural


grade cementitious mortar system as per manufacturer technical specifications. If
required shuttering pockets to be made to pour repairing mortar for major / congested
reinforcement area.

- If honey-comb seems as a major structural defect i.e. not enclosed by a circle of 50mm
and / or where the concrete cover has been reduced by more than 50 mm the issue to be
raised to the Consultant for further clarification / action.

Page 56 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.

9.13.4 Uneven Casting / Bulging / Not in Size:

- Identify Structure / area the where Uneven Casting / Bulging / deviation in size found.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/09 RCC REPAIRING WORK 00 53-57

- Mark the defective area, consults to Project Head / Quality Head for further correction /
rectification.

- If defect seems as a major structural defect i.e. bulging more than 25 mm, deviate from
size / shape / location by more than 15mm or other deviation from the approved project
specifications, the issue to be raised to the Consultant for further clarification / action.

- The affected defective area shall be hammered or chiseled to cut / break in a straight in
horizontal / vertical line and shall be cleaned, brushed, to remove all the loose concrete
and small particles such as sand.

- These defective areas shall be repaired by an approved shrinkage controlled structural


grade cementitious mortar system as per manufacturer technical specifications.

9.13.5 Tie-Rod / Wall Tie Hole Fillings:

- Remove all PVC pipes / Wall Tie Sleeves or temporary material from the main structure.

- The area shall be cleaned with compressed air and shall be washed out by clean water.

- Tie-rod / Wall Tie hole shall be filled by an approved shrinkage controlled structural grade
cementitious mortar system as per manufacturer technical specifications.

- Ensure hole shall be filled 100 % from both sides

- Check for water leakage test by running water for 02 days at regular interval.

9.14 Post-completion Inspection

Page 57 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Visual / measurable inspection of concrete member / structure shall be done after de-
shuttering for the checks of surface irregularities, honey-comb, cracks, major deflections,
bulging, etc. carried out as per post pour inspection checklist.

- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/10 WATER-PROOFING WORK – RAFT, R/WALL AND LIFT PIT 00 58-59

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Bricks / AAC Blocks
 Fiber Mesh
 Ready Mix Repairing Mortar
 Water-Proofing Compound / Membrane

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following Specifications / Standards / Code and / or others as
applicable.
- IS 1542 - 1992 - Sand for Plaster
- IS 1489 – 1991- PPC cement
- IS 1077 - 1992- Common Burnt Clay Building Bricks
- IS 2645:2003 - Specification for Integral Waterproofing Compounds for Cement
Mortar and Concrete Specification
- Material Manufacturer Technical Specifications

3. Tools and Equipment:


Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Bucket, Measuring Jar, Float,Wire Brush, Grinder, Chisel, Hammer, Blower, Pressure Grouting
Machine, Measuring Tape, Spirit Level, Plumb Bob, Weigh Balance, Brush / Roller / Spray
Machine, etc.
4. Work Procedure:

Page 58 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

If method statement submitted by the Water-Proofing contractor to Dosti Approval prior to start
of the work, then Approved contractor method statement to be implement at site.
9.1 Pre-Check:
- For Night Work water-proofing work permission to be taken from Site Engineer prior to
work start.
- Check RCC/ PCC / Civil work completed wherever required.
- Clearance from MEP (Services) department, if required.
- Ensure all material for waterproofing available at site with required quantity.
- Highly undulated surface and major repair to be complete prior.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/10 WATER-PROOFING WORK – RAFT, R/WALL AND LIFT PIT 00 58-59

9.2 Work Procedure:


9.2.1 Surface Preparation.
- The substrate shall be PCC concrete of sufficient thickness to ensure a firm substrate that
will not crack or deform under normal trafficable conditions during waterproofing
installation, and structural concreting operations. It should be free from debris and other
irregularities, which may puncture and damage the waterproof liner.
- Surface to be treated must be workable dry and free from oil grease and foreign particles.
- All laitance, loose and foreign particles shall be removed by mechanical scrubbing only.
- Any standing water on the substrate should be removed.
- All honeycomb, highly undulated, tie-rod holes, damaged surfaces and cracks should be
repaired.
- Injection grouting at all major honeycombed portions / construction joints of retaining
wall shall be carried out.
9.2.2 Procedure:-

- Ensure approved detailed drawing of Water-Proofing system is available.


- Application of chemical waterproofing coat / membrane (Crystalline / Elastomeric /
Polymer / Poly Urethane) can be done, on flat surface & wall portion.
- All the cutouts shall be treated & sealed by using non shrink grout.
- Application / laying of water-proofing material shall be done as per submitted / approved
technical specification of material or as per approved applicator method statement.
- Drain pipe mouth shall be fitted with PVC grating or filter media form inside and chicken
mesh / wire mesh from outside.
- Pressure release pipes shall be fixed as per approved drawings and as per manufacturer
technical specification.
- Ensure lapping of membrane minimum 75 mm or specified by manufacture as per
manufacturer specification. For continuous sheet, protection to be provided to avoid
damages.

Page 59 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- If required, as per manufacture specifications protection coat shall be provided to the


Water-proofing coat / compound / membrane after application / installation. Adequate
slope shall be provided towards sump/drain pipe.
- Visual / measurable inspection shall be done after Water-proofing work for the checks of
Even Application / Installation, Lapping, finishing, etc. carried out as per post pour
inspection checklist.
- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Bricks
 Fiber Mesh
 Ready Mixed Non-Shrink Repairing Mortar
 Pipe Penetration Sealant
 Water-proofing Compound

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 1542- 1992 - Sand for Plaster
- IS 1489 - 1991-PPC cement
- IS 1077 - 1992 – Common Burnt Clay Building Bricks
- IS 2645 – 2003 - Specification for Integral Waterproofing Compounds for Cement
Mortar and Concrete Specification
- Material Manufacturer Technical Specifications
- IS: 13182 - Waterproofing & Damp-proofing of wet areas in buildings
- IS: 13435 - Acrylic Based polymer waterproofing compounds : Method of
test Part 1-5.

3. Tools and Equipment:

Page 60 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud
Pan, Bucket, Measuring Jar, Float, Wire Brush, Grinder, Chisel, Hammer, Blower,
Pressure Grouting, Measuring Tape, Spirit Level, Plumb Bob, Weigh Balance, etc.

4. Work Procedure:
9.15 Work Procedure:
9.15.1 Surface Preparation.
- Highly undulated surface and major repair to be complete prior.
- Level to be shifted from reference point to all toilets / bath and rooms before proceeding
for work
- Surface to be treated must be workable dry and free from oil grease and foreign particles.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63

- All laitance, loose and foreign particles shall be removed by wire brush or mechanical
scrubbing.
- All honey-comb, highly undulated, damaged surfaces and cracks should be repaired.
- Injection grouting at all major honeycombed portions and construction joints shall be
carried out, if necessary, after physical observation
- Coving shall be done at the all corners by Ready Mix Repairing mortar and shall be
grouted properly before application of Water-roofing.
- Area shall be tested for 3 days by ponding, to test for leakages and to serve water hungry
concrete surface.
- In case of major leakage, gravity grouting or pressure grouting shall be resorted to stop
leakages. Grouting to be done as per manufacturers specification.
- Levels of water-proofing shall be clearly marked on the walls with slope towards outlet, as
specified in drawing or minimum 1:100 otherwise.
- Check for any steel or cut end of rebar is exposed at top of slab. If exposed steel is seen
that concrete is to be chiseled off to the depth of 25mm around exposed steel. Steel to be
cut with cutter or grinder 25mm below slab top surface. Slab to be restored with polymer
mortar prepared as per manufacturers specification and cure for 3 days.
- Treatment to cutouts / Outlet pipes to done by using seal tape, polymer modified mortar
or grout.
9.15.2 Procedure:

- Prepare the chemical mix by slowly pouring the powder component in liquid polymer
component or as per manufacturer’s recommendation. Mixing shall be done by using a
suitable mechanical impeller only. Achieve a brush-able paste. Ensure pot life material for
consumption of material.
- Apply 1st coat by brush/roller on the surface evenly. After application it should be left for
4 to 5 hrs for drying & setting or re-coat-able time recommended by manufacturer.

Page 61 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Prepare more mix as above and apply second coat after drying of first coat. Preferably
apply the second coat in right angle direction to first coat. Allow the second coat to dry
for 4 to 5 hours or recommended by manufacturer.
- Application of chemical waterproofing coat shall be extended up to 1.OO mtr. On wall.
- Ensure that material has been consumed as per specified quantities mentioned in
technical data sheets for the concerned material use.
- Post application moist curing shall be done for 3 days.
- If required Sand Broadcasting shall be done on Water-proofing membrane to provide
mechanical key for further finishes.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63


- Base coat using cement mortar in proportion 1:4 or as specified with approved
waterproofing compound shall be applied over top of base slab. Maximum thickness of
base coat shall be 25 mm at upper end of slope.
- Proper slope shall be given to base coat as per drawing towards drain spout and drain
spout to be fitted simultaneously with the base coat, as an additional precaution to take
care of seepage, if any. Base coat shall also be applied to the sides of the wall up to one
meter or as specified above the finished floor level (F.F.L) of the adjacent floor.
- Drain pipe mouth shall be fitted with PVC grating or filter media form inside and chicken
mesh / wire mesh from outside.
- Curing of base coat shall be done by ponding for 3 days and checked against leakage.
Leakage, if observed, shall be rendered with reapplication of base coat to ensure no
leakage.
- Floor traps and other plumbing lines shall be installed in brick masonry after application
of base coat.
- Slope of 1:100 or as specified shall be provided for piping and water proofing. Floor trap
shall be fixed with respect to finished floor level (F.F.L) of the slab.
- Rendering of holes shall be done using compatible bonding agents; SBR based expansive
grouts, waterproofing compounds.
- Application of brick bat coba shall be started, once plumbing lines are satisfactory
pressure tested.
- Bricks selected for using as Brick Bat coba shall be either full brick or 3/4th brick made out
of one complete brick by breaking into required size, using mallets.
- Brick bat shall not be stored in the form of a heap at one place and soaked thoroughly for
about 45 minutes prior to their placing.
- Use of plasticizer in mortars is recommended to increase workability as per
manufacturer’s specifications. Mortar mixed shall be used within 1Hour of preparation.
- Presoaked brick-bats shall then be laid in straight / radial, by inserting brickbats to a
depth of about 15mm by light tamping with the help of mallets. Thickness between
adjacent layers of brickbats shall not exceed 25mm.

Page 62 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Application of brick-bats shall proceed from one corner and shall be laid in radial pattern /
straight pattern to drain of any water which has seeped through. Level Pads for the same
shall be given by Site Engineer, considering into account adequate slope.
- The brickbat Layer shall then be cured for minimum 3 days by ponding.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound till top of brick-bats.
- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- Plaster work shall be done by cement sand mortar in the proportion 1:4 with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63

- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.

5. Final Coat with Integral W/P Compound

4. Brick Bat with Integral W/P Compound

3. Base Coat (25mm) with Integral W/P Compound

2. Water-proofing coating

1. Concrete Base Material grouted with expandable grout material

Page 63 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


WATER-PROOFING WORK – PLANTER, TERRACE, LANDSCAPE, HARDSCAPE,
MS/12 00 64-67
SWIMMING POOL

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Bricks
 Fiber Mesh
 Geotextile Sheet
 Water-proofing Compound

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 1542 - 1992 - Sand for Plaster
- IS 1489 - 1991-PPC cement
- IS 1077 - 1992 – Common Burnt Clay Building Bricks
- IS 2645 - 2003 - Specification for Integral Waterproofing Compounds for Cement
Mortar and Concrete Specification
- Manufacturer Technical Specifications
- IS: 13182 - Waterproofing &Damp-proofing of wet areas in buildings
- IS: 13435 - Acrylic Based polymer waterproofing compounds : Method of
test Part 1-5.
3. Tools and Equipment:
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Bucket, Measuring Jar, Float, Wire Brush, Grinder, Chisel, Hammer, Blower, Pressure
Grouting, Measuring Tape, Spirit Level, Plumb Bob, Weigh Balance, etc.

Page 64 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

4. Work Procedure:
If method statement submitted by the Water-Proofing contractor to Dosti Approval prior to start
of the work, then Approved contractor method statement to be implement at site.
9.16 Pre-Check:
- Prior to start any activity on site, the consulting engineer must be notifying.
- RCC and Civil work complete in all respect. No repairing work pending before handed-
over to Water-proofing agency.
- Clearance from MEP (Services) department.
- Ensure all material for waterproofing available.

REF NO PROCEDURE TITLE REV. NO PAGE NO


WATER-PROOFING WORK – PLANTER, TERRACE, LANDSCAPE, HARDSCAPE,
MS/12 00 64-67
SWIMMING POOL
- Highly undulated surface and major repair to be complete prior.
- Construction Joint, Paper Joint treatment should be done before work commencement.
- Check and ensure all conduits / outlets fixed properly.
9.17 Work Procedure:
9.17.1 Surface Preparation.
- Surface to be treated must be workable dry and free from oil grease and foreign particles.
- All laitance, loose and foreign particles shall be removed by mechanical scrubbing
(grinding) only.
- All honey-comb, highly undulated, damaged surfaces and cracks should be repaired.
- Injection grouting at all major honeycombed portions and construction joints shall be
carried out, if necessary, after physical observation.
- Area shall be cured for at least 3 days by ponding, to test for leakages and to serve water
hungry concrete surface.
- In case of major leakage, gravity grouting or pressure grouting shall be resorted to stop
leakages. Grouting to be done as per manufacturers specification.
- Levels of water-proofing shall be clearly marked on the walls with slope towards outlet, as
specified in drawing or minimum 1:100 otherwise.
- Check for any steel or cut end of rebar is exposed at top of slab. If exposed steel is seen
that concrete is to be chiseled off to the depth of 25mm around exposed steel. Steel to be
cut with cutter or grinder 25mm below slab top surface. Slab to be restored with polymer
mortar prepared as per manufacturers specification and cure for 3 days.
- Coving shall be done at the all corners by Ready Mix Repairing mortar and shall be
grouted properly before application of Water-roofing.
9.17.2 Procedure:

- Application of chemical waterproofing coat (crystalline / elastomeric / polymer / PU etc.)


can be done, entire inner structure before base coat.

Page 65 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- For Cementitious/crystalline chemical coat: Prepare the chemical mix by slowly pouring
the powder component in liquid polymer component or as per manufacturer’s
recommendation. Mixing shall be done by using a suitable mechanical impeller only.
Achieve a brush-able paste. Only paste which can be consumed in half hour shall be
made.
- Apply first coat of paste by brush / roller on the surface evenly. After application it should
be left for 4 to 5 hours for drying & setting or re-coat-able time recommended by
manufacturer.
- Prepare more mix as above and apply second coat after drying of first coat. Preferably
apply the second coat in right angle direction to first coat. Allow the second coat to dry
for 4 to 5 hours.

