Professional Documents
Culture Documents
Method Statement Manual
Method Statement Manual
Disclaimer: This document is the proprietary property of Dosti Realty Ltd. and is meant for its intended
purposes only. No part of this document shall be disclosed, reproduced, published or shared privately with
any third party without the prior written consent of an authorized officer.
Page 1 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
INDEX
Ref No Method Statement / Work Instruction Revision Page No
- TITLE PAGE 00 1
- INDEX 00 2-3
MS/A BASIC REQUIREMENT TO START “NEW SITE” 00 4-9
MS/B SURVEYING WORK 00 10-13
MS/C WBM ROAD WORK 00 14-17
MS/D COMMON GUIDELINES FOR ALL ACTIVITIES 00 18-20
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE 00 21-27
WORKS
WORK BELOW PLINTH LEVEL 28-45
MS/01 PILING WORK 00 28-33
MS/02 EXCAVATION WORK 00 34-36
MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING 00 37-38
AND PCC WORK
MS/04 PRESSURE RELEASE PIPE GROUTING 00 39-39
MS/05 BACKFILLING WORK 00 40-43
MS/06 ANTI-TERMITE WORK 00 44-45
CONCRETE RELATED WORK 46-53
MS/07 RCC WORK 00 46-47
MS/08 VACUUM DEWATERING FLOORING / TRUSS SCREED 00 48-52
FLOORING WORK
MS/09 RCC REPAIRING WORK 00 53-57
WATER-PROOFING WORK 58-72
MS/10 WATER-PROOFING WORK – RAFT, R/WALL AND LIFT PIT 00 58-59
MS/11 WATER-PROOFING WORK – TOILET, BATH, BALCONY 00 60-63
MS/12 WATER-PROOFING WORK – PLANTER, TERRACE, 00 64-67
LANDSCAPE, HARDSCAPE, SWIMMING POOL
MS/13 WATER-PROOFING WORK - UGT, STP, OHWT 00 68-70
MS/14 EXPANSION JOINT TREATMENT WORK 00 71-72
MASONRY WALL AND PLASTER WORK 73-81
MS/15 MASONRY WORK 00 73-75
MS/16 SAND MORTAR PLASTER WORK 00 76-78
MS/17 GYPSUM PLASTER WORK 00 79-81
BUILDING FINISHING WORK 82-97
MS/18 TILE / MARBLE AND CHINA CHIPS FLOORING WORK 00 82-84
MS/19 MARBLE & TILE CLADDING (DADO) WORK 00 85-86
MS/20 KITCHEN PLATFORM WORK 00 87-88
MS/21 DOOR AND WINDOW WORK 00 89-91
MS/22 SUSPENDED CEILING (FALSE CEILING ) WORK 00 92-93
MS/23 PUTTY WORK 00 94-95
Page 2 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Note: Additional activity based Method Statement will be added in next revision.
Page 3 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. INITIAL REQUIREMENTS
2. PREPARATION ON SITE
a. CLEANING SITE AND LEVELLING
- Before starting any work on site, cleaning of land, cutting unwanted trees/bushes should
be carried out with permission from T.M.C. / B.M.C. with specialised agencies for taking
all required Measurements correctly, for demarcation and layout.
- If large trees are obstructing proposed buildings or structures then necessary written
permission from corporation authority should be obtained for transplanting / cutting the
trees.
(Application to do well in advance as it requires times to get permission.)
- If any undulations or soil heaps are in the premises, these should be levelled by JCB.
Page 4 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
b. BOUNDARIES MARKING
- Before starting any work on site, Engineer In charge should demand for security services
of reputed company.
- A shed using G.I. sheet to be erected near the entrance of project or at convenient area
within site.
- This shed can be used for storing and stacking of all initial required tools, reports, and
office files.
- Boundary marking should be done by using stones fixed in concrete on each corner/every
turning point after specific distance.
- This stone should be painted in red oil paint. While doing this initial marking, reference
should be taken from existing boundary stones, some trees on boundaries, nallah bunds,
and initial enquiries with local people, etc.
- While doing this initial boundary marking on sites reaction of adjacent plot owners should
also be judged.
- Any minor disputes regarding measurement should be settled with consent from the
directors.
- A rough sketch of fixed boundaries to be prepared.
- Permanent boundary marking work should be started by doing Total station survey.
- Total station survey for actual demarcation should be done with reference to existing
boundaries.
- While doing this survey, all existing structures such as existing well, bore well, nearby
nallah, electric poles, high-tension line, trees, etc., should be shown on drawing.
- Demarcation drawing should be prepared in the office, which will be based on the field
survey.
- Comparisons of T.L.R.'s demarcation and architects drawings should be done by super
imposing the drawings.
- Major discrepancies should be reported to H. O.
- Architects will visit, inspect site and then finalize the revised demarcation.
- Based on this revised final demarked drawing, architect will prepare final layout of
buildings.
d. CONTOUR SURVEY
- Contour survey means to know the actual level i.e. ups and downs of the plot.
- Fix the permanent benchmark with reference to main road and approach road on the
existing main drainage chambers top, etc.
Page 5 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Engineer & Architect has to decide the grid interval 3 meter or 5 meter, as per the plot
condition.
- Grid interval depends on the plot conditions e.g. for plain ground, for sloping ground, for
steep ground, hilly areas.
- Then from collected data i.e. levels and interval distance. Surveyor will prepare the
contour map.
PLANNING FOR APPROACH ROADS AND TEMPORARY STRUCTURES / WATER STORAGE AND
OTHER STRUCTURES
Approach roads and internal roads are very important for vehicular transport.
- Approach roadside boundaries should be marked with lime powder or guard stones and
internal roads side margin/boundaries should be marked with lime powder or steel rods.
- Internal road distribution should be same as per sanctioned layout plan.
- In rainy season, if there is possibility of formation and accumulation of mud on road, it is
very important to construct W.B.M. roads in earlier seasons only.
- So that it cannot disturb work activities and material can be stocked undisturbed.
- On approach road as well as on the main road hoardings as well as way to boards, tree
guards with plants should be provided.
- Planning of approach road and other structures should be done in advance as per
sanctioned buildings layout so that no structure / road should obstruct proposed
buildings.
- Planning for the location of material hoist & passenger hoist.
- Consider the material stacking space for each building with free vehicular movement
without obstructing any temporary structures.
- This is very important otherwise what is normally observed shifting of temporary sheds
from one place to another to accommodate proposed permanent structures. This may
lead to considerable increase in cost due to improper advance planning.
Page 6 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
3. WATCHMAN CABIN
- Location nearest to main gate, facing the road direction from where more vehicular flow
is expected.
- Temporary office and stores at site will remain as it is till completion of the project means
that should not be demolished earlier
- Processing & Non Processing area need to confirm by Architects & sanctioned by
management.
5. WATER ARRANGEMENT
- If sufficient water from open Well Corporation or other authorities is not available then
taking bore well is advisable.
- If there is a shortage or non-availability of water then it is necessary to get the tropical
geological
- survey to find out the maximum ground water table for bore well purposes.
- Number of bore wells depends upon the requirement of water for the completion of the
project. (asper VASTU, N-E corner should select. Bore should not disturb bldg. structure.)
- After completion of the bore well, pump installation with temporary GI / PVC line is to be
laid up to the central water storage tank.
- Water should be sent for testing to find out various impurities, PH value, so as to use the
potable water for construction.
- Engineer should be aware about the pump, which depends on horizontal and vertical
growth of the project.
- Another pump should be installed over the temporary water storage tank so that we can
use the water for construction curing purposes.
- Selection of pump capacity should be done in such a way that same pump could be
shifted to other project constructional activities.
- Minimum one water outlet with gate valve should be provided in front of each building
for temporary water arrangement for proper curing and construction activity.
- Also water tank or UG Tanks as per dwg should construct to store water for construction
use in case of bore failure. One line of bore must be also found various impurities and
suitability for construction.
Page 7 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
6. ELECTRICITY ARRANGEMENT
- For this normally a three-phase meter is required for operating pumps, polishing
machines etc.
- The following documents should be submitted to the Electricity Board for getting new
connection
a) Application on A-1 form, b) 7/12 Abstract.
c) Copy of commencement certificate from Municipal Corporation. d) Copy of power of
attorney. e) Copy of sanctioned drawings from the corporation. f) Property tax receipt.
- The above procedure should be followed up with Electricity Board by concerned electrical
contractor.
- The assistant Engineer or Sub Engineer of the service connection department then will
visit the site for study of location for supply point.
- As per Electricity Board rules, meter location should be nearest to the point of supply.
- A meter room should be construct as per convenient.
- It is important to construct the compound wall at the beginning of the project; this
improves the overall security of the project. The construction of other structures like
watchman’s cabin, store,site offices, godowns, steel yards, etc.
- The compound wall boundary must be check as per T.L.R. & get approve from licence
dept.
- This activity can give ideas to the prospective customers and visitors
- For construction of the compound wall gate etc. proper drawing should be issued by the
Architect.
- After approval of this drawing the actual construction of compound wall begins.
- Provision for chain link fencing over M.S. angle should be made for security purposes.
8. GATE
- Only one entrance to the project or plot should be maintained to avoid theft, outgoing or
incoming materials, and site staff timing restrictions and to control the visitors or
customers entries to the site.
- If the main gate is not fixed at least a 'stop and start pole' should be used and which the
watchman will control.
- Once the compound wall and gate is complete, tree plantation should be done along the
fencing.
- This will result in a favourable impression in a perspective client's mind.
Page 8 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Before starting main building line out, the site engineer must confirm the actual
boundaries and check set back margins simultaneously in co ordination with Architect.
- Temporary makings of external building corners and other structures like under ground
water tank, swimming tank, etc. should be done with steel rods fixed with cement
concrete 15 cm above ground and painted with white oil paint.
- Cross check this marking with set back from actual plot boundaries.
- At this stage total buildings should be properly shown on layout with their set back as per
the given rule.
- This layout drawing should be approved by the architect and confirmed by the resident
architect.
- While checking this layout, mark open spaces and road portion on ground as per
approved layout drawings.
10. STORE/GODOWNS
- Store should be centrally located near all buildings and not obstruct any vehicular
movement as well as proposed permanent structure. Flooring of cement godown should
be raised 45 cm from existing ground level with smooth I.P.S. floor finishing.
- This being a temporary structure can be made from G.I. sheets or brick masonry to avoid
leakage in monsoon.
- It should be 100% water proof with two openings (so that old cement can be used first)
and perfect security.
- It should have sufficient capacity of storage.
- Sufficient light provision must be providing.
- Stock name board showing W M Y for each batch of material should be placed.
Page 9 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
Page 10 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 11 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 12 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Column control
- Three offset points or two lines are to be marked on the current slab defining the base of
the column.
Slab edge
- Survey points set out on the slab below each span are plumbed to the next level to
control the edge of slab form. Grid lines shall be established top of the slab prior to
casting and edges shall be marked and confirmed by representative of sub-contractors
precast department. Once slab been cast all grid lines to be marked by surveyor.
Accuracy
- At all times the aim is to achieve an accuracy of 5mm in relation to the secondary survey
control in setting the formwork at any one level. This applies to both horizontal and
vertical position.
Page 13 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Course Aggregate
Screenings (filler material)
Binding Material
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
b. Screenings :
- The material which is used up to fill up the excess voids present in the compacted layer of
course aggregate is called as screenings.
- Screening material is nothing but the aggregates of smaller size than the course
aggregates. Below table shows the standard grading required of screening for
construction of WBM road.
- In order to reduce the overall cost of WBM road, IRC has recommended to use non-plastic
materials such as kankar nodules, murum or gravel.
Page 14 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 15 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
V. Application of Screenings :
- After the rolling operation is properly finished screenings is applied to properly fill the
voids remained after the compaction of aggregates. The screening may be applied in 3 or
more layers as per the site conditions.
- After uniformly spreading of screening compaction is carried out with the help of dry
rollers for each layer of screenings. After compaction brooming of the each layer should
be properly done to remove the uncompacted screening material.
Page 16 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 17 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
A) Reference Documents:
Contractor –
As per work Order / BOQ, check the scope of the Contractor.
Responsible to prepare schedule and submit to Dosti for Approval.
