Professional Documents
Culture Documents
053 Jsa Quay Wall Superstructure RV 02
053 Jsa Quay Wall Superstructure RV 02
REVISION STATUS
REV. DATE DESCRIPTION
6 Rebar Installation Use of defective sling while lifting Pre-job/Tool Box talk/JSA discussed and all hazards and controls YES
Hit by slings. explained and understood prior to starting the job
Amputation Lifting and Hoisting PTW obtained and signed.
Foreman
Equipment damage HSSE Officer
Use only trained crane operator with certification
Ineffective Communication
Effective Signaling by use of competent Banksman .
between rigger and operator
Keep eye out for people close-by
Pinch point
Inspect rigging tools and shackles daily
Sharp edges
Daily pre-use inspection of cranes to be carried out
CHELE-CCCC4-HSE-JHA-2021-053
Defective/damage rigging tools to be removed from the site to prevent
use
Use tag line to control loads while load may swing
Rigger to be free and away from rigging of shear rings prior to crane
lifting
Warning signs put in place with safe alternative route provided
Keep hand away from line of fire
rebars should not be lifted over personnel
Lifting area properly barricaded with signage in place
Ensure sharp edges protection
Put caps on ends of exposed rebars/reinforcement cages
Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
7 Side form work Overhead hazards Obtain Lifting and Hoisting PTW prior to any lifting YES
installation Manual handling injuries Involvement of skilled personnel
Pinch points Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
Cuts/abrasion explained and understood prior to starting the job
HSSE Officer
Falls
Barricade off work area
Unskilled personnel .
Crane operator must be competent and certified
Unauthorized access to the work
Lifting gears must be in good condition
area
Radius of the lifting must be barricaded to prevent people walking into
Hit by moving machine/vehicle
the lifting zone
Equipment Failure
Warning Signs will be placed around the lifting zone
Fall of forms
Slings shackles inspected for damage before use
Use of defective slings/gears
Defective tools and shackles to be removed from use.
Poor communication
Competent rigger to guide the crane operator and coordinate lifting
process
Two-way radio shall be used for effective communication
Keep eye out for people close-by
Full-time supervision and safety personnel
Allow only authorized personnel in the work area
Post signs to communicate additional information
Use of proper manual handling techniques
Never work under a rigged load
Make sure there is enough lighting in the work area
Clear all concrete and loose materials from forms to prevent anything
from falling overhead
Use of taglines to direct/control suspended formwork
Do not place hands in between forms
Use pry bars to release the forms
Fall protection must be used when climbing forms
CHELE-CCCC4-HSE-JHA-2021-053
Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
8 Concrete Pouring/casting Personnel injury during Involvement of skilled personnel YES
movement of heavy vehicles Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
Manual handling explained and understood prior to starting the job
HSSE Officer
Unskilled personnel Ensure all operators know the safe limitations of their equipment
Vehicles/equipment collisions Assign a competent banksman when equipment is moving at the .
Slip ,trip & fall working area
Inappropriate PPE’s/Tools during Ensure strict measures to separate mechanical plants and enforce swing
concrete work radius as a no go area for any person or vehicle to avoid collision
Skin contact with concrete or Ensure all machines and equipments are in good conditions
other chemicals Regular preventive and corrective maintenance of equipment must be
Machine failure/mechanical observed
failure Use only designated roads for delivery of concrete
Concrete in contact with eyes Ensure the use of respiratory protective equipment
Inhalation of harmful dust Housekeeping regimes to help keep site clear
Machine vs personnel interface Ensure there is good access for concrete personnel and equipment
Environmental hazards (fuelling Keep other people not directly involved with concrete pouring clear
and leakages) from area
Traffic congestion Give warning prior to starting or re-commencing the pour
Poor access to working area Check hoses for air sources e.g blockage, change in supply, poor mix or
Violent ejection of concrete from delays in pour
hose at first delivery Ensure delivery hose is not damaged prior to concrete pouring
Noise Be aware of potential for blow back in the line/pipe
Ensure appropriate edge protection
Ensure connecting pipes are adequately secured
Ensure brackets are positioned close together to minimize excessive
movement
Ensure that pipe’s operating pressure is appropriate for diameter of
pipe
Check pipe to ensure it is of correct thickness for operating pressure
Do not use damaged pipes
Provide support where a change in direction or reducer occurs
Provide adequate hearing protection (ear plugs)
Provide rest time or alternate work rotation
Avoid long periods of twisting, repetitive movements
Use of appropriate PPE’s during concrete works (Eye protection, rubber
gloves, gum shoes)
Availability of fresh water at site
First aid box should be in place at site
wash off splattered concrete ASAP with fresh water or neutralizing
solution
Use a spotter for concrete trucks and all vehicles in tight or congested
CHELE-CCCC4-HSE-JHA-2021-053
areas
Use chute man to swing concrete chute back & forth & signal concrete
truck driver
Chute man needs to commute with rest of crew when moving chutes or
repositioning truck
Use mesh over rebar to cover holes produced by rebars. Exposed mesh
will be trip hazards until concrete placed. Keep mesh ends tied down
Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
9 Form wok removal and Overhead hazards Obtain Lifting and Hoisting PTW prior to any lifting YES
concrete curing Manual handling injuries Involvement of skilled personnel
Pinch points Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Foreman
Cuts/abrasion explained and understood prior to starting the job
HSSE Officer
Falls
Barricade off work area
Unskilled personnel .