REF NO PROCEDURE TITLE REV. NO PAGE NO


WATER-PROOFING WORK – PLANTER, TERRACE, LANDSCAPE, HARDSCAPE,
MS/12 00 64-67
SWIMMING POOL
- Application of chemical waterproofing coat shall be extended above 200 mm of top level
of soil filling.
- Ensure that material has been consumed as per specified quantities mentioned in
technical data sheets for the concerned material use.
- If suggested, Post application moist curing shall be done for 3 days.
- Laying of 300 GSM Non-oven geotextile protection plus separation layer for horizontal
surface.
- Base coat using cement mortar in proportion 1:4 or Screed as specified by QA
Department with approved waterproofing compound shall be applied over top of base
slab. Maximum thickness of base coat shall be 25 mm at upper end of slope.
- Proper slope shall be given to base coat as per drawing towards drain spout and drain
spout to be fitted simultaneously with the base coat, as an additional precaution to take
care of seepage, if any. Base coat shall also be applied to the sides of the wall up to one
meter or as specified above the finished floor level (F.F.L) of the adjacent floor.
- Drain pipe mouth shall be fitted with PVC grating or filter media form inside and chicken
mesh / wire mesh from outside.
- Curing of base coat shall be done by ponding for 3 days and checked against leakage.
Leakage, if observed, shall be rendered with reapplication of base coat to ensure no
leakage.
- Floor traps and other plumbing lines shall be installed in brick masonry after application
of base coat.
- Slope of 1:100 or as specified shall be provided for piping and water proofing. Floor trap
shall be fixed with respect to finished floor level (F.F.L) of the slab.
- Rendering of holes shall be done using compatible bonding agents; SBR based expansive
grouts, waterproofing compounds.
- Application of brick bat coba / foam concrete / light weight concrete shall be started,
once plumbing lines are satisfactory pressure tested.

Page 66 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Bricks selected for using as brick bat coba shall be either full brick or 3/4th brick made out
of one complete brick by breaking into required size, using mallets.
- Brick bat shall not be stored in the form of a heap at one place and soaked thoroughly for
about 45 minutes prior to their placing. For AAC / Light Weight block shall be dipped in
water before placing.
- Use of plasticizer in mortars is recommended to increase workability as per
manufacturer’s specifications. Mortar mixed shall be used within 1 Hour of preparation.
- Presoaked brick-bats shall then be laid in straight / radial, by inserting brickbats to a
depth of about 15mm by light tamping with the help of mallets. Thickness between
adjacent layers of brickbats shall not exceed 25mm.
- Application of brick-bats shall proceed from one corner and shall be laid in radial pattern /
straight pattern to drain of any water which has seeped through. Level Pads for the same
shall be given by Site Engineer, considering into account adequate slope.
REF NO PROCEDURE TITLE REV. NO PAGE NO
WATER-PROOFING WORK – PLANTER, TERRACE, LANDSCAPE, HARDSCAPE,
MS/12 00 64-67
SWIMMING POOL
- The brickbat Layer shall then be cured for minimum 3 days by ponding.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound or Screed till top of brick-
bats.
- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- For PU Water-proofing application, sand broadcasting to be done immediate after final
coating of compound to give mechanical key for plaster work.
- Plaster work shall be done by cement sand mortar in the proportion 1:3 with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.

Page 67 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/13 WATER-PROOFING WORK - UGT, STP, OHWT 00 68-70

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Fiber Mesh
 Water-proofing Compound

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 1542 - 1992 - Sand for Plaster
- IS 1489 - 1991 - PPC cement
- IS 1077 - 1992 – Common Burnt Clay Building Bricks
- IS 2645 - 2003 - Specification for Integral Waterproofing Compounds for Cement
Mortar and Concrete Specification
- Manufacturer Technical Specifications

3. Tools and Equipment:


Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Bucket, Measuring Jar, Float,Wire Brush, Grinder, Chisel, Hammer, Blower, Pressure Grouting,
Measuring Tape, Spirit Level, Plumb Bob, Weigh Balance, etc.
4. Work Procedure:
If method statement submitted by the Water-Proofing contractor to Dosti Approval prior to start
of the work, then Approved contractor method statement to be implement at site.
9.18 Pre-Check:

Page 68 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Prior to start any activity on site, the consulting engineer must be notifying.
- RCC and Civil work complete in all respect. No repairing work pending before handed-
over to Water-proofing agency.
- Clearance from MEP (Services) department.
- Ensure all material for waterproofing available.
- Highly undulated surface and major repair to be complete prior.
9.19 Work Procedure:
9.19.1 Surface Preparation:
- Surface to be treated must be workable dry and free from oil grease and foreign particles.
- All laitance, loose and foreign particles shall be removed by mechanical scrubbing only.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/13 WATER-PROOFING WORK - UGT, STP, OHWT 00 68-70

- All honey comb, highly undulated, damaged surfaces and cracks should be repaired by
using approved repairing material
- Injection grouting at all major honeycombed portions / construction joints shall be carried
out, if necessary, after physical observation
- All the shuttering wall tie holes shall be grouted with non-shrink grout.
- Area shall be cured for at least 3 days by ponding, to test for leakages and to serve water
hungry concrete surface. Ensure 100 % Water to be stored for pre-ponding.
- In case of major leakage, gravity grouting or pressure grouting shall be resorted to stop
leakages. Grouting to be done as per manufacturers specification.
- Levels of water-proofing shall be clearly marked on the walls with slope towards outlet, as
specified in drawing or minimum 1:100 otherwise.
- Check for any steel or cut end of rebar is exposed at top of slab. If exposed steel is seen
that concrete is to be chiseled off to the depth of 25mm around exposed steel. Steel to be
cut with cutter or grinder 25mm below slab top surface. Slab to be restored with polymer
mortar prepared as per manufacturers specification and cure for 3 days.
- Coving shall be done at the all corners by Ready Mix Repairing mortar and shall be
grouted properly before application of Water-roofing.
9.19.2 Procedure:

- Install coving at horizontal and vertical corners using polymer modified mortar or using
CM 1:4 with admixed at a dosage of manufacturer recommendation per bag of 50 kg
cement at required thickness, finishing in half round or fillet in shape.
- Application of chemical waterproofing coat (crystalline / elastomeric / polymer / PU etc.)
can be done, entire inner structure before base coat. Prefer food grade coating.
- Base coat using cement mortar in proportion 1:4 or as specified by QA Department with
approved waterproofing compound shall be applied over top of base slab. Maximum
thickness of base coat shall be 25 mm at upper end of slope.

Page 69 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Proper slope shall be given to base coat as per drawing towards drain spout and drain
spout to be fitted simultaneously with the base coat, as an additional precaution to take
care of seepage, if any. Base coat shall also be applied to the sides of the wall up to one
meter or as specified above the finished floor level (F.F.L) of the adjacent floor.
- Drain pipe mouth shall be fitted with PVC grating or filter media form inside and chicken
mesh / wire mesh from outside.
- Curing of base coat shall be done by ponding for 3 days and checked against leakage.
Leakage, if observed, shall be rendered with reapplication of base coat to ensure no
leakage.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound.
-
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/13 WATER-PROOFING WORK - UGT, STP, OHWT 00 68-70

- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- For PU Water-proofing application, sand broadcasting to be done immediate after final
coating of compound to give mechanical key for plaster work.
- For UGT/OWHT food grade paint or tiling should be applied from internal side as top layer
of a system.
- For STP coal tar epoxy coating shall be done from internal sides of the walls.
- Soffits of all the structures shall be treated by using appropriate waterproofing system.
- Top of the slab shall be make waterproofed by application of chemical waterproofing coat
(crystalline / elastomeric / polymer / PU etc.) .Protection screed shall be provided to the
treatment.
- Terminate the edge of the membranes as per manufacturer technical specification.
- Plaster work shall be done by cement sand mortar in the proportion 1:4with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
- Approved protection coat to be apply after completion of Water-proofing work.
- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.

Page 70 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/14 EXPANSION JOINT TREATMENT WORK 00 71-72

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Expansion Joint material / fillers

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications

3. Tools and Equipment:


Scrubber, Material Applicator Gun, Water Jet
4. PROCEDURE:
- The gap of expansion joints is never left open. It is filled with a compressible material so
as to make it water tight. The following materials are required to render the expansion
joint watertight.
 Joint Filler
 Sealing Compound
 Water Bars
 Physical Sheets/ Plates
- Prior to starting preparation, close the area to be prepared to all traffic and other trades.
- The preferred method of substrate (plastered surface) preparation is; scrapping, sanding,
and light surface grinding.

Page 71 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- If any part of the surface is contaminated by oil, grease, or fuel, the contamination shall
be removed before other forms of preparation are undertaken.
- At free edges such as doorways the emulsion shall be terminated properly.
- Prepare the surface using the chosen method, removing all laitance and weak or friable
matters (i.e. Tarfelt etc.). The finished surface should have a profile of medium to fine
sandpaper.
- Surface defects exposed during preparation such as shrinkage cracks, blowholes, minor
honeycombs, and minor damages, etc. shall be treated properly by using suitable surface
filler, preferably, cementations materials
- When it is known prior to starting work on the surface that repairs are required, the
repairs should be executed before general preparation is undertaken.
- When surface preparation is complete, clean the surface with dry clean cloth to remove
all dust and debris if any.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/14 EXPANSION JOINT TREATMENT WORK 00 71-72

- Protect areas such as windows, doors, ceilings, etc. that may be splashed when the
emulsion is being applied.
- Treat expansion joint as suggested by consultant or approved method submitted by
manufacturer / vendor.
- The joints in the wall are not left exposed and to be covered with covering sheets which
may be of aluminum, hard board, AC sheet or timber plank.
- Expansion joint in the roof shall invariably be provided with joint filler and water bar.
- Roofing Slab:
- The gap of the joint should be sealed with a water bar and sealing compound. In order to
prevent cracks in the masonry above or below the expansion joint R.C.C or plain concrete
bed blocks should be provided in the masonry below the expansion joint in the slab.

Page 72 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/15 MASONRY WORK 00 73-75
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Brick / AAC / Solid / Hollow Concrete Blocks
 Bond-it / Bonding Agent or Chemical
 Ready Mix Block Jointing Mortar
 Reinforcement Steel
 Concrete
 Hold Fast / Mechanical Holders / Fixtures
 Door and Window Fastener

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 3495 – 1992-Code of Brick Testing
- IS 2212 - 1991 - Code of Practice for Brickwork
- IS 1077 – 1992-Code for specification Common Burn clay Building Bricks
- IS 2185 - 1984 - Concrete Masonry Units
- IS 6041 – 1985 - Construction of Autoclaved Cellular Concrete Block Masonry
- IS6042 – 1969 - Code of Practice for Block Testing &Specifications respectively.
- Manufacturer Technical Specifications

3. Tools and Equipment:

Page 73 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Spirit Level,
Mud Pan, Mallet (Wooden / Rubber), shuttering plywood, drill machine, block cutter, Measuring
Jar, Brush, etc.
4. Work Procedure:
9.20 Pre-Check:
- Ensure the availability of detailed layout of the building showing room dimensions,
thickness of walls at various locations in the building.
- Ensure RCC work complete respect to all activities, ensure curing period is completed.
- Ensure that Details of openings (with sizes) to be provided in the walls for doors,
windows, ventilators, exhaust fan openings & other openings, details of door, window,
ventilator frames.
- Clearance from MEP department / vendor to be taken before block work commences.
- Ensure approved Material available.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/15 MASONRY WORK 00 73-75


- Chipped loose concrete & loose material, surface washed out, Hacking / applying bonding
agent to RCC columns / & beam bottom where masonry is butting.
- If required, Curing compound removed from RCC member.
- If Required, DPC shall be provided.
9.21 Work Procedure for Masonry:
- The area/floor proposed to start the masonry work activity should be cleaned from any
loose concrete, foreign bodies, debris, old mortar, dust, etc.
- Before starting first layer, the level of slab to be checked and leveled with conventional
mortar / concrete.
- Mark the masonry and mullions layout as per drawing.
- Right Angle, dimension, plumb, door and window opening to be checked respect to long
wall. Upon approval of layout, masonry work shall be started.
- First layer shall be constructed with cement mortar of with proportion 1:6 or as specified
in approved specification.
- Bricks shall be fully immersed in water for minimum 04 hrs before work commencement.
- From second layer the AAC / Light Weight block work shall be constructed by using ready
mix mortar 2 to 4mm thick for AAC / Light Weight Blocks. For Brick / solid & hollow
concrete block work Conventional mortar can be used as per specifications.
- Tooting for masonry work / Coping, Sill level and arrangement of lintel to be checked as
per drawing.
- Vertical joints of masonry should be staggered and thickness of joints shall be as per
specifications.
- For AAC / Light Weight Blocks: At every 5 layer GI flat (Hold Fast) will be fixed with 8mm
anchor bolts or concrete band shall be provided as per approved drawings. Solid blocks
shall be used at the location of the Hold fast.
- For Bricks / Solid & Hollow Block: At every 1.2mtr. Concrete band of grade M20 with
minimum 04 nos of 8 mm Steel bars provided as per approved drawings.

Page 74 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- At door frame head level concrete band of grade M20 with minimum 04 nos of 8 mm
Steel bars to casted followed by Minimum 3 days curing.
- Masonry work shall be constructed up to 25mm below slab level, and GI flat (Hold Fast)
fixed to slab and vertical joint of block work at every 2.0 m c/c.
- Top one layer will be left and will be filled with cement mortar mixed with non-shrink
Compound later after keen confirmation of deflection details. To provide the mechanical
key & arrest cracks at the top of the wall joint, 12mm size aggregate packing shall be done
over non shrink mortar.
- Opening for Door, Windows, MEP, HVAC shall be checked and verified during the
execution.
- If required, raking / brooming shall be done immediately after completion of work.
- Check verticality and evenness of block work for every layer. The walls shall be taken up
truly in plumb of true to the required batter where specified. All courses shall be laid truly
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/15 MASONRY WORK 00 73-75
horizontal and all vertical joints shall be truly vertical. Vertical joints in alternate course
shall come directly over the other. Care shall be taken to keep the perpends properly
aligned within following permissible tolerances:
 Deviation from vertical within a storey shall not exceed 6mm per 3m height.
 Deviation from position shown on plan of any brickwork shall not exceed 10
mm.
 A set of tools comprising of wooden straight edge, masonic spirit levels,
square, 1m rule line and plumb shall be kept on site of work for every three
masons for proper check during the progress of work.
- Joints shall be filled racked suitable by raking tools. The face of brickwork shall be finished
flush unless otherwise specified. The faces of brickwork shall be cleaned with wire brush
so as to remove any splashes of mortar during the course of raising the brickwork.
- As far as possible services should be planned with the help of vertical chases. Horizontal
chases should be avoided. The depth of vertical chases and horizontal chases shall not
exceed one third and one sixth of the thickness of masonry respectively. Vertical chases
should not be closer than 2m in any stretch of a wall. These shall be kept away from
bearings of beams and lintels. No chase shall be permitted in half brick load bearing walls.
- The brickwork shall be constantly kept moist on all faces for a minimum period of 7 days.
Brickwork done during the day shall be suitably marked indicating the date on which the
work is done so as to keep a watch on curing period. The brickwork shall be protected in
high temperatures and humid conditions from excessive evaporation of water from
mortar and grout.
- Scaffolding shall be provided to allow easy approach to every part of work. The
Scaffolding shall be self-supported double scaffolding having minimum 400 wide work
platforms.