At every inspection level, prior intimation to be given to Dosti for work inspection and
further approval.
Responsible to maintain all inspection and sample report and one sample to be submitted
to the Dosti.
Material Inspection should be done by contractor whether purchased by own or supplied
by the Dosti. Material inspection shall be witnessed by the Dosti.
Page 18 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Pre-Investigation Report
- Work Inspection Report
- Checklist for every inspection
- Concrete Log Sheet and Batch Sheet
- BBS
- Pour Plan
- Pour Card
- Area Marking Drawings
- Concrete Log sheet
- Batch Sheet
- Cube Test Register
- Material Samples
- In-House Material Test Report
- Non-Conformance / Observation Report
- 3rd Party Test Report
F) Quality Assurance and Quality Control:
Page 19 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
G) Acceptance Criteria:
- Use of PPE’s like safety shoes, dust masks, hand gloves, helmet, etc.
- Proper illumination to be provided for working during night.
- Material safety data sheet (MSDS) needs to be submitted prior start of work.
- Electrical equipment’s and machinery should have tag with month color code.
- Safety risk assessment shall be submitted separately for all work activities.
- Pile driving, Rebar cage lowering, concreting and casing extraction should be constantly
supervised.
- Rigs shall be moved on level and uniform ground.
- Welding and gas cutting activities must ensure safety compliance, like availability of
flash-back arrestor, double earthing for welding machine, separate identifications for
oxygen and DA hose etc.
- Proper housekeeping, Maintenance of piling rig is mandatory.
- Regular tool box meeting should be conducted.
Page 20 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
- Concrete Mix shall be designed as per required grades and to ensure that the concrete
will fulfill all project requirements. Concrete Mix Design shall be undertaken as per the IS
10262.
- Preliminary Concrete Mix Designs and necessary test shall be carried out to achieve
controlled concrete of desired Quality, Density, Durability and Strength.
- If required, Concrete Mix Design trial to be taken before finalization of Mix Design to
check performance of the Mix.
- Concrete Mix Design shall be submitted by the RMC Vendor or Contractor for approval
along with all concrete ingredients test details, all in aggregates graph and detail Concrete
Mix Design calculation.
- For out-side RMC Supplier and Vendors following procedure shall be adopted
o Trial mix of proposed grade shall be witnessed by QC / Site Engineer and record
the results for final Concrete Mix Design approval.
o RMC Plant visit shall be done by QC Engineer / Manager to verify RMC QC process,
In-house testing of material, lab set-up, calibration of plant and lab equipment’s,
etc.
o Witness the fresh concrete sampling at RMC plant for carry out fresh concrete test
and also for cube casting.
o Witness and monitor cube casting and shall be marked for test witness.
Page 21 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
B. Clearance for Concreting:
The pour card shall be completed with approved pour plan, Work Inspection Report and
checklist of formwork and duly signed and certified by Site Engineer / QA QC Engineer
before starting of concrete.
C. Concrete Requisition:
- 24 hrs. Prior to the planned pour following detail / requirements to be submitted to the
concerned person or department.
- Location, Structure Details, Quantity, Grade of Concrete, Data and Time of Pour, Slump /
Flow requirements at field, Pouring Method, Name and Contact Number of responsible
person shall be mentioned in requisition request.
- If cement sand slurry required for pumping operation, mention separately.
Page 22 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
- All equipment’s used for transportation and placing of concrete will be thoroughly
cleaned and maintained properly after each period of placement.
E. QAQC Inspection and Acceptance at Site:
- Once the concrete arrives at site the details of delivery challan shall be verified by
Engineer and then check for fresh concrete properties like slump / flow, temperature,
cohesiveness etc.
- On unloading of concrete Site Supervisor / Site Engineer shall sign the delivery challan for
acceptance of concrete with date and time.
- Pouring / Concrete Log Sheet shall be maintained during concreting and shall be
sign/certified by Site and QA QC Engineer.
- Re-dosing shall be as per Concrete Mix Design approval.
F. Placing:
- Pour sequence shall be approved before work commencement.
- While planning the pour depending upon the area and quantity the following points is to
be considered.
o Rate of Pour of concrete
o No. of Masons required
o No. of Vibrators Required
o Area Lighting
o Proper Access
o Concrete placement – Crane/Manual/Pump
- As per drawing/specification construction joint shall be provided and treated properly.
- The mix after discharging from the transit mixer shall be transported by wheel barrows,
buckets, pump’s, etc. without causing segregation and loss of cement slurry and without
altering its desired properties, with regards to water cement ratio, slump, cohesion and
homogeneity.
- Precaution shall be taken during raining season to avoid surface run-off or direct rain
water contaminations in the concrete pour. Plastic sheet / shade shall be provided.
- Concrete will be deposited in successive layers to its final position, as nearly as
practicable, to avoid segregation due to re-handling.
- The concrete shall be placed and compacted before initial setting of concrete commences
and each layer of concrete shall be compacted fully before the succeeding layer in placed.
- For locations where direct placement is not possible and in particular through narrow
forms, suitable drop chutes will be provided to confine the concrete in movement.
- To avoid cold joints casting is to be planned in such a manner to cover all the grids.
Page 23 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
G. Compaction:
- Each layer of fresh concrete shall be thoroughly compacted by mechanical vibrators to
the minimum practicable consolidated volume.
- The concrete to be vibrated shall be placed in position in level layers of suitable thickness
not greater than the effective length of the vibrating needle.
- Vibrator needle shall be inserted vertically inside the Concrete and shall be allowed to
penetrate through by its own weight. Vibration shall not be stopped when needle is
immersed in concrete.
- The vibrator shall penetrate fully into the layer being placed and also penetrate about 100
to 200 mm or as required in the already consolidated lower layer for good bond and
homogeneity between the two layers and to prevent the formation of cold joints. The
vibrators shall be withdrawn slowly out of the concrete so as to allow the concrete to flow
back into the hole behind the vibrator.
- The specified spacing between the inserting positions shall be maintained uniformly
throughout the surface of concrete so that the concrete is uniformly vibrated.
- The spacing shall provide some overlapping of the area vibrated at each insertion. It is
better insert the vibrating head at a number of places than to leave it at one place for a
long time.
- Vibrator shall be prevented from coming into contact with the shuttering sides,
embedded parts, etc. under and over vibration shall be avoided.
H. Concrete Finishing:
- Finish concrete surface should be as per specified in the approved construction drawing
and specification. Recommended dip broom finish unless specified in specifications.
I. Curing Of Concrete:
- The curing shall be started immediately after initial setting start and same shall be
continued for a minimum of 7 days for OPC cement and 10 days for blended cement.
- Exposed surface of concrete shall be kept in a damp or wet condition by ponding or by
covering with a layer of hessian cloth, gunny bags or similar materials.
- The curing water shall be the same as that is used for construction purpose.
- At time of high ambient temperature cover with wet Hessian cloth and Commence
continuous curing in at regular interval to keep in wet condition.
- If wish to curing by Curing compound, then separate approval to be taken from Dosti
Quality Department.
Page 24 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
J. Sampling and Strength of Concrete:
- Sample from fresh concrete shall be taken as per IS 1199 & ITP, and cubes shall be cast,
cured and tested in accordance with IS 516 and IS 456.
- In order to get relatively quicker idea of the quality of concrete, optional test of
compressive strength at 7 and 14 days or as specified out in addition to the 28 days
compressive strength.
- Other Third Party Test shall be carried out as per ITP / QUALITY PLAN.
K. Reinforcement:
- Grade and make of reinforcement steel, coupler splices etc. shall be as per project
specification / approvals.
- Steel / coupler should be passed all in-house and third party test before cutting / bending
/ laying.
- Reinforcement shall be clean and free from rust, mud and oil.
- Reinforcement shall conform to the details given in the approved bar bending schedule
and as per approved drawings.
- Reinforcement shall be checked for correct position and for tying. Hooks and bends are
placed as specified by drawings. Lap length and lap zone is accurate & staggered and
anchorage checked.
- Reinforcement verticality / alignment shall be checked at regular interval / distance.
- Coupler fixed and tight for splicing and Coupler location are Staggered.
- Number, size and anchorage of stirrups as per drawing.
- Spacing and arrangement of stirrups and anchorage as per drawing.
- It shall also be checked for the size of bars, spacing between bars, welding or splicing (also
with coupler), binding wire bent inside, enough chairs and cover blocks kept in proper
position. Suitable good Quality binding wire shall be used.
- Treatment shall be done on dowels kept for further work.
- If required rebar grouting shall be done as per approved material and approved method.
- Reinforcement inspection record shall be maintained with Work Inspection Request (WIR)
& Checklist.
- Approved and same grade of cover block with correct size and spacing.
Page 25 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
Page 26 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/E COMMON GUIDELINES FOR ALL TYPE OF CONCRETE RELATED WORK 00 21-27
P. Post-pour Inspection:
- Visual / measurable inspection of concrete member / structure shall be done after de-
shuttering for the checks of surface irregularities, honey-comb, cracks, etc. carried out as
per post pour inspection checklist.
- Observation / Snags to be handed over to the Contractor for their compliance with their
acceptance and projected compliance date.
- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer / Dosti Site Engineer. Repair shall be done as per approved methodology; not
following this protocol shall result in NCR being issued.
Page 27 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Concrete and Concrete Ingredients (Cement, Fly Ash, GGBS, Micro-silica, Fine and Coarse
Aggregate, Water, Admixtures, etc.)
Concrete
The grade of concrete shall not be less than M-30 with minimum cement content of
400 kg / m3.
Steel
Binding Wire
Cover Block / Spacers
Liner
Bentonite
Page 28 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
9.1 Pre-checks/ Preparation:
- Prior to start any activity on site, the consulting / responsible Dosti Engineer must be
notified.
- Ensure loose Soil compacted and compaction testing certified prior starting piling.
- Contractor - Discuss the method of working with all Dosti as well as Contractor Engineers
& Supervisors.
- All the related documents such as Work Order, Concrete Mix Design, GFC / Shop
Drawings, Method Statement, Material Approval, etc. must be approved and available
upon request.
- Ensure the approved source of ready mix Concrete and grade of concrete.
- Cube Mould, Thermometer, Slump Cone, Flow Table, etc. shall be arranged prior to the
concreting operation.
- Arrange the concrete testing area with proper shading and lighting.
9.2 Excavation of Pile Shaft:
- The capacity of the rig shall be adequate so as to reach the desired depth. Discuss with
Dosti Engineer before start of work.
- Provision shall be kept for chiseling within the borehole in case of any underground
obstruction / hard strata. However, chiseling shall be carried out only with the approval
of DOSTI/Consultant.
- In case pile is required to be socketed in medium or good quality rock strata, the
equipment mobilized shall have adequate capability to do so up to the required socket
length. From the purpose of classification of rock for the determination of length of
socketing, pilot drill holes shall be carried out in the areas to be piled.
- Rock drilling shall be carried out using double tube core barrel. Drilling and storing of rock
cores shall conform to relevant IS codes.
- The piles shall be installed as accurately as possible as per the designs and drawings. The
permissible positional deviations shall be governed by IS: 2911 (Part I /Sec.2). In case of
piles deviating beyond such permissible limits, the piles shall be replaced or
supplemented by additional piles, as directed by DOSTI/Consultant.
Page 29 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 30 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 31 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 32 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 33 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
The Contractor shall deploy any or all of the following resources as dictated by the volume and
nature of excavation.
2.1. Tools & tackles for manual Excavation
- Spade.
- Crow-bar
- Shovel
- Basket
2.2. Plant & Machinery for Mechanized Excavation
- Excavators / Rock Cutters
- Dumper
- Jack hammer
- De watering Pumps
2.3. Other
- Surveying equipment, trowel, etc.
3. Work Procedure:
All the material that can be easily excavated by mechanical equipment as described in
hereunder.
