Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

CHELE-CCCC4-HSE-JHA-2021-053

CLIENT/PROJECT LEKKI DEEP SEA PORT


HEALTH, SAFETY &
ENVIRONMENTAL PROGRAM JSA
DOCUMENT NO: CHELE-CCCC4-HSE-JHA-2021-053
(JOB SAFETY ANALYSIS)
ACTIVITY TITLE: QUAY WALL SUPERSTRUCTURE CONTRACTOR: CHINA HARBOR ENGINEERING COMPANY
DATE: SEPTEMBER 18, 2021

REVIEW AND APPROVAL RECORD OF THE PRESENT DOCUMENT


ACTION NAME DESIGNATION SIGNATURE DATE

PREPARED BY WANG JIA NONG HSSE ENGINEER 18/09/2021

REVIEWED BY Dr. IZUOGU SUNDAY HSSE MANAGER 18/09/2021

APPROVED BY LIUJIANWEI HSSE DIRECTOR 18/09/2021

REVISION STATUS
REV. DATE DESCRIPTION

JSA revised 001 SEPTEMBER 06, 2021 Use of jackhammer

JSA revised 002 SEPTEMBER 18, 2021 Working near water


CHELE-CCCC4-HSE-JHA-2021-053

HAZARD/RISK MANAGEMENT HAZARD/RISK IDENTIFICATION WORK AREA: PILE DRIVING AREA


Can all personnel in the group answer YES to the Does the work involve/require?
following questions: ACTIVITY: QUAY WALL SUPERSTRUCTURE
• Is a separate lifting plan required? NO
• Have all the significant hazards involved with the
• Working in a noisy area? NO HSSE OFFICER: ISHEKE JOSIAH
work been identified? YES
• Line breaching or potential Hydrocarbon release? NO EWUBAREH GODSPOWER
• Have control measures been identified for these
hazards? YES • Any Environmental impact? NO
• Have the people responsible for implementing these • Manual handling, moving objects/loads? YES HSSE MANAGER: DR. SUNDAY IZUOGU
(If yes obtain/complete a manual handling
control measures been identified and are the controls
assessment)
in place? YES
• Working near objects that may move? NO
HSE DIRECTOR: MR. LI WEI
• Has the method of communication been agreed and
tested? YES • Working in an area with poor lighting or a tight/confined
Space? NO PROJECT MANAGER:MR. TANG MING GANG
• Is everyone aware what is being done at the work- • Working at height? YES
site? YES
• Working near areas that could cause personnel to slip,
• Are we aware of what everyone else is doing at the trip or fall? YES
work-site? YES • Using portable electric equipment? YES
• Does everyone know that any changes to the work • Working with dangerous goods and substances
plan have been communicated to everyone involved hazardous to health? YES
in the work? YES
• Personnel who are new to the location or each other?
• Does everyone know that any new people joining YES
the work party must be given a full and thorough
• Equipment which is potentially dangerous? NO
update off what is going on? YES
If so the work may be hazardous and care should be
taken to ensure the work is done safely
If the answer to any of these questions is Remember, everyone is responsible for:
NO, then the safety of people is at risk. • Using the correct tools for the job
• Being aware of the hazards around them and
remaining vigilant to change.
The tool box talk leader should confirm the
• Using/wearing the correct PPE for the task.
understanding of the group by asking open • Making themselves aware of, and working within the
questions on the above points requirements of the PTW system and construction
procedures
CHELE-CCCC4-HSE-JHA-2021-053
S/N0 Operation/Activity Possible Hazardous Situations Indicate Necessary Measure to be taken (how can the hazards be Responsible Control in
Stage (The Steps (What could go wrong and What prevented and /or eliminated) (Who is going place
involved in doing the would the effects be) to take action)
job) YES NO
 Poor/inadequate planning  Lifting, Excavation, Hot work and Work at Height PTW completed and
1 Preparation/planning  Poor communication obtained HSSE Manager
 Unauthorized work  Pre-job/Tool Box talk/JSA discussed and all hazards and controls Supervisor
 Unskilled personnel explained and understood prior to starting the job. HSSE Officer.
 Unsafe system of work  Sufficient lighting towers to illuminate the work area if night work
 Poor PPE selection should be carried out.
 Effective means of communication established
YES