Page 75 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Scaffolding shall be strong to withstand all dead, live and impact loads, which are likely to
come on them. No support shall be taken from block work masonry wall for erecting the
scaffolding.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/16 SAND MORTAR PLASTER WORK 00 76-78

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Cement (OPC / PPC)
 Sand (River / Crushed / Silpoze)
 Fiber / Metal Mesh
 Bond-it / Hack Aid Plast / Approved Bonding Agent
 Ready Mix Mortar

2. Technical Specifications and Applicable Standards:


Cement Sand Mortar Plaster Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
- IS 1542:1992 - Sand for Plaster
- IS 4031:1988 - Code for Cement Testing (Physical)
- IS 4032:1985 - Code for Cement Testing (Chemical)
- IS 12269:1987 - OPC cement
- IS 1489:1991-PPC cement
- Material Manufacturer Technical Specifications

3. Tools and Equipment:


Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Hawk, Mud
Pan, Sand Paper, Joint Knife, Step Ladder, Bucket, Measuring Jar, Float and Straight Edge, etc.
4. Work Procedure:

Page 76 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

9.22 Pre-Check:
- Ensure the availability of detailed layout of the building showing room dimensions,
thickness of walls at various locations in the building.
- Ensure that Details of openings (with sizes) to be provided in the walls for doors,
windows, ventilators, exhaust fan openings & other openings, details of door, window,
ventilator frames.
- Visible inspection of masonry shall be done to check no cracks in block work/Bricks and
structural repairing should be done prior to work start such as tie-rode holes to be
plugged, removing nails, ply pieces from RCC, etc.
- Curing period of masonry work should be completed.
- Curing compound removed from RCC member.

9.23 Work Procedure for Plaster:-


- Take clearance from the MEP services before start of the work.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/16 SAND MORTAR PLASTER WORK 00 76-78
- Any unavoidable projections in masonry and concrete surfaces shall be chiseled back.
- Provide fiber mesh of 150mm width at junctions of Masonry and RCC and any other
chased area.
- Fix all conduits, chases with chicken wire mesh 150mm wide
- Ensure door and window frames shall be fixed in correct line, level, plumb, and diagonal
and covered properly before Plaster Work commencement.
- Clean and dampen the surface before work start.
- For external plaster, the plastering operations shall be started from the top floor and
carried downwards.
- Bonding adhesive shall be applied for RCC surface as per technical specification or Hack
any exposed faces of concrete which form substrate for plastering.
- Fix the mortar gauges / pads with line level and thickness as per technical specifications.
- Mixing of mortar will be done on clean sheet/Tray by measuring the cement and sand to
the ratio as per given specification. For Ready Mix Mortar follow Manufacturer technical
specifications.
- Carry out the plastering as per the drawing and technical specification by ensuring the
following:
o Plaster thickness.-12mm thick (Internal wall) & Plaster thickness.- 18-20 mm thick
(External wall) in two coats.
o Plaster to ceilings, soffits or stairs flight slabs and similar locations, where called
for, shall be 6mm thick with CM 1:3 (1 part of cement and 3 parts of sand)
o Cement Mortar ratio-1:4/1:6, mixing shall be as per specifications.
o Approved Water proofing chemicals to be added in 2nd coat of external plaster.
o Check for opening sizes: width, plumb for jambs and level for head and sill, line
level and plumb.
- Plaster shall be leveled and lined by aluminum hollow section, 2-3 m long.

Page 77 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Offsets of door, window, beams, columns, jams, soffits shall be uniform in length, level,
right-angle.
- Finishing of plaster shall be carried out with wooden float (randhas) or trowelled smooth
with sheet metal trowels as specified. Care shall be taken to avoid excessive trowelling
and overworking of the wooden float.
- Making the grooves at the junction of concrete and masonry and as per the architectural
drawing.
- Always stop a day's work at corner
- Final surface finish(scratch, sand face) should be as project / approved technical
specifications.
- One meter overlap between 1st coat and 2nd coat to be provide at joint of plaster.
- Drip course wherever indicated in the drawings shall be provided at the time of Plastering
to prevent travelling of water drops from the projections. Unless otherwise, Specified,
projected strip form drip course shall be provided.
- Plaster at the top of the wall shall be done in one time with inward slope.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/16 SAND MORTAR PLASTER WORK 00 76-78
- Plaster shall be cut to correct horizontal or vertical line at the end of the day or if work
requires to be suspended for any reason. Joint cut to be done at corner of walls.
- Cut the plaster at skirting level and checked for uneven or undulation in wall surface with
line Dori and aluminium Patti.
- Clean the cement mortar immediately after the completion of work.
- Mortar cube shall be casted for compressive strength. (70.6*70.6*70.6mm).
- Mention the date at the end of the day.
- Curing of all types of plaster shall be started 24 Hrs. after finishing the plaster. The plaster
shall be kept wet for a period of 7 days. Before second coat ensure minimum 3days
during for 1st coat plaster.

Page 78 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/17 GYPSUM PLASTER WORK 00 79-81

1. Materials:

All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Bond it or approved bonding agent
 Gypsum(Type-Hemihydrate/Plaster of Paris/Anhydrous/Keene’s plaster)
 Glass Fiber Mesh / Metal Mesh.
 Sand paper (80-220no.)

2. Technical Specifications and Applicable Standards:


Gypsum Plaster Work shall be carried out as per following specifications / standards / code and /
or others as applicable.
IS 2542 – Method of Test for Gypsum Plaster
IS 2547 - Gypsum Building Plaster
IS 4082 – Recommendation of Stacking and Storage

3. Tools and Equipment:


Electric Peddle Mixer, Bucket, Aluminum straight edge, Plumb bob, Right-Angle, Trowel,
Measuring Jar & Brush etc.

4. Work Procedure:
9.24 Pre-Check:
- Source / brand of Gypsum shall be confirmed and approved.
- Source / brand of bonding agent on RCC surface shall be confirmed and approved.

Page 79 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Detailed layout of the flat showing room dimension shall be available.


- Openings shall be provided as per drawing.
- Clearance from MEP (Services) department shall be taken before wall gypsum work
commences.
- Visible inspection of masonry shall be done to check no cracks in block work/Bricks/RCC
wall.
- Any unavoidable projections in masonry and concrete surfaces shall be rectified.
- All the nails, binding wires, concrete projections & wooden pieces shall be removed from
concrete surface & brick masonry.
- All the dust, oil spots & green algae if any shall be cleaned from concrete & brick masonry
surface with the help of wire brush.
- Masonry wall shall be dry 100% or SSD in case of brick wall and precaution shall be taken
for water leakages on wall before commencing gypsum work.
- If Required, Curing compound to be removed from RCC.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/17 GYPSUM PLASTER WORK 00 79-81


9.25 Work Procedure for Gypsum Plaster:-
- Bonding agents shall be applied as per instructions of manufacturer.
- Bonding adhesive (Bond it) or other approved material shall be applied for RCC surface
24hrs before fixing Gypsum Pad (Dhada) and Punning. Ensure the consistency in
application of bonding adhesive. Bonding adhesive shall be applied uniformly on the
surface.
- Provide glass fiber mesh of 150mm width at the junction of block masonry/Brick masonry
and RCC, 75mm on masonry and 75mm on RCC, also above concealed electrical conduit.
- When plastering on vertical surfaces, to ensure even thickness and a true surface, plaster
is done to serve as gauges (Bull Marks), from the adjacent surface of these gauged areas
shall be truly in plane of finished plaster surface .Fixing of Gypsum bull mark (Dhada) with
line, level, right angle and thickness as per technical specifications, spacing @1.5 to 2.0m
c/c distance. Level pads and right angle of all rooms shall be respect to the lobby.
- If Suggested, Angle/ corner bead (Corner Protection) to be fixed at the corner of Masonry
except door and window opening.
- Gypsum plaster shall be start from top to vertically downward.
- If thickness of plaster increases above 12mm and up to 25mm then base coat of cement
plaster to be done with rough finish in cement mortar mix proportion 1:4.
- Minimum 3 days curing to be done after base coat / rendered plaster.
- Mixing of Gypsum as per Technical Data Sheet. Mix One Coat Gypsum plaster to water
(not vice versa) to have workable consistency, use a mixing rod for thorough mixing and
avoid lumps and unmixed residues.
- Water to plaster ratio (As per Technical Data Sheet) should be maintained as to have good
cohesive workable mix.

Page 80 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Mix Gypsum plasters as much as required depending upon the immediate scope of work,
partially used material to be kept well secured in dry place. Consume within pot life.
- Once the mix has begun to set, additional water is not to be added, as performance
properties of plaster will get altered, thus affecting workability, cohesiveness, adhesion
properties and strength.
- Punning of gypsum plaster to be carried out from one end of wall and get the wall
complete.
- Gypsum shall be applied in a uniform surface slightly more than the specified thickness
and brought to a true surface, by working an aluminum straight edge reaching across the
gauges, with small upward and sideways movement at a time.
- Avoid using a wet brush on to the finished surface, as that would leave permanent brush
marks and thus spoil the surface.
-

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/17 GYPSUM PLASTER WORK 00 79-81


- A single coat should not exceed 13mm in thickness, if at all thickness required is more
than 13 mm, plaster is to be applied in multiple coats.(As per Product Specifications).
- Check Gypsum work for alignment and plumb during work is in progress.
- Cut the gypsum plaster at skirting level in proper line and level as per site instruction.
- Check for opening sizes, plumb for jambs, level for head and sill etc.
- Plaster shall be cut to correct horizontal or vertical line at the end of the day or if work
requires to be suspended for any reason.
- Clean the plaster material fallen on floor immediately after completion of day work.
- After complete drying usually 72 hrs. (Depending on the thickness and weather
conditions), the plain smooth leveled surface is ready for painting.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly as per IS 4082 on proper platform at daily working area
also.

Page 81 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/18 TILE / MARBLE AND CHINA CHIPS FLOORING WORK 00 82-84

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Marble / Tile / Pieces of the glazed tiles i.e. china chips
 Cement (PPC)
 White Cement
 Sand (River / Crushed / Silpoze)
 Joint / Crack filler
 Bubble Guard Sheet
 Ebro tape 3inch thick.

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS1130:1969-Specification of Marble (Block, Tiles, Slabs)
- IS1478:1992 - Clay Flooring Tiles
- IS13630 (1to15):2006- Ceramic Tiles Method of Sampling & Testing
- 15622:2006 - Pressed Ceramic Tiles
- 13712:2006-Code for Ceramic Tiles Definition &Classification
- Manufacturer Technical Specifications

3. Tools and Equipment:

Page 82 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Spirit Level, Right angle, Mallet ( Wooden / Rubber),Thickness Gauge, Float and Straight Edge,
etc.
4. Work Procedure
4.1. Tile / Marble Flooring:
4.1.1. Pre-Check:-
- Ensure the availability of detailed layout of the building showing room dimensions,
marble floor pattern at various locations in the building.
- Area should be cleaned from loose particles and other debris.
- Cracks if any on slab should be grouted as per approved methodology.
- Waterproofing work completed in all respect, slopes checked. If Required DPC provided at
places.
- Partition Wall back coat plaster completed.
- Clearance taken from MEP and Civil department.
- RCC repairing shall be done prior as per approved methodology.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/18 TILE / MARBLE AND CHINA CHIPS FLOORING WORK 00 82-84

4.1.2. Work Procedure for Flooring:-


- Level marking on wall and level pad on the floor shall be as per approved FFL.
- If bedding is more as per Site condition, then PCC to be done as per specification Mix
(1:3:6) and followed by curing 3days minimum.
- Cement sand mortar mix for bedding material as per ratio 1:6 or specified to be laid on
floor as per level pad.
- Marble to be cut as per approved floor pattern and dimension.
- Defective and damaged Marble/Tiles to be removed and placed at one area.
- Marble/Tiles fixing to be start as per start point mentioned in drawing, on bedding mortar
with cement slurry as per 4.5kg/sq.mt / specified.
- Fixing of marble/tiles skirting with cement to correct line and level.
- For Ceramic Tiles: Soaking to be done 2hrs prior before the application.
- Bedding mortar laying shall not more than 5-6 square meter at a time.
- In wet areas, slope of 1:120 should be maintained to drain water.
- Marking of floor drains on marble/tiles checked for cutting of floor trap.
- Cracks on marble to be cleaned and filled with approved crack filler & for tiles replaced
with new tiles.
- The surface of the flooring during laying shall be frequently checked with a straight edge
about 2 mtr. long, so as to obtain a true surface with the required slope.
- Where full size tiles cannot be fixed these shall be cut (sawn) to the required size, and
their edge rubbed smooth to ensure straight and true joints.
- Tiles which are fixed in the floor adjoining the wall shall enter not less than 10 mm under
the plaster, skirting or dado.

Page 83 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Grouting of marble joints as per approved material and specification.


- The finished floor shall not sound hollow when tapped with a wooden mallet.
- No loose tiles shall be accepted. Joints cannot be too wide and too narrow, and shall be in
straight lines or as per the layout drawing. Joints shall be parallel to wall and orthogonal.
- No loose stone shall be accepted.
- Joints shall not be too wide or too narrow and shall be in straight line. Joints shall be
parallel to the rectangular wall.
- Cleaning, Curing and floor protection with bubble guard sheet fixing with Ebro 3inch tape.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area also.
- After work completion hollowness to be checked, no void sound when tapped.
- Finished work to be barricade and movement restricted for 24 hrs.
4.1.3. Polishing:
4.1.3.1. Pre-Check:-
- Ensure marble flooring work is completed in all respect.
- Cracks and joints are filled properly with approved material.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/18 TILE / MARBLE AND CHINA CHIPS FLOORING WORK 00 82-84


- Marble joints are cleaned thoroughly in all respect.
- All other works are completed except final painting.
- Doors are fixed and completed with locking arrangements.
4.1.3.2. Work procedure for polishing:
- Marble flooring is washed completely with water.
- Marble polishing is done with machine of stone no 0 to 5.
- Again joints and cracks are filled if damages found while polishing.
- Pre final mirror polishing is done with hand machine of stone no 5x.
- Final mirror polishing and buffing is done at the time of handover or as per instruction of
site engineer.
- If any tile is disturbed or damaged, it shall be refitted or replaced, properly jointed and
polished.
- Marble protection is done as per instruction of site engineer in charge / specification.
4.2. China Chips Flooring:
- Ensure Water-proofing work completed and handed over for flooring work.
- Cement sand mortar mix for bedding material as per ratio 1:8 or specified to be laid on
floor as per level pad.
- Bedding checked for level and slope.
- If design pattern available, then mark on bedding before start of work and get approval
from site Engineer.
- China Chips fixing to be start as per start point mentioned in drawing, on bedding mortar
with cement slurry as per 4.5kg/sq.mt / specified.