Page 34 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 35 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 36 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING AND PCC WORK 00 37-38
1. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
- IS 12269- 1987 - OPC cement
- IS 1489 - 1991 - PPC cement
- IS 383-1970 - Specification for Coarse and Fine Aggregates from Natural Sources
for Concrete
- IS 2386 - 1963 - Methods of Test for Aggregates for Concrete
(Part 1 – 8)
- IS 516-1959- Methods of Tests for Strength of Concrete
- IS 1199-1959 - Methods of Sampling and Analysis of Concrete
- IS 3812-2003 - Specification for Fly Ash for use as Pozzolana and Admixture
- IS 4926-2003- Ready-Mixed Concrete — Code of Practice
- IS 4990 - 1993 - Plywood for Concrete Shuttering Work - Specification
- IS 10262 - 1982- Concrete Mix Proportioning - Guidelines
- IS 2502-1963- Code of Practice for Bending and Fixing of Bars for Concrete
Reinforcement
- IS 9103 – 1999 - Concrete Admixtures – Specification
3. Work Procedure:
9.1 Pre-checks/ Preparation:
- Prior to start any activity on site, the Site Engineer must be notified.
- Ensure that all workers are aware of the evacuation plan. Cordon off the work area.
- Discuss the method of working with all supervisors as per approved pour plan.
- Ensure soil compaction test certificate before Soling / Plum Concrete / PCC work, if
required.
- Anti-termite treatment should be done before concreting.
- Stand by mechanical equipment’s shall be checked for emergency break-down happened
like Concrete Pump, Mechanical Vibrator, Power Floater, etc.
Page 37 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
MS/03 RUBBLE SOLING, PLUM CONCRETE, ROCK ANCHORING AND PCC WORK 00 37-38
- All the related documents such as Concrete Mix Design, Shop Drawings, Method
Statement, Material Approval, Pour Plan, Pour Card and Inspection Checklists, etc. must
be approved and available upon request.
- Cube Moulds, Thermometer, Slump Cone, Flow Table, etc. shall be arranged prior to the
concreting operation.
- Any accumulated rainwater shall be pumped from the spill collection sump or bailed out
only under controlled circumstances and if contaminated, should be disposed of in
accordance with legislation.
- Clean the Excavation formation and remove the loose materials. Leveling & proper
dimension should be checked as per the approved drawings.
9.2 Rubble Soling Work Procedure
- Fix the 10mm or 12mm bar at 5m or 10m interval and mark all levels on it like Footing
PCC Top, Bottom Level of PCC, Top Level of Rubble Soling, Bottom Level of Rubble Soling,
etc.
- Start laying of stone as per your given standards, generally, all are preferred “Rubble
Soling” Where we need to keep all the stone should be dense, and minimum gaps are
kept between them and fix the small stone chips in the gaps of stones.
- Fix Line Dori to the marked bar at the top level of Rubble soling. And lay all the area as per
the marking, if any stone height is more than your desired height then it should be cut by
the hammer.
9.3 Plum Concrete Work Procedure
- The volume of the plum from the concrete will not exceed 40% (percent) of overall
volume.
- Plum will comprise of black trap basalt of crushing strength of minimum 100 Kg /Sq.cm.
- Plum concrete density 1650 kg/Cubic.meter
- Each layer plum concert maximum height 900mm did not exceed more hight in one layer
- NO two stones are closer than 150mm to each other either sideway or bottom to the top
layer.
9.4 Work Procedure for Rock Anchoring for Raft Foundation:
- Ensure design received from consultant for rock anchoring.
- Achieve depth of anchor hole and check depth, location, alignment of Anchor whole as
per GFC / Design.
- Place reinforcement in anchor hole and grout with approved material.
- Pull-out test to be carried out to check the designed load.
9.1 PCC Work Procedure
- Wherever necessary, Fix Shuttering where PCC to be laid.
- Surface should be saturated and free from foreign particles.
- Provide proper level pads for level before starting PCC.
Place the PCC, spread it by panja or spade & Compact by rammers/wooden batten with handle in
both ends & Level it.
Page 38 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 39 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Murum / Soil
Controlled Low Strength Material (CLSM)
A controlled low-strength material (CLSM) is a self-consolidating, cementing material
used primarily as a backfill as an alternative to compacted fill. Many terms have been
used to describe this material, including flow-able fill, un-shrink-able fill, controlled
density fill, flow-able mortar, plastic soil-cement, and soil-cement slurry; however, the
correct terminology is controlled low-strength material.
Work shall be carried out as per following specifications / standards / code and / or others
as applicable.
- IS 1200 (PART 1)-1992 - Methods of Measurement of Building and Civil
Engineering Works - Earthwork
- IS 2720 - Methods of Test for Soils
PART 2: 1983 - Determination of Water Content.
PART 7: 1980 - Determination of Water Content - Dry Density relation
using light compaction
PART 8: 1983 - Determination of Water Content - Dry Density relation
using heavy compaction
PART 28: 1974 - Determination of Dry Density of Soils in place by the Sand
Replacement Method.
PART 29: 1975- Determination of Dry Density of Soils in place by the Core
Cutters Method
- IS 3764 - 1992 - Safety Code for Excavation Work.
- ACI 229R-99 - Controlled low strength materials
4. Work Procedure:
- The Site Engineer shall ensure that the material to be used for backfilling is in accordance
with the relevant Specification.
Page 40 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 41 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Inspection shall be done by Site Engineer when the specified levels/limits of backfilling are
reached.
- Site Engineer shall check the backfilling process-using Checklist for backfilling.
- The Project Manager shall ensure that sufficient quantity of Machineries’, Material &
Manpower is available to execute specified job as per construction Master schedule &
Joint measurements to be taken for record purpose
Quality Control of Backfill
- Prior to carrying out filling Project Team shall carry out sufficient laboratory moisture -
density tests to evaluate compaction. From these tests, the maximum dry density and
optimum moisture content for the approved fill material shall be determined.
- The laboratory tests shall be in accordance with Indian Standards IS:2720 - Parts 2, 7 and
8. Based on the type of soil, suitable test shall be adopted.
- When earth filling is being carried out field tests shall be carried out at various stages to
ensure that adequate compaction is being achieved. The field tests shall be in accordance
with IS:2720, Part 28 and 29.
- The compacted surface shall be carried out to the dimensions and levels as indicated on
the drawing within a tolerance of ± 25 mm.
- Frequency of Field Density Tests to ensure adequate Quality Control on compaction of
earth fill, the following minimum number of field density tests or directed by the Site
Engineer / instructed by the consultant shall be performed.
o One test for every 500 cubic meters of fill material placed for fill construction in
site grading.
Page 42 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 43 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
Page 44 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- This treatment will start after the foundation and the plinth beam work is over. The
treatment shall be carried out as below.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 45 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 46 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
- Ensure all guidelines listed in above for concrete activities. (Page NO 18-27)
- Recommended only one RMC manufacturer / supplier for individual casting.
- Level to be ensured before start of pouring of concrete.
- Ensure pouring sequence and monitor concrete pouring rate.
- Height of pouring concrete should not exceed 1.5 m.
- Construction joint should be avoided in the column.
- Proper cover as per structural drawings to be maintained.
Page 47 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Concrete and Concrete Ingredients (Cement, Fly Ash, GGBS, Micro-silica, Fine and Coarse
Aggregate, Water, Admixtures, etc.)
Shuttering / MS Channels
Shuttering Oil
Curing Compound
Construction / Joint filler
RMC Material Source / Brand, Concrete Mix Design, RMC Vendors / Suppliers shall be
approved.
Sealant
Bonding Agent
PP Fibers
Floor Hardener
Isolation Sheet
Page 48 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
9.1 Formwork:-
- Initial suitable layout of construction joints and isolation joints shall be decided prior to
start of vacuum dewatering flooring work. (As per approved ridge line drawings)
- Approved Pour sequence, Treatment of construction joint etc. will be followed as per GFC
Drawing /Engineer In-Charge.
- All formwork material shall be approved prior to work start.
- Two side track rails (mild steel arrangement) to be provided with required level and
gradient on which the leveling beam and surface vibrator would be erected. The surface
of the MS channels guides (on which the surface vibrator is supported) shall be cleaned
from concrete. Align the guide channels to true line and level. Panel casting layout shall
be strictly followed as per layout of construction joint.
- While fixing shutter space of at least 1 feet shall be left from walls. This will help to facility
the movement of person operating the machine.
- Stop ends to be provided for both ends with MS arrangement or equivalent. Area of pour
will be decided as per site condition and direction of client engineer.
9.2 Embedded Items:-
- All Inserts of any kind like, sleeves, pipes, bolts and nuts, anchor bolts, MEP conduits, etc.
are to be accurately placed as per approved drawing and tied properly to avoid any
displacement during concreting, get clarification / confirmation from MEP / concerned
engineer.
9.3 Pre-checks/ Preparation:-
- Prior to start any activity on site, the Site Engineer must be notified.
- The base concrete surface shall be thoroughly cleaned and dusted off by water Jet Spray
or Air Compressor. All dead mortar, loose concrete, dust, dirt, scales smoke splashes,
mortar droppings and grease shall be thoroughly removed before started the work.
Page 49 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- All major honey comb, damaged surfaces and cracks of main RCC structure should be
repaired.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 50 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- The mix after discharging from the transit mixer shall be transported by wheel barrows,
buckets, pump’s, etc. without causing segregation and loss of cement slurry and without
Page 51 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Continuing the above process the surface vibrator to be run for the second time along
with leveling on the finished concrete surface.
- Immediately after leveling, the concrete shall be compacted / treated with truss vibrator
or immediate start dewatering by vacuum sheet to dewater excess water.
Page 52 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Groove shall be cut by mechanical saw within 72hrs or as soon as concrete is ready to
accept the saw cut.
- Fill the grooves with approved bitumen or bitumen sealant/Polysulphide sealant or as per
project specification.
- Groove cleaning and drying needs to be ensured.
REF NO PROCEDURE TITLE REV. NO PAGE NO
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Repairing Material
Shuttering Ply / Shuttering Scheme
Shuttering Oil
Curing Compound
Bonding Agent
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
IS 456-2000 - Plain and Reinforced Concrete - Code of Practice
IS 12269 - 1987 - OPC cement
IS 1489 - 1991 - PPC cement
IS 516 – 1959 - Methods of Tests for Strength of Concrete
IS 13311 – 1992 – Non Destructive Testing of Concrete – Method of Test
4. Work Procedure:
- Ensure Corrective Action (CA) and Preventive Action (PA) Should be submitted to the
Dosti Site Team / Quality team for their approval. Only after approval of CAPA repairing
work can start
- The surface preparation of the concrete to be repaired and the mixing, application and
curing of the repair mortars/ micro-Concrete/Cementitious grout/epoxy grout/PU grout
Page 53 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 54 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Where detection of a possible continuation of the crack with water filling is not possible
(on vertical faces) the crack repair shall be discussed between DOSTI and the Contractor,
looking for similarities with horizontal cracks in the same area.
- Where similarities are not found and/or agreed the crack shall be deemed to be deep and
injected with epoxy and the V-cut further repaired/sealed as per above.
- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/09 RCC REPAIRING WORK 00 53-57
Page 55 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.
- Areas where after removal of the defective concrete the rebar becomes exposed and/or
where the extend of the repair is such that formwork has to be used are defined as Major
honeycomb.
- Identify the loose concrete and honey combs areas of the defective areas.
- The area shall be cleaned with compressed air and shall be washed out by clean water.
- If the defective concrete extends to the rebar a clear gap of at least 20mm shall be
created behind the rear face of the rebar, such that a gloved hand can comfortably reach
behind the main bars.
- All exposed rebar shall be carefully cleaned by wire brushing before the repair and the
concrete faces to be scrabbled and wetted as per requirement/recommendation of the
manufacturer of the repair micro concrete.
- All the concrete dust that left over is then washed away with water or blown away using
compressed air. This is to ensure good bonding between the concrete and there repair
material.
- Ensure that the surface is free from oil, grease or any loose material.
- If honey-comb seems as a major structural defect i.e. not enclosed by a circle of 50mm
and / or where the concrete cover has been reduced by more than 50 mm the issue to be
raised to the Consultant for further clarification / action.
Page 56 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- NDT test to be carried out to check repairing. Both UPV and RH recommended to verify
the repairing work.
- Identify Structure / area the where Uneven Casting / Bulging / deviation in size found.
- Mark the defective area, consults to Project Head / Quality Head for further correction /
rectification.