 Equipment and all tools inspected prior to use and defective items
removed from use and replaced.
 Use of trained personnel for the task
 Competent personnel to plan the job
 Appropriate PPE issued (Protective Footwear, hard hats, hand gloves,
rain coat/ Umbrella and safety glasses (clear glasses worn for night
work, if required to do night shift).
2 Mobilization of  Involvement of unskilled  Trained & skilled staff to be authorized for working Supervisor
equipment & Materials personnel HSSE Officer
 Ensure that all personnel prior to start the have been inducted and
 Unauthorised/ uninspected oriented about the hazard in the job site
equipment/tools at site  Ensure JSA briefing & Daily TBT to all workforce prior to commence
 Unskilled and un-inducted activity
personnel starting the job
 Personnel injury / property  Use of authorized & designated routes
damage  Only inspected Equipments/Tools must be allowed at work site
 Slip, Trip & fall  Use right tools for right job
 Inclement weather condition  Ensure safe transportation of equipment/materials at work site
 Hand Injury
 All of materials to be secured while its transportation to work site
 Back Injury YES
 Stop work in case of any inclement weather conditions (Heavy Rain,
 SIMOPS
storm, fog etc.)
 Ensure area is barricaded off from other work activities
 Ensure workers/operators properly inducted about the proper
positioning
 Ensure proper hauling of materials/get help if required
 Ensure workers are complying with the min. PPE req. Safety shoes,
helmet, safety glass, and dust mask.
 Restrict movement of heavy vehicles/equipments in rain/fog
 PPE issued (Protective Footwear, hard hats, hand gloves and safety
glasses, reflective clothing)
3 Set up of work area  Fire  Area free from obstruction. Supervisor YES
 electric shock  Sufficient space available. HSSE Officer
CHELE-CCCC4-HSE-JHA-2021-053
 Pinch point  Area barricaded and safety signs in place
 Obstructed access  Fire extinguisher/fire point in place.
 Unauthorized personnel  Area well illuminated by placing tower lights for maximum effectiveness
if working past 18:30hrs.
 Area kept clear and dry.
 PPE issued (Protective Footwear, hard hats, hand gloves and safety
glasses,(clear glasses worn for night work).
4 Survey the pile level for  Manual handling/property loss  Careful handling with total machine/survey apparatus Surveyor
form work installation  Sharp edges  Ensure Use of hand gloves (PPE’s) HSSE Officer
(Performing Survey with  Inappropriate PPE’s  Do not left un attendant any of equipment/tools in the area
Total station)  Hand injury when installing  Consult with HSE in case of any confusion/query
survey pegs/cube blocks  Be careful while working at excavation adjacent
 Road traffic  Maintain good housekeeping at site
 Poor communication  Be aware of road traffic while performing survey
 Pre-job briefing and tool box talk will be performed prior to starting the
YES
job
 Area barricaded against vehicular collision.
 Passage/pathways for workers are inspected daily to ensure
materials/equipments/tools are not kept along the passage/pathways
 Surveyor not allowed to work in open field during rain
 Improper body positioning
 Keep hands and finger out of line of fire
 Use of radio phone for proper communication
5 Rebar Preparation  Injury and damage to body parts  Use certified tools for rebar bending
from improper tool usage  Ensure correct usage of tools
 Use of maskeshift arrangements  Don’t use makeshift tools Foreman
 Sprain on body parts  Ensure worker rotation to avoid sprain in body parts HSSE Officer
 Untrained person  Use good support and good ergonomic postures
 Uninspected tools  Skilled and trained personnel are deployed .
 Electric shock  Used double insulated tools YES
 Unguarded machines  Ensure cable are not frayed and in good condition
 Flying particles  Use guards for rotating parts
 Unauthorized workers are restricted from entry into the work area
 Use appropriate PPE for the job
 Use of proper eye protection against flying particles