Page 84 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Ensure joints between china chips should not exceed 3 to 4 mm.


- To achieve uniform surface, china chips to be pressed / hammered with wooden / rubber
mallet.
- Curing to be monitored for minimum 3 days by ponding method.
- For color joints, add color pigments in white cement during fixing / joints filling of china
chips.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/19 MARBLE & TILE CLADDING (DADO) WORK 00 85-86

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Marble (Natural / Artificial) / Tile (Vitrified / Ceramic)
- Cement (PPC)
- White Cement
- Sand (River / Crushed / Silpoze / Quartz)
- Joint / Crack filler
- Adhesive
- Bubble Guard Sheet
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS1130:1969 -Specification of Marble (Block, Tiles, Slabs)
- IS13630 (1to15):2006 -Ceramic Tiles Method of Sampling & Testing
- 15622:2006 -Pressed Ceramic Tiles
- 13712:2006 -Code for Ceramic Tiles Definition &Classification
- Manufacturer Technical Specifications

3. Tools and Equipment:

Page 85 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Spirit Level, Right angle, Mallet ( Wooden / Rubber),Thickness Gauge, Float and Straight Edge,
Line thread , Plumb, etc.

4. Work Procedure
4.1. Pre-check:
- Ensure availability of detailed layout of the flat showing all marble pattern.
- Area should be cleaned from loose particles and other debris.
- Wall back coat plaster complete as per requirement.
- Water proofing work completed in all aspect (Applicable in wet areas).
- Clearance taken from MEP department.
- Tile/marble color, shade, make as per approved sample.
4.2. Work Methodology – Application / Fixing:-
- Level marking on wall and level pad on the wall shall be as per approved FFL.
- For Marble: To be cut as per approved pattern and dimension (Dry Lay Method).
- For Tiles: Tiles to be selected as per approved pattern, dimension, make & colour.
- Defective and damaged Tiles /Marble to be removed and placed at one area.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/19 MARBLE & TILE CLADDING (DADO) WORK 00 85-86

- Provision for MEP points coming on wall to be made before fixing of Marble/Tiles.
- For Ceramic Tiles: Soaking to be done 2hrs prior before the application / fixing.
- For Ready-mix Mortar / Adhesive: Marble/Tile fixing to be done using 6mm to 10mm
thick or as specified approved tile adhesive to correct line and level. Proportioning as per
manufacturer specifications.
- For Conventional Mortar: Marble/Tile fixing to be done using 6mm to 10mm thick
conventional mortar in correct line and level. Proportioning 1:2(1water:2Cement) or as
specified.
- Additional plaster coat (1Cement:4Sand or as specified) should be applied if mortar
thickness exceeds 10-15mm.
- Approved grooved pattern to be followed at right angle joints.
- Laying pattern/starting point shall be as per latest architectural drawing.
- Joints are well cleaned and grouted with white cement and matching colour pigments as
per approved make.
- Cracks on marble to be cleaned and filled with approved crack filler. For tiles it should be
replace with a new one.
- No hollow sound when tapped.
- Cleaning, Curing and wall protection as per specification / BOQ/work order.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area.
- Finished work shall be barricaded and movement restricted.

Page 86 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

4.3. Work Methodology – Polishing :-


- Ensure marble dado work is completed in all respect.
- Cracks and joints are filled properly with approved material.
- Marble joints are cleaned thoroughly in all respect.
- All other works are completed except final painting.
- Doors are fixed and completed with locking arrangements.
- Dado marble wall is washed completely with water.
- Marble polishing shall be done with hand machine of stone No 0 to 5 or as specified.
- Again joints and cracks are filled if damages while polishing.
- Pre final mirror polishing is done with hand machine of stone No 5x or as specified.
- Final mirror polishing and buffing is done at the time of handover or as per instruction of
site engineer.
- Marble dado Protection is done as per instruction of Site Engineer / specification.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/20 KITCHEN PLATFORM WORK 00 87-88

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Marble/Granite
- Kadappa
- Grey Cement Grade PPC / White Cement
- River Sand/Crushed Sand.
- Joint filler.(Approved Make)
- Tile Adhesive. (Approved make)
- Crack filler. (Approved make)
- Bubble sheet / Low Grade Gypsum
- Construction Water
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- Manufacturer Technical Specification
- IS 1130 – 1969 - Code of practice
3. Tools and Equipment:

Page 87 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Clean tray, Spirit level, Aluminum Patti, Drum, Right-angle, Trowel, Rubber Hammer, Parma,
mallet, Line thread, Plum bob, Thickness gauge, right angle etc.
4. Work Procedure:
4.1. Pre-Check:
- Ensure availability of detailed layout of the flat showing wall marble pattern.
- Area should be cleaned from loose particles and other debris.
- If Required, Wall back coat plaster complete as per requirement Kitchen dado.
- Water proofing work completed in all aspect (Applicable in wet areas) near sink & outlets.
- Clearance taken from MEP department. All the concealed MEP works in the walls of the
kitchen platform shall be completed before start of the kitchen platform work.
4.2. Work procedure:
- Clean the area prior to start of the work
- The position & marking of vertical & horizontal supports should be marked on wall as per
drawing. Level marking on wall and level pad on the wall as per approved FFL.
- Fix vertical kadappa /Marble / Granite on the floor with proper line and level.
- Minimum 15 to 20 mm deep recess shall be in wall up to desired height. Fixing of sub
base of platform on the vertical support should be in line & level.
- Adequate curing should be carried out prior to fixing of the horizontal kadappa element
with proper anchoring as per approved drawing.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/20 KITCHEN PLATFORM WORK 00 87-88


- Fix granite top above the kadappa with cement mortar bed 1:1 or with approved
material. Maintain proper slope in correct direction towards the sink.
- Ensure that the nahani trap should be fixed at sink bottom & sealing of the hole of outlet
in wall with rich cement mortar.
- Fascia should be fix with approved epoxy resin work should include drilling of holes &
making of notches, grouting with epoxy & cement finishing As per Approved detail
drawing by architect.
- Granite / Marble (Natural / Composite) should be cut to receive stainless steel kitchen
sink with edge polish as per approved by the architects.
- The edges of the Granite / Marble top should be polished & groove should be maintained
as per Architects Reqts.
- A slot should be left for gas pipe line in kitchen platform.
- All joints should be filled with joint filler.
- Any MEP points coming on wall to be cut on before fixing of marble/Tiles/Granite.
- For Marble/granite: To be cut as per approved pattern and dimension.
- Top of platform should be covered with POP or approved protection sheet.
- Cleaning, Curing and wall protection as per specification / BOQ/work order.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area.

Marble Platform Polishing

Page 88 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Pre-Check:
- Ensure Granite/marble work is completed in all respect.
- Cracks and joints are filled properly with approved material.
- Marble/Granite joints are cleaned thoroughly in all respect.
- All other works are completed except final painting.
Work procedure:
- Kitchen Dado tiles wall is washed completely with water.
- Marble polishing is done with hand machine of stone no 0 to 5.
- Again joints and cracks are filled if damages while polishing.
- Pre final mirror polishing is done with hand machine of stone no 5x.
- Final mirror polishing and buffing is done at the time of handover or as per instruction of
site engineer.
- Marble Protection is done as per instruction of site engineer / specification.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/21 DOOR AND WINDOW WORK 00 89-91

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Door / Window Frames
 Door / Window Shutter
 Anchor and Fasteners
 Hinges
 Foam / Fillers / Sealants
 Window Track / Channels

2. Technical Specifications and Applicable Standards:


Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 287 - Indian Standard Recommendations for permissible moisture content for timber
used for different purposes.
- IS 303 - Indian Standard Specification for plywood for general purposes.
- IS 1003 - Indian Standard Specification for Timber panelled and glazed shutters - part 1 -
door shutters, Part 2 - windows and ventilator shutters.

Page 89 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- IS 1141 - Seasoning of Timber – Code of Practice


- IS 1285 - Wrought aluminum and aluminum alloy extruded round tube and hollow
sections (for general engineering purposes).
- IS 1948 - Aluminum Doors, Windows and Ventilators
- IS 2202 - Indian Standard Specification for wooden flush door shutters (solid core type)
part I - plywood face panels, part 2 - particle board face panels and hard board face
panels.
- IS 2338 - Indian Standard Code of practice for finishing of wood and wood based
materials, part 1 - operations and workmanship, part 2 – schedules.
- IS 2553 - Indian Standard Specification for safety glass. part 1 - General purpose.
- 2835 - Indian Standard Specification for flat transparent sheet glass.
- IS 3614 - Fire check Doors (Parts 1 & 2)
- IS 4020 - Indian Standard Specification for door shutters, method of tests, Parts 1 to 17.
- Material Manufacturer Technical Specification
3. Tools and Equipment:
Window / Door Frame, Window / Door Shutter, Right-angle, Hold Fast, Anchor Fastener, Hand
Tools, Hammer Drill, Screwdrivers, Spanners, Files and Small Tools, etc.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/21 DOOR AND WINDOW WORK 00 89-91

4. Work Procedure:
4.1. Pre-Check:
- Ensure the handing over of RCC work is done in all respect.
- Ensure the opening provided as per drawings.
- Clearance from MEP (Services) dept. taken before work commences.
- Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing work.
4.2. Work procedure:
Door and Window Frame:
- Door/Window frame shall be made of specified wood and shall be in accordance with
detailed drawings.
- The members of the frame shall be planed smooth and accurate to the full dimensions.
Rebates, rounding, molding etc. shall be done before the members are joined into frames.
- Joints in the frame work shall be perfect with square edges and shall be pinned with hard
wood/bamboo pins of 10 to 15 mm dia.
- Wood Work shall be painted/polished or otherwise treated as specified. All exposed
portions shall be coated with wood primer and concealed surface by bituminous paints as
per specifications.
- Each doors and frames tagged with sticker with door number and location.

Page 90 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Before any surface treatment is applied, the woodwork shall be approved by the Dosti.
The frames shall be fixed to the masonry by 300 mm x 25 mm x 6 mm M.S. hold fasts
embedded in M15 grade concrete block 350 mm x 100 mm x 100 mm in the hole of
Masonry. In case of concrete, frames shall be fixed by 120 to 140mm long, 10mm dia
nylon fasteners.
- All area should be cleaned prior to start of the work.
- Check Door openings in the structures should be as per approved shop drawing.
- Any deviation in the opening with respect to the shop drawing should be rectified.
- All door / window frames should be conducted moisture test prior to the fixing.
- While fixing frame opening direction of door / window shutter checked.
- Door frame fixed in line, level and right angle should be fixed with proper approved
anchoring as per project specification.
- All gaps between the frame & the wall should be properly closed with approved material.
- All door / window frames should be in plumb prior to fixing.
- All door / window accessories should be fixed as per approved GFC drawing / Shop
Drawings.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/21 DOOR AND WINDOW WORK 00 89-91

Door and Window Shutter:


1. Delivery, Storage and Handling
- Store Door and Window frames in clean dry ventilated area. Stack door frames flat and
off floors, supported to prevent wharfing. No other materials to be place on top of
stacked doors.
- All doors will be packed with plastic, cardboard protection to edges.
- Store flat over level surface above floor on wood blocks.
- Each door and window frames tagged with sticker with door number and location.
- All door frames delivered with finish factory painting final touch will be at site before
handing over
2. Installation of door and Window Shutter
- Check the tagged each door and window shutter. Locate as per the approved shop
drawing and door / Window schedule.
- Verify opening dimension and angles and levels from finish floor line reference to ensure
that frames fit the openings. Align and fit the door / Window in frame to each desired
location and elevation.
- Door shutters shall be complete with all operations fittings and fixtures like hinges,
overhead hydraulic door closers, Tower bolts, locking device, handles, doorstopper etc.

Page 91 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Aluminum Window Fixing Procedure


- Install, align and fit the doors in frames with uniform clearance and bevel to provide 3mm
at heads, jambs and between pairs of doors, bottom of door to top of decorative floor
finish or covering as per approved shop drawings.
- For aluminum window drainage provision should be made at approval distance. Framing
should be fixed by screws as approved or instructed by Dosti Engineer.
- For outer window running water test to be carried out to check leakages.
- For Aluminum Window Check for Wool Pile, Silicon Sealant at all corners of glass shutters.
- Architraves’ will be fixed by nail and to be covered. All surrounding gaps will be filled with
silicone or approved material.
- Completed doors and windows shall operate freely and smoothly without rattle or bound
condition.
- Clean stains and traces of cleaning fluid.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/22 SUSPENDED CEILING (FALSE CEILING ) WORK 00 92-93

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Perimeter channel.
- Ceiling angle.
- Intermediate channel.
- Ceiling section.
- Nylon sleeves/Screw.
- Soffit cleat.
- Anchor fastener
- Hex nut & Hex bolt.
- Connecting clip.
- Wafer head screw.
- Dry wall screw.
- Jointing compound.
- Joint paper tape.
2. Technical Specifications and Applicable Standards:
Gypsum Plaster Work shall be carried out as per following specifications / standards / code and /
or others as applicable.

Page 92 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

IS 2095-2011 - Gypsum Plaster Board


IS 2547-1973 - Gypsum Building Plaster
IS 277:2003 - Specification for Galvanized Steel Sheets
IS 14687:1999 - False work for concrete structures -Guidelines

3. Tools and Equipment:


Clean bucket, Plumb bob, Right-angle, Trowel, Measuring jar, Brush, Level tube, Puddle mixer,
Aluminum Patti, Drill machine, ladder, Mechanical Hammer, etc.
4. Work Procedure:
4.1. Pre-Check:-
- Source / brand / make of material shall be confirmed and approved.
- Detailed layout of the flat showing room dimension shall be available.
- Openings shall be provided as per drawing.
- Clearance from MEP (Services) department shall be taken before wall gypsum work
commences.
- Wall gypsum completed up to false ceiling required level with fire sealant .
- RCC slab above false ceiling should be dry 100% and precaution to be taken for water
leakages.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/22 SUSPENDED CEILING (FALSE CEILING ) WORK 00 92-93
- Any unavoidable projections in Gypsum finish masonry and concrete surfaces shall be
rectified.
- Slab bottom and wall shall be dry 100%.
4.2. Work Procedure:
- Grid and level marking for angle to be suspended with soffit cleat and anchor fastener.
(No drilling and Anchoring on RED mark PT slab).
- Angle fixed as per level along the perimeter of the wall/partition.
- Suspended ceiling angle fixed as per level and c/c distance with soffit cleat, anchor
fastener, nut and bolt.
- Intermediate channel is fixed to the ceiling angle as per level and c/c distance with wafer
head screw.
- Secondary ceiling section is fixed to the channel as per level and c/c distance with wafer
head screw.
- To form the supporting grid work, stringer channels shall be fitted on to top heads in
position and levels adjusted with help of nut.
- Final level shall be maintained with help of check nut.
- Lapping of Angle, Channel, ceiling section as per specification or 300mm and should be
alternate.
- Only one lapping is allow for single running channel & section.