- If defect seems as a major structural defect i.e. bulging more than 25 mm, deviate from
size / shape / location by more than 15mm or other deviation from the approved project
specifications, the issue to be raised to the Consultant for further clarification / action.
- The affected defective area shall be hammered or chiseled to cut / break in a straight in
horizontal / vertical line and shall be cleaned, brushed, to remove all the loose concrete
and small particles such as sand.
- Remove all PVC pipes / Wall Tie Sleeves or temporary material from the main structure.
- The area shall be cleaned with compressed air and shall be washed out by clean water.
- Tie-rod / Wall Tie hole shall be filled by an approved shrinkage controlled structural grade
cementitious mortar system as per manufacturer technical specifications.
- Check for water leakage test by running water for 02 days at regular interval.
Page 57 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Visual / measurable inspection of concrete member / structure shall be done after de-
shuttering for the checks of surface irregularities, honey-comb, cracks, major deflections,
bulging, etc. carried out as per post pour inspection checklist.
- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Cement (OPC / PPC)
Sand (River / Crushed / Silpoze)
Bricks / AAC Blocks
Fiber Mesh
Ready Mix Repairing Mortar
Water-Proofing Compound / Membrane
Page 58 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
If method statement submitted by the Water-Proofing contractor to Dosti Approval prior to start
of the work, then Approved contractor method statement to be implement at site.
9.1 Pre-Check:
- For Night Work water-proofing work permission to be taken from Site Engineer prior to
work start.
- Check RCC/ PCC / Civil work completed wherever required.
- Clearance from MEP (Services) department, if required.
- Ensure all material for waterproofing available at site with required quantity.
- Highly undulated surface and major repair to be complete prior.
Page 59 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Cement (OPC / PPC)
Sand (River / Crushed / Silpoze)
Bricks
Fiber Mesh
Ready Mixed Non-Shrink Repairing Mortar
Pipe Penetration Sealant
Water-proofing Compound
Page 60 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud
Pan, Bucket, Measuring Jar, Float, Wire Brush, Grinder, Chisel, Hammer, Blower,
Pressure Grouting, Measuring Tape, Spirit Level, Plumb Bob, Weigh Balance, etc.
4. Work Procedure:
9.15 Work Procedure:
9.15.1 Surface Preparation.
- Highly undulated surface and major repair to be complete prior.
- Level to be shifted from reference point to all toilets / bath and rooms before proceeding
for work
- Surface to be treated must be workable dry and free from oil grease and foreign particles.
- All laitance, loose and foreign particles shall be removed by wire brush or mechanical
scrubbing.
- All honey-comb, highly undulated, damaged surfaces and cracks should be repaired.
- Injection grouting at all major honeycombed portions and construction joints shall be
carried out, if necessary, after physical observation
- Coving shall be done at the all corners by Ready Mix Repairing mortar and shall be
grouted properly before application of Water-roofing.
- Area shall be tested for 3 days by ponding, to test for leakages and to serve water hungry
concrete surface.
- In case of major leakage, gravity grouting or pressure grouting shall be resorted to stop
leakages. Grouting to be done as per manufacturers specification.
- Levels of water-proofing shall be clearly marked on the walls with slope towards outlet, as
specified in drawing or minimum 1:100 otherwise.
- Check for any steel or cut end of rebar is exposed at top of slab. If exposed steel is seen
that concrete is to be chiseled off to the depth of 25mm around exposed steel. Steel to be
cut with cutter or grinder 25mm below slab top surface. Slab to be restored with polymer
mortar prepared as per manufacturers specification and cure for 3 days.
- Treatment to cutouts / Outlet pipes to done by using seal tape, polymer modified mortar
or grout.
9.15.2 Procedure:
- Prepare the chemical mix by slowly pouring the powder component in liquid polymer
component or as per manufacturer’s recommendation. Mixing shall be done by using a
suitable mechanical impeller only. Achieve a brush-able paste. Ensure pot life material for
consumption of material.
- Apply 1st coat by brush/roller on the surface evenly. After application it should be left for
4 to 5 hrs for drying & setting or re-coat-able time recommended by manufacturer.
Page 61 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Prepare more mix as above and apply second coat after drying of first coat. Preferably
apply the second coat in right angle direction to first coat. Allow the second coat to dry
for 4 to 5 hours or recommended by manufacturer.
- Application of chemical waterproofing coat shall be extended up to 1.OO mtr. On wall.
- Ensure that material has been consumed as per specified quantities mentioned in
technical data sheets for the concerned material use.
- Post application moist curing shall be done for 3 days.
- If required Sand Broadcasting shall be done on Water-proofing membrane to provide
mechanical key for further finishes.
Page 62 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Application of brick-bats shall proceed from one corner and shall be laid in radial pattern /
straight pattern to drain of any water which has seeped through. Level Pads for the same
shall be given by Site Engineer, considering into account adequate slope.
- The brickbat Layer shall then be cured for minimum 3 days by ponding.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound till top of brick-bats.
- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- Plaster work shall be done by cement sand mortar in the proportion 1:4 with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
REF NO PROCEDURE TITLE REV. NO PAGE NO
- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.
2. Water-proofing coating
Page 63 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Cement (OPC / PPC)
Sand (River / Crushed / Silpoze)
Bricks
Fiber Mesh
Geotextile Sheet
Water-proofing Compound
Page 64 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
If method statement submitted by the Water-Proofing contractor to Dosti Approval prior to start
of the work, then Approved contractor method statement to be implement at site.
9.16 Pre-Check:
- Prior to start any activity on site, the consulting engineer must be notifying.
- RCC and Civil work complete in all respect. No repairing work pending before handed-
over to Water-proofing agency.
- Clearance from MEP (Services) department.
- Ensure all material for waterproofing available.
Page 65 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- For Cementitious/crystalline chemical coat: Prepare the chemical mix by slowly pouring
the powder component in liquid polymer component or as per manufacturer’s
recommendation. Mixing shall be done by using a suitable mechanical impeller only.
Achieve a brush-able paste. Only paste which can be consumed in half hour shall be
made.
- Apply first coat of paste by brush / roller on the surface evenly. After application it should
be left for 4 to 5 hours for drying & setting or re-coat-able time recommended by
manufacturer.
- Prepare more mix as above and apply second coat after drying of first coat. Preferably
apply the second coat in right angle direction to first coat. Allow the second coat to dry
for 4 to 5 hours.
Page 66 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Bricks selected for using as brick bat coba shall be either full brick or 3/4th brick made out
of one complete brick by breaking into required size, using mallets.
- Brick bat shall not be stored in the form of a heap at one place and soaked thoroughly for
about 45 minutes prior to their placing. For AAC / Light Weight block shall be dipped in
water before placing.
- Use of plasticizer in mortars is recommended to increase workability as per
manufacturer’s specifications. Mortar mixed shall be used within 1 Hour of preparation.
- Presoaked brick-bats shall then be laid in straight / radial, by inserting brickbats to a
depth of about 15mm by light tamping with the help of mallets. Thickness between
adjacent layers of brickbats shall not exceed 25mm.
- Application of brick-bats shall proceed from one corner and shall be laid in radial pattern /
straight pattern to drain of any water which has seeped through. Level Pads for the same
shall be given by Site Engineer, considering into account adequate slope.
REF NO PROCEDURE TITLE REV. NO PAGE NO
WATER-PROOFING WORK – PLANTER, TERRACE, LANDSCAPE, HARDSCAPE,
MS/12 00 64-67
SWIMMING POOL
- The brickbat Layer shall then be cured for minimum 3 days by ponding.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound or Screed till top of brick-
bats.
- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- For PU Water-proofing application, sand broadcasting to be done immediate after final
coating of compound to give mechanical key for plaster work.
- Plaster work shall be done by cement sand mortar in the proportion 1:3 with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.
Page 67 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Cement (OPC / PPC)
Sand (River / Crushed / Silpoze)
Fiber Mesh
Water-proofing Compound
Page 68 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Prior to start any activity on site, the consulting engineer must be notifying.
- RCC and Civil work complete in all respect. No repairing work pending before handed-
over to Water-proofing agency.
- Clearance from MEP (Services) department.
- Ensure all material for waterproofing available.
- Highly undulated surface and major repair to be complete prior.
9.19 Work Procedure:
9.19.1 Surface Preparation:
- Surface to be treated must be workable dry and free from oil grease and foreign particles.
- All laitance, loose and foreign particles shall be removed by mechanical scrubbing only.
- All honey comb, highly undulated, damaged surfaces and cracks should be repaired by
using approved repairing material
- Injection grouting at all major honeycombed portions / construction joints shall be carried
out, if necessary, after physical observation
- All the shuttering wall tie holes shall be grouted with non-shrink grout.
- Area shall be cured for at least 3 days by ponding, to test for leakages and to serve water
hungry concrete surface. Ensure 100 % Water to be stored for pre-ponding.
- In case of major leakage, gravity grouting or pressure grouting shall be resorted to stop
leakages. Grouting to be done as per manufacturers specification.
- Levels of water-proofing shall be clearly marked on the walls with slope towards outlet, as
specified in drawing or minimum 1:100 otherwise.
- Check for any steel or cut end of rebar is exposed at top of slab. If exposed steel is seen
that concrete is to be chiseled off to the depth of 25mm around exposed steel. Steel to be
cut with cutter or grinder 25mm below slab top surface. Slab to be restored with polymer
mortar prepared as per manufacturers specification and cure for 3 days.
- Coving shall be done at the all corners by Ready Mix Repairing mortar and shall be
grouted properly before application of Water-roofing.
9.19.2 Procedure:
- Install coving at horizontal and vertical corners using polymer modified mortar or using
CM 1:4 with admixed at a dosage of manufacturer recommendation per bag of 50 kg
cement at required thickness, finishing in half round or fillet in shape.
- Application of chemical waterproofing coat (crystalline / elastomeric / polymer / PU etc.)
can be done, entire inner structure before base coat. Prefer food grade coating.
- Base coat using cement mortar in proportion 1:4 or as specified by QA Department with
approved waterproofing compound shall be applied over top of base slab. Maximum
thickness of base coat shall be 25 mm at upper end of slope.
Page 69 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Proper slope shall be given to base coat as per drawing towards drain spout and drain
spout to be fitted simultaneously with the base coat, as an additional precaution to take
care of seepage, if any. Base coat shall also be applied to the sides of the wall up to one
meter or as specified above the finished floor level (F.F.L) of the adjacent floor.
- Drain pipe mouth shall be fitted with PVC grating or filter media form inside and chicken
mesh / wire mesh from outside.
- Curing of base coat shall be done by ponding for 3 days and checked against leakage.
Leakage, if observed, shall be rendered with reapplication of base coat to ensure no
leakage.
- After curing is over, the surface shall be applied with a finishing coat of cement sand
mortar in the proportion 1:4 with water-proofing compound.
-
REF NO PROCEDURE TITLE REV. NO PAGE NO
- Top coat shall be of neat cement slurry of adequate consistency and shall be monolithic
with brick-bats.
- For PU Water-proofing application, sand broadcasting to be done immediate after final
coating of compound to give mechanical key for plaster work.
- For UGT/OWHT food grade paint or tiling should be applied from internal side as top layer
of a system.
- For STP coal tar epoxy coating shall be done from internal sides of the walls.
- Soffits of all the structures shall be treated by using appropriate waterproofing system.
- Top of the slab shall be make waterproofed by application of chemical waterproofing coat
(crystalline / elastomeric / polymer / PU etc.) .Protection screed shall be provided to the
treatment.
- Terminate the edge of the membranes as per manufacturer technical specification.
- Plaster work shall be done by cement sand mortar in the proportion 1:4with water-
proofing compound on vertical surface.
- Finished surface shall then be cured for at least 7 days by ponding and then tested for
leakages, if any.
- Approved protection coat to be apply after completion of Water-proofing work.
- Date of finishing shall be marked on the surface for curing by ponding for about 7 days.
Page 70 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Expansion Joint material / fillers
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
Page 71 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- If any part of the surface is contaminated by oil, grease, or fuel, the contamination shall
be removed before other forms of preparation are undertaken.
- At free edges such as doorways the emulsion shall be terminated properly.
