Professional Documents
Culture Documents
Design Project Title: 100,000 Mta of Soda Ash Production Plant
Design Project Title: 100,000 Mta of Soda Ash Production Plant
Design Project Title: 100,000 Mta of Soda Ash Production Plant
PLANT MANAGER
ASSOC. PROF. DR. MOHAMAD WIJAYANUDDIN ALI
SUBMISSION DATE
11TH JUNE 2017
ii
ACKNOWLEDGEMENT
We would like to express our deepest gratitude to God as with the blessing this
project has successfully been completed.
First and foremost, we would like to express our sincere gratitude to our plant
design project supervisor, Assoc. Prof. Dr. Wijayanuddin Ali for the continuous
support for our design project, for his patience, motivation, enthusiasm and immense
knowledge.
Besides, a big thank is forwarded to Dr. Azizul Azri Mustaffa, Dr. Nor Alafiza
Yunus, Dr. Zarina Ab. Muis, Prof. Dr. Mohd. Rozainee Taib, Dr. Ramli Mat, Assoc.
Prof. Dr. Noorhalieza Ali, Dr. Muhammad Abbas Ahmad Zaini and Mr. Khairuddin
Ahmad for their endless guidance and comments for continuous improvement. Also,
we would like to thank all UTM friends for their support and valuable inputs regarding
the project. As well, we also wish to express our gratitude to our beloved family
members who are always being there for us through thick and thin.
iii
EXECUTIVE SUMMARY
Soda ash also known as sodium carbonate is an important raw material and
chemical intermediates which is used primarily in growing industries in Asia-Pacific
such as glass manufacturing, detergents and soap manufacturing, other chemicals such
caustic and others, etc. Therefore, Y Chemical Sdn. Bhd. has proposed an integrated
production plant which focuses on producing 100,000 MTA of soda ash to be
constructed at Gebeng Industrial Estate, Pahang. Soda ash is synthesized by Dual
process, also known as modified Solvay. The reaction involved sodium chloride,
ammonia, water and carbon dioxide as the reactant to produce soda ash and having
ammonium chloride as by-product. The main reactions, carbonation and calcination,
occur at a conversion of 75% and 100% respectively. The ultimate objective of the
design project is to produce a high purity of soda ash as high as 99.99% fulfilling the
industrial standard purity for soda ash.
TABLE OF CONTENTS
ACKNOWLEDGEMENT ii
TABLE OF CONTENTS iv
Glass Production 3
Flat Glass 4
Glass Container 4
Environmental Applications 5
Global Demand 9
Local Demand 12
Land Price 19
Raw Materials 19
Market Supply 20
Climate 21
Availability of Labor 21
Transportation 22
Tax Incentives 33
vi
Land Price 34
Utilities 35
Logistics 35
Labor 36
Raw Materials 37
Market Supply 38
Administration Area 39
Operation Site 39
Reaction Paths 42
Justification on Selection 52
Sodium Chloride 56
Water 57
Brine 58
vii
Ammonia 59
Carbon Dioxide 60
Ammonium Chloride 61
Sodium Bicarbonate 62
Alternative 1 66
Alternative 2 81
Evaporator 165
Pumps 177
Compressors 179
Dissolver (D – 1) 186
Calciner (R – 2) 195
Evaporator (S – 2) 199
Pumps 209
Pump 1 (P – 1) 209
Pump 2 (P – 2) 211
Compressors 213
xi
Compressor 1 (K – 1) 213
Compressor 2 (K – 2) 215
Housekeeping 221
Transportation 225
Utility 226
Flammability 227
Explosion 229
Dissolver 236
Calciner 242
Evaporator 245
Pumps 249
Compressors 251
Pre-commissioning 254
Dissolver 260
Calciner 264
Evaporator 266
xiii
Pumps 272
Compressors 274
REFERENCES 234
APPENDICES 237
xiv
LIST OF TABLES
LIST OF FIGURES
12.5 Elliptical type headed vessel, with feed and top nozzles 278
13.1 Undiscounted cash flow diagram (with i = 0%) 231
13.2 Cash flow diagram with varies interest rate 232
xxi
LIST OF SYMBOLS
ρ Density kg/m3
MW Molecular weight g/mol
o
T Temperature C
o
Tb Boiling point temperature C
o
Tm Melting point temperature C
∆Tm Mean temperature difference o
C
o
TLM Log mean temperature C
∆Tmin Temperature minimum difference o
C
P Pressure atm
Pvap Vapor pressure atm
Hofus Heat of fusion J/g
̂ 𝑓o
∆𝐻 Standard heat of formation J/g
̂𝑐 o
∆𝐻 Standard heat of combustion J/g
∆Hv Heat of vaporization kJ/kg
Hosol Heat of solution J/g
Cp Specific heat capacity J/g.K
SG Specific gravity Dimensionless
𝑚̇ Mass flowrate g/hr
F Mass flowrate g/hr
𝑛̇ Mole flowrate mol/hr
x Mass fraction Dimensionless
y Mole fraction Dimensionless
∆H Enthalpy kW
xxii
Qc Cooling duty kW
QH Heating duty kW
o
Tpinch Pinch temperature C
Xp Product mole fraction Dimensionless
XF Feed mole fraction Dimensionless
V Volume m3
Q Heat duty kW
A Area ft.2
AR Radiant surface area ft.2
Ac Convective surface area ft.2
AHX Heat Exchanger area ft.2
U Heat coefficient Btu/hr.ft2.oF
BOD Biological oxygen demand ppm
COD Chemical oxygen demand ppm
SS Suspended solid ppm
FM Material of construction factors Dimensionless
Rpm Revolution per minute Rev/min
D Diameter m
Di Internal diameter m
Do Outer diameter m
E Fractional weld efficiency Dimensionless
Tc Corrosion allowance in.
W Weight Ib
ts Shell thickness in.
S Maximum allowable stress psi
Pd Design pressure psig
θ Retention time sec
z Height ft.
H Henry’s Law constant Dimensionless
∆Pflood Pressure drop at flooding mmH2O/m
Uf Flooding velocity ft./s
N Number of plates Dimensionless
LT Length of tube ft.
xxiii
LIST OF ABBREVIATIONS
LIST OF APPENDICES
Soda ash, also known as sodium carbonate, is one of inorganic chemicals that
are produced in large amounts in the world. It can be made from mineral trona or
sodium carbonate-bearing brines which mainly found in United States and other parts
of Africa, or from the chemical reaction of primarily salt and limestone. Globally, two
types of soda ash are being made which are natural and synthetic. United states focused
in producing soda ash more on natural type since it is the world’s largest natural deposit
of trona. It makes United States natural soda ash is highly competitive in world markets
because majority of the world soda ash is made synthetically which is costlier to be
manufactured. Figure 1.1 shows the molecular structure of sodium carbonate.
Referring to Day (1998), the history of U.S. soda ash industry begins in the
early seventeen centuries, when the Jamestown settlers wanted a source of alkali to
manufacture their glassware, this effort was continued until the late nineteenth century.
During this time, natural soda ash deposits were developed in the West while the
synthetic soda ash plants were build up in the East. This manufacturing soda ash were
withstanding until the twentieth century. Some of the operations started to shut down
little by little until it is hard to prove that they once existed. U.S. history shown that
the product was in strong demand due to the Industrial Revolution of the nineteenth
century, World Wars I and II, and the Korean Conflict. All of the chemical, glass and
metals industries are relying on the soda ash production.
In 1861, after realizing the impacts from Leblanc process, a Belgian industrial
chemist Ernest Solvay was discovered another method of producing soda ash. It uses
salt, limestone, ammonia and coal to manufacture it. One of the secret successes is
they were adding of carbonating towers in the process. The speciality of this process
is the ammonia recovery system making it less harmful to the environment. In fact,
this process has been patent and it becomes most world’s soda ash manufacture in
1890. In addition, the materials used in the Solvay process are inexpensive and
plentiful. Thus, it makes soda ash production market became a flourishing industry
with several plants opening over the world.