Page 93 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- The overall grid system shall be rigid by self-locking joints, in accordance with false ceiling
patterns perfectly leveled and aligned at desirable height as per drawings.
- Gypsum board is fixed as per level with dry wall screw, screw fixed as per specification or
230mm c/c 2mm inside from the bottom face of the board.
- Provide edge runner at all sides to avoid cracks at junction.
- Gypsum board / metal board used should have no corner damages, no small cut pieces
and cracks.
- Gaps filling and finishing done with joining compound and joint paper tape.
- Marked cutouts on gypsum board to be get approved by MEP before cutting. Cut outs or
opening to be made with suitable frame and support for light fittings, grills, diffusers, etc
as per drawing and specification.
- Housekeeping done on daily basis, working area should be clean and safe.
- Modification work will be done prior approval and as per site requirement.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/23 PUTTY WORK 00 94-95

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Putty
- Sand paper (80-220no.)
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- Putty Manufacturer Technical Specification
3. Tools and Equipment:
Electric Peddle Mixer, Clean pan, Putty application Trowel, etc.
4. Work Procedure:
4.1. Pre-Check:
- Ensure the handing over of RCC work is done in all respect.
- Ensure the opening provided as per drawings.
- Clearance from MEP (Services) dept. taken before putty work commences.
- Compatibility of proposed putty with proposed paint system shall be ensured.

Page 94 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
- Check any cracks or damage on RCC/ Gypsum to be repaired before commencement of
work.
- Check compatibility with gypsum / paint or any other substrate.
4.2. Work procedure for putty:
- Clean the wall/ceiling surface by removing dust, curing compound and other materials.
- While applying putty on RCC surface, the substrate shall be grinded mechanically. All
loose material, binding wire shall be removed. Honeycombing if any shall be repaired by
approved material. Wash the substrate with clean water.
- Type of putty shall be carefully selected based on area of application.
- 1st coat primer to be applied on surface of RCC/Gypsum.
- Mixing of putty with mechanical mixer as per manufacturer technical data sheet /
specification.
- Punning of 1st coat putty (Thickness 1.25mm or as specified) to be carried out from one
end of wall/ceiling and get the wall/ceiling complete.
- Sanding of putty work to be done with 180 Micron Sanding paper after 1st coat gets dry
to get smooth surface.
- Minimum 8hrs interval to be kept between 1st and 2nd coat of putty.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/23 PUTTY WORK 00 94-95
- Punning of 2nd (Thickness 1.25mm or as specified) coat putty to be carried out after
completion of 1st coat, from one end of wall/ceiling and get the wall/ceiling complete.
- Cut the putty punning at skirting level in proper line and level as per site instruction.
- Sanding of putty work to be done after 2nd coat by 320 micron Sanding paper gets dry to
get smooth surface.
- Clean the Putty material fallen on floor immediately after completion of day work.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area also.

Page 95 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/24 PAINTING (INTERNAL AND EXTERNAL) WORK 00 96-97

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Water-proofing material / system
- Paint
- Paint Primer
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Paint Manufacturer Technical Specification
IS: 6278: Code of practice for white washing and colour washing.
IS: 2395: Code of practice for painting concrete, masonry and plaster
Surfaces.
IS: 712: Specification for building limes.
IS: 55: Specification for Ultramarine blue for paints.
IS: 63: Specification for whiting for paint and putty.
IS: 5411: Specification for plastic Emulsion paint for interior use.
IS: 2338: Code of practice for finishing of wood and wood based materials.
IS: 5410: Cement paint, colour as required.
IS: 384: Brushes, paint and varnishes, lat.

Page 96 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

IS: 486: Brushes, sash, tool for paints and varnishes.


IS: 110: Ready mixed paint, brushing, gray filler enamels for use over primers.
IS:426: Paste filler for colour coats.
IS:345: Wood filler, transparent Liquid.
IS:3585: Ready mixed paint, alum, brushing, priming, water resistant for woodwork.
IS: 426: Paste filler for colour coats.
IS: 106: Ready mixed paint, brushing, priming for enamels, for use on metals.
3. Tools and Equipment:
Electric Peddle Mixer, Clean pan, Scrapper blade, Paint brush, Roller (Coarse), Spray Machine,
Water Jet, Wire Brush, Air Blower, Measuring Jar, etc.
4. Work Procedure:
4.1. Pre-Check:
- Ensure the handing over of Gypsum plaster/Putty work in all respect.
- All fixtures are covered properly as per site instruction.
- Flooring & skirting are covered properly as per site instruction.
- Clearance from MEP (Services) dept. taken before work commences.
- Compatibility of proposed primer / texture with proposed paint system shall be ensured.
- Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing paint work.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/24 PAINTING (INTERNAL AND EXTERNAL) WORK 00 96-97
- Ensure that the approved material, brand and color of paint.
- Painting system / sequence / pattern shall be as per approved specification.
- Before starting work under this section large size samples of coating including preparation
of surface shall be made at the site and approval obtained from the consultant and
Architect before proceeding with the finishing works. Only after specific approval has
been given to the samples, work shall commence. The actual work shall be done as per
the approved samples.
4.2. Work procedure
- For External Paint, Joint inspection of dead wall / exposed to rain wall to be done with
Dosti / RCC Contractor / Paint Contractor representative to check leakages /
honeycombing / major cracks / tie rod or Wall Tie hole filling / grinding / bulging, etc.
Only after rectification of RCC may allow for paint work.
- For External Paint, While applying basecoat on RCC surface, the substrate shall be
grinded mechanically. All loose material, binding wire shall be removed. Honeycombing if
any shall be repaired by approved material.
- Clean the wall/ceiling surface by removing dust, oil, grease laitance, curing compound and
other materials.
- For External Paint, if required apply Water-Proofing coat on dead wall as per
manufacturer specifications.
- Mix primer as per manufacturer technical data sheet / specification.

Page 97 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Apply one coat of primer (Thickness as specified) with the help of brush/roller from one
end of wall/ceiling and get the wall/ceiling complete and allow getting dry.
- Mix paint as per technical data sheet / specification.
- Apply 1st coat of paint (Thickness as specified) with the help of approved brush / roller
etc. From one end of wall/ceiling and get the wall/ceiling completes.
- Allow the 1st coat of paint to get dry completely before application of 2nd coat.
- Apply 2nd coat of paint after 1st coat complete dry/ final handing over (Thickness as
specified) with the help of approved brush / roller etc. from one end of wall/ceiling and
get the wall/ceiling complete.
Check for completion.
- Paint texture / finished surface shall be as per agreed / approved. shade variation in color
not accepted
- Clean the paint material fallen on floor immediately after completion of day work.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area also.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/25 EMBEDDED ELECTRICAL CONDUIT 00 98-99

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Electrical Pipes
 Back Boxes
 Adapters
 Fillers / Joint Solvent
 Repairing Mortar

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications
 IS 9537- Part 1 - Conduits for electrical installations, Part 1: General requirements
 IS 732:1989 - Code of Practice for electrical wire installation

3. Tools and Equipment:

Page 98 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Pipe Cutter, Binding Wire, Nails / lockers, Hammer, etc

4. Work Procedure:
- Clearance shall be taken from Civil Team to proceed the work.
- Ensure that the work area is ready and safe to start the installation of electrical conduits.
- Prior to start the installation, ensure the approved GFC drawings and shall be available on
request.
- Mark the correct location of the back boxes or pull boxes in line and level and place
thermo coal or equivalent material secured with masking tape on these locations.
- Install the Electrical conducting of slab or any other concrete structure should be securely
fastened with binding wires to reinforcement rods or shuttering to withstand concrete &
screed pour.
- The jointing of conduits shall be done with suitable coupler and solvent cement(approval
from civil team). The conduits shall be bonded tightly to the back boxes / pull boxes with
suitable adapters.
- All bends of conducting shall be made by using correct size of bending spring. Ensure the
radius of any conduit bend shall not be less than four times the outside diameter of the
conduit to satisfy the easy cabling / wire pulling requirements.
- Ensure all open end of the conduit are capped / plugged properly before concrete
pouring.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/25 EMBEDDED ELECTRICAL CONDUIT 00 98-99

- During concrete pouring presence of electrical supervisor shall be ensured.


- In vertical wall the conduits shall run vertically from the back boxes. Horizontal runs shall
be avoided on walls.
- In masonry wall chased portion shall be filled with approved repairing mortar.
- In Masonry wall ensure conduit fixer should be within the wall external surface that can
be filling shall be done properly and sufficient to permit a minimum thickness of 15mm
for plaster cover.
- Alignment of the conduits shall be designed in such a way that there should not be a
congestion of the conduits at any particular location.
9.1 Post-completion Inspection
- Visual / measurable inspection shall be done after de-shuttering.
- Observation / Snags to be handed over to the Contractor for their compliance with their
acceptance and projected compliance date.
- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.
- Work handed over to the Civil Team for further work.

Page 99 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/26 ELECTRICAL WORK AND TESTING 00 100-105


1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Electrical Conduits
 Back Boxes / Cable Trays / Raceways
 Adapters
 Fillers / Joint Solvent
 Earthing Pipe, Plates & Strips
 RMU / Feeder Pillar / Panels / Transformers / DG etc.
 Air Circuit Breaker / Moulded Case Circuit Breaker
 HRC Fuses
 Cables & Wires
 Power Distribution Board & TV, Tel DB
 Switches, Sockets
 Lightning Arrester

2. Technical Specifications and Applicable Standards:

Page 100 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications
 IS 3043 / 1987 Code of practice for earthing.
 IS 3427 / 1997 A.C metal enclosed switchgear & control gears for rated voltage
above 1KV up to & including 52KV.
 IS 3837 / 1976 Accessories for rigid steel conduits for electrical wiring.
 IS 13947 / Part3 / 1993 Specification for low voltage switchgear & control gear.
 IS 13947 / Part1 / 1993 Specification for low voltage switchgear & control gear.
 IS 4615 / 1968 Switch socket outlets (Non-Interlocked type).
 IS 5578 / 1984 Guide for marking of insulated conductors.
 IS 6381 / 1972 Specifications for construction & testing of electrical apparatus with type
of protection ‘e’.
 IS 732 / 1989 Code of practice for electrical wiring installation.
 IS 3854 / 1997 Switches for domestic & similar purpose.
 IS 2309 / 1989 Code of practice for lighting production.
 IS 1937 / Part3 / 1983 Conduits for electrical installations.
 IS 2706 / Part1 to 5/1992 Current transformers.
 IS 13118 / 1991 Specification for HVAC circuit breakers.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/26 ELECTRICAL WORK AND TESTING 00 100-105


 IS 374 / 1979 Ceiling fans.
 IS 5578 / 1984 Guide for marking of insulated conductors.
 IS 418 / 1978 Tungsten filament general service electrical lamp.
 IS 694 / 1990 PVC insulated cable & cords for power / lighting.
 IS 13010 / 2002 A.C watt-hour meters.
 IS 732 / 1989 Electrical wiring installation (up to 650V).
 IS 10870 / 1984 Code of safety for hexane.
 IS 1248 / Part1 / 1993 Direct acting indicating instruments & their accessories.
 IS 1248 / Part2, 6 /1983 Direct acting indicating instruments & their accessories.
 IS 1248 / Part7, 8/1984 Direct acting indicating instruments & their accessories.
 IS 1248 / Part9/1983 Direct acting indicating instruments & their accessories.
 IS 1293 / 1988 3 pin plugs & socket outlets.
 IS 1554/Part1 to 3/1988 PVC insulated cables – heavy duty.
 IS 13947/Part 1 to 5/1993 Low voltage switchgear & control gear.
 IS 1651 / 1991 Lead acid cell batteries.
 IS 9537 / Part 5 / 2000 Conduits for electrical installation.

3. Tools and Equipment:

Page 101 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Pipe Cutter, Binding Wire, Nails / lockers, Hammer, Screw Driver, Electronic Multimeter tester,
Megger Meter, Electrical Knife, Drill, etc

4. PROCEDURE:

- Collect the drawings for the electrical system for the building with the respective
consultant & the same to be discussed with electrical contractor & reconfirmed before
starting the work.
- Re-check the electrical load capacity of the building including all the common areas &
amenities & if it adheres to the norms as mentioned by the competent authorities.
- To check the provision of all items in the drawings whether they are as per our norms viz,
main panels, electrical cables, cable trays, ELCB’s, MCB’s & their capacity, junction boxes
etc.
- To provide 6” dia. Conduits with inspection chambers at every 15mtrs from the
compound wall to the sub-station /meter room for main supply for the building. All
corner junctions to have inspection chamber. Provide separate conduits for L.V. & H.V.
cables.
- Check all the materials to be used for the system & whether they adhere to the ISI norms.
Get third party test certificate from the manufacturer before start of the work.
- All anchor fastener hooks to be screw type. Proper ‘Z’ angles to be used for supporting
PVC pipes in the electrical ducts.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/26 ELECTRICAL WORK AND TESTING 00 100-105
- To make a sample for the shaft piping including the ‘Z’ angle, To install the junction boxes
(isolator, telephone, cable TV, security System) as per the specifications. Proper
numbering on cables in shaft to be done.
- The shaft door height to be minimum 1500mm (preferable full height) & width 600mm to
lock the shutters with master key locks only. Keeps the slab level of shaft higher then
surrounding slab level.
- All electrical cables & wires to be as per ISI norms. Aluminium armoured cables to be used
in the electrical ducts & to be terminated in the isolator boxes .Copper cables then to be
laid from the meter room to flat DB according to the designed load in PVC pipes.
- Ensure that proper earthing has been provided for the individual flats & has been done in
every switch box.
- All openings in the electrical duct (on either sides) to be maximum 4” wide & the same to
be filled with light weight vermiculate concrete by supporting a GI sheet on angle frame.
Ensure that proper extra PVC sleeves are left in the electrical duct while doing the
concrete for future expansion.
- To provide 5amp socket & light point on every alternate floor in the electrical shaft.
- All Electrical conduits in beams to be dropped by 3” with sleeve in beam bottom. (after
de-shuttering of slab & beams)

Page 102 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Ensure that all bracket light points, switch plates etc are in line & level. Check the
operation of all the switches for smooth working.
- All feeder pillars, panels to be installed on a concrete base @ 300mm above FFL.
- Ensure that the meter room & the LV room is provided with sufficient ventilation &
lighting. Also check for any moisture formation or water leakage in both the rooms.
- Proper numbering of meters to be done for respective flats, common areas. Initial reading
to be taken & noted down.
- Lightning arrestors to be installed on the highest point in the building. The copper stripes
25mm x 3mm (two nos.) to be properly saddled along the external face of the building &
then taken up to the earthing pits.
- The earthing plate should not be less that 600mm x 600mm x 3.15mm & should be placed
on the edge. The top edge of the plate to be 1500mm below ground level.
- Place a funnel on the GI pipe mouth & make a chamber for the same with proper grating
on the top.
- Minimum distance between the two earthing pits to be at least 3.0mtrs & to be done in
an area which is likely to remain wet almost all the time.
- Ensure the entire system is checked /tested & commissioned. To prepare as built drawing
(by the consultant) for the cabling & wiring done on site.
- The CM&CE shall study the drawings and specifications. If any discrepancies are found, he
shall consult/liaise with the consultant for clarifications. The drawings shall be approved
by the Architect prior to their submission to any authorities.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/26 ELECTRICAL WORK AND TESTING 00 100-105
- Ensure preparation of the co-ordination drawings for services. The co-ordination drawings
is for the identification of services inter crossing with each other and penetration through
structural elements.
- Ensure that provision is made for penetration through structural elements and co-
ordinate routing of services to achieve design intention.
- Co-ordination with the purchasing department shall submit samples of materials and
catalogues of equipment to the Architect for study and approval.
- The Project planner shall liaise with the sub-contractor to produce a material delivery and
installation schedule. The Project planner Shall incorporate the schedule into the
Construction Master Program.
- Just before the arrival of the materials, the Site Engineer/Store Manager together with
the sub-contractor shall select a suitable location on site for storage and safe-keeping
(Handling, Storage and Preservation of Materials procedure)
- When physical work commence, co-ordinate and monitor the progress of the works.
- Carry out testing & commissioning of the system. The Contractor shall submit all the
relevant test results/certificate.
- Check and verify the installation works by completing checklist for Electrical works.
- Upon completion, Ensure that the sub-contractor submit the as-built drawings and
maintenance manuals to the owner (Project Handover procedure).