6 Rebar Installation  Use of defective sling while lifting  Pre-job/Tool Box talk/JSA discussed and all hazards and controls YES
 Hit by slings. explained and understood prior to starting the job
 Amputation  Lifting and Hoisting PTW obtained and signed.
Foreman
 Equipment damage HSSE Officer
 Use only trained crane operator with certification
 Ineffective Communication
 Effective Signaling by use of competent Banksman .
between rigger and operator
 Keep eye out for people close-by
 Pinch point
 Inspect rigging tools and shackles daily
 Sharp edges
 Daily pre-use inspection of cranes to be carried out
CHELE-CCCC4-HSE-JHA-2021-053
 Defective/damage rigging tools to be removed from the site to prevent
use
 Use tag line to control loads while load may swing
 Rigger to be free and away from rigging of shear rings prior to crane
lifting
 Warning signs put in place with safe alternative route provided
 Keep hand away from line of fire
 rebars should not be lifted over personnel
 Lifting area properly barricaded with signage in place
 Ensure sharp edges protection
 Put caps on ends of exposed rebars/reinforcement cages
 Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
7 Side form work  Overhead hazards  Obtain Lifting and Hoisting PTW prior to any lifting YES
installation  Manual handling injuries  Involvement of skilled personnel
 Pinch points  Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
 Cuts/abrasion explained and understood prior to starting the job
HSSE Officer
 Falls
 Barricade off work area
 Unskilled personnel .
 Crane operator must be competent and certified
 Unauthorized access to the work
 Lifting gears must be in good condition
area
 Radius of the lifting must be barricaded to prevent people walking into
 Hit by moving machine/vehicle
the lifting zone
 Equipment Failure
 Warning Signs will be placed around the lifting zone
 Fall of forms
 Slings shackles inspected for damage before use
 Use of defective slings/gears
 Defective tools and shackles to be removed from use.
 Poor communication
 Competent rigger to guide the crane operator and coordinate lifting
process
 Two-way radio shall be used for effective communication
 Keep eye out for people close-by
 Full-time supervision and safety personnel
 Allow only authorized personnel in the work area
 Post signs to communicate additional information
 Use of proper manual handling techniques
 Never work under a rigged load
 Make sure there is enough lighting in the work area
 Clear all concrete and loose materials from forms to prevent anything
from falling overhead
 Use of taglines to direct/control suspended formwork
 Do not place hands in between forms
 Use pry bars to release the forms
 Fall protection must be used when climbing forms
CHELE-CCCC4-HSE-JHA-2021-053
 Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
8 Concrete Pouring/casting  Personnel injury during  Involvement of skilled personnel YES
movement of heavy vehicles  Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
 Manual handling explained and understood prior to starting the job
HSSE Officer
 Unskilled personnel  Ensure all operators know the safe limitations of their equipment
 Vehicles/equipment collisions  Assign a competent banksman when equipment is moving at the .
 Slip ,trip & fall working area
 Inappropriate PPE’s/Tools during  Ensure strict measures to separate mechanical plants and enforce swing
concrete work radius as a no go area for any person or vehicle to avoid collision
 Skin contact with concrete or  Ensure all machines and equipments are in good conditions
other chemicals  Regular preventive and corrective maintenance of equipment must be
 Machine failure/mechanical observed
failure  Use only designated roads for delivery of concrete
 Concrete in contact with eyes  Ensure the use of respiratory protective equipment
 Inhalation of harmful dust  Housekeeping regimes to help keep site clear
 Machine vs personnel interface  Ensure there is good access for concrete personnel and equipment
 Environmental hazards (fuelling  Keep other people not directly involved with concrete pouring clear
and leakages) from area
 Traffic congestion  Give warning prior to starting or re-commencing the pour
 Poor access to working area  Check hoses for air sources e.g blockage, change in supply, poor mix or
 Violent ejection of concrete from delays in pour
hose at first delivery  Ensure delivery hose is not damaged prior to concrete pouring
 Noise  Be aware of potential for blow back in the line/pipe
 Ensure appropriate edge protection
 Ensure connecting pipes are adequately secured
 Ensure brackets are positioned close together to minimize excessive
movement