3
Idea of manufacturing soda ash continue over time especially in 1980. The new
process was named as Dual process which is also known as modified Solvay process
because the founder made some modifications to the initial Solvay process. It was
established and operated in Japan. The difference that has been made is, it does not
required limestone as a raw material, it makes the Dual process became cheaper in
terms of chemical usage. Besides, Solvay process is recovering the ammonia during
the process, however in the Dual process, it retained the ammonium chloride and
crystallized out by separating it using several amounts of sodium chloride. The
advantage of separating ammonium chloride is because it could be a great quality of
fertilizer and can be commercialized. Thus, Dual process is the most preferable way
of producing synthetic soda ash and in fact, it has become widely used over the world
especially in China.
Glass Production
Flat Glass
The flat glass industry mainly produces glass used in the building sector such
as private and public housing, after-market segment such as windows and door
segments. Besides, it is also highly used in automotive industry especially in tempered
glass manufacture. A significant growth in this industry had experienced during the
last decades, increasing vehicle over the world resulting in increasing use of glass, as
well as in modern buildings and in renovation. Moreover, the invention of the double
or triple glazing windows, which are used to improve the thermal performance, is one
of the key factors of the flat glass industry development.
Glass Container
Furthermore, due to the its solubility and reactivity in water, it is also become
a primary raw material to produce other chemicals such as sodium phosphates, sodium
silicates, photographic chemicals, chrome chemicals and sodium bicarbonate, which
can be used as an additive in the food, beverage, detergent and coatings.
Soda ash also is identical with caustic soda. Thus, it can be applied as a
functional substitute for caustic soda and indirectly offering a good profit. Some of the
applications are pH adjustment, production of sodium chemicals such as sodium
sulphate and sodium phosphates, craft pulping and flue gas desulfurization.
Commonly, medium dense or lighter dense of soda ash are being used in
manufacturing detergents. It is due to some of soda ash benefits such as promoting
agglomeration, being a carrier for surfactants and source of alkali for pH adjustment.
Environmental Applications
Soda ash is commonly used in water treatment to raise the pH of acidic water
by injecting it into a water system. Some of the examples are to improve the alkalinity
of lakes affected by acid rain and in reducing acid content of power plant emissions.
Advantages of using soda ash over calcite and magnesia, it does not create hardness
6
problems in treated water and it can treat water with a pH as low as 4. It is also sensitive
to temperature and works optimally at ambient temperature.
Soda ash is a white, odourless and granular solid. It is non-combustible and can
be reacted with acids to release carbon dioxide gas and heat. This product may irritate
skin, eyes and respiratory tract. It is also not toxic to the environment, nor to aquatic
organisms. Simultaneous exposure to soda ash need to be avoided. If moisture is
presence, soda ash and lime dust can combine to form caustic soda (NaOH) which may
cause burns. The physical and chemical properties of soda ash from Material Safety
Data Sheet (MSDSs) is summarized as shown in Table 1.1 below. The complete
7
MSDSs from 3 different sources or industries are presented in Appendices. While, the
toxicity data is presented in Table 1.2.
In 2015, the global soda ash market size was USD 15.94 billion. World soda
ash production was estimated to be 53.4 million metric tonnes, slightly more than the
revised total of 52.7 million metric tonnes in 2014. The production size in 2014, 2013
and 2012 was recorded as 52.7 million metric tonnes, 51.3 million metric tonnes and
51.7 million metric tonnes respectively. As for 2016, no specific market outlook yet to
be published. Based on Top Market Report of soda ash released by
MarketsandMarkets, the soda ash market is estimated to witness a Compound Annual
Growth Rate (CAGR) of 6.1% between 2014 and 2019 in terms of value, and is
anticipated to generate a global market value of $22,090 million by 2019.
Soda ash market faces a boost implication from the wider application in
growing industries such as glass especially from container and flat glass sectors,
chemicals, soap & detergent, pulp & paper, metallurgy, water treatment and many
more manufacturing industries. Figure 1.2 depicts that the market demand of soda ash
in glass industry covers around 50%, followed by chemicals, soap and detergents, and
others which fill the rest 50% of market demand. This glass application segment is
expected to generate over 35 million tons by 2024 and is supposed to account for just
9
under 50% of the entire demand. Soda ash demand for soaps & detergents is highest
in India and accounted for over 35% of the regional market.
Figure 1.2 Global soda ash market demand by applications (ANSAC, 2017)
Global Demand
Figure 1.3 Global soda ash market demand by regions (ANSAC, 2017)
Furthermore, increasing demand for glass and soaps & detergents also make
Asia-Pacific an attractive market for capacity expansion. Asia-Pacific is the fastest
growing soda ash market across the world, followed by North America and Europe.
The opportunities are cited in growing residential requirements in China and India;
and fast growing economies in South East Asia. Chemical industry is also expected to
present opportunities, supported by favourable growth in paper industry and improved
food processing industries, the overall market remains attractive for coming years. In
2017, it was forecasted by IHS that the global demand for soda ash spotted highest in
Middle East, Indian Subcontinent and Northeast countries as shown in Figure 1.4.
11
Some key players in soda ash market are Solvay SA (Belgium), Tata Chemicals
Limited (India), FMC Corporation (U.S.), OCI Chemical Corporation (U.S.), Nirma
Limited (India), Ciech SA (Poland), Soda Sanayii AS (Turkey), GHCL Limited
(India), DCW Limited (India), and Oriental Chemical Industries (Korea).
Low cost of natural soda ash is likely to benefit the producers in the U.S.,
Turkey, and others. Referring to market outlook published by ICIS, soda ash market
in US has enjoyed strong demand for the past two years, followed by short term
negative trend, while for 2016 remains positive. Figure 1.5 illustrates the fluctuation
of soda ash prices over months in 2015 which shows the positive comeback by the end
of the year. Based on USGS 2014 report, it was known that the total exports of soda
ash in 2013 and 2014 were around 6.47 million metric tonnes and 6.67 million metric
12
tonnes with average price per unit of $187/metric tonne and $195/metric tonne
respectively. Per the U.S. Census Bureau, U.S. exports of soda ash for year 2015 were
6.39 million metric tonnes, which represented about 55% of U.S. soda ash production.
However, the quantity of soda ash exported from China declined to 1,978,049
tonnes in 2016 compared with 2,197,158 tonnes in 2015 (IndMin). Average export
prices also dropped to $194.63/tonne compared to year 2015 and 2014, in which the
average prices were $209.32/tonne and $217.39/tonne respectively.
Local Demand
concerned. Referring to USGS statistics in Figure 1.6, Figure 1.7 and Figure 1.8 below,
the quantity of soda ash being imported from US alone reached almost 106,000 MTA
in year 2016 compared to 80,000 metric tonnes in 2015, 85,000 metric tonnes in 2014
and 91,000 metric tonnes in 2013 respectively. In 2017 and onwards, the demand may
go higher up to 200,000 MTA including imports from China and India.
Figure 1.6 US exports of soda ash to Malaysia in 2016 (till November)
14
15
As for exports from US, the price of soda ash increased over years and faced a
slight fall in year end of 2016 as shown in statistics above which is simplified in Figure
1.9 below. The average price of soda ash was recorded as $191, $200, $208 and $195
from 2013 till 2016 respectively. This significantly shows that the price of soda ash
may face a fall and an increase by the end of the year. According to data obtained from
MOLBASE, the price of soda ash being commercialised is $240/tonne.
17
205 208
200
200
USD/MT
195
195
190
191
185
180
2013 2014 2015 2016
YEAR
Figure 1.9 US exports soda ash prices from 2013 till 2016
This project is aimed to cater the demand of local applications of soda ash by
reducing the imports of US soda ash which is believed to cost more compared to other
exporters. As known earlier, the local demand may rise up to 200,000 MTA in 2017,
therefore at least 50% of the quantities has been decided to be fed via designed plant.
The proposed capacity of the soda ash plant is 100,000 MTA, align with statistics
shown above. It is undeniable that there are several other major soda ash exporters
such as China and India, which may supply double the amount of US exporters.
However, several practical constraints found by accepting supply from US such as
product cost, transportation costs and local currency conversion value. Compared to
China and India, the soda ash produced by US is much expensive due to currency
conversion from US dollar to Ringgit Malaysia which is 1 USD ≈ RM 4.50. Besides,
transporting soda ash in large quantities from US is higher compared to nearby
countries such as Thailand and China (F and D, 1967). Thus, a cheaper soda ash
product and services will be produced and supplied to meet local needs by designing
this 100,000 MTA capacity of production plant.
