Health, Safety & Environmental Program Jsa (Job Safety Analysis)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

CHELE-CCCC4-HSE-JHA-2021-025

CLIENT/PROJECT LEKKI DEEP SEA PORT


HEALTH, SAFETY & ENVIRONMENTAL
PROGRAM JSA (JOB SAFETY ANALYSIS) DOCUMENT NO: CHELE-CCCC4-HSE-JHA-2021-025

ACTIVITY TITLE: LIFTING OF PILE PIPES CONTRACTOR: CHINA HARBOR ENGINEERING COMPANY DATE: SEPTEMBER 22, 2020

REVIEW AND APPROVAL RECORD OF THE PRESENT DOCUMENT


ACTION NAME DESIGNATION SIGNATURE DATE

PREPARED BY OSIOBE WEALTH HSSE OFFICER

REVIEWED BY CHEN JIAYU HSSE SUPERVISOR

APPROVED BY LIU JIANWEI HSSE MANAGER

REVISION STATUS
REV. DATE DESCRIPTION

HAZARD/RISK MANAGEMENT HAZARD/RISK IDENTIFICATION


Can all personnel in the group answer YES to the Does the work involve/require? WORK AREA: FABRICATION WORKSHOP
CHELE-CCCC4-HSE-JHA-2021-025

following questions:
• Is a separate lifting plan required? NO ACTIVITY: LIFTING OF HEAVY PILE PIPES
• Have all the significant hazards involved with the
• Working in a noisy area? YES
work been identified? YES
• Line breaching or potential Hydrocarbon release? NO SUPERVISOR: MR. CHEN
• Have control measures been identified for these
hazards? YES • Any Environmental impact? NO
HSSE OFFICER: OSIOBE WEALTH
• Have the people responsible for implementing these • Working near objects that may move? YES
control measures been identified and are the controls • Working in an area with poor lighting or a tight/confined
in place? YES Space? NO PROJECT MANAGER: MR. TING MING GANG
• Has the method of communication been agreed and • Working at height? NO
tested? YES
• Working near areas that could cause personnel to slip, HSE MANAGER: LIU JIANWEI
trip or fall? YES
• Is everyone aware what is being done at the work-
site? YES • Using portable electric equipment? YES
• Working with dangerous goods and substances
• Are we aware of what everyone else is doing at the
work-site? YES hazardous to health? NO
• Personnel who are new to the location or each other? NO
• Does everyone know that any changes to the work
plan have been communicated to everyone involved • Equipment which is potentially dangerous? YES
in the work? YES
If so the work may be hazardous and care should be
• Does everyone know that any new people joining taken to ensure the work is done safely
the work party must be given a full and thorough
update off what is going on? YES
Remember, everyone is responsible for:
• Using the correct tools for the job
• Being aware of the hazards around them and
If the answer to any of these questions is remaining vigilant to change.
NO, then the safety of people is at risk. • Using/wearing the correct PPE for the task.
• Making themselves aware of, and working within the
requirements of the PTW system and construction
The tool box talk leader should confirm the procedures
understanding of the group by asking open
questions on the above points

JOB SAFETY ANALYSIS (JSA) FOR LIFTING WITH GANTRY CRANES


S/N0 Operation/Activity Possible Hazardous Situations Indicate Necessary Measure to be taken (how can the Responsible Control in
Stage (The Steps (What could go wrong and What hazards be prevented and /or eliminated) (Who is going to take place
involved in doing the would the effects be) action) YES þNO
job) CHELE-CCCC4-HSE-JHA-2021-025
1 Movement of gantry  Fall • PTW completed and obtained HSSE Supervisor
crane to workshop area  Poor lifting accessories • Pre-job/Tool Box talk/JSA discussed and all hazards and Construction Manager
 Collision controls explained and understood prior to all signing JSA. HSSE Officer
• PPE issued (Protective Footwear, hard hats, coveralls, hand
gloves and safety glasses,(clear glasses worn for night work, if
Type of Permit Required required to do night shift).
Additional PPE Requirements
(please indicate by ticking • Equipment and all tools inspected prior Special
to usetools or equipment required
and defective
(Please list)
box) items removed from use and replaced.
General Permit to Work þ 1. Mandatory PPE •þ Sufficient
Drillinglighting
Rigs towers to illuminate the work areaShackles
if night YES þ
Hot Work 2. Face shield work should
Welding be carried out.
Machines Grease Pump
Lifting Permit þ 3. Fall arrestor • Jewelries,
Gantryrings, bracelets etc. removed priorþto starting
Cranes Excavator
work.
Excavation Certificate 4. High visibility vest þ Pay loader With Bucket Concrete Pump + Hoses
• trailer installed with stand-shore to prevent fall
Man basket Certificate 5. Dust Mask Pay loader With Fork Man Basket
 Use of competent and licensed trailer drivers
MEWP Certificate 6. Breathing Apparatus Self-Loading Mixers/Washer Truck Shovels, Pile Head Mold, Hammers,
Other.__________________ Wire Ropes And Slings þ Surveyor Equipment’s
7. Other.______________
2 ___ Set up of work area  Cuts • Trolleys
Area free from obstruction. CFA Cage Vibrator
Foreman Piping
JSA Review Process
Bruises Sufficient
Y N space available. Comments Permit Receiver
• Area barricaded and safety signs in place Safety Officer
Was the work crew involved in formulating the JSA? Y YES
• First aid box/first Aider available
Did the work crew review/discuss the JSA prior to starting task? • Y issued (Protective Footwear, hard hats, coveralls, hand
PPE
Was the JSA referred to during the task? Y gloves and safety glasses,(clear glasses worn for night work).
3 Were Installation
the job steps followed?  Poor lifting accessories
of gantry  Y Pre-job Tool Box Talk/JSA discussed and all hazards and control Foreman
crane.  falls explained and understood prior to all signing JSA Permit Receiver
Can you suggest improvements to the JSA? (Provide details)
 Fatality  Trained and certified crane operators deployed to install gantry HSSE Officer
 Electrical hazards crane
 Burns from welding  Crane certified and inspected prior to installation
 Welding spatters falling from  The crane track conditions to be checked for obstruction
height  Pre-use inspection of lifting accessories such as slings and belts
 Barricade the area from unauthorized personnel
 Install signage to indicate a critical lifting is being carried out
 Ensure all cables are properly installed and earthed YES
 Ensure fire extinguisher and first aid box are put in place
 Ensure no work is being carried out under the gantry crane
during installation
 Use of fall arrest protection such as full body harness while at
height
 PPE issued (Protective Footwear, hard hats, coveralls, hand
gloves and safety glasses,(clear glasses worn for night work),
face shields and aprons for welders.

4 Preparation and  Slips • PTW completed and obtained HSSE Supervisor


selection of proper lifting  Trips • Pre-job/Tool Box talk/JSA discussed and all hazards and Construction Manager
belts and sling ropes and  Falls controls explained and understood prior to all signing JSA. Foreman
other tools required to • PPE issued (Protective Footwear, hard hats, coveralls, hand HSSE Officer
 Cuts
carry out the lifting gloves and safety glasses,(clear glasses worn for night work, if
 bruises etc. required to do night shift).

You might also like