- Prepare the surface using the chosen method, removing all laitance and weak or friable
matters (i.e. Tarfelt etc.). The finished surface should have a profile of medium to fine
sandpaper.
- Surface defects exposed during preparation such as shrinkage cracks, blowholes, minor
honeycombs, and minor damages, etc. shall be treated properly by using suitable surface
filler, preferably, cementations materials
- When it is known prior to starting work on the surface that repairs are required, the
repairs should be executed before general preparation is undertaken.
- When surface preparation is complete, clean the surface with dry clean cloth to remove
all dust and debris if any.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/14 EXPANSION JOINT TREATMENT WORK 00 71-72
- Protect areas such as windows, doors, ceilings, etc. that may be splashed when the
emulsion is being applied.
- Treat expansion joint as suggested by consultant or approved method submitted by
manufacturer / vendor.
- The joints in the wall are not left exposed and to be covered with covering sheets which
may be of aluminum, hard board, AC sheet or timber plank.
- Expansion joint in the roof shall invariably be provided with joint filler and water bar.
- Roofing Slab:
- The gap of the joint should be sealed with a water bar and sealing compound. In order to
prevent cracks in the masonry above or below the expansion joint R.C.C or plain concrete
bed blocks should be provided in the masonry below the expansion joint in the slab.
Page 72 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 73 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Spirit Level,
Mud Pan, Mallet (Wooden / Rubber), shuttering plywood, drill machine, block cutter, Measuring
Jar, Brush, etc.
4. Work Procedure:
9.20 Pre-Check:
- Ensure the availability of detailed layout of the building showing room dimensions,
thickness of walls at various locations in the building.
- Ensure RCC work complete respect to all activities, ensure curing period is completed.
- Ensure that Details of openings (with sizes) to be provided in the walls for doors,
windows, ventilators, exhaust fan openings & other openings, details of door, window,
ventilator frames.
- Clearance from MEP department / vendor to be taken before block work commences.
- Ensure approved Material available.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 74 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- At door frame head level concrete band of grade M20 with minimum 04 nos of 8 mm
Steel bars to casted followed by Minimum 3 days curing.
- Masonry work shall be constructed up to 25mm below slab level, and GI flat (Hold Fast)
fixed to slab and vertical joint of block work at every 2.0 m c/c.
- Top one layer will be left and will be filled with cement mortar mixed with non-shrink
Compound later after keen confirmation of deflection details. To provide the mechanical
key & arrest cracks at the top of the wall joint, 12mm size aggregate packing shall be done
over non shrink mortar.
- Opening for Door, Windows, MEP, HVAC shall be checked and verified during the
execution.
- If required, raking / brooming shall be done immediately after completion of work.
- Check verticality and evenness of block work for every layer. The walls shall be taken up
truly in plumb of true to the required batter where specified. All courses shall be laid truly
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/15 MASONRY WORK 00 73-75
horizontal and all vertical joints shall be truly vertical. Vertical joints in alternate course
shall come directly over the other. Care shall be taken to keep the perpends properly
aligned within following permissible tolerances:
Deviation from vertical within a storey shall not exceed 6mm per 3m height.
Deviation from position shown on plan of any brickwork shall not exceed 10
mm.
A set of tools comprising of wooden straight edge, masonic spirit levels,
square, 1m rule line and plumb shall be kept on site of work for every three
masons for proper check during the progress of work.
- Joints shall be filled racked suitable by raking tools. The face of brickwork shall be finished
flush unless otherwise specified. The faces of brickwork shall be cleaned with wire brush
so as to remove any splashes of mortar during the course of raising the brickwork.
- As far as possible services should be planned with the help of vertical chases. Horizontal
chases should be avoided. The depth of vertical chases and horizontal chases shall not
exceed one third and one sixth of the thickness of masonry respectively. Vertical chases
should not be closer than 2m in any stretch of a wall. These shall be kept away from
bearings of beams and lintels. No chase shall be permitted in half brick load bearing walls.
- The brickwork shall be constantly kept moist on all faces for a minimum period of 7 days.
Brickwork done during the day shall be suitably marked indicating the date on which the
work is done so as to keep a watch on curing period. The brickwork shall be protected in
high temperatures and humid conditions from excessive evaporation of water from
mortar and grout.
- Scaffolding shall be provided to allow easy approach to every part of work. The
Scaffolding shall be self-supported double scaffolding having minimum 400 wide work
platforms.
Page 75 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Scaffolding shall be strong to withstand all dead, live and impact loads, which are likely to
come on them. No support shall be taken from block work masonry wall for erecting the
scaffolding.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Cement (OPC / PPC)
Sand (River / Crushed / Silpoze)
Fiber / Metal Mesh
Bond-it / Hack Aid Plast / Approved Bonding Agent
Ready Mix Mortar
Page 76 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
9.22 Pre-Check:
- Ensure the availability of detailed layout of the building showing room dimensions,
thickness of walls at various locations in the building.
- Ensure that Details of openings (with sizes) to be provided in the walls for doors,
windows, ventilators, exhaust fan openings & other openings, details of door, window,
ventilator frames.
- Visible inspection of masonry shall be done to check no cracks in block work/Bricks and
structural repairing should be done prior to work start such as tie-rode holes to be
plugged, removing nails, ply pieces from RCC, etc.
- Curing period of masonry work should be completed.
- Curing compound removed from RCC member.
Page 77 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Offsets of door, window, beams, columns, jams, soffits shall be uniform in length, level,
right-angle.
- Finishing of plaster shall be carried out with wooden float (randhas) or trowelled smooth
with sheet metal trowels as specified. Care shall be taken to avoid excessive trowelling
and overworking of the wooden float.
- Making the grooves at the junction of concrete and masonry and as per the architectural
drawing.
- Always stop a day's work at corner
- Final surface finish(scratch, sand face) should be as project / approved technical
specifications.
- One meter overlap between 1st coat and 2nd coat to be provide at joint of plaster.
- Drip course wherever indicated in the drawings shall be provided at the time of Plastering
to prevent travelling of water drops from the projections. Unless otherwise, Specified,
projected strip form drip course shall be provided.
- Plaster at the top of the wall shall be done in one time with inward slope.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/16 SAND MORTAR PLASTER WORK 00 76-78
- Plaster shall be cut to correct horizontal or vertical line at the end of the day or if work
requires to be suspended for any reason. Joint cut to be done at corner of walls.
- Cut the plaster at skirting level and checked for uneven or undulation in wall surface with
line Dori and aluminium Patti.
- Clean the cement mortar immediately after the completion of work.
- Mortar cube shall be casted for compressive strength. (70.6*70.6*70.6mm).
- Mention the date at the end of the day.
- Curing of all types of plaster shall be started 24 Hrs. after finishing the plaster. The plaster
shall be kept wet for a period of 7 days. Before second coat ensure minimum 3days
during for 1st coat plaster.
Page 78 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Bond it or approved bonding agent
Gypsum(Type-Hemihydrate/Plaster of Paris/Anhydrous/Keene’s plaster)
Glass Fiber Mesh / Metal Mesh.
Sand paper (80-220no.)
4. Work Procedure:
9.24 Pre-Check:
- Source / brand of Gypsum shall be confirmed and approved.
- Source / brand of bonding agent on RCC surface shall be confirmed and approved.
Page 79 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 80 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Mix Gypsum plasters as much as required depending upon the immediate scope of work,
partially used material to be kept well secured in dry place. Consume within pot life.
- Once the mix has begun to set, additional water is not to be added, as performance
properties of plaster will get altered, thus affecting workability, cohesiveness, adhesion
properties and strength.
- Punning of gypsum plaster to be carried out from one end of wall and get the wall
complete.
- Gypsum shall be applied in a uniform surface slightly more than the specified thickness
and brought to a true surface, by working an aluminum straight edge reaching across the
gauges, with small upward and sideways movement at a time.
- Avoid using a wet brush on to the finished surface, as that would leave permanent brush
marks and thus spoil the surface.
-
Page 81 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Marble / Tile / Pieces of the glazed tiles i.e. china chips
Cement (PPC)
White Cement
Sand (River / Crushed / Silpoze)
Joint / Crack filler
Bubble Guard Sheet
Ebro tape 3inch thick.
Page 82 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Spirit Level, Right angle, Mallet ( Wooden / Rubber),Thickness Gauge, Float and Straight Edge,
etc.
4. Work Procedure
4.1. Tile / Marble Flooring:
4.1.1. Pre-Check:-
- Ensure the availability of detailed layout of the building showing room dimensions,
marble floor pattern at various locations in the building.
- Area should be cleaned from loose particles and other debris.
- Cracks if any on slab should be grouted as per approved methodology.
- Waterproofing work completed in all respect, slopes checked. If Required DPC provided at
places.
- Partition Wall back coat plaster completed.
- Clearance taken from MEP and Civil department.
- RCC repairing shall be done prior as per approved methodology.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 83 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 84 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Marble (Natural / Artificial) / Tile (Vitrified / Ceramic)
- Cement (PPC)
- White Cement
- Sand (River / Crushed / Silpoze / Quartz)
- Joint / Crack filler
- Adhesive
- Bubble Guard Sheet
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- IS1130:1969 -Specification of Marble (Block, Tiles, Slabs)
- IS13630 (1to15):2006 -Ceramic Tiles Method of Sampling & Testing
- 15622:2006 -Pressed Ceramic Tiles
- 13712:2006 -Code for Ceramic Tiles Definition &Classification
- Manufacturer Technical Specifications
Page 85 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Electric Peddle / Half Bag Tilting Mixture, Clean Tray, Trowel, Measurement Boxes, Mud Pan,
Spirit Level, Right angle, Mallet ( Wooden / Rubber),Thickness Gauge, Float and Straight Edge,
Line thread , Plumb, etc.
4. Work Procedure
4.1. Pre-check:
- Ensure availability of detailed layout of the flat showing all marble pattern.
- Area should be cleaned from loose particles and other debris.
- Wall back coat plaster complete as per requirement.
- Water proofing work completed in all aspect (Applicable in wet areas).
- Clearance taken from MEP department.
- Tile/marble color, shade, make as per approved sample.
4.2. Work Methodology – Application / Fixing:-
- Level marking on wall and level pad on the wall shall be as per approved FFL.
- For Marble: To be cut as per approved pattern and dimension (Dry Lay Method).
- For Tiles: Tiles to be selected as per approved pattern, dimension, make & colour.
- Defective and damaged Tiles /Marble to be removed and placed at one area.
- Provision for MEP points coming on wall to be made before fixing of Marble/Tiles.
- For Ceramic Tiles: Soaking to be done 2hrs prior before the application / fixing.
- For Ready-mix Mortar / Adhesive: Marble/Tile fixing to be done using 6mm to 10mm
thick or as specified approved tile adhesive to correct line and level. Proportioning as per
manufacturer specifications.
- For Conventional Mortar: Marble/Tile fixing to be done using 6mm to 10mm thick
conventional mortar in correct line and level. Proportioning 1:2(1water:2Cement) or as
specified.
- Additional plaster coat (1Cement:4Sand or as specified) should be applied if mortar
thickness exceeds 10-15mm.
- Approved grooved pattern to be followed at right angle joints.
- Laying pattern/starting point shall be as per latest architectural drawing.
- Joints are well cleaned and grouted with white cement and matching colour pigments as
per approved make.
- Cracks on marble to be cleaned and filled with approved crack filler. For tiles it should be
replace with a new one.
- No hollow sound when tapped.
- Cleaning, Curing and wall protection as per specification / BOQ/work order.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area.
- Finished work shall be barricaded and movement restricted.
Page 86 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Marble/Granite
- Kadappa
- Grey Cement Grade PPC / White Cement
- River Sand/Crushed Sand.
- Joint filler.(Approved Make)
- Tile Adhesive. (Approved make)
- Crack filler. (Approved make)
- Bubble sheet / Low Grade Gypsum
- Construction Water
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- Manufacturer Technical Specification
- IS 1130 – 1969 - Code of practice
3. Tools and Equipment:
Page 87 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Clean tray, Spirit level, Aluminum Patti, Drum, Right-angle, Trowel, Rubber Hammer, Parma,
mallet, Line thread, Plum bob, Thickness gauge, right angle etc.