 Ensure that pipe’s operating pressure is appropriate for diameter of
pipe
 Check pipe to ensure it is of correct thickness for operating pressure
 Do not use damaged pipes
 Provide support where a change in direction or reducer occurs
 Provide adequate hearing protection (ear plugs)
 Provide rest time or alternate work rotation
 Avoid long periods of twisting, repetitive movements
 Use of appropriate PPE’s during concrete works (Eye protection, rubber
gloves, gum shoes)
 Availability of fresh water at site
 First aid box should be in place at site
 wash off splattered concrete ASAP with fresh water or neutralizing
 solution
 Use a spotter for concrete trucks and all vehicles in tight or congested
CHELE-CCCC4-HSE-JHA-2021-053
areas
 Use chute man to swing concrete chute back & forth & signal concrete
truck driver
 Chute man needs to commute with rest of crew when moving chutes or
repositioning truck
 Use mesh over rebar to cover holes produced by rebars. Exposed mesh
will be trip hazards until concrete placed. Keep mesh ends tied down
 Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
9 Form wok removal and  Overhead hazards  Obtain Lifting and Hoisting PTW prior to any lifting YES
concrete curing  Manual handling injuries  Involvement of skilled personnel
 Pinch points  Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
 Cuts/abrasion explained and understood prior to starting the job
HSSE Officer
 Falls
 Barricade off work area
 Unskilled personnel .
 Ensure personal hygiene
 Unauthorized access to the work
 Availability of fresh water at site
area
 wash off splattered concrete ASAP with fresh water or neutralizing
 Hit by moving machine/vehicle
 solution
 Equipment Failure
 Crane operator must be competent and certified
 Fall of forms
 Lifting gears must be in good condition
 Use of defective slings/gears
 Radius of the lifting must be barricaded to prevent people walking into
 Poor communication the lifting zone
 Contact with cement dust  Warning Signs will be placed around the lifting zone
 Inhalation of cement dust  Slings shackles inspected for damage before use
 Defective tools and shackles to be removed from use.
 Competent rigger to guide the crane operator and coordinate lifting
process
 Two-way radio shall be used for effective communication
 Keep eye out for people close-by
 Full-time supervision and safety personnel
 Allow only authorized personnel in the work area
 Post signs to communicate additional information
 Use of proper manual handling techniques
 Never work under a rigged load
 Make sure there is enough lighting in the work area
 Clear all concrete and loose materials from forms to prevent anything
from falling overhead
 Use of taglines to direct/control suspended formwork
 Do not place hands in between forms
 Use pry bars to release the forms
 Fall protection must be used when climbing forms
CHELE-CCCC4-HSE-JHA-2021-053
 Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
10 Use of Jackhammer  Lower back, arm and shoulder  Pre-job/Tool Box talk/JSA discussed and all hazards and controls Supervisor
strain explained and understood prior to starting the job HSE Officer
 Pinched hand on side of  Be sure that hammer is unplugged and perform pre-use inspection
compartment according to the manual.
 Possible hernia  2 people needed to lift jack hammer
 Pinched finger from connecting  Use lighter jackhammer 60lbs instead of 90lbs if possible
hose  Wear gloves when connecting hoses
 Electric shock  Wear ear plugs
 Possible hearing loss  Eye protection Is required against flying particles
 Flying particles  Position feet apart keeping a safe distance from blade of hammer YES
 Jackhammer hitting feet  Respiratory protection against dust
 Rotating parts  Dust suppression where necessary to reduce dust
 Dust  Keep the work area as small as possible
 Heavy vibration  Alternate workers throughout the day if working with tool for 8hours
 Hold the hammer by insulated gripping surfaces when performing an
operation.
 PPE issued (Protective Footwear, hard hats, coveralls, hand gloves and
safety glasses (clear glasses worn for night work, if required to do night
shift).
11 Installation of precast  Crushed by swinging loads.  Obtain Lifting and Hoisting PTW prior to any lifting YES
beams  Unexpected rollover of the crane  Pre-job/Tool Box talk/JSA discussed and all hazards and controls
as a result of improper setting up explained and understood prior to starting the job Foreman
of the crane on an uneven  Use only trained crane operator with certification HSSE Officer
ground.  Barricade the area covering radius of crane under the load being lifted