Ensure personal hygiene
Unauthorized access to the work
Availability of fresh water at site
area
wash off splattered concrete ASAP with fresh water or neutralizing
Hit by moving machine/vehicle
solution
Equipment Failure
Crane operator must be competent and certified
Fall of forms
Lifting gears must be in good condition
Use of defective slings/gears
Radius of the lifting must be barricaded to prevent people walking into
Poor communication the lifting zone
Contact with cement dust Warning Signs will be placed around the lifting zone
Inhalation of cement dust Slings shackles inspected for damage before use
Defective tools and shackles to be removed from use.
Competent rigger to guide the crane operator and coordinate lifting
process
Two-way radio shall be used for effective communication
Keep eye out for people close-by
Full-time supervision and safety personnel
Allow only authorized personnel in the work area
Post signs to communicate additional information
Use of proper manual handling techniques
Never work under a rigged load
Make sure there is enough lighting in the work area
Clear all concrete and loose materials from forms to prevent anything
from falling overhead
Use of taglines to direct/control suspended formwork
Do not place hands in between forms
Use pry bars to release the forms
Fall protection must be used when climbing forms
CHELE-CCCC4-HSE-JHA-2021-053
Appropriate PPE(safety helmet, safety goggles, ear plugs, safety
footwear, reflective vests) to be worn at all times
10 Use of Jackhammer Lower back, arm and shoulder Pre-job/Tool Box talk/JSA discussed and all hazards and controls Supervisor
strain explained and understood prior to starting the job HSE Officer
Pinched hand on side of Be sure that hammer is unplugged and perform pre-use inspection
compartment according to the manual.
Possible hernia 2 people needed to lift jack hammer
Pinched finger from connecting Use lighter jackhammer 60lbs instead of 90lbs if possible
hose Wear gloves when connecting hoses
Electric shock Wear ear plugs
Possible hearing loss Eye protection Is required against flying particles
Flying particles Position feet apart keeping a safe distance from blade of hammer YES
Jackhammer hitting feet Respiratory protection against dust
Rotating parts Dust suppression where necessary to reduce dust
Dust Keep the work area as small as possible
Heavy vibration Alternate workers throughout the day if working with tool for 8hours
Hold the hammer by insulated gripping surfaces when performing an
operation.
PPE issued (Protective Footwear, hard hats, coveralls, hand gloves and
safety glasses (clear glasses worn for night work, if required to do night
shift).
11 Installation of precast Crushed by swinging loads. Obtain Lifting and Hoisting PTW prior to any lifting YES
beams Unexpected rollover of the crane Pre-job/Tool Box talk/JSA discussed and all hazards and controls
as a result of improper setting up explained and understood prior to starting the job Foreman
of the crane on an uneven Use only trained crane operator with certification HSSE Officer
ground. Barricade the area covering radius of crane under the load being lifted
Injury due to damage lifting tools. Signalman to be wherever it is applicable .