4. Work Procedure:
4.1. Pre-Check:
- Ensure availability of detailed layout of the flat showing wall marble pattern.
- Area should be cleaned from loose particles and other debris.
- If Required, Wall back coat plaster complete as per requirement Kitchen dado.
- Water proofing work completed in all aspect (Applicable in wet areas) near sink & outlets.
- Clearance taken from MEP department. All the concealed MEP works in the walls of the
kitchen platform shall be completed before start of the kitchen platform work.
4.2. Work procedure:
- Clean the area prior to start of the work
- The position & marking of vertical & horizontal supports should be marked on wall as per
drawing. Level marking on wall and level pad on the wall as per approved FFL.
- Fix vertical kadappa /Marble / Granite on the floor with proper line and level.
- Minimum 15 to 20 mm deep recess shall be in wall up to desired height. Fixing of sub
base of platform on the vertical support should be in line & level.
- Adequate curing should be carried out prior to fixing of the horizontal kadappa element
with proper anchoring as per approved drawing.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 88 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Pre-Check:
- Ensure Granite/marble work is completed in all respect.
- Cracks and joints are filled properly with approved material.
- Marble/Granite joints are cleaned thoroughly in all respect.
- All other works are completed except final painting.
Work procedure:
- Kitchen Dado tiles wall is washed completely with water.
- Marble polishing is done with hand machine of stone no 0 to 5.
- Again joints and cracks are filled if damages while polishing.
- Pre final mirror polishing is done with hand machine of stone no 5x.
- Final mirror polishing and buffing is done at the time of handover or as per instruction of
site engineer.
- Marble Protection is done as per instruction of site engineer / specification.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Door / Window Frames
Door / Window Shutter
Anchor and Fasteners
Hinges
Foam / Fillers / Sealants
Window Track / Channels
Page 89 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
4.1. Pre-Check:
- Ensure the handing over of RCC work is done in all respect.
- Ensure the opening provided as per drawings.
- Clearance from MEP (Services) dept. taken before work commences.
- Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing work.
4.2. Work procedure:
Door and Window Frame:
- Door/Window frame shall be made of specified wood and shall be in accordance with
detailed drawings.
- The members of the frame shall be planed smooth and accurate to the full dimensions.
Rebates, rounding, molding etc. shall be done before the members are joined into frames.
- Joints in the frame work shall be perfect with square edges and shall be pinned with hard
wood/bamboo pins of 10 to 15 mm dia.
- Wood Work shall be painted/polished or otherwise treated as specified. All exposed
portions shall be coated with wood primer and concealed surface by bituminous paints as
per specifications.
- Each doors and frames tagged with sticker with door number and location.
Page 90 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Before any surface treatment is applied, the woodwork shall be approved by the Dosti.
The frames shall be fixed to the masonry by 300 mm x 25 mm x 6 mm M.S. hold fasts
embedded in M15 grade concrete block 350 mm x 100 mm x 100 mm in the hole of
Masonry. In case of concrete, frames shall be fixed by 120 to 140mm long, 10mm dia
nylon fasteners.
- All area should be cleaned prior to start of the work.
- Check Door openings in the structures should be as per approved shop drawing.
- Any deviation in the opening with respect to the shop drawing should be rectified.
- All door / window frames should be conducted moisture test prior to the fixing.
- While fixing frame opening direction of door / window shutter checked.
- Door frame fixed in line, level and right angle should be fixed with proper approved
anchoring as per project specification.
- All gaps between the frame & the wall should be properly closed with approved material.
- All door / window frames should be in plumb prior to fixing.
- All door / window accessories should be fixed as per approved GFC drawing / Shop
Drawings.
Page 91 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Perimeter channel.
- Ceiling angle.
- Intermediate channel.
- Ceiling section.
- Nylon sleeves/Screw.
- Soffit cleat.
- Anchor fastener
- Hex nut & Hex bolt.
- Connecting clip.
- Wafer head screw.
- Dry wall screw.
- Jointing compound.
- Joint paper tape.
2. Technical Specifications and Applicable Standards:
Gypsum Plaster Work shall be carried out as per following specifications / standards / code and /
or others as applicable.
Page 92 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 93 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- The overall grid system shall be rigid by self-locking joints, in accordance with false ceiling
patterns perfectly leveled and aligned at desirable height as per drawings.
- Gypsum board is fixed as per level with dry wall screw, screw fixed as per specification or
230mm c/c 2mm inside from the bottom face of the board.
- Provide edge runner at all sides to avoid cracks at junction.
- Gypsum board / metal board used should have no corner damages, no small cut pieces
and cracks.
- Gaps filling and finishing done with joining compound and joint paper tape.
- Marked cutouts on gypsum board to be get approved by MEP before cutting. Cut outs or
opening to be made with suitable frame and support for light fittings, grills, diffusers, etc
as per drawing and specification.
- Housekeeping done on daily basis, working area should be clean and safe.
- Modification work will be done prior approval and as per site requirement.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Putty
- Sand paper (80-220no.)
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
- Putty Manufacturer Technical Specification
3. Tools and Equipment:
Electric Peddle Mixer, Clean pan, Putty application Trowel, etc.
4. Work Procedure:
4.1. Pre-Check:
- Ensure the handing over of RCC work is done in all respect.
- Ensure the opening provided as per drawings.
- Clearance from MEP (Services) dept. taken before putty work commences.
- Compatibility of proposed putty with proposed paint system shall be ensured.
Page 94 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
- Check any cracks or damage on RCC/ Gypsum to be repaired before commencement of
work.
- Check compatibility with gypsum / paint or any other substrate.
4.2. Work procedure for putty:
- Clean the wall/ceiling surface by removing dust, curing compound and other materials.
- While applying putty on RCC surface, the substrate shall be grinded mechanically. All
loose material, binding wire shall be removed. Honeycombing if any shall be repaired by
approved material. Wash the substrate with clean water.
- Type of putty shall be carefully selected based on area of application.
- 1st coat primer to be applied on surface of RCC/Gypsum.
- Mixing of putty with mechanical mixer as per manufacturer technical data sheet /
specification.
- Punning of 1st coat putty (Thickness 1.25mm or as specified) to be carried out from one
end of wall/ceiling and get the wall/ceiling complete.
- Sanding of putty work to be done with 180 Micron Sanding paper after 1st coat gets dry
to get smooth surface.
- Minimum 8hrs interval to be kept between 1st and 2nd coat of putty.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/23 PUTTY WORK 00 94-95
- Punning of 2nd (Thickness 1.25mm or as specified) coat putty to be carried out after
completion of 1st coat, from one end of wall/ceiling and get the wall/ceiling complete.
- Cut the putty punning at skirting level in proper line and level as per site instruction.
- Sanding of putty work to be done after 2nd coat by 320 micron Sanding paper gets dry to
get smooth surface.
- Clean the Putty material fallen on floor immediately after completion of day work.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area also.
Page 95 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Water-proofing material / system
- Paint
- Paint Primer
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Paint Manufacturer Technical Specification
IS: 6278: Code of practice for white washing and colour washing.
IS: 2395: Code of practice for painting concrete, masonry and plaster
Surfaces.
IS: 712: Specification for building limes.
IS: 55: Specification for Ultramarine blue for paints.
IS: 63: Specification for whiting for paint and putty.
IS: 5411: Specification for plastic Emulsion paint for interior use.
IS: 2338: Code of practice for finishing of wood and wood based materials.
IS: 5410: Cement paint, colour as required.
IS: 384: Brushes, paint and varnishes, lat.
Page 96 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Page 97 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
- Apply one coat of primer (Thickness as specified) with the help of brush/roller from one
end of wall/ceiling and get the wall/ceiling complete and allow getting dry.
- Mix paint as per technical data sheet / specification.
- Apply 1st coat of paint (Thickness as specified) with the help of approved brush / roller
etc. From one end of wall/ceiling and get the wall/ceiling completes.
- Allow the 1st coat of paint to get dry completely before application of 2nd coat.
- Apply 2nd coat of paint after 1st coat complete dry/ final handing over (Thickness as
specified) with the help of approved brush / roller etc. from one end of wall/ceiling and
get the wall/ceiling complete.
Check for completion.
- Paint texture / finished surface shall be as per agreed / approved. shade variation in color
not accepted
- Clean the paint material fallen on floor immediately after completion of day work.
- Housekeeping to be carried out on daily basis, work area to be clean and safe.
- Material to be stacked properly on proper platform at daily working area also.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Electrical Pipes
Back Boxes
Adapters
Fillers / Joint Solvent
Repairing Mortar
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
IS 9537- Part 1 - Conduits for electrical installations, Part 1: General requirements
IS 732:1989 - Code of Practice for electrical wire installation
Page 98 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
4. Work Procedure:
- Clearance shall be taken from Civil Team to proceed the work.
- Ensure that the work area is ready and safe to start the installation of electrical conduits.
- Prior to start the installation, ensure the approved GFC drawings and shall be available on
request.
- Mark the correct location of the back boxes or pull boxes in line and level and place
thermo coal or equivalent material secured with masking tape on these locations.
- Install the Electrical conducting of slab or any other concrete structure should be securely
fastened with binding wires to reinforcement rods or shuttering to withstand concrete &
screed pour.
- The jointing of conduits shall be done with suitable coupler and solvent cement(approval
from civil team). The conduits shall be bonded tightly to the back boxes / pull boxes with
suitable adapters.
- All bends of conducting shall be made by using correct size of bending spring. Ensure the
radius of any conduit bend shall not be less than four times the outside diameter of the
conduit to satisfy the easy cabling / wire pulling requirements.
- Ensure all open end of the conduit are capped / plugged properly before concrete
pouring.
REF NO PROCEDURE TITLE REV. NO PAGE NO
Page 99 of 129
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
IS 3043 / 1987 Code of practice for earthing.
IS 3427 / 1997 A.C metal enclosed switchgear & control gears for rated voltage
above 1KV up to & including 52KV.
IS 3837 / 1976 Accessories for rigid steel conduits for electrical wiring.
IS 13947 / Part3 / 1993 Specification for low voltage switchgear & control gear.
IS 13947 / Part1 / 1993 Specification for low voltage switchgear & control gear.
IS 4615 / 1968 Switch socket outlets (Non-Interlocked type).
IS 5578 / 1984 Guide for marking of insulated conductors.
IS 6381 / 1972 Specifications for construction & testing of electrical apparatus with type
of protection ‘e’.
IS 732 / 1989 Code of practice for electrical wiring installation.
IS 3854 / 1997 Switches for domestic & similar purpose.
IS 2309 / 1989 Code of practice for lighting production.
IS 1937 / Part3 / 1983 Conduits for electrical installations.
IS 2706 / Part1 to 5/1992 Current transformers.
IS 13118 / 1991 Specification for HVAC circuit breakers.
Pipe Cutter, Binding Wire, Nails / lockers, Hammer, Screw Driver, Electronic Multimeter tester,
Megger Meter, Electrical Knife, Drill, etc
4. PROCEDURE:
- Collect the drawings for the electrical system for the building with the respective
consultant & the same to be discussed with electrical contractor & reconfirmed before
starting the work.
- Re-check the electrical load capacity of the building including all the common areas &
amenities & if it adheres to the norms as mentioned by the competent authorities.
- To check the provision of all items in the drawings whether they are as per our norms viz,
main panels, electrical cables, cable trays, ELCB’s, MCB’s & their capacity, junction boxes
etc.
- To provide 6” dia. Conduits with inspection chambers at every 15mtrs from the
compound wall to the sub-station /meter room for main supply for the building. All
corner junctions to have inspection chamber. Provide separate conduits for L.V. & H.V.
cables.
- Check all the materials to be used for the system & whether they adhere to the ISI norms.
Get third party test certificate from the manufacturer before start of the work.
- All anchor fastener hooks to be screw type. Proper ‘Z’ angles to be used for supporting
PVC pipes in the electrical ducts.
- Ensure that all bracket light points, switch plates etc are in line & level. Check the
operation of all the switches for smooth working.
- All feeder pillars, panels to be installed on a concrete base @ 300mm above FFL.
- Ensure that the meter room & the LV room is provided with sufficient ventilation &
lighting. Also check for any moisture formation or water leakage in both the rooms.