Page 103 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- The engineer shall require the sub-contractor to submit all the necessary warranty
certificates at completion (Warranty Submission and Safekeeping procedure).
- Ensure that sufficient quantity of Electrical material & manpower are available to execute
specified job as per construction master schedule & Joint measurements to be taken for
Record purpose.
- Adequate safety measures, pollution control facilities and various statutory stipulations
wherever applicable to be ensure at site by S.O.
Operation
- Material: Material used will be as approved by the Client. The sizes, routes and routing
will be as per the approved shop drawing.
- Storage and Protection: Deliver components parts to site, completely identified in
accordance with shop and certified drawings prepared for this work. Store in accordance
with the manufacturer’s instructions, above ground, properly protected from the weather
and construction activities.

Installation
- During the course of the installation of the conduit system, procedures for working and
dressing the installation as recommended shall be employed.
- All bends and sets shall be in accordance with applicable IS codes and standards formed
with the aid of a helical spring fitted internally, with if necessary, the conduit warmed
sufficiently for it to move without avoidable wall thinning of the outside of the bend.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/26 ELECTRICAL WORK AND TESTING 00 100-105
- Conduit system shall be installed so as to ensure compliance with the requirements of
Specified Standard and Regulation.
- Joints between PVC conduit and fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit, inclusive of draw in
boxes etc., exceeds three meters in length or wherever it’s necessary.
- The minimum and maximum sizes of conduit to be employed shall be 20mm and
25mmdiameter respectively.
Fixing of Conduits
- When conduits are run on shuttering, prior to the laying of concrete , additional security
must be provided near to every box and at intervals of not more than .3 meters by
binding short lengths of GI wire twisted around the conduit and reinforcing steel. The
conduits shall be adequately fixed to prevent excessive movement and damage during
the pouring and setting of concrete and shall be protected from mechanical damage.
Check there is no damage before concrete is poured.
- Where conduits are left "open ended" prior to wiring they shall be protected by PVC end
caps or plugs to prevent the ingress of building material.
- All conduits runs must be designed to permit wiring to be readily installed after the
complete erection of the conduits through the available draw-in, accessory and luminary
suspension boxes.

Page 104 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Ensure conduits are not concealed until works has been inspected and approved.
- Fixing Conduits with GI boxes in the walls
- Upon finishing the block work in each floor, start marking the location of all the switches,
sockets, telephone outlets, TV outlets, break glass and bells as per the GFC (Good for
Construction) drawings. Then Start chasing and chipping the marked locations by using
grinder, chisel or any other tool as necessary. we will fix the GI boxes with minimum 5
mm away from the wall to make sure that the box is flush with the plaster. Next day we
will terminate the conduits with the GI boxes.
Fixing conduits and GI boxes in the columns
- Before casting any column in the site, we have to check if there is any Switch Socket, bell
or break glass fixed on the column. If there is any, we have to fix the GI or PVC box in the
proper way ensuring that it touches the shutter of the Column from inside and the
conduit will be extended to the top of the column.
Fixing of Distribution Board’s Enclosure
- Ask the client to locate plaster level points only in the location where recessed D.B. is to
be installed so that we can fix the enclosures properly and to ensure the enclosures are
completely flush with plaster. The mounted height of the enclosures will be as per the
instructions of client. Distribution board will be aligned, leveled and securely fastened to
the wall. The surface mounted panel boards will be fixed as per client’s instruction.
-
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/26 ELECTRICAL WORK AND TESTING 00 100-105


- Distribution board interiors will not be installed in cabinets until all conduits connections
to the cabinet have been completed.

Wiring for lighting & Power Points


- Before starting the wiring for the above mentioned activities, we have to make sure that
the plasterwork is finished completely in that area / floor & there is no more water still on
the walls.
- For the light & Power circuits, wires & cables will be used as per the approved material
submittal. The wires and cables will be installed in conduits, trunking and ladders as per
the approved shop drawings. For branch circuit work, originating from light and power
panel boards will be arranged as per the approved drawings. Loads on various phases of
panel boards will be balanced as per he approved load schedules. Lubricants will be used
if necessary to avoid any damage to the wire or cable during the pulling stage and to
prevent any stresses on conductors. At every branch circuit outlet and pull-box, every
cable passing through will be left slack to allow inspection and for connection to be made.
Cables terminating in outlet boxes will be left with at least 250mm extra length for
terminations. All circuits will be properly labeled during the pulling work to facilitate the
terminations at the respective devices. After the pulling circuit works completely, all the
circuits will be checked and tested for any open circuits, short circuits, earthling continuity
and excessive resistance leakage.

Page 105 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Installing of protective devices within the DB (MCB, ELCB, etc.)


- All materials will be furnished and installed as per the approved GFC. A highly skilled
electrician will be carrying out this work. Dressing of standard conductor will be done by
using ferrules of sizes suitable for accommodating all stands of the conductor.
- After finishing the first coat of painting near the final DB’s, start numbering the
conductors and then begin installing the components on DIN rail and terminate the wires
as per the Load Distribution Schedules
Installation of Switches and accessories
- The switch plates and its accessories shall be installed as per the GFC. After first coat of
painting begin the process of installing the switch plate by terminating the wires to the
respective accessories. Ensure that wires are terminated as per the markings on the
accessories. Enough slack should be left for future maintenance. The final step of
installation is to fasten the switch plate to the concealed modular box with the help of
screws. After the final coat of painting install the switch plate cover.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/27 FIRE FIGHTING WORK 00 106-110

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 G.I. Pipes – C’ class / G.I. fitting threaded
 Butterfly Valves / Wafer Type Check Valves / Ball valves/Gate valve / Solenoid Valve / Air
Release Valve
 Strainers
 Anchor Fasteners
 Anti Vibration Mounting
 Coupling
 Electrical Panels
 Gun metal Single / Double headed Hydrant Valves, three way Fire Brigade inlet, hose reel
drum & shut off Nozzle Canvas hose
 Fireman AXE
 Fire Hose
 Pressure switch / Pressure Gauges
 Sprinkler Heads

Page 106 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

 Cable Tray
 Water spray nozzles, Deluge valve
 Fire Alarm Panel
 MCP, Smoke & Heat detector, Gas Leak Detector, Control Modules, Hooter, Fire Alarm
Cable, Fault Isolator
 PA system ( Amplifier, Speaker, Microphone, PA system Cable )
 PVC insulated Aluminum / Copper Conductor Amored Cables

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications
 IS 1648 - 1961 : - Code of practice for fire safety of buildings (general) fire fighting
equipment and its maintenance.
 IS 3844 - 1966 :- Code of practice for installation of internal Fire Hydrants in Multi-storied
Buildings.
 IS : 554 Dimensions for pipes threads where pressure tight joints are required on the
threads
 IS : 638 Sheet rubber jointing and rubber insertion jointing.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/27 FIRE FIGHTING WORK 00 106-110


 IS : 778 Copper alloy ball , ball and check valves for water work purposes.
 IS : 780 Sluice valves for water – works purposes ( 50 mm to 300 mm ).
 IS : 901 Couplings double male and double female, instantaneous pattern for fire fittings.
 IS : 1239 Mild steel tubes, tubular and other wrought ( Part I & II ) steel fittings,
 IS : 884 Swinging type wall mounted hose reel with drum.
 IS : 388 Hose tubing.
 IS : 4038 Foot valves for water – works purposes
 IS 5290 Landing valves.
 IS : 10221 Anti corrosion treatments for under ground MS pipes.
 IS : 5312 Swing check type reflux ( non- return ) valves.
 IS : 636 – 1988 Fire Fighting Delivery hose.
 IS : 903 - 1984 : Specification for Fire Hose, Delivery Coupling, Branch pipe, Nozzles.
 IS : 12469 : Pumps
 Rules for Automatic sprinkler installation & Tariff advisory Committee.
 Standards as accepted by Local Fire Brigade.

3. Tools and Equipment:


Fire Pumps, Pipe Cutter, Hammer, Screw Driver, Electronic Multimeter tester, Megger Meter,
Electrical Knife, Drill, etc

Page 107 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

8.0 PROCEDURE:

- Ensure RCP plan before star of work.


Fire Pumps
- The fire pump shall be horizontally mounted single stage centrifugal end suction type and
direct driven by electrical motor, as specified. The pump rating and performance shall be
as described in the drawings, or Bill of Quantities. Contractor should pump ratings / check
the space availability for pump room & provide shop drawings before procurement of
pumps.
- Pump shall be capable of delivering 150 % of the rated capacity at 65 % of the rated head
and the no-delivery head shall not exceed 120 % of rated head. Pump casing shall
withstand 1.5 times the working pressure.
CONTROL PANELS
- Unless otherwise specified in the tender specifications, the entire equipment shall be
suitable for operating on 415 volts, 50 cycles, earthed neutral, 3 phase, 4 wire A.C system.
- The equipment and panel shall be as per CFO’s requirements
- The contractor shall submit the fabrication drawings of the Pump Panel indicating all
enclosures separately for all Pumps etc. for approval by the Engineer-In-Charge. Drawings
shall indicate cable inlets, outlets, chamber dimensions and front and side elevations. This
drawings shall take into account all fuses, contactor, switches & meters etc.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/27 FIRE FIGHTING WORK 00 106-110


- The control panel including circuit breakers, fuse / switches and isolators shall be
provided with labels suitably engraved with legible characters (not less than 5 mm high)
indicating the use of the equipment’s and its reference numbers .
- The Contactor rating shall be suitable for the rating of the Main Fire Pump and other
Pump: Contractor shall co-ordinate and supply the total panel suitable for the pumps
offered by him.
- Control wiring from pressure switches of different settings in Hydrant line, Sprinkler line
Jockey Pump, Booster Pumps, for sequence of operation shall be included to complete
the system. Control code with ferrule marking shall also be made.
- The wiring shall be PVC insulated and PVC armoured sheathed aluminium conductor
copper cable of 650 / 100 volts grade conforming to IS 1553 ( 1964 ) as required from Fire
Pump Board to motor and cable of suitable size.

PIPING.
- Hangers and supports shall be capable of carrying the sum total of all concurrently acting
loads. They shall be designed to provide the required supporting effects and allow
pipelines movements as necessary. All guides, anchors, braces, dampners, expansion
joints and structural steel to be attached to the building / structure, trenches etc. shall be

Page 108 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

provided by the Contractor. Hangers and components for all piping shall be approved
before fixing
- The piping system and components shall be capable of withstanding 150 per cent of the
maximum working pressure. Pipes shall be pressure tested to hydrostatic test pressure of
20 kg /cm2. The pressure shall be maintained for a period of two hours and there shall be
no drop in pressure at the end of this period.
- Flanged joints shall be used for connections to vessels, equipment, flanged, valves and
also suitable straight lengths of pipeline lengths of pipeline of strategic points to facilitate
erection and subsequent maintenance work.
- Flanged joints shall be used for connections to vessels, equipment, flanged, valves and
also suitable straight lengths of pipeline lengths of pipeline of strategic points to facilitate
erection and subsequent maintenance work.
- Non-return valves shall be cast iron wafer swing check type or dual plate / flap type An
arrow mark in the direction of flow shall be marked on the body of the valve. These valves
shall conform to IS : 5312. The flap shall be cast iron and flap seat ring of loaded gun
metal.

YARD HYDRANT
- Yard Hydrant valve shall be as per IS : 5290 and IS marked. The valve shall be oblique type
complete with hand wheel, quick coupling connection, spring and gun metal blank cap as
per IS : 5290. The hydrant shall be tapped from the 150 / 100 dia main with elbow and
standpipe 80 mm dia at approx. 1-2 m above ground level.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/27 FIRE FIGHTING WORK 00 106-110

INTERNAL LANDING VALVE.


- The Internal landing valve shall be single / double headed of gun metal conforming to IS:
5290. It shall be oblique type, complete with hand wheel, quick coupling connection,
spring and gun metal blank cap.

HOSE REEL
- The hose reel shall be directly tapped from the riser through a 20 mm dia pipe, the drum
and the reel being firmly held against the wall by use of dash fasteners. The Hose Reel
shall be swinging type ( 180 degrees ) and the entire Drum, Reel etc. shall be as per IS :
884. The rubber tubing shall be of approved quality and the nozzle shall be 6mm dia shut
off type.

EXTERNAL HOSE CABINET


- Hose for yard hydrant shall be housed in a Hose Cabinet of Size 750mm x 600mm with
suitable depth including glass and locking arrangement.
- The cabinet shall be of minimum 16 SWG MS sheet and framing of MS tubular sheet as
per drawing with center opening glazed doors (clear glass of 5.5-mm thickness). The glass
shall be firmly fixed by means of steel clips and screw.

Page 109 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

FIRE BRIGADE INLET .


- Fire Brigade Inlet connection shall be taken directly to the Riser. It shall comprise of four
instantaneous male inlet coupling with plug and steel chain. The inlet shall have a non
return valve and a sluice valve on the upto like riser. The Fire Brigade Inlet shall be
complete with necessary components like special fittings of medium quality MS bends,
flanged tees etc. The plug shall be brass.
- Fire Brigade Inlet for Tank Filling by Fire Brigade shall be four way with gun metal
instantaneous male inlet coupling connections for connection with Fire Brigade vehicle,
complete with cap, chain and plug.