18
There are some factors that should be considered in selecting the suitable site.
This is very important because the characteristics of a site location will have a market
effect on the success or otherwise of a commercial venture (J., 2013). The choice of
the final site should be based on a complete survey of the advantages and
disadvantages of available industrial estates. However, only a brief review of the
principle factors is illustrated below.
Land Price
In order to reduce the total investment and construction cost, the preferred land
is the land with the most economical or reasonable prices. It is very vital to choose the
lowest land price when starting a new plant to gain the highest economic value for
chemical plant. Nevertheless, it should also provide storage and handling
infrastructures. Sufficient suitable land must be available for the proposed plant for
future expansion. The land characteristics (geological factors) at the proposed plant
site should be examined carefully by referring to respective authorities to get approval
and quotations.
Raw Materials
The source of raw materials is needed to be taken into account during the
selection process of the plant site. The closer the site to the raw materials suppliers,
the cost of transportation will be cheaper. On the other hand, the risk of losing the raw
material during transportation also can be reduced. In case it involves imports from
other countries, the site must be very near to a good seaport or any relevant spot.
source of power. Similarly, a competitively priced fuel must be available on site for
steam and power generation as well as in a continuous supply.
Market Supply
For materials that are produced in bulk quantities; such as soda ash where the
cost of the product per tonne and the cost of transportation play a significant fraction
of the sales price, so the plant should be located close to the primary market. This
consideration may be less important for low volume production, high-priced products.
In an international market, there may be an advantage to be gained by locating the
plant within an area with preferential tariff agreements. In fact, the site plant that is
close to the raw material suppliers and for the market buyers able to gain higher profit
margin.
All industrial processes produce waste products, and full consideration must
be given for the disposal. The disposal of toxic and harmful effluents will be covered
by local regulations, and the appropriate authorities must be consulted during the initial
site survey to determine the standards that must be met. An environmental impact
assessment (EIA) should be made for each new project or major modification or
addition or an existing process based on local regulations.
The proposed plant must be fit in with and be acceptable to the local
community. Full consideration must be given to the safe location of the plant so that it
does not impose a significant additional risk to the community. Align with Siting and
21
Zoning of Industrial and Residential Area (DOE, 2012), the heavy industrial area
should be located at least 500 m away from the residential area to ensure the safe
production and healthy environment.
Climate
Adverse climatic conditions at a site will increase costs. Suitable climate can
make the plant operation run smoothly. Thus, the location that has climate obstacle
such as flood, earthquake and heavy downpour of rainfall needs to be avoided.
However, in Malaysia, it is neither big disasters nor extreme climate changes to be
worried of.
The political stability also very important in selecting the right site location as
it is going to affect the operation of the plant. Tax concessions and other inducements
are often given by governments to attract new investment to preferred locations.
Availability of Labor
Transportation
The transport of materials and products to and from the plant will be an
important consideration in site selection. If practicable, a site should be selected that
is close to at least two major forms of transport such as road, rail or a sea port. Road
transport is being increasingly used, and is suitable for long- distance transport of bulk
chemicals. Air transport is convenient and efficient for the movement personnel and
essential equipment and supplies, and the proximity of the site to a major airport should
be considered.
After reviewing some factors that have significant effect on site location, a
study is done on several locations, which are suitable to construct a soda ash plant.
Basically, the manufacture of soda ash is categorized as a chemical based industry and
therefore must be sited in a special zone provided by the government.
Teluk Kalong Industrial Estate is about 9.6 km from Kemaman. This area is
proposed for petrochemical and heavy industry. The developer of Teluk Kalong is
Perbadanan Memajukan Iktisad Negeri Terengganu (PMINT). The price of the land is
in the range of RM 7,800,000 and the area still available is about 5 acres.
This industrial area provide convenience in order to get the raw material, which
is ammonia due to the present of Petronas Chemical Group Sdn Bhd at Kertih. This
site also fulfils the requirement in term of transportation as for the seaport facility,
Teluk Kalong has the advantageous of having Kemaman Port, which is nearby (10km
away). Whereas, it also link by Kuala Terengganu - Kuala Lumpur New Highway and
Federal Road Kuala Terengganu – Kerteh - Teluk Kalong - Gebeng-Kuantan - Kuala
Lumpur.
The availability of vast industrial land for the chemical and petrochemical
industry at Gebeng Industrial Park has made it world class petrochemical
manufacturing zone. The selling price of land in Gebeng IV for industries is RM 15
per square feet and the available land is about 250 acres.
New infrastructure, facilities and supporting industries in this area will further
enhance Gebeng’s petrochemical industry development. These include the
construction of roads, to increase accessibility to and from this area. A railway link is
24
scheduled to connect Kuantan Port – Gebeng - Kemaman Port - Kerteh - Tok Arun.
Main road to Kuantan also provide ease of transportation of raw materials and
products. Kuantan Port can allow export and import activities run smoothly.
Sungai Semambu and Pengurusan Air Pahang Berhad become the source for
water supply at Gebeng Industrial Estate. Tenaga Nasional Berhad (TNB) provides
about 800 MW of electricity. Manpower can be obtained from local educational
institutions such as Polytechnic Kuantan and Kolej Yayasan Pahang.
In terms of accessibility, the city of Kota Kinabalu also ideal for international
businesses with the availability of direct international flights from and to major cities
in the region such as Kuala Lumpur, Bangkok, Manila, Singapore, Hong Kong, and
Taipei. Besides, Sapangar Port, which is located only 5 km away from KKIP is a deep-
sea port poised to become the main hub for international trade shipping.
Kidurong township. The industrial which is known as Kidurong Heavy Industrial Area
is linked to the Kidurong township and Bintulu town.
While for the road facilities, Kemena Bridge opens the first trunk road system
in the state which linked to Brunei, Sibu and Kuching. The highway from Bintulu town
to the Kidurong Industrial Area is a dual-carriageway, along which street lightings are
provided. Bintulu Port currently ranks second in the country after Malaysia's premier
port, Port Klang.
Sarawak Electricity Supply Corporation (SESCO) and Bakun Power Plant also
can supply electricity to this plant. The Bintulu Water Supply Treatment Plant and
Syarikat Air Sarawak also will be the water supply for this industry.