- Proper numbering of meters to be done for respective flats, common areas. Initial reading
to be taken & noted down.
- Lightning arrestors to be installed on the highest point in the building. The copper stripes
25mm x 3mm (two nos.) to be properly saddled along the external face of the building &
then taken up to the earthing pits.
- The earthing plate should not be less that 600mm x 600mm x 3.15mm & should be placed
on the edge. The top edge of the plate to be 1500mm below ground level.
- Place a funnel on the GI pipe mouth & make a chamber for the same with proper grating
on the top.
- Minimum distance between the two earthing pits to be at least 3.0mtrs & to be done in
an area which is likely to remain wet almost all the time.
- Ensure the entire system is checked /tested & commissioned. To prepare as built drawing
(by the consultant) for the cabling & wiring done on site.
- The CM&CE shall study the drawings and specifications. If any discrepancies are found, he
shall consult/liaise with the consultant for clarifications. The drawings shall be approved
by the Architect prior to their submission to any authorities.
- The engineer shall require the sub-contractor to submit all the necessary warranty
certificates at completion (Warranty Submission and Safekeeping procedure).
- Ensure that sufficient quantity of Electrical material & manpower are available to execute
specified job as per construction master schedule & Joint measurements to be taken for
Record purpose.
- Adequate safety measures, pollution control facilities and various statutory stipulations
wherever applicable to be ensure at site by S.O.
Operation
- Material: Material used will be as approved by the Client. The sizes, routes and routing
will be as per the approved shop drawing.
- Storage and Protection: Deliver components parts to site, completely identified in
accordance with shop and certified drawings prepared for this work. Store in accordance
with the manufacturer’s instructions, above ground, properly protected from the weather
and construction activities.
Installation
- During the course of the installation of the conduit system, procedures for working and
dressing the installation as recommended shall be employed.
- All bends and sets shall be in accordance with applicable IS codes and standards formed
with the aid of a helical spring fitted internally, with if necessary, the conduit warmed
sufficiently for it to move without avoidable wall thinning of the outside of the bend.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/26 ELECTRICAL WORK AND TESTING 00 100-105
- Conduit system shall be installed so as to ensure compliance with the requirements of
Specified Standard and Regulation.
- Joints between PVC conduit and fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit, inclusive of draw in
boxes etc., exceeds three meters in length or wherever it’s necessary.
- The minimum and maximum sizes of conduit to be employed shall be 20mm and
25mmdiameter respectively.
Fixing of Conduits
- When conduits are run on shuttering, prior to the laying of concrete , additional security
must be provided near to every box and at intervals of not more than .3 meters by
binding short lengths of GI wire twisted around the conduit and reinforcing steel. The
conduits shall be adequately fixed to prevent excessive movement and damage during
the pouring and setting of concrete and shall be protected from mechanical damage.
Check there is no damage before concrete is poured.
- Where conduits are left "open ended" prior to wiring they shall be protected by PVC end
caps or plugs to prevent the ingress of building material.
- All conduits runs must be designed to permit wiring to be readily installed after the
complete erection of the conduits through the available draw-in, accessory and luminary
suspension boxes.
- Ensure conduits are not concealed until works has been inspected and approved.
- Fixing Conduits with GI boxes in the walls
- Upon finishing the block work in each floor, start marking the location of all the switches,
sockets, telephone outlets, TV outlets, break glass and bells as per the GFC (Good for
Construction) drawings. Then Start chasing and chipping the marked locations by using
grinder, chisel or any other tool as necessary. we will fix the GI boxes with minimum 5
mm away from the wall to make sure that the box is flush with the plaster. Next day we
will terminate the conduits with the GI boxes.
Fixing conduits and GI boxes in the columns
- Before casting any column in the site, we have to check if there is any Switch Socket, bell
or break glass fixed on the column. If there is any, we have to fix the GI or PVC box in the
proper way ensuring that it touches the shutter of the Column from inside and the
conduit will be extended to the top of the column.
Fixing of Distribution Board’s Enclosure
- Ask the client to locate plaster level points only in the location where recessed D.B. is to
be installed so that we can fix the enclosures properly and to ensure the enclosures are
completely flush with plaster. The mounted height of the enclosures will be as per the
instructions of client. Distribution board will be aligned, leveled and securely fastened to
the wall. The surface mounted panel boards will be fixed as per client’s instruction.
-
REF NO PROCEDURE TITLE REV. NO PAGE NO
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
G.I. Pipes – C’ class / G.I. fitting threaded
Butterfly Valves / Wafer Type Check Valves / Ball valves/Gate valve / Solenoid Valve / Air
Release Valve
Strainers
Anchor Fasteners
Anti Vibration Mounting
Coupling
Electrical Panels
Gun metal Single / Double headed Hydrant Valves, three way Fire Brigade inlet, hose reel
drum & shut off Nozzle Canvas hose
Fireman AXE
Fire Hose
Pressure switch / Pressure Gauges
Sprinkler Heads
Cable Tray
Water spray nozzles, Deluge valve
Fire Alarm Panel
MCP, Smoke & Heat detector, Gas Leak Detector, Control Modules, Hooter, Fire Alarm
Cable, Fault Isolator
PA system ( Amplifier, Speaker, Microphone, PA system Cable )
PVC insulated Aluminum / Copper Conductor Amored Cables
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
IS 1648 - 1961 : - Code of practice for fire safety of buildings (general) fire fighting
equipment and its maintenance.
IS 3844 - 1966 :- Code of practice for installation of internal Fire Hydrants in Multi-storied
Buildings.
IS : 554 Dimensions for pipes threads where pressure tight joints are required on the
threads
IS : 638 Sheet rubber jointing and rubber insertion jointing.
8.0 PROCEDURE:
PIPING.
- Hangers and supports shall be capable of carrying the sum total of all concurrently acting
loads. They shall be designed to provide the required supporting effects and allow
pipelines movements as necessary. All guides, anchors, braces, dampners, expansion
joints and structural steel to be attached to the building / structure, trenches etc. shall be
provided by the Contractor. Hangers and components for all piping shall be approved
before fixing
- The piping system and components shall be capable of withstanding 150 per cent of the
maximum working pressure. Pipes shall be pressure tested to hydrostatic test pressure of
20 kg /cm2. The pressure shall be maintained for a period of two hours and there shall be
no drop in pressure at the end of this period.
- Flanged joints shall be used for connections to vessels, equipment, flanged, valves and
also suitable straight lengths of pipeline lengths of pipeline of strategic points to facilitate
erection and subsequent maintenance work.
- Flanged joints shall be used for connections to vessels, equipment, flanged, valves and
also suitable straight lengths of pipeline lengths of pipeline of strategic points to facilitate
erection and subsequent maintenance work.
- Non-return valves shall be cast iron wafer swing check type or dual plate / flap type An
arrow mark in the direction of flow shall be marked on the body of the valve. These valves
shall conform to IS : 5312. The flap shall be cast iron and flap seat ring of loaded gun
metal.
YARD HYDRANT
- Yard Hydrant valve shall be as per IS : 5290 and IS marked. The valve shall be oblique type
complete with hand wheel, quick coupling connection, spring and gun metal blank cap as
per IS : 5290. The hydrant shall be tapped from the 150 / 100 dia main with elbow and
standpipe 80 mm dia at approx. 1-2 m above ground level.
HOSE REEL
- The hose reel shall be directly tapped from the riser through a 20 mm dia pipe, the drum
and the reel being firmly held against the wall by use of dash fasteners. The Hose Reel
shall be swinging type ( 180 degrees ) and the entire Drum, Reel etc. shall be as per IS :
884. The rubber tubing shall be of approved quality and the nozzle shall be 6mm dia shut
off type.
SPRINKLER SYSTEM
PENDENT TYPE SPRINKLER HEAD.
- Sprinkler heads shall be quartzoid bulb type with bulb, valve assembly yoke and the
deflector. The sprinkler shall of approved make and type with 15 mm nominal dia outlets.
- The bulb shall be made of corrosion free material strong enough to withstand any water
pressure likely to occur in the system. The bulb shall shatter when the temperature of the
surrounding air reaches to 68 degree C.
- The nominal bore shall be 15 mm dia colour of liquid shall be Red.
- The Sprinkler head shall be approved by TAC/FOC/UL/FM
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
G.I. Pipes & Insulating Materials
Copper Pipes & Insulating Materials
PVC/UPVC Pipes
Anchor Fasteners, Clamps, Threaded rod & MS angles
Anti Vibration Mounting
Thermostat & Temperature sensors
Electrical Panels
Cable Tray
G.I. Ducts & Insulating Materials
Air Grills & Diffusers
Fire Dampers
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
IS : 554 Dimensions for pipes threads where pressure tight joints are required on the
threads
SMACNA / ASHRAE
4. PROCEDURE:
- Ensure horizontal ductwork is adequately supported at equal distances in accordance
with Construction Drawings with all brackets fixed to the vertical face of ribbed
beams of the structure.
- Air balancing & Temperature mapping to be done by Vendor & report to be shared with
client for cross-verification & record.
- All materials must be as per approved Make list & specification and Vendor to get all
materials cross-verified by client before installation at site as per approved GFC & tender
specifications.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
Water Pipes For Sanitary Fittings
a. PVC / CPVC Pipes Copper Pipes / Lead
a. Hand Wash Basin
Pipes b. Sinks (glazed or stainless-steel sinks)
b. G.I. Pipe. c. Bath Tubs
Plumbing Drainage System d. CP Tabs, Showers, Diverters etc.
c. Stone ware pipe: e. Water Closet
d. C.I. Soil/ Waste pipe 1. Indian type
e. C.I. Soil / Vent Pipe: 2. European type or pedestal types
f. C. I. Nahni Trap 3. Anglo-Indian type
g. Stone ware gully Trap f. Urinals
h. C.I. Man-hole cover & Frame 1. Bowl type or lip type urinals
i. Anti-Siphonage pipe 2. Stall type
j. C.P. Cocks g. Flushing cisterns Page 114 of 129
1. Low level 10 liters capacity
2. High level 10 liters capacity
QUALITY MANAGEMENT SYSETM
DOSTI REALTY LTD Document Ref No.
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
Manufacturer Technical Specifications
SP 35 : 1987 Handbook on Water Supply and Drainage (with Special Emphasis on
Plumbing)
IS 1200 : Part XIX : 1981 Method of Measurement of Building and Civil Engineering Works
- Part XIX : Water Supply, Plumbing and Drains
IS 12183 : Part 1 : 1987 Code of practice for plumbing in multi- storied buildings: Part 1
Water supply
IS 14810 : 2000 Copper Tubes for Plumbing – Specification
IS 3486: 1966 Cast Iron Spigot And Socket Drain Pipes. Socket Drain Pipes
IS 1729:2002 Cast Iron/Ductile Iron Drainage Pipes and Pipe Fittings for Over Ground Non-
Pressure Pipeline Socket and Spigot Series
Heavy Duty Clamps, Hammer, Measuring Tape, Marker, Wood Saw, Half Round File, Hack-saw
Frame, Drill Machine, Anchor Punch, Marking Line / Dori, Screw Driver flat and Star set, Fix
Adjustable Spanner, Monkey Pliers / Electrical Pliers, Kalwa Cutter, Pipe Wrench, Plumb, Spirit
Level, Right Angle, etc
4. Work Procedure:
Given below are method statements for general plumbing installations. This may need to be
modified in specific cases depending on the nature of the installations.
a. Excavation of Trenches :
- Mark layout of the pipeline and obtain approval from the DOSTI representative. Barricade
sides of trenches to be excavated.
- Start excavation works (Using manual labour or an excavator machine). Ensure that the
width does not exceed the maximum specified.
- Use a leveling instrument to make depth markings all along the length of the excavation.
In certain situations, it may not be practical to use a leveling instrument in a plumbing or
sewerage installation. In such cases, a tube level could be used.
- Allow for deeper excavations to accommodate the PCC base of inspection chambers and
at collars/joints of pipes.
- Additional care should be exercised for excavations deeper than 1.5m, especially in loose
soils. Arrangements should be made for shoring the sides of trenches.