 Injury due to damage lifting tools.  Signalman to be wherever it is applicable .
 Improper installation of pre-cast  Keep eye out for people close-by
slab  Inspect rigging tools and shackles daily
 Defective rigging.  Defective/damage rigging tools to be removed from the site to prevent
 Equipment failure. use
 Collision with the vehicles using  Rigger to be free and away from rigging of beams prior to crane lifting
the road. each load
 Breaking of sling material while  Temporal road closure and warning signs put in place with safe
lifting alternative route provided.
 Hit by slings.  Slings, Shackles certified for safe use.
 Amputation  Trained and qualified riggers used
 Slings shackles inspected for damage and colour coded
 Slings and shackles (SWL) as per the load to be lifted.
 Tag Lines not less than 2 meter must be attached to load and properly
controlled by riggers.
 Test lift and to ensure the material is balanced and weight is correct.
 Fingers and hands kept clear of pinch points.
 PPE issued and worn (safety shoes, safety goggles, hard hats, coveralls,
CHELE-CCCC4-HSE-JHA-2021-053
hand gloves)
12 Installation of Quay wall  Breaking of sling material while  Slings, Shackles certified for safe use.
equipments lifting  Trained and qualified riggers used
 Hit by slings.  Full time supervision
 Amputation  Proper pre-task planning
 mechanical failure  Slings shackles inspected for damage Foreman
 pinch point  Defective tools and shackles to be removed from use. HSSE Officer
 poor communication Slings and shackles (SWL) as per the load to be lifted.
 unskilled personnel  Tag Lines not less than 2 meter must be attached to load and properly .
 uneven lifts controlled by riggers.
YES
 improper installation  Test lift and to ensure the material is balanced and weight is correct.
 Pre-job/Tool Box talk/JSA discussed and all hazards and controls
explained and understood prior to starting the job
 Hoisting PTW signed before the commencement of lifting activity.
 Use of two-way radio for communication
 Use of trained crane operators and riggers for lifting activity
 Fingers and hands kept clear of pinch points.
 PPE issued and worn (safety shoes, safety goggles, hard hats, , hand
gloves)
13 Work near water  Man over board  Pre-job/Tool Box talk/JSA discussed and all hazards and controls
 Drowning explained and understood prior to starting the job
 Flooding  Life jackets to be worn at all times
 Slips, trips and falls from uneven,  Lifebuoys to be available in the working area at all time
unstable or boggy ground  Hard barriers and adequate warning signage posted
 Full-time HSE Monitoring
 Effects of adverse weather Foreman
 Ensure that emergency procedures are in place and all staff are aware
conditions HSSE Officer
of this information
 Ensure work area is free from debris (so far as is reasonably practicable) YES
 Implement an adequate inspection / maintenance programme
 Assess height of water, flow and tides if appropriate. Postpone work if
necessary
 Appropriate PPE to be worn at all times. Buoyancy Aids etc
 Keep area clear of obstruction / debris to avoid trips/falls
 Never work alone or out of view of work mates
 In the event of floods stay on high grounds
CHELE-CCCC4-HSE-JHA-2021-053
14 Welfare Facilities  Heat stress  Adequate clean drinking water to be provided. Foreman
 Environmental issues  Toilet will be provided for personnel working on site. No usage of open HSSE Officer
air excretion will be permitted.
 Intermittent breaks to be observed.
 Wash hand stations installed close to the work area YES
 Weather condition /temperature monitoring.
 Heat stress awareness of workers / preparedness of medical team / HSE
team.
Type of Permit Required
Additional PPE Requirements
(please indicate by ticking Special tools or equipment required
(Please list)
box)
General Permit to Work þ 1. Mandatory PPE þ Drilling Rigs Shackles þ
Hot Work þ 2. Face shield Welding Machines þ Grease Pump
Lifting Certificate 3. Fall arrestor þ Cranes þ Excavator þ
Excavation Permit þ 4. High visibility vest þ Pay loader With Bucket þ Concrete Pump + Hoses þ
Man basket Certificate 5. Dust Mask þ Pay loader With Fork Man Basket
MEWP Certificate 6. Breathing Apparatus Self-Loading Mixers/Washer Truck þ Shovels, Pile Head Mold, Hammers, þ
Other.__________________ Wire Ropes And Slings þ Surveyor Equipment’s
7. Other.______________
___ Trolleys CFA Cage Vibrator
JSA Review Process Y N Comments
Was the work crew involved in formulating the JSA? Y
Did the work crew review/discuss the JSA prior to starting task? Y
Was the JSA referred to during the task? Y
Were the job steps followed? Y
Can you suggest improvements to the JSA? (Provide details)

You might also like