Land Price Price of land less Price of land RM Price of land >RM
than RM 50 per 50-100 per square 150per square feet
square feet feet
Supply of Own country Take it from Take it from
Raw Material Have pipeline of beside country beside country
gas and the distance and the
is about < 60 distance is >
km 60 km
Use a pipeline Import use a
system pipeline
Transportation Systematic Systematic Good federal
Federal road & federal road & road &
highway highway highway
Airport facilities No railway No railway
Near to port system system
Railway system Near to port Near to port
Airport facilities Airport
facilities
Utilities Low tariff and Complete water Less water
complete water supply supply and
supply Electrical power high of cost
Electrical power plant Electrical
plant and low of Supply of gas or system is not
cost steam system complete and
Supply of gas or high of cost
steam system No gases
supply system
Local Incentives from Incentives from the No incentives from
Government the Local Local Organization the Local
Incentives Organization of of Country Organization of
Country Development Country
Development Development
28
Incentives from
special company
Workers A lot of Medium Difficult to
Supply worker’s supply workers supply find workers
Low investment Low supply
investments High
investment
Table 1.5 Comparison between Gebeng, XXX and YYY
Area Teluk Kalong, Gebeng Phase IV, Tanjung Langsat, Kota Kinabalu Tanjung Kidurong
Proposed Terengganu Pahang Johor Industrial Park Industrial Area,
(KKIP) Sarawak
Location 9.6 km from 40 km from 42 km from 25 km from 20 km from Bintulu
Kemaman Kuantan Johor Bahru. K.Kinabalu 10 km from Kidurong
5 km from 5 km from 5 km from Johor 5 km to Sapangar township
Kemaman port Kuantan Port Port. Port. 9
30 km to KK
gj
10 5 5 International Airport
gj gj 16 km south to h
gj
Tuaran E
h h h
1
E E 8
E
1
1 1 gj
1
1
Types of Heavy Industries1 Chemical & 1 Heavy Industry
1 Medium & Heavyh Heavy Industries
Nearby Petrochemical &1 Petrochemical Marine Related
1
Industries E
0
Industry 1
Chemicals Industry d
1
0 0 Chemical & 0 d
d d 1
10 d8 Petro-chemical
d9
d d 19
gj d
gj 10
gj 2
gj
d 0
hd hd gj
Land Price RM 7,800,000 RM 15.00 per square RM 50.00 per square RM 4,300,000 h
d RM 9,500,000 1
h
E 2
feet 2
E feet h2
4 10 5d
E d4
E
11 1 E14
gj 1
gj gj 1gj
Area Still 5 acres 250 acres 13.345 acres gj 2.56 acres 1
d 2 acres 1
11d d
h
d
h110 11 1
h1 1 1
Available h 2 1h
1
gj
1 1
1gj 11
gj gj gj
E E E1 v
1E
E
29
0h1 1
1
1
10h h1 h
10
h
1 d 01
dv v
E1
v
1dE E0 E
1d E
1 1 d1
d1
1 1d1 1d 1
1d 1
1 1 d1
d1
0 0d1 1d 1
0d 1
0 v d0
21 21 1d 1 1
Raw Petronas Chemical Nearby Petronas Pride Chem KLH Chemicals Sdn Petronas Chemical
Materials Group Bhd @ Kertih Chemical Group Bhd Industries Sdn Bhd Bhd Kota Kinabalu Group Bhd @ Bintulu
Supplier (Ammonia) @ Kertih (Ammonia) Pasir Gudang Johor (sodium chloride) (Ammonia)
KLH Chemicals Sdn (ammonia) Sabah Ammonia Urea KLH Chemicals Sdn
Bhd Pahang (sodium KLH Chemicals Sdn (SAMUR) Bhd Bintulu (sodium
chloride) Bhd Pasir Gudang chloride)
(sodium chloride) 10
8 10 10
gj
gj gj 10 gj
gj h
Developer PMINT – Perbadanan
h PKNP – Perbadanan
h Johor Corporation SEDCO – Sabah h
Lembaga Pembangunan
h E
Memajukan IktisadE Kemajuan NegeriE (JCORP) Economic Development Bintulu E
Negeri Terengganu Pahang TPM TechnoparkE Corporation 1
1 1 1
Sdn Bhd 1 K.K.I.P Sdn Bhd 1
110 1 10
1
10 1 10
1 10
1gj 1gj gj 1
gj
0 gj
Electricity Paka Power Plant
0h Tenaga Nasional
0h 1
Sultan Iskandar
h Sabah Electricity Sarawak Electricity
0
dh h
IPP YTL Powerd Berhad dE Power StationE0 Sdn Bhd Supply Corporation
d
E
Generation Sdn. run by Tenaga d KKIP Power PlantE
d E
Bakun Power Plant
d
d1 d1 1
Bhd. Nasional Berhad Sdn Bhd. d1 1
d d
Tasik Kenyir d1 d1 (TNB) 1
21 1
Hydroelectric 21 21 YTL Power 1d 2
10 1 1
Station 1 10 Generation Sdn2
0 10 10
1
0 gj 0
Bhd 1 d0
gj gjd
dd dd d
h 1d d
h1
1d 10d h
110
d d
E 1d d
E
gj 1d gj1 E 1
1d d
1 vd d
1v
1
h 1
vh2 v2 2
1 2 2
1
E Ev 1
1 11 1
1 1
1
30
1 1
d 1
d d0 d d
1 1 0 0
1 1d 1
1 1
d
1 1
1 d
1 1d 1 1
0 0 d d
v vd v
v v
d
d d d
Water Supply Terengganu Loji Air Semambu Syarikat Air Diversified Water Bintulu Water
Waterworks Pengurusan Air Johor Resources Sdn. Supply Treatment
Department capacity Pahang Berhad Loji Air Sungai Bhd. Plant
Kenyir Dam (PAIP) Layang 10 Syarikat Air
10
10 gj Sarawak Sdn Bhd
10
gj
gj gj h 10
h gj
Road Kuala Terengganu
h – East Coast E
JB East Coasth KK – Sulaman Road
E Pan Borneo
h
Facilities Kuantan – KL –E Expressway Highway to E Road to airport 1 Highway
1
New Highway 1 connecting to Singapore, Senai-
1 1 E
5
Federal Road Gebeng By-Pass 1 Desaru Highway,
1 1
51
1 gj
K.Terengganu- and Kuantan By- 1 Pasir Gudang gj
1 1
Kerteh-Teluk 1 Pass 0 North – South 0
h h1
Kalong-Gebeng-0 Kuantan-Kerteh Highway 0 d
E
d E
Kuantan-KL d Railway Linking Pasir Gudang-Tg.
d d 0
d 1 1d
the Kerteh Kupang-Tuas d d
d 1
9
Industrial Area dand Highway 1d
d 9d 2
Kuantan Port to2 its 1 1d
gj gj2 1
2 right 0
h 10 1 h1
02
1 d
gj d d d1
E Ed 1
d
Airport Kuala Terengganu1 Kuantan Airport
h1 Senai 11
K.K. International d Bintulu Airport dd
1 1
Airport E1 International Airport d d1
1 11
Kerteh Airport 1 Airport v
2
1v 21
Kuantan Airportv1 10 Changi 1v
1
0 1 gj International 0 1v
10
d 1h Airport (nearby) 10d d
10
d
jh gj1
d 0E 10
1
gj
d
31
E h1
d d1 gj 1h
d
1 Ev
2 d1 h v
E
2
1 1
1 d1 E 1
1
1 1
d 20 1 1
d
0 1
1 1 1
Port Facilities Kemaman Port Kuantan Port Johor Port Sdn. Sepangar Bay Port. Bintulu Port
Kerteh minor Port Transport under Bhd.
Kuantan Port Kuantan Port
Consortium. 9 9 9
10
10 gj gj
gj
gj gj h h
Local Pioneer Status h Pioneer Status Pioneer Statush Pioneer Status Pioneer Status
h
Government Investment Tax E Investment Tax Investment TaxE Investment Tax E Investment Tax E
Incentive Allowance (ITA) Allowance (ITA)E Allowance (ITA) Allowance (ITA)1 Allowance (ITA)1
1
1 1 1 19
19 9 91 9
1 1 1
gj 1 gj
1gj gj gj
1 0 0
Workers Local and foreign
0h Local and foreign
h Local and h0
foreign Local and foreign
h Local and foreign
h
0
Supply employees employees E employees Ed employees E
d employees d
E
dE
Universiti Malaysia Polytechnic d Universiti UiTM Kota d Universiti Malaysia
d
1
d1 1 1d 1
Terengganu Kuantan d Teknologi Kinabalu d Sarawak d
1
1d
d1 Kolej Yayasan 1d Malaysia 1
2 2
1
1
210 Pahang 1
2
UiTM Pasir 12 1
1 10
1
Gudang 01 0
1gj
0 0 010
1 gj
d d
dhd d
10
dd
10 dgj
d h
1 1
d
1E
d gjd dgj1 dh
1 E
1 1
d
Total Score 111 11d 122 hd 107 dh 1 106 dE 106
1 1
v v
2
v12 E2 2Ev 21
v 1
1
1 11 11 11
1
d
0d 1d d1 d1
0
1
d1 11 11 10
d
1
32
d1 01 10 1d
d
v
dv dv vd vd
d
2 d d d
2
1 d d 2
1
d 2 2 1
d
33
Based on the ranking, Gebeng Industrial Park, Pahang is the most suitable site
to construct a soda ash manufacturing plant. Basically, the land price at Gebeng is the
cheapest among others and the available land also higher. The estimated land size to
build soda ash plant is about 10 acres and Gebeng the only one which meet this
requirement. The most important factor on this site selection is to meet the demand of
soda ash for glass manufacturing, chemicals, soaps and detergents production and
water treatment in that area. Other factors that highlight on this site selection are
detailed in following subsections. Figure 1.10 depicts the targeted site location in
Pahang, Peninsular Malaysia.