SPRINKLER SYSTEM
PENDENT TYPE SPRINKLER HEAD.

- Sprinkler heads shall be quartzoid bulb type with bulb, valve assembly yoke and the
deflector. The sprinkler shall of approved make and type with 15 mm nominal dia outlets.
- The bulb shall be made of corrosion free material strong enough to withstand any water
pressure likely to occur in the system. The bulb shall shatter when the temperature of the
surrounding air reaches to 68 degree C.
- The nominal bore shall be 15 mm dia colour of liquid shall be Red.
- The Sprinkler head shall be approved by TAC/FOC/UL/FM

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/27 FIRE FIGHTING WORK 00 106-110

EXTENDED THROW SIDE WALL SPRINKLER HEAD (OPTIONAL) :


- These sprinkler shall be fast Response Type with Fusible Alloy melting at 69 deg C-71 deg
C. The material shall be of Gun Metal / Stainless steel. The coverage shall be upto max. 20
M2 with forward throw upto 6M and side wise 2 M either side with spray pattern of 120
degree minimum. The fast response shall be achieved by quick heat absorbing metal fins
or any other technology and the sprinkler shall be listed by FM/ UL / OC/ LPC.

INSTALLATION CONTROL VALVE FOR SPRINKLER


- Installation Control Valve will be Diaphragm actuated and the body and cover to be C.I as
per IS : 210 The seat shall be of bronze and the sealing by Rubber. The valve shall
comprise of following:
Wet Pilot Actuator, Water Motor Gong, Strainer, a flow test, a drain valve. It shall have
check valve, and a Drip check, alarm test valve, pressure indicator and all other
components as required. Further, a retard chamber shall also be provided to compensate
for water surges.

Page 110 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/28 HVAC WORK 00 111-113

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 G.I. Pipes & Insulating Materials
 Copper Pipes & Insulating Materials
 PVC/UPVC Pipes
 Anchor Fasteners, Clamps, Threaded rod & MS angles
 Anti Vibration Mounting
 Thermostat & Temperature sensors
 Electrical Panels
 Cable Tray
 G.I. Ducts & Insulating Materials
 Air Grills & Diffusers
 Fire Dampers

Page 111 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

 Air Conditioning Units


 PVC insulated Aluminum / Copper Conductor Armored Cables

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications
 IS : 554 Dimensions for pipes threads where pressure tight joints are required on the
threads
 SMACNA / ASHRAE

3. Tools and Equipment:


Pipe Cutter, Hammer, Screw Driver, Electronic Multimeter tester, Megger Meter, Electrical Knife,
Drill, etc

4. PROCEDURE:
- Ensure horizontal ductwork is adequately supported at equal distances in accordance
with Construction Drawings with all brackets fixed to the vertical face of ribbed
beams of the structure.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/28 HVAC WORK 00 111-113


- Care will be taken during setting out, that ductwork runs between ceiling module lines so
as to maintain maximum flexibility for any future relocation of lighting fixtures or
other services.
- Ductwork supports unless otherwise indicated will be installed to provide a
minimum space of 15mm between finished covering and adjacent work, and 100mm
clearance from suspended ceiling.
- Supports or hangers will be placed within 300mm of any 45° –90° bend.
- Screwed drop rods will have thread adjustment in either direction available after
leveling of ductwork and associated plenum box’s.
- Ducts will be supported within 300mm of mating flanges or joints.
- As indicated on relevant approved construction drawings where more than one duct can
be supported on one hanger – the size of the hanger will be assessed on the sum
of the maximum widths.
- Ductwork passing through non fire rated walls and floors will be adequately supported on
either side.
- All locknuts are tightened correctly. At all open end’s check for debris then cover with
suitable material to prevent any ingress of debris vermin, or moisture.

Page 112 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Vendor Supervisor to ensure that there are no dents, distortion or buckling of


ducting during installation being aware that damaged sheet metal work will be rejected.
- Supports are to be fixed at correct levels checking the bracket material is compatible with
the installation and the correct method used for thermal insulation.
- Ducting to be installed allowing sufficient space for expansion/contraction and
thermal insulation.
- Fixing of flanges to ductwork will be by the approved details and in compliance with the
specification requirements:
a) Clean both flange faces to be joined.
b) Add gasket jointing material to flanges to be mated.
c) Using only undamaged rust free bolts nuts and washers join mating flanges
together and tighten bolts.
d) Clean any excess jointing material from flanges.
- Continuously check horizontal and vertical alignment of ductwork and compliance
with contractors drawings and specification requirements by using spirit level plumb
or other suitable instrument.
- In line equipment is to be independently supported from main structure and not
blockwork walls or sub-structure.
- Silencers, fire dampers, balancing dampers & other plant items will be installed as
per contractors drawings, and will be supported adequately.
- Vendor Supervisor to check before end of work day’s by recording in his diary (as
necessary) that:
- The correct type of supports are being installed,
- Supports are adequately supporting the ductwork and associated plant equipment.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/28 HVAC WORK 00 111-113


- Test holes to be provided and plugged ready for commissioning and control equipment.
- Ensure terminal equipment is installed as specified.
- Supervisor to ensure that all completed installations look neat and tidy, and that
there is adequate spacing between ductwork and in line equipment
- allowing access for operation and ease of maintenance, to approved contractors
drawings and manufacture’s recommendations.
- Duct leakage test must be performed by Vendor & witnessed by Client prior to final
commissioning to ensure for no air leakages in duct work. Sealant to be used properly at
all sharp edges of Duct corners to avoid any air leakages.
- The supervisor in charge and the QC officer shall continuously monitor the
activities (by recording the defects or snags into his House Process Inspection List)
to ensure that all components indicated on the approved contractors drawings have
been installed and that the installation is in accordance with the contract requirements.
- Pressure test of all Copper pipes to be performed by vendor before gas charging & test to
be witnessed by client to observe leakages in pipeline if any & further to be rectified by
vendor and test report to be shared to client for record.

Page 113 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Air balancing & Temperature mapping to be done by Vendor & report to be shared with
client for cross-verification & record.
- All materials must be as per approved Make list & specification and Vendor to get all
materials cross-verified by client before installation at site as per approved GFC & tender
specifications.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Water Pipes For Sanitary Fittings
a. PVC / CPVC Pipes Copper Pipes / Lead
a. Hand Wash Basin
Pipes b. Sinks (glazed or stainless-steel sinks)
b. G.I. Pipe. c. Bath Tubs
Plumbing Drainage System d. CP Tabs, Showers, Diverters etc.
c. Stone ware pipe: e. Water Closet
d. C.I. Soil/ Waste pipe 1. Indian type
e. C.I. Soil / Vent Pipe: 2. European type or pedestal types
f. C. I. Nahni Trap 3. Anglo-Indian type
g. Stone ware gully Trap f. Urinals
h. C.I. Man-hole cover & Frame 1. Bowl type or lip type urinals
i. Anti-Siphonage pipe 2. Stall type
j. C.P. Cocks g. Flushing cisterns Page 114 of 129
1. Low level 10 liters capacity
2. High level 10 liters capacity
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

2. Technical Specifications and Applicable Standards:

Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
 Manufacturer Technical Specifications
 SP 35 : 1987 Handbook on Water Supply and Drainage (with Special Emphasis on
Plumbing)
 IS 1200 : Part XIX : 1981 Method of Measurement of Building and Civil Engineering Works
- Part XIX : Water Supply, Plumbing and Drains
 IS 12183 : Part 1 : 1987 Code of practice for plumbing in multi- storied buildings: Part 1
Water supply
 IS 14810 : 2000 Copper Tubes for Plumbing – Specification
 IS 3486: 1966 Cast Iron Spigot And Socket Drain Pipes. Socket Drain Pipes
 IS 1729:2002 Cast Iron/Ductile Iron Drainage Pipes and Pipe Fittings for Over Ground Non-
Pressure Pipeline Socket and Spigot Series

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120

 IS 2556-6 :1995 Vitreous Sanitary Appliances (Vitreous China), Part 6: Specific


Requirements of Urinals and Partition Plates
 IS 781:1984 Cast Copper Alloy Screw Down Bib Taps And Stop Valves for Water Services

3. Tools and Equipment:

Heavy Duty Clamps, Hammer, Measuring Tape, Marker, Wood Saw, Half Round File, Hack-saw
Frame, Drill Machine, Anchor Punch, Marking Line / Dori, Screw Driver flat and Star set, Fix
Adjustable Spanner, Monkey Pliers / Electrical Pliers, Kalwa Cutter, Pipe Wrench, Plumb, Spirit
Level, Right Angle, etc
4. Work Procedure:
Given below are method statements for general plumbing installations. This may need to be
modified in specific cases depending on the nature of the installations.

Page 115 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

a. Excavation of Trenches :
- Mark layout of the pipeline and obtain approval from the DOSTI representative. Barricade
sides of trenches to be excavated.
- Start excavation works (Using manual labour or an excavator machine). Ensure that the
width does not exceed the maximum specified.
- Use a leveling instrument to make depth markings all along the length of the excavation.
In certain situations, it may not be practical to use a leveling instrument in a plumbing or
sewerage installation. In such cases, a tube level could be used.
- Allow for deeper excavations to accommodate the PCC base of inspection chambers and
at collars/joints of pipes.
- Additional care should be exercised for excavations deeper than 1.5m, especially in loose
soils. Arrangements should be made for shoring the sides of trenches.
- Care should be taken that excess excavations are always avoided. If in doubt, excavate
less and take out the extra depth in the next stage. Filled in soil invariably settles taking
the pipe with it, disturbing alignments.
- Ensure that excavated earth is always stored away from the edge of the trench.
b. External piping – Water supply
- Mark pipe lines in ground according to working drawing and provide barricading.
- Excavate trenches to required depths as per working drawings.
- Prepare base of trench for laying pipes, as per technical specifications.
- Lay the pipes on the prepared base and support them at adequate intervals.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120


- Test the pipes for leaks under pressure in the presence of DOSTI representative and
maintain a ‘test certificate’ duly signed by the representatives of the client and
contractor.
- Coat the pipes with the specified anti-corrosive treatment (if metal pipes are used).
- Provide encasement with sand/granular material, if specified.
- Backfill trenches in layers including compaction.
c. External piping- Sewerage & Storm Water
- Mark pipe lines in ground according to working drawings.
- Excavate trenches to required depths with proper barricading.
- Prepare base for laying pipes.
- Lay pipes according to specified gradient.
- Perform hydraulic/smoke test and obtain certification form DOSTI representative.
- Provide encasement with concrete / sand/ granular material, as specified.
- Backfill trenches in layers including compaction.

Page 116 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

d. Shaft Piping
- Ensure all the civil works activities are completed before start of the shaft piping.
- Mark for pipes on the plastered shaft walls according to details in the working drawings.
Ensure that the plastering is completed as it will be almost impossible to plaster walls
after the pipes are in place.
- Fix brackets as per details shown on the working drawings. A clear gap of 25 to 50mm
shall be maintained between pipe and wall surface. The brackets should be made of non-
corrosive material.
- Clamp pipe assemblies on to the brackets. Make sure the pipes are in ‘line’ (horizontal
runs) or in ‘plumb’ (vertical stacks). Where expansion / contraction will be a concern,
ensure that pipes are not rigidly held to brackets.
- Make cut-outs on the shaft walls for branch pipes at locations shown on the drawings.
- Insert sleeves wherever required. Ensure that annular space in sleeves is not more than
25mm. Annular space shall be filled with yarn and flexible sealant after installation of pipe
through the sleeve.
- Provide branches on the pipe assembly for connections to internal pipework. Provide
isolating valves on water supply pipes at locations shown on working drawings; at easily
reachable heights.
- Test the pipes for leaks under specified pressure for the specified duration.
- Tests must be witnessed and approved by Dosti’s representative.
- If Required, Paint the pipes as per approved colour code and provide identification labels
where called for.
- Take measurement of pipes installed. A representative of Dosti must be present and
should acknowledge the records.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120


- Terminate soil, waste and vent pipes with vent cowls at specified heights above terrace
level. Ensure that vent cowls are not terminated within one meter (horizontally and
vertically) from any window openings. Terminate water supply risers with automotive air
vents (with isolating valves) and down pipes with drain plug/drain valve – all as per
drawings. Ensure that water supply pipework would be self-venting and self-draining.
- Connect the soil stack(s) to inspection chamber(s) at ground level.
- Connect waste stacks(s) to the gully trap(s) at ground level. Connect the gully trap(s) to
the inspection chamber(s).
e. Pipes in Wall Chases
- Make sure that walls are at least rough-plastered and finish levels are marked by the civil
contractor. If proper cladding levels are not marked, the pipes could be too deep or too
shallow inside. Pipes deep in the wall will require use of extension nipples at faucets.
- Mark pipe lines on walls as shown on the working drawing.

Page 117 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Chase the walls to required depth using a chasing machine. Chase before Water-proofing
work.
- Assemble piping starting from branch left in shaft and install in the wall chase with
clamps. Use pre-fabricated assemblies wherever possible.
- Locate fixture outlets according to working drawing and tile-module drawings. Title
modules shall be marked on walls by the civil contractor.
- Sensor Urinal - Before tiles fixing need to check proper electrical points with dimensions
mentioned by Company on proper location. If there is battery system than during tiling
person should fix sensor base box to avoid tiles wastage & Proper finish.
- Plug all openings and test the pipework for leaks under specified pressure and for
required duration. Test should be witnessed and approved by authorized personnel.
- Apply anti-corrosive coating or wrapping on the pipe, as specified (if metal pipes are
used). Ensure that the tested pipe joints are not disturbed.
- Insulate hot water pipes with the specified material.
- Water pressure test to be witnessed by the Dosti Representative and shall keep record for
the same.
Note:
- Wherever possible, pipes may be pre-insulated/pre-wrapped, leaving joints, prior to
installation in the wall chase.
- Close the wall chases with cement mortar. If site conditions require a depth of more than
100mm to be chased, it is advisable to use a suitable mesh while plastering and ‘making
good’.

f. Pipes in sunken floor or suspended in ceiling (Drainage)


- Make sure that base water-proofing of toilet floors is completed.
- Locate and mark positions of soil and waste outlets. Make core drills where necessary.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120


- Assemble pipe headers and connect them to branches left in the shaft for this purpose.
Pre-fabricate wherever possible.
- Make sure that pipes are in proper slope and are supported adequately. Always ensure
that the spacing of supports is as per specifications. Ensure that floor traps are installed in
level (not tilted) so that the water seal is not diminished.
- Test the pipes and attend to leaks, if any.
- Supervise the filling of sunken floors by civil contractor so that the alignment and slope of
drainage pipes are not disturbed. It is in the plumbing contractor’s interest to ensure that
water proofing of the core drills is done and tested.
- Keep all open ends plugged to prevent ingress of construction debris.
g. Sanitary fixtures & CP fittings

Page 118 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Flush the installed pipework (water supply and drainage) to remove debris or blockages, if
any.
- Install sanitary fixtures, faucets and washroom accessories. Use screws with nylon
washers to fix vitreous chinaware and PTPE tape for installation of faucets to pipework.
- Check CP fittings for leaks and firmness. Refit them if necessary. Ensure that proper tools
are used. They must not make scratches or any other kind of damages on the chrome
plated fixtures.
- Commission the toilets in the presence of the Dosti’s Engineer.
- Handover the toilets formally using the forms provided for the purpose.
The water distribution system should be thoroughly disinfected before being put to use. The
following simple procedures will ensure satisfactory results:
- Flush and clean water tank(s) and distribution pipework with potable water to remove
dirt and any foreign matter.
- Fill the tank(s) with water mixed with chlorine solution at the rate of 50 parts per million.
Retain chlorinated water in the system allowing the chlorine to spread throughout
pipework.
- Open the farthest draw-off points or drain plug/valve to draw water. Repeat the
procedure till odour of chlorine is felt at all locations when checked at random.
- Drain out chlorinated water and fill the system with potable water.

h. Installation of Wash Basin


- Drainage and Water Supply pipe work should be inspected prior to installation of wash
basin.
- Wash basin extension piece, connectors, fittings and accessories shall be verified by from
Dosti MEP department.
- Any discrepancies from the wash basin requirements to be coordinated to the Dosti MEP
Dept or Consultant for modification.
REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120

- Wash basin should be checked for any damage, scratches and defects prior to installation.
- Install the wash basin once clearance and access provided by the Dosti. Refere approved
GFC / Shop drawing.
- Silicon sealant to be provided in between the wash basin’s rims and Counter.
- Install waste pipe to siphon bend with gasket flushed on the wall from the bottle trap.
- Cover the wash basin with plastic or cartons till testing and commissioning.