- Care should be taken that excess excavations are always avoided. If in doubt, excavate
less and take out the extra depth in the next stage. Filled in soil invariably settles taking
the pipe with it, disturbing alignments.
- Ensure that excavated earth is always stored away from the edge of the trench.
b. External piping – Water supply
- Mark pipe lines in ground according to working drawing and provide barricading.
- Excavate trenches to required depths as per working drawings.
- Prepare base of trench for laying pipes, as per technical specifications.
- Lay the pipes on the prepared base and support them at adequate intervals.
d. Shaft Piping
- Ensure all the civil works activities are completed before start of the shaft piping.
- Mark for pipes on the plastered shaft walls according to details in the working drawings.
Ensure that the plastering is completed as it will be almost impossible to plaster walls
after the pipes are in place.
- Fix brackets as per details shown on the working drawings. A clear gap of 25 to 50mm
shall be maintained between pipe and wall surface. The brackets should be made of non-
corrosive material.
- Clamp pipe assemblies on to the brackets. Make sure the pipes are in ‘line’ (horizontal
runs) or in ‘plumb’ (vertical stacks). Where expansion / contraction will be a concern,
ensure that pipes are not rigidly held to brackets.
- Make cut-outs on the shaft walls for branch pipes at locations shown on the drawings.
- Insert sleeves wherever required. Ensure that annular space in sleeves is not more than
25mm. Annular space shall be filled with yarn and flexible sealant after installation of pipe
through the sleeve.
- Provide branches on the pipe assembly for connections to internal pipework. Provide
isolating valves on water supply pipes at locations shown on working drawings; at easily
reachable heights.
- Test the pipes for leaks under specified pressure for the specified duration.
- Tests must be witnessed and approved by Dosti’s representative.
- If Required, Paint the pipes as per approved colour code and provide identification labels
where called for.
- Take measurement of pipes installed. A representative of Dosti must be present and
should acknowledge the records.
- Chase the walls to required depth using a chasing machine. Chase before Water-proofing
work.
- Assemble piping starting from branch left in shaft and install in the wall chase with
clamps. Use pre-fabricated assemblies wherever possible.
- Locate fixture outlets according to working drawing and tile-module drawings. Title
modules shall be marked on walls by the civil contractor.
- Sensor Urinal - Before tiles fixing need to check proper electrical points with dimensions
mentioned by Company on proper location. If there is battery system than during tiling
person should fix sensor base box to avoid tiles wastage & Proper finish.
- Plug all openings and test the pipework for leaks under specified pressure and for
required duration. Test should be witnessed and approved by authorized personnel.
- Apply anti-corrosive coating or wrapping on the pipe, as specified (if metal pipes are
used). Ensure that the tested pipe joints are not disturbed.
- Insulate hot water pipes with the specified material.
- Water pressure test to be witnessed by the Dosti Representative and shall keep record for
the same.
Note:
- Wherever possible, pipes may be pre-insulated/pre-wrapped, leaving joints, prior to
installation in the wall chase.
- Close the wall chases with cement mortar. If site conditions require a depth of more than
100mm to be chased, it is advisable to use a suitable mesh while plastering and ‘making
good’.
- Flush the installed pipework (water supply and drainage) to remove debris or blockages, if
any.
- Install sanitary fixtures, faucets and washroom accessories. Use screws with nylon
washers to fix vitreous chinaware and PTPE tape for installation of faucets to pipework.
- Check CP fittings for leaks and firmness. Refit them if necessary. Ensure that proper tools
are used. They must not make scratches or any other kind of damages on the chrome
plated fixtures.
- Commission the toilets in the presence of the Dosti’s Engineer.
- Handover the toilets formally using the forms provided for the purpose.
The water distribution system should be thoroughly disinfected before being put to use. The
following simple procedures will ensure satisfactory results:
- Flush and clean water tank(s) and distribution pipework with potable water to remove
dirt and any foreign matter.
- Fill the tank(s) with water mixed with chlorine solution at the rate of 50 parts per million.
Retain chlorinated water in the system allowing the chlorine to spread throughout
pipework.
- Open the farthest draw-off points or drain plug/valve to draw water. Repeat the
procedure till odour of chlorine is felt at all locations when checked at random.
- Drain out chlorinated water and fill the system with potable water.
- Wash basin should be checked for any damage, scratches and defects prior to installation.
- Install the wash basin once clearance and access provided by the Dosti. Refere approved
GFC / Shop drawing.
- Silicon sealant to be provided in between the wash basin’s rims and Counter.
- Install waste pipe to siphon bend with gasket flushed on the wall from the bottle trap.
- Cover the wash basin with plastic or cartons till testing and commissioning.
5. Post-completion Inspection
- Visual / measurable inspection shall be done after de-shuttering.
- No repair work shall be carried out without first informing / jointly inspecting with QAQC
Engineer. Repair shall be done as per approved methodology; not following this protocol
shall result in NCR being issued.
- On handling over the as-fitted drawings and O&M manuals, a joint site visit shall be
arranged with the client’s representative to ensure all works are completed to their
satisfaction and obtain a certificate to that extent. Date of this certificate will be the start
date of Defects Liability Period.
- A detailed checklist shall be prepared for each activity as listed above and
acknowledgements may be taken from the supervising agency
6. Records:
As-Installed or As built Drawings
- Mark changes made from the working drawings; if any. These records should be
maintained from time to time during progress of work.
- Prepare ‘As-Installed’ drawings. This is an essential requirement often ignored. After the
construction team leaves the project site, it would be impossible to identify pipe routings
etc. without these drawings.
Operation & Maintenance Manuals
The O & M manuals should contain following minimum information:
- A brief description about the project and the installations carried out. Schedule of
mechanical / electrical equipment installed.
- Schedule of sanitary fixtures installed.
- Schedule of as-fitted drawings.
- Manufacturer’s operation & maintenance manuals and any warranties issued by
manufacturers.
- List of recommended spare parts.
- Notes / recommendations on preventive and remedial maintenance works.
- List of manufacturers with their local contact details.
- Technical catalogs of important products used on the installations.
REF NO PROCEDURE TITLE REV. NO PAGE NO
MS/29 WATER SUPPLY, SANITARY FITTINGS AND PLUMBING WORK 00 114-120
- Reports / certificates of all tests conducted during progress of work and any
commissioning reports.
- Virtual completion certificate
- On handling over the as-fitted drawings and O&M manuals, a joint site visit shall be
arranged with the Dosti’s representative to ensure all works are completed to their
satisfaction and obtain a certificate to that extent. Date of this certificate will be the start
date of Defects Liability Period.
- A detailed checklist shall be prepared for each activity as listed above and
acknowledgements may be taken from the supervising agency.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
G.I. Pipes – C’ class / G.I. fitting threaded
CPVC – SDR 11 / Composite Multilayer Pipes
Anchor Fasteners / MS angles for support structure
Solar Panels / Solar water storage Tank / Water Heater
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
12933 (Part 1) : 1990 - Solar flat plate collector : Part 1 , General requirements
12933 (Part 2) : 1990 - Solar flat plate collector : Part 2 Components
12933 (Part 3 ) : 1990 - Solar flat plate collector : Part 3 Measuring instruments.
12933 ( Part 4 ) : 1990 - Solar flat plate collector : Part 4 Performance requirements and
accepted criteria
12933 ( Part 5 ) : 1990 - Solar flat plate collector : Part 5 Test methods
4. PROCEDURE:
- Vendor shall visit the site to study the site condition and suggest type of system that will
be best suited for efficient & economical working of system
- Two types of Solar Water Heater available; one based on Flat Plate Collector (FPC) and
other based on Evacuated Tube Collector (ETC).
- Vendor shall furnish shop drawings showing the location of solar panels, storage tank,
pumps, valves, piping etc. complete for approval to Client/Consultant prior to
commencement of work.
- The solar panels shall be placed facing south for maximizing the use of solar energy.
Structural Concreting Work shall be carried out as per following specifications / standards
/ code and / or others as applicable.
Manufacturer Technical Specifications
- Need to check the lifting & placing method – it is feasible or not , it should cast in single
or two parts.
- Easy approach for fixing & maintenance if any in future.
Painting works :
- Allow the metal paste to completely dry and using reputed emery paper, sanding to be
done to the nearest perfection.
- Always avoid chamfered or scaled edges and ensure all joints to be in perfect plane and
right angles.
- Check the dimensions of the opening by using right angle before fixing the window grill, it
is always better to take site measurement for grill making, in order to avoid uneven gaps
between grill and wall.
- Apply one coat of reputed brand of metal primer (Zinc oxide primer) using brush or
sprayer before grills being fixed in position.
- Ensure Brackets or side supports or hold fasts are placed in position before fixing the
railings or grills.
- Enamel Painting for grills and handrails to be done in two coats, after the completion
of external wall painting works.
- It is highly advisable to use Anchor bolts for concrete or block masonry instead of coach
screw.
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Fabricated Glass Panels
- Railings
- Brackets
- Anchor Fasteners
- Base Plates
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Material Manufacturer Technical Specification
3. Tools and Equipment:
Drill, Screw Driver, Hammer, Tool box, Spanner, Anchor Fastener, Base Plates, Brackets, etc.
4. Work Procedure:
4.1. Off-site work:
- The Glass / Panel cladding or aluminium composite panel is received by fabrication
department in horizontally laid, type protected and evenly (to size) stacked sheets.
- The movements of materials are on roller controlled tables and marking / cutting /
grooving / folding/ rolling and assembly of angles to the ACP are done by skilled laborers
at the assembly tables to suit the fabrication orders that are in line with the shop
drawings.
- The items that flow the above said sequence of works include column cladding for items
- Highlighted while the other fabrication items less column cladding do not involve rolling.
Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
4.2. TRANSPORT / DELIVERY / STORAGE ON SITE
- The intimation for delivery is given to site 48 hours prior and the same is conducted in
proper procedure, where in the materials are packed on horizontally laid bed (trailer /
truck) with wooden supports as cushions to avoid damages.
- The loads are received and transported to an already assigned area, free of any
environmental conditions to damages the materials. Storage space is necessarily pre-
determined and free of potentially stamp and rough surfaces.
- Logistic team ensures delivery of it on site, to location of install hot before the exact day
of installation to avoid damages.
4.3. INSTALLATION
1. Pre installation
2. Installation
3. Post Installation
1. Materials:
All Materials should be approved before commencement of work. Source and make shall be
approved for all materials.
- Fabricated Façade panels
- EPDM Gasket
- Railings
- Brackets
- Anchor Fasteners
2. Technical Specifications and Applicable Standards:
Work shall be carried out as per following specifications / standards / code and / or others as
applicable.
– Material Manufacturer Technical Specification
3. Tools and Equipment:
Drill Machine, Screw Driver, Hammer, Tool box, Spanner, Saw Cutter, etc.
4. Work Procedure:
4.1. Off-site work:
- The metal wall cladding or aluminium composite panel is received by fabrication
department in horizontally laid, type protected and evenly (to size) stacked sheets.
- The movements of materials are on roller controlled tables and marking / cutting /
grooving / folding/ rolling and assembly of angles to the ACP are done by skilled laborers
at the assembly tables to suit the fabrication orders that are in line with the shop
drawings.
- The items that flow the above said sequence of works include column cladding for items
- Highlighted while the other fabrication items less column cladding do not involve rolling.
Wall and ceiling should be dry 100% and precaution to be taken for water leakages on
wall before commencing putty work.
4.2. TRANSPORT / DELIVERY / STORAGE ON SITE
- The intimation for delivery is given to site 48 hours prior and the same is conducted in
proper procedure, where in the materials are packed on horizontally laid bed (trailer /
truck) with wooden supports as cushions to avoid damages.
- The loads are received and transported to an already assigned area, free of any
environmental conditions to damages the materials. Storage space is necessarily pre-
determined and free of potentially stamp and rough surfaces.
- Materials for all types of ACP less column cladding are stacked horizontally while the
column cladding materials are stored vertically.
- Logistic team ensures delivery of it on site, to location of install hot before the exact day
of installation to avoid damages.
4.3. INSTALLATION
1. Pre installation
2. Installation
3. Post Installation
Note: For glass façade work, separate methodology to be submitted by Contractor / Vendor /
Manufacturer for Dosti approval before work start.