Tax Incentives
The major tax incentives for companies investing in the manufacturing sector are the
Pioneer Status and the Investment Tax Allowance as displayed in Table 1.6.
34
Land Price
For a plant capacity of 274 metric tonne per day, a land size that is needed to build the
plant is about 10 acres with total price of RM 6,534,000.
Utilities
Electric Tariff (High Voltage Peak/ Off-peak Industrial Tariff) by Tenaga Nasional
Berhad (TNB):
0 – 227 m3 0.92
Logistics
From the transportation aspect, Gebeng is near to the Sultan Ahmad Shah
Airport is situated just 12 km from Kuantan, Pahang. Malaysia Airlines, the national
carrier and other domestic airlines, operates flights daily between Kuantan and Kuala
36
Lumpur. Two roads link the Gebeng and Port Industrial Estates to Kuantan. Gebeng
IV is only 30 km from Kuantan. Gebeng is located at 25 km from Kuantan town in
Pahang and 5 km from Kuantan Port. The coastal road is the original highway between
Kuantan and Kuala Terengganu and it is rarely more than 1 km from the shoreline.
The road is constructed to rural highway standards but is constrained by unlimited
direct access which has resulted in the majority of the distance between Kuantan and
Kg. Balok become congested with local traffic, pedestrians and livestock associated
with residential and local center strip development. Besides that, there is New Gebeng
By-Pass that will directly link with East Coast Expressway to connect Kuala Lumpur
as well as Kuantan town and Kuantan Port. This will provide a cost effective means
of transportation and greater accessibility in the transfer of consignments and raw
material to and from Gebeng Industrial Estate to the domestic and international
markets and also to the rest of Malaysia.
Labor
long-term, the Malaysia Labor Force Participation Rate is projected to trend around
67.90 percent in 2020, per econometric models.
Based on the figure above, it can be noted that the number of persons who are
employed and unemployed but looking for is keep on rising through these past years.
Some of these people might have the skills to operate the plant and others who can be
train. Thus, cheap labour is easily available. Malaysia is the world's 67th largest
country by area, and a country of this size has a population to match. Kuantan's
population is approximately 366229 based on statistics in year 2017 which is believed
to increase more in the future. This will give higher chances for the graduates and
adults who are seeking for the job.
Raw Materials
Most of the raw materials such as sodium chloride can be supplied by local
industries in Kuantan itself. Besides, it is planned to build the plant nearby the
ammonia production plant so that can access the raw material ammonia conveniently
and almost can get carbon dioxide. With this, transportation cost will decrease. The
transfer of the raw materials will be either using container truck or shipment from the
38
port to the plant by using sub-contractor. Besides, CUF at Gebeng was set up in year
1999 as part of development of Gebeng Integrated Petrochemical Complex. It
provides centralised utilities such as steam, power, demineralised water, nitrogen gas
and others to the nearby Petrochemical plants.
Market Supply
Figure 1.12 shows a rough sketch of designed plant layout. A few safety and
accessibility aspects have been reviewed and stressed in the planning at this plant’s
layout. There are two major areas in the plant, one is administration area and another
is operation site.
Administration Area
Administration office, canteen, changing room and the first aid room are
included in the administration area. These areas must always away from the operation
site where high accident area is especially the production plant. The first aid room is
located beside the operation area and near the main gate because this placement
enables injured workers have a first aid services and can be send to hospital easily.
Operation Site
The vehicle weighing point is important as it can detect the amount of product
load in and out from the plant. Other than that, the assembly point must locate at the
wide space. Raw material storage tanks are position near the fire station. The
placement of all the equipment in operation site is closed to fire station permits proper
counter actions to prevent any bad consequences to be taken in a short time in case of
any accident or emergencies.
Maintenance workshop has been places near to the operation site and the boiler
system. It is placed there so that any spoilt equipment at both sites can be done quickly
40
and properly. Control room, quality control laboratory and R&D lab is positioned
before the operation site, also nearby raw materials and warehouse. With this,
observations and process controls of all operations can be done smoothly and safely
Since the plant need boiler system, they are built near to the operation site to
supply steam. The load product also near to the warehouse and main gate to make sure
the product is easy to load and deliver to the supplier.
41
Parking Lot
Guard
Vehicle
House
Weighing
Point
Assembly Point
Administration
Building &
Load
Warehouse
Office Product
Materials
Storage
R & D Lab QC Lab
2
1
Maintenance
Work-shop
Fire
Control
Room
Boiler Boiler
Feed System
Storage
Future
Expansion Future
Expansion
Reaction Paths
This was a process invented to make alkali sodium carbonate on a large scale.
The process itself was very polluting. It released huge volumes of an acid gas
(hydrogen chloride) into the air that wrecked the surrounding land. Sodium chloride
was mixed with sulfuric acid before being heated with charcoal and limestone. First,
sea salt (sodium chloride) was boiled in sulfuric acid to yield sodium sulfate
and hydrogen chloride gas. Next, the sodium sulfate was blended with crushed
limestone (calcium carbonate) and coal, and the mixture was burnt, producing sodium
carbonate along with carbon dioxide and calcium sulfide. The sodium carbonate was
extracted from the ashes with water, and then collected by allowing the water to
evaporate.
43
In 1861, Ernest Solvay developed the ammonia-soda process and hence the name
“Solvay” process. It uses salt, limestone and coke or natural gas as raw materials and
ammonia as a cyclic reagent. It is based on the fact that ammonia reacts with carbon
dioxide and water to form ammonium bicarbonate. In these reactions, the preformed
ammonium bi- carbonate reacts with salt to form sodium bicarbonate. This sodium
bicarbonate is then calcined to low density soda ash. Almost all the ammonia formed
by this reaction is recovered and recycled. So, the raw materials for Solvay process are
salt, limestone, and carbon. Ammonia may be considered as a catalyst.
crystallized out and separated by the addition of sodium chloride. In this process, the
sodium bicarbonate is calcined, soda ash is then formed.
In North America, soda ash is obtained from the mineral trona, which contain
~90% of a mixed carbonate-hydrogen carbonate of sodium: Na(HCO3).(CO3).2H2O.
In the so-called monohydrate process of extraction, trona is mined like coal, crushed
and then calcined in rotary a kiln which converts the sesquicarbonate to the carbonate.
Resulting sodium carbonate is dissolved in water, the insoluble impurities filtered off
and the solution evaporated to dryness, thereby yielding the monohydrate
Na2CO3.H2O. Heating this product gives anhydrous sodium carbonate, Na2CO3.
45
Table 1.10 Properties and Prices of Raw Material, Product and By-products
Molecular
Chemical Chemical Cost
Weight Sources
Compounds Formula (RM/Kg)
(Kg/Kmol)
Sodium
58.440 NaCl 0.52 Molbase
Chloride
Sulphuric
98.079 H2SO4 0.22 ICIS
Acid
Calcium Adinath
100.087 CaCO3 1.33
Carbonate Petrochem
Carbon 12.011 C 2.73 Molbase
Hydrochloric
36.461 HCl 0.22 ICIS
Acid
Calcium
72.143 CaS 3.45 ICIS
Sulphide
Carbon
44.010 CO2 0.74 Molbase
Dioxide
Sodium
105.989 Na2CO3 1.08 Molbase
Carbonate
Calcium
110.980 CaCl2 0.95 Molbase
Chloride
Ammonia 17.031 NH3 0.84 Molbase
Water 18.01528 H2O 8.4⨯10-4 PAIP
Ammonium
53.491 NH4Cl 2.14 Molbase
Chloride
Na2CO3•NaHCO3•
Trona 226.0300 0.70 ICIS
2H2O
Sodium
39.997 NaOH 2.60 Molbase
Hydroxide
Leblanc Process: 2NaCl + H2SO4 + CaCO3 + 2C → Na2CO3 + 2CO2 + CaS + 2HCl
Kg/Kg
1.1028 0.9254 0.9443 0.2266 1.0000 0.8305 0.6807 0.6880
Na2CO3
Gross Profit = [(1.0000 x 1.08) + (0.8305 x 0.74) + (0.6807 x 3.45) + (0.6880 x 0.22)] - [(1.1028 x 0.52) + (0.9254 x 0.22) + (0.9443 x 1.33) +
(0.2266 x 0.23)]
= RM 4.1943 – RM 2.6516
= RM 1.54 / Kg
46
47
Gross Profit = [(1.0471 x 0.95) + (1.0000 x 1.08)] - [(0.9443 x 0.66) + (1.1028 x 0.49)]
= RM 2.0747 – RM 1.8294
= RM 0.25 / Kg
Gross Profit = [(1.0000 x 1.08) + (1.0094 x 2.14)] – [(1.1028 x 0.74) + (0.3214 x 0.84)
+ (0.4152 x 0.52) + (0.1700 x 8.4⨯10-4)]
= RM 3.2401 – RM 1.1508
= RM 2.09 / Kg
48
49
Higher investment in ammonia recovery units than
crystallization unit of NH4Cl
Dual Process Replaces calcium chloride as a by-product with More expensive that the Solvay process
the more useful ammonium chloride Requires existing machinery to be replaced or significantly
Both economical and environmentally friendly modified
than both the Leblanc and the original Solvay
processes
Energy consumption lower than Solvay process
Carbonating No by-product Only can produce dense soda ash.