5. Post-completion Inspection
- Visual / measurable inspection shall be done after de-shuttering.

Page 119 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.
- On handling over the as-fitted drawings and O&M manuals, a joint site visit shall be
arranged with the client’s representative to ensure all works are completed to their
satisfaction and obtain a certificate to that extent. Date of this certificate will be the start
date of Defects Liability Period.
- A detailed checklist shall be prepared for each activity as listed above and
acknowledgements may be taken from the supervising agency
6. Records:
As-Installed or As built Drawings

- Mark changes made from the working drawings; if any. These records should be
maintained from time to time during progress of work.
- Prepare ‘As-Installed’ drawings. This is an essential requirement often ignored. After the
construction team leaves the project site, it would be impossible to identify pipe routings
etc. without these drawings.
Operation & Maintenance Manuals
The O & M manuals should contain following minimum information:
- A brief description about the project and the installations carried out. Schedule of
mechanical / electrical equipment installed.
- Schedule of sanitary fixtures installed.
- Schedule of as-fitted drawings.
- Manufacturer’s operation & maintenance manuals and any warranties issued by
manufacturers.
- List of recommended spare parts.
- Notes / recommendations on preventive and remedial maintenance works.
- List of manufacturers with their local contact details.
- Technical catalogs of important products used on the installations.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120

- Reports / certificates of all tests conducted during progress of work and any
commissioning reports.
- Virtual completion certificate
- On handling over the as-fitted drawings and O&M manuals, a joint site visit shall be
arranged with the Dosti’s representative to ensure all works are completed to their
satisfaction and obtain a certificate to that extent. Date of this certificate will be the start
date of Defects Liability Period.
- A detailed checklist shall be prepared for each activity as listed above and
acknowledgements may be taken from the supervising agency.

Page 120 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/30 SOLAR HEATER WORK 00 121-122

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 G.I. Pipes – C’ class / G.I. fitting threaded
 CPVC – SDR 11 / Composite Multilayer Pipes
 Anchor Fasteners / MS angles for support structure
 Solar Panels / Solar water storage Tank / Water Heater

Page 121 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

 NRV / Control Valves / Temperature Sensors


 Control Panels
 Electrical cables

2. Technical Specifications and Applicable Standards:

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications
 12933 (Part 1) : 1990 - Solar flat plate collector : Part 1 , General requirements
 12933 (Part 2) : 1990 - Solar flat plate collector : Part 2 Components
 12933 (Part 3 ) : 1990 - Solar flat plate collector : Part 3 Measuring instruments.
 12933 ( Part 4 ) : 1990 - Solar flat plate collector : Part 4 Performance requirements and
accepted criteria
 12933 ( Part 5 ) : 1990 - Solar flat plate collector : Part 5 Test methods

3. Tools and Equipment:


Pipe Cutter, Hammer, Screw Driver, Drill, etc

4. PROCEDURE:
- Vendor shall visit the site to study the site condition and suggest type of system that will
be best suited for efficient & economical working of system
- Two types of Solar Water Heater available; one based on Flat Plate Collector (FPC) and
other based on Evacuated Tube Collector (ETC).
- Vendor shall furnish shop drawings showing the location of solar panels, storage tank,
pumps, valves, piping etc. complete for approval to Client/Consultant prior to
commencement of work.
- The solar panels shall be placed facing south for maximizing the use of solar energy.

REF NO PROCEDURE TITLE REV. NO PAGE NO


MS/30 SOLAR HEATER WORK 00 121-122
- All technical details/specifications of solar panels, storage tank, pressure ratings of all
equipment’s/accessories shall be provided by vendor for taking approval from
client/consultant.
- Vendor to ensure for installation of all materials as per approved Make list, specification,
GFC drawing & get it cross-verified by client.
-
- Pipe Leakage test to be performed by vendor & to intimate client for Joint inspection for
the leakage test in advance.
- Vendor to check all the valves are working well and the system is filled with water
completely before putting the system in operation.

Page 122 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Vendor is responsible to ensure for achieving design temperature. Temperature test to be


performed on output water of solar system by vendor and test report to be submitted to
client for record.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/31 FABRICATION AND ELEVATION WORK 00 123-124


1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
 Rivets, bolts, nuts, threaded fasteners
 GRC Material
 Ready Made Fins

2. Technical Specifications and Applicable Standards:

Page 123 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
 Manufacturer Technical Specifications

3. Tools and Equipment:


Welding Shield, Goggles, safety belt, barricade, Chisels, Cutting machine, Cutting blades, Steel
cutting disk, cutting torches, Hack saw, cutters, hammer, press brakes, welding machine, welding
rods, cable wire, CNC punch, brush.
4. PROCEDURE:
a. Grill Fabrication
- If the fabrication works are done at project site, a 3 phase electrical connection with
suitable working platform must be provided.
- The materials being used for the fabrication works should be of good quality, and free
from cracks, defective edges, surface flaws and rough texture.
- All the joints of members should be properly welded from both sides.
- Before commencing the window grill fixing, civil works including all window jams, sills,
corners, inside and outside plaster should be completed.
- It is better to complete granite stone coping also, before grills or railing works, so that
cutting of granite can be avoided.
- By means of drilling holes gently over granite surface, railing vertical legs can be easily fix
including grouting.
- Extra weld should be grinded off, and grinding should be within limits, otherwise excess
grinding results in weaken the joints.
- After grinding work for the edges completed, metal paste filling to be done for edges,
gaps and all corners.
b. Elevation Treatments-
a) Cornice
b) Fins
c) Jaliwork

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/31 FABRICATION AND ELEVATION WORK 00 123-124


Need to check the following points.
- Opening size V/s max size of manufacturing need to consider at design stage to provide
one piece product.
- Material to be finalize – GRC/FRP/Cat in situ.
- Mould if cast in situ – MS or along with Alu form only.
- Method of Fixing need to finalise in co ordination with vendor along with third party
certification for load carrying /pull out test & hardwares such as- Anchor fastner, screw,
etc . The same to be approve from RCC consultant.

Page 124 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Need to check the lifting & placing method – it is feasible or not , it should cast in single
or two parts.
- Easy approach for fixing & maintenance if any in future.

Painting works :
- Allow the metal paste to completely dry and using reputed emery paper, sanding to be
done to the nearest perfection.
- Always avoid chamfered or scaled edges and ensure all joints to be in perfect plane and
right angles.
- Check the dimensions of the opening by using right angle before fixing the window grill, it
is always better to take site measurement for grill making, in order to avoid uneven gaps
between grill and wall.
- Apply one coat of reputed brand of metal primer (Zinc oxide primer) using brush or
sprayer before grills being fixed in position.
- Ensure Brackets or side supports or hold fasts are placed in position before fixing the
railings or grills.
- Enamel Painting for grills and handrails to be done in two coats, after the completion
of external wall painting works.
- It is highly advisable to use Anchor bolts for concrete or block masonry instead of coach
screw.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/32 HAND RAILING, BALLUSTER WORK 00 125-126

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Fabricated Glass Panels
- Railings
- Brackets
- Anchor Fasteners

Page 125 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Base Plates
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Material Manufacturer Technical Specification
3. Tools and Equipment:
Drill, Screw Driver, Hammer, Tool box, Spanner, Anchor Fastener, Base Plates, Brackets, etc.
4. Work Procedure:
4.1. Off-site work:
- The Glass / Panel cladding or aluminium composite panel is received by fabrication
department in horizontally laid, type protected and evenly (to size) stacked sheets.
- The movements of materials are on roller controlled tables and marking / cutting /
grooving / folding/ rolling and assembly of angles to the ACP are done by skilled laborers
at the assembly tables to suit the fabrication orders that are in line with the shop
drawings.
- The items that flow the above said sequence of works include column cladding for items
- Highlighted while the other fabrication items less column cladding do not involve rolling.
Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
4.2. TRANSPORT / DELIVERY / STORAGE ON SITE
- The intimation for delivery is given to site 48 hours prior and the same is conducted in
proper procedure, where in the materials are packed on horizontally laid bed (trailer /
truck) with wooden supports as cushions to avoid damages.
- The loads are received and transported to an already assigned area, free of any
environmental conditions to damages the materials. Storage space is necessarily pre-
determined and free of potentially stamp and rough surfaces.
- Logistic team ensures delivery of it on site, to location of install hot before the exact day
of installation to avoid damages.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/32 HAND RAILING, BALLUSTER WORK 00 125-126

4.3. INSTALLATION
1. Pre installation
2. Installation
3. Post Installation

4.3.1. Pre Installation:

Page 126 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Preparatory activities include decadence of space of installation fixing of angles / brackets


/ supports / railing section for installation of cladding installation is performed in line with
the approved shop drawings.
- Ensure that all materials and accessories shall be approved and as per specification.
- Survey marking available and verified for bracket and mullion.
4.3.2. Installation of Railing / Glass Panels:
- Base plate shall be fixed properly by anchor fastener.
- Size of all railing / panels shall be checked before installation.
- Dimensions and coding / Specifications of baluster, glass panel / ACP to be as per
drawing.
- Bracket and mullion installation to be as per drawing and survey marking.
- S.S counter sunk through bolts, hexagonal socket screws, aluminium washers are fitted as
per drawing.
- S.S Pins, S.S Pan head self-tapping screw, isolator gasket, steel washers fitted as per
drawing.
- Aluminium handrail to the panel is fitted as per drawing.
- Approved thick laminated glass (heat strengthened) with ceramic frit at spandrel area
installed as per drawing.
- Radius of curvature of balustrade panels shall be as per drawing.
- EPDM Gasket fixing, Norton tape bonding and application of structural silicone sealant
and insulators placed as per specifications.
- Spacing to be maintained between column cladding panels and balustrade panels as per
drawing.
- Protection cover shall be removed from panels.
- Glass panels shall be fixed properly to avoid any damages during installation.
- Check line, level, and alignment of railing / panels before finalizing.
- QC Engineer will carry out an internal inspection.
- After clearance by DOSTI engineer shall proceed for grinding work, if required.
4.3.3. Post Installation:
- Protection to be provided for glass panels. Abro tape to be fixed of glass panel.
- Welded area to be finished proper.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/33 FAÇADE WORK 00 127-128

1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Fabricated Façade panels
- EPDM Gasket
- Railings
- Brackets

Page 127 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

- Anchor Fasteners
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Material Manufacturer Technical Specification
3. Tools and Equipment:
Drill Machine, Screw Driver, Hammer, Tool box, Spanner, Saw Cutter, etc.

4. Work Procedure:
4.1. Off-site work:
- The metal wall cladding or aluminium composite panel is received by fabrication
department in horizontally laid, type protected and evenly (to size) stacked sheets.
- The movements of materials are on roller controlled tables and marking / cutting /
grooving / folding/ rolling and assembly of angles to the ACP are done by skilled laborers
at the assembly tables to suit the fabrication orders that are in line with the shop
drawings.
- The items that flow the above said sequence of works include column cladding for items
- Highlighted while the other fabrication items less column cladding do not involve rolling.
Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
4.2. TRANSPORT / DELIVERY / STORAGE ON SITE
- The intimation for delivery is given to site 48 hours prior and the same is conducted in
proper procedure, where in the materials are packed on horizontally laid bed (trailer /
truck) with wooden supports as cushions to avoid damages.
- The loads are received and transported to an already assigned area, free of any
environmental conditions to damages the materials. Storage space is necessarily pre-
determined and free of potentially stamp and rough surfaces.
- Materials for all types of ACP less column cladding are stacked horizontally while the
column cladding materials are stored vertically.

REF NO PROCEDURE TITLE REV. NO PAGE NO

MS/33 FAÇADE WORK 00 127-128

- Logistic team ensures delivery of it on site, to location of install hot before the exact day
of installation to avoid damages.
4.3. INSTALLATION
1. Pre installation
2. Installation
3. Post Installation

Page 128 of 129


QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.

Document Name: Rev


Work Method Statements / Work Instructions R-0

4.3.1. Pre Installation:


- Preparatory activities include decadence of space of installation fixing of angles /
brackets / supports for installation of cladding installation is performed in line with the
approved shop drawings.
- The above are approved prior to delivery of panels to be able to proceed of installation
of the same.
4.3.2. Installation of cladding:
- The approved first fix or pre fix and works area is cleared of all deposits / left over on site
and any environmentally and hazards i.e. Oil / Water / etc. that may hamper / damage
materials.
- The panels will be taken to the location in horizontally and positioned vertically.
- The panel will be placed in the correct location and drilled and fixed to the first fix
ensuring grooves are properly matched and aligned.
- Same procedure will be repeated for the remaining panels.
- Other trades that are coordinated on the shop drawings are allowed to work as required
post the inspection of the works, installed and or received by SISJV.
- After completing the panel installation EPDM gasket will be inserted to the vertical
grove.
- QC Engineer will carry out an internal inspection.
4.3.3. Post Installation:
- Special protection tapes over the ACP panels are cleared only after reliant trades have
attended to these works and are cleared of any dust / any other activities within the area
of work.

Note: For glass façade work, separate methodology to be submitted by Contractor / Vendor /
Manufacturer for Dosti approval before work start.

Page 129 of 129

You might also like