Improper installation of pre-cast Keep eye out for people close-by
slab Inspect rigging tools and shackles daily
Defective rigging. Defective/damage rigging tools to be removed from the site to prevent
Equipment failure. use
Collision with the vehicles using Rigger to be free and away from rigging of beams prior to crane lifting
the road. each load
Breaking of sling material while Temporal road closure and warning signs put in place with safe
lifting alternative route provided.
Hit by slings. Slings, Shackles certified for safe use.
Amputation Trained and qualified riggers used
Slings shackles inspected for damage and colour coded
Slings and shackles (SWL) as per the load to be lifted.
Tag Lines not less than 2 meter must be attached to load and properly
controlled by riggers.
Test lift and to ensure the material is balanced and weight is correct.
Fingers and hands kept clear of pinch points.
PPE issued and worn (safety shoes, safety goggles, hard hats, coveralls,
CHELE-CCCC4-HSE-JHA-2021-053
hand gloves)
12 Installation of Quay wall Breaking of sling material while Slings, Shackles certified for safe use.
equipments lifting Trained and qualified riggers used
Hit by slings. Full time supervision
Amputation Proper pre-task planning
mechanical failure Slings shackles inspected for damage Foreman
pinch point Defective tools and shackles to be removed from use. HSSE Officer
poor communication Slings and shackles (SWL) as per the load to be lifted.
unskilled personnel Tag Lines not less than 2 meter must be attached to load and properly .
uneven lifts controlled by riggers.
YES
improper installation Test lift and to ensure the material is balanced and weight is correct.
Pre-job/Tool Box talk/JSA discussed and all hazards and controls
explained and understood prior to starting the job
Hoisting PTW signed before the commencement of lifting activity.
Use of two-way radio for communication
Use of trained crane operators and riggers for lifting activity
Fingers and hands kept clear of pinch points.
PPE issued and worn (safety shoes, safety goggles, hard hats, , hand
gloves)
13 Work near water Man over board Pre-job/Tool Box talk/JSA discussed and all hazards and controls
Drowning explained and understood prior to starting the job
Flooding Life jackets to be worn at all times
Slips, trips and falls from uneven, Lifebuoys to be available in the working area at all time
unstable or boggy ground Hard barriers and adequate warning signage posted
Full-time HSE Monitoring
Effects of adverse weather Foreman
Ensure that emergency procedures are in place and all staff are aware
conditions HSSE Officer
of this information
Ensure work area is free from debris (so far as is reasonably practicable) YES
Implement an adequate inspection / maintenance programme
Assess height of water, flow and tides if appropriate. Postpone work if
necessary
Appropriate PPE to be worn at all times. Buoyancy Aids etc
Keep area clear of obstruction / debris to avoid trips/falls
Never work alone or out of view of work mates
In the event of floods stay on high grounds
CHELE-CCCC4-HSE-JHA-2021-053
14 Welfare Facilities Heat stress Adequate clean drinking water to be provided. Foreman
Environmental issues Toilet will be provided for personnel working on site. No usage of open HSSE Officer
air excretion will be permitted.
Intermittent breaks to be observed.
Wash hand stations installed close to the work area YES
Weather condition /temperature monitoring.
Heat stress awareness of workers / preparedness of medical team / HSE
team.
Type of Permit Required
Additional PPE Requirements
(please indicate by ticking Special tools or equipment required
(Please list)
box)
General Permit to Work þ 1. Mandatory PPE þ Drilling Rigs Shackles þ
Hot Work þ 2. Face shield Welding Machines þ Grease Pump
Lifting Certificate 3. Fall arrestor þ Cranes þ Excavator þ
Excavation Permit þ 4. High visibility vest þ Pay loader With Bucket þ Concrete Pump + Hoses þ
Man basket Certificate 5. Dust Mask þ Pay loader With Fork Man Basket
MEWP Certificate 6. Breathing Apparatus Self-Loading Mixers/Washer Truck þ Shovels, Pile Head Mold, Hammers, þ
Other.__________________ Wire Ropes And Slings þ Surveyor Equipment’s
7. Other.______________
___ Trolleys CFA Cage Vibrator
JSA Review Process Y N Comments
Was the work crew involved in formulating the JSA? Y
Did the work crew review/discuss the JSA prior to starting task? Y
Was the JSA referred to during the task? Y
Were the job steps followed? Y
Can you suggest improvements to the JSA? (Provide details)