Caustic Soda
Monohydrate More cost-effective than synthetic soda ash Requires the use of large amounts of coal, fuel oil, natural
Process production gas or mixtures thereof for calcination step
(Natural Lack of trona
Trona)
50
The reaction paths are rated from 1 to 5 with 5 as the best rating and being presented in Table 1.12 below.
51
52
Justification on Selection
The selection on reaction path is very crucial since there are many criteria need
to be taken into account apart from gross profit of reaction path alone. From 5 reaction
routes suggested in the section above, reaction path 3 which is Dual Process is selected
based on Table 1.11 and Table 1.12 which include several aspects such as GP value,
product yield, inherent safety, equipment and other costs. Firstly, GP of reaction 3 is
the highest among the 5 process routes which is very optimistic towards profit. In term
of safety, this selected reaction path shows a safe process. For instance, in reaction
path 1, the process releases hydrogen chloride gas which becomes hydrochloric acid
in the atmosphere and calcium sulfide was spread on nearby fields, releasing hydrogen
sulfide, the toxic gas that produces the "rotten egg" odour. As for reaction path 2, the
safety needs to be monitored additionally since calcium chloride is produced as a by-
product. Besides, Dual process replaces calcium chloride as a by-product with the
more useful ammonium chloride, which can be recycled to be reused in the process,
refined and used as a fertilizer. This eliminated the need for waste beds and other
disposal methods to take place, as the by-products can be used in other productions.
Furthermore, Dual process is more economic and environmental friendly process
which require less energy consumption compared to rest of process routes.
CHAPTER 2
Referring to previous section, the process that will be used is Dual process. All
the required raw materials are able to be supplied by local industries nearby the Gebeng
Industrial Park Phase IV, Gebeng, Kuantan Pahang. The raw materials are ammonia,
sodium chloride, carbon dioxide and water. Water can be supplied through pipeline by
Pengurusan Air Pahang Berhad (PAIP), Pahang water supplier. Other raw materials
with their respective available sources are tabulated in Table 2.1as shown below.
54
Table 2.1 Sources available for raw materials in sodium chloride production
Raw
Supplier Location Transport
materials medium
No 36, Jalan IM 14/8, Kawasan
Sodium KLH Chemicals
Industri Indera Mahkota, 25200 Container
Chloride Sdn. Bhd. Truck
Kuantan, Pahang
No 36, Jalan IM 14/8, Kawasan
Sodium KLH Chemicals
Industri Indera Mahkota, 25200 Container
Hydroxide Sdn. Bhd. Truck
Kuantan, Pahang
Petronas
Kompleks Pentadbiran
Chemicals
Petrokimia Petronas, 23400,
Ammonia
Kerteh, Kemaman, Terengganu
Ammonia Sdn. Bhd. Container
Truck
Lot 4, Kaw. Perindustrian
Teknogas (M)
Tanjung Kling, Tanjung Bruas
Sdn. Bhd.
Jetty, 76400 Melaka
Lot 43, Semambu Industrial
Estate, Mukim of Kuala
The Linde Group
Kuantan, 25350 Kuantan,
Pahang
Callserv 24, Jalan IM14/1, Industri Piping System
Carbon or
Sdn. Bhd. Ringan Prima Kota, Bandar High Pressure
Dioxide
Indera Mahkota, 25200 Cylinder
Container
Kuantan, Pahang
Southern No 2, Jalan Gebeng 2/10,
Industrial Gas Kawasan Perindustrian Gebeng
Sdn Bhd 26080, Kuantan, Pahang
55
In Dual process, there are 4 main raw materials involved as listed in the previous part.
Those raw materials are listed according to their specifications as tabulated in Table
2.2 as shown below.
Table 2.2 Raw Materials with their respective specifications (assuming continuous
operation)
Specifications
Raw
Physical state Purity Amount required Physical state
material
at room temp. (%) (mt/d) during supply
Sodium
Solid 99.99 402.96 Solid
Chloride
Liquidified
Ammonia Gas 99.99 88.08
Gas
Carbon Liquidified
Gas 99.50 113.76
Dioxide Gas
Water Liquid 85.00 93.12 Liquid
56
There are 8 major components to be considered in designing the soda ash production
plant. The summary of physical properties of every component obtained from MSDSs
are listed from Table 2.3 to Table 2.10, whereas Table 2.11 represents the toxicity data
of listed components for safety considerations in handling the components.
Sodium Chloride
Water
Brine
Ammonia
Carbon Dioxide
Ammonium Chloride
Sodium Bicarbonate
The toxicity data are summarized from several Material Safety Data Sheets
(MSDSs) in Table 2.11. It is used to indicate the toxicity level for each material
produced or used throughout the reaction. Besides, it is also being used as a reference
in deciding which compound is the most harmful or hazardous and need to be separated
first.
An informal approach introduced by Rudd et al. (1973), has been adopted in this
design project. There are total of five synthesis steps included in designing soda ash
production plant using two different alternatives. Process heuristics are considered, by
referring to a book, titled as Product and Process Design Principles by Seider et al.
(2010) while designing the process flowsheet to ensure safe and effective production.
Alternative 1
For the manufacturing of soda ash, the reaction used is well known and widely
used, however, the most challenging part for the chemical engineer is to select the best
alternative technology that produce soda ash. Reaction path 3 is being used for this
alternative too due to its positive factors. The process flowsheet for this first step is
displayed in Figure 2.1. Table 2.12 shows the overall reaction and gross profit of each
reaction path.
Table 2.12 Gross Profit for each reaction pathway of soda ash
Economic
Route Overall Reaction Potential
(RM/kg)
1 2NaCl+H2SO4+CaCO3+2C → Na2CO3+2CO2+CaS+2HCl 1.54
2 2NaCl+CaCO3 → Na2CO3+CaCl2 0.25
3 2NaCl+2NH3+ CO2+H2O → Na2CO3+2NH4Cl 2.09
4 2NaOH+CO2 → Na2CO3.H2O 0.86
5 2Na2CO3•NaHCO3•2H2O → 3Na2CO3+5H2O+CO2 0.19
67
Figure 2.1 shows the very first step toward creating the process flowsheet of
soda ash production using Dual Process. Each main reaction operation involved is
positioned with arrows representing its feed and product chemicals. Hereby, there are
2 main operations here to produce soda ash as main product. The first reaction is
carbonation of ammoniated brine from the ammonia absorption tower which was in an
exothermic condition. Secondly, the production of light soda ash through thermal
decomposition of sodium bicarbonate. The thermal decomposition is carried out in a
calciner operating at 200℃ (Patel, 2010a). The total production capacity of soda ash
was set at 100,000 mt/yr, assuming operation annually without considering shutdown
period. By performing simple material balances based on Figure 2.1, the results show
that each flowrate is 943.50 mtmol/yr or 0.1077 mtmol/hr which is used as a basis for
further manual calculations.
Sodium chloride and water are fed at 1:3, 16.79 mt/hr and 50.37 mt/hr
respectively before mixing with 3.67 mt/hr ammonia in ammonia absorption vessel.
The reaction of 9.48 mt/hr carbon dioxide with ammoniated brine results in production
of 18.1 mt/hr sodium bicarbonate (NaHCO3) and 11.52 mt/hr ammonium chloride
(NH4Cl). The calcination of sodium bicarbonate eventually produces 11.42 mt/hr soda
ash.
Figure 2.1 Main reaction operations in light soda ash production
68
69
In order to achieve the distribution of chemicals in Figure 2.2, the purified brine
consisting sodium chloride in water solution are mixed with ammonia in 1:1 ratio via
absorption process. Here, the ammonia is assumed to be absorbed ideally (100%) by
the brine solution which is an exothermic reaction releasing heat up to 70℃. Besides
that, carbonation reaction plays the vital role in production of both ammonium chloride
and soda carbonate. Per Heuristic 2, the use of an excess reactant, sodium chloride
solution to consume completely a valuable reactant, ammonia and in this case in
carbonation tower with assistance of carbon dioxide. The operation reaction is
designed in temperature range of (45 – 55)℃ at 1 atm which ends with 75% of
conversion of sodium chloride fed (Khan, 2011). Since water is fed at huge amount,
the additional or remaining water is needed to be recycled after separation from NaCl
and NH4Cl via evaporation, and the recycled stream is approximately equivalent to [(1
– 0.75)/0.75] ⨯ 50.37 or 46.49 mt/hr of water. While, the remaining stream of NaCl is
[(1 – 0.75)/0.75] ⨯ 16.79 or 4.20 mt/hr of NaCl which is delivered out together with
NH4Cl as fertilizer. As well, the mixture can be sent to market for application medical
treatment purposes as illustrated by (National Center for Biotechnology Information,
2017).
70
71
There are total of four separation systems have been introduced for the soda
ash production plant to get the higher purity of it. The separation systems are
implemented based on their physical states, volatility and even solubility. Table 2.13
below shows the summary of some physical properties of the materials involved in the
production.
From the table, it can be clearly seen that the absorption of ammonia into brine
can be done even though in exothermic condition. This is because the solubility of
ammonia at 70℃ is observed at 170 kg/kg water. Besides, stream consisting carbon
dioxide and water leaving from thermal decomposition can be easily separated via
their boiling point difference or simply physical state difference at room conditions.
Separation drum is placed to separate both components leaving CO2 to top recycling
gas stream and H2O to bottom recycling liquid stream right after a condenser or cooler.
top stream while aqueous components in bottom liquid stream (Singhal, 2009). The
solids of NaHCO3 is calcined further to produce light soda ash as the main product.
Since both ammonium chloride and sodium chloride solids are readily soluble
in water, the separation can be done firstly via evaporation of water from solids surface.
The assumption is made such that the water is fully evaporated as water vapor at top
stream, leaving solids in bottom. The vapor is then collected, condensed and
transported to the dissolver which acts as a mixer as well, whereas the solids are sent
for packaging as mixed fertilizers.
Figure 2.3 Process flowsheet including separation units in soda ash production
73
74
Figure 2.4 shows the possible flowsheet includes the temperature, pressure and
phase differences. The operations involved are as follows:
11. Stream leaving evaporator consisting plenty of water vapor needs cooling at
25℃ as well to change its phase into liquid state.
12. The liquid stream of water is pumped back to the dissolver at 4 atm.
Figure 2.4 Temperature, pressure and phase changes (represented by green arrow) in soda ash production
76
77
(NH4Cl) solids with conversion of 75% of NaCl fed. It must be noted that NH4Cl
formed at solid state, but remained in the solution at aqueous state due to high
solubility in water. The remaining NaCl in aqueous state also being transported
via exit stream from bottom outlet point of the tower.
8. Rotary Filter. The filtration of NaHCO3 solids from slurries is done here with
aid of suction at 1 atm. The rotary drum has plenty of small pores where the
solids cannot pass through it and eventually stick on the wall lining of the rotary
drum, forming thick layer. This layer is removed through rotation of the filter at
cutting point, which will be collected in the collector below it. The rotation
speed can be controlled such that the sufficient amount of solids formed.
Whereas, the filtrate consisting aqueous NH4Cl and NaCl is discharged from
bottom exit of rotary filter as liquid solution.
9. Calciner. The calciner operates at temperature of 200℃ to ensure the desired
100% conversion is achieved. At the same time, carbon dioxide and water vapor
also observed to be escape into top outlet of the tower. The temperature is set
more than minimum decomposing temperature which is 50℃, simply because to
ensure complete conversion of NaHCO3 into soda ash (Na2CO3) which was fed
from nearly top of the tower. Hot soda ash (anhydrous) will be transported in the
bottom stream for further process.
10. Cooler 3/Condenser 1 and Cooler 4. The condenser is designed to cool the top
outlet stream of CO2 and H2O vapor to 25℃ to condense the H2O vapor into
liquid state to separate out from CO2 stream. Whereas, Cooler 4 is designed to
cool the hot Na2CO3 solids in bottom stream of calciner to similar temperature as
well before transporting to packaging. cw is used as the cold utility for both
coolers to bring down the high temperature.
11. Separation Drum. This unit is purposely installed for the complete separation
of liquid H2O and gaseous CO2 at 25℃. The water stream leaving the bottom of
the column is then directed to wastewater treatment system while the gaseous
CO2 is discharged to the mixer before entering the carbonation tower.
12. Compressor 2. The recycled stream of gaseous CO2 is pumped at 4 atm to
Mixer 2 (M2) to reduce the fresh feed of CO2 into carbonation tower. The
temperature of CO2 is observed a significant increase in the stream due to
pressure increase.
79
13. Heater 1. The bottom stream of filter consisting dissolved solids of NH4Cl and
NaCl is heated to reach the saturation point of water at around 99.6℃ to ensure
the water at saturated liquid state for easier separation from solid molecules.
14. Evaporator. The dehydration process takes place at 100℃ with aid of lps
circulating throughout the evaporator to evaporate out the large amount of water
vapor. The evaporation rate is assumed at 100% and leaving exact amount of
solids to be delivered as fertilizer.
15. Cooler 5 and Cooler 6/Condenser 2. The cooling of NH4Cl-NaCl mixture and
H2O vapor to 25℃ is done with aid of cw. The solids are sent for packaging
while the condensed water will be pumped to dissolver.
16. Pump 2. Liquid water is pumped at 4 atm back into dissolver to reduce fresh
feed amount of water as well as complete mixing with NaCl feed. No
temperature difference is observed.
Figure 2.5 Task integration flowsheet on soda ash production
80
81
Alternative 2
82
Figure 2.7 Process flowsheet of soda ash production showing the chemicals distribution
83
Based on Figure 2.8, there are three separation systems have been introduced
for the soda ash production plant to get the higher purity of it. The separation systems
are implemented based on their physical states, volatility and even solubility. The
summary of some physical properties of the materials involved in the production
referred to Table 2.13 above.
84
85
Figure 2.4 show the possible flowsheet includes the temperature, pressure and
phase differences. The temperature, pressure and phase differences are almost similar
with Alternative 1. The changes are notified as shown in Figure below. The other
differences in temperature, pressure and phase can be referred to Alternative 1.
1. The aqueous stream leaving the bottom of filtration process is further needed
to decrease the temperature to 0OC. This process is to crystallize out the
ammonium chloride, NH4Cl from the water and aqueous sodium chloride. This
process is operating at 1 atm.
2. The phase change of NH4Cl occurs in crystallization process through low
temperature cooling by using refrigerant. Ammonium chloride leaves the
cooling crystallizer in solid form as a byproduct in this soda ash production.
3. The temperature of aqueous stream which contains sodium chloride and water
is needed to increase from 0 OC to 25 OC in order to allow the unreacted sodium
chloride and water is recycling back into the feed stream.
Figure 2.9 Temperature, pressure and phase changes (represented by green arrow) in soda ash production
86
87
88
89
The reaction paths are rated from 1 to 2 with 2 as the best rating and being presented
in Table 1.xx below.
From the above comparison table, it can be concluded that the first alternative
is preferable compared to the second alternative. The reason why the first alternative
is better because this alternative is more environmental friendly compared to second
alternative. In first alternative, carbon dioxide from the calciner is recycled back to the
carbonation tower while in second alternative, the carbon dioxide from the calcination
process is released to the surrounding after proper gas treatment to reduce the
concentration of carbon dioxide. Untreated carbon dioxide in the air may contribute to
the "Greenhouse Effect" and gives rise to global warming. This results in additional
operating cost in Alternative 2.
expensive since it required refrigerant to cooling down the temperature from 25OC to
0OC. Thus, the first alternative is selected.
Complete Process Flow Diagram (PFD)
Figure 2.11 Complete process flowsheet for soda ash production (drawn using Microsoft Visio)
92
CHAPTER 3
NaCl (s) + NH3 (g) + CO2 (g) + H2O (l) NaHCO3 (s) + NH4Cl (s)
2NaHCO3 (s) Na2CO3 (s) + CO2 (g) + H2O (v)
Overall: 2NaCl (s) + 2NH3 (g) + CO2 (g) + H2O (l) Na2CO3 (s) + 2NH4Cl (s)
Carbonation Reaction
Calcination Reaction
Reference Conditions
General assumptions:
1. Standard temperature is 25℃ and standard pressure is 1 atm.
2. Kinetic energy and potential energy are neglected.
3. No heat loss due to friction, conduction and convection during flow in pipeline.
96
4. Heat of mixing and heat of dissolution are neglected for dissolver and mixer.
5. Energy due to pressure changes in rotary filter is neglected.
Formula involved:
1. Material balances:
Input = Output
̂𝑣
𝐻 = 𝑚̇𝐻
̂𝑓
𝐻 = 𝑚̇𝐻
̇
̂𝑜𝑢𝑡 − ∑ 𝑚̇𝑖𝑛 𝐻
∆𝐻 = ∑ 𝑚̇𝑜𝑢𝑡 𝐻 ̂𝑖𝑛
𝑇 𝑇
̂𝑖 = 𝐻𝑓𝑖 + ∫
𝐻 𝐶𝑝𝑙 𝑑𝑇 + 𝐻𝑣𝑖 + ∫ 𝐶𝑝𝑣 𝑑𝑇
𝑇𝑟𝑒𝑓 𝑇𝑟𝑒𝑓
where 𝐶𝑝 = 𝑎 + 𝑏𝑇 + 𝑐𝑇 2 + 𝑑𝑇 3
* The parameters are obtained from Table B.2 from Appendix B in (Felder and
Rousseau, 2005), and thermodynamics properties data in Section 2.3 above.
Summary of Material Balances (Equipment)
The summary of material balances involving all unit operations is listed in Table 3.1.
97
Outlet: 9 Pout: 4 atm, Tout: 128℃
Inlet: 9 Mixer 2 CO2 (g) 4.74 CO2 (g) 9.48
Outlet: 10 (128℃, 4atm) Recycled CO2 (g) 4.74
Inlet: 10 Cooler 2 CO2 (g) 9.48 CO2 (g) 9.48
Outlet: 11 Tout: 45℃
Inlet: 7, 11 Carbonation Reactor NaCl (aq) 16.79 NaHCO3 (s) 18.10
Outlet: 12 (45℃, 4atm) H2O (l) 50.37 NH4Cl (aq) 11.52
75% of NaCl
NH3 (aq) 3.67 NaCl (aq) 4.20
CO2 (g) 9.48 H2O (l) 46.49
Inlet: 12 Rotary Filter NaHCO3 (s) 18.10 NaHCO3 (s) 18.10
Outlet: 13, 14 (45℃, 1atm) NH4Cl (aq) 11.52 NH4Cl (aq) 11.52
NaCl (aq) 4.20 NaCl (aq) 4.20
H2O (l) 46.49 H2O (l) 46.49
Inlet: 14 Calciner NaHCO3 (s) 18.10 CO2 (g) 4.74
100% of
Outlet: 15, 17 (200℃, 1atm) H2O (v) 1.94
NaHCO3
Na2CO3 (s) 11.42
Inlet: 15 Cooler 3 Na2CO3 (s) 11.42 Na2CO3 (s) 11.42
Outlet: 16 Tout: 25℃
Inlet: 17 Cooler 4 CO2 (g) 4.74 CO2 (g) 4.74
Outlet: 18 Tout: 25℃ H2O (v) 1.94 H2O (l) 1.94
Inlet: 18 Separation Drum CO2 (g) 4.74 CO2 (g) 4.74
Outlet: 19, 20 (25℃, 1atm) H2O (l) 1.94 H2O (l) 1.94
Inlet: 20 Compressor 2 Recycled CO2 (g) 4.74 Recycled CO2 (g) 4.74
98
Outlet: 21 Pout: 4 atm, Tout: 128℃
Inlet: 13 Heater 1 NH4Cl (aq) 11.52 NH4Cl (aq) 11.52
Outlet: 22 Tout: 99.6℃ NaCl (aq) 4.20 NaCl (aq) 4.20
H2O (l) 46.49 H2O (l) 46.49
Inlet: 22 Evaporator NH4Cl (aq) 11.52 NH4Cl (s) 11.52
Outlet: 23, 25 (100℃, 1atm) NaCl (aq) 4.20 NaCl (s) 4.20
H2O (l) 46.49 H2O (v) 46.49
Inlet: 23 Cooler 5 NH4Cl (s) 11.52 NH4Cl (s) 11.52
Outlet: 24 Tout: 25℃ NaCl (s) 4.20 NaCl (s) 4.20
Inlet: 25 Cooler 6 H2O (v) 46.49 H2O (l) 46.49
Outlet: 26 Tout: 25℃
Inlet: 26 Pump 2 Recycled H2O (l) 46.49 Recycled H2O (l) 46.49
Outlet: 27 Pout: 4 atm
99
100
The material and energy balances for each stream are computed by inserting all required process parameters with aid of build-in formula in
Microsoft Excel. The complete results are presented in Table 3.3 below.
102
∆H (kW) -17096.12 -32800.45 -254741.52 -2765.01 -254641.47 -256233.60 -256233.60 -11772.51 -11650.65 -23301.30 -23500.00 -289951.29 -233476.42 -56488.83
Stream 15 16 17 18 19 20 21 22 23 24 25 26 27
Phase Solid Solid Vapor+Gas Mixed Liquid Gas Gas Mixed Solid Solid Vapor Liquid Liquid
Temperature (℃) 200.0 25.0 200.0 25.0 25.0 25.0 128.0 99.6 100.0 25.0 100.0 25.0 25.0
Pressure (atm) 1 1 1 1 1 1 4 1 1 1 1 1 4
Mass Flow (g/hr)
NaCl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4200000.00 4200000.00 4200000.00 0.00 0.00 0.00
H2O 0.00 0.00 1940000.00 1940000.00 1940000.00 0.00 0.00 46490000.00 0.00 0.00 46490000.00 46490000.00 46490000.00
NH3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CO2 0.00 0.00 4740000.00 4740000.00 0.00 4740000.00 4740000.00 0.00 0.00 0.00 0.00 0.00 0.00
NH4Cl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11520000.00 11520000.00 11520000.00 0.00 0.00 0.00
NaHCO3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Na2CO3 11420000.00 11420000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Mass Flow (g/hr) 11420000.00 11420000.00 6680000.00 6680000.00 1940000.00 4740000.00 4740000.00 62210000.00 15720000.00 15720000.00 46490000.00 46490000.00 46490000.00
Mole Flow (mol/hr)
NaCl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71868.58 71868.58 71868.58 0.00 0.00 0.00
H2O 0.00 0.00 107658.16 107658.16 107658.16 0.00 0.00 2579911.21 0.00 0.00 2579911.21 2579911.21 2579911.21
NH3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CO2 0.00 0.00 107702.79 107702.79 0.00 107702.79 107702.79 0.00 0.00 0.00 0.00 0.00 0.00
NH4Cl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 215367.36 215367.36 215367.36 0.00 0.00 0.00
NaHCO3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Na2CO3 107746.01 107746.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Mole Flow (mol/hr) 107746.01 107746.01 215360.95 215360.95 107658.16 107702.79 107702.79 2867147.15 287235.94 287235.94 2579911.21 2579911.21 2579911.21
∆H (kW) -33259.02 -33847.21 -17300.56 -20320.57 -8548.06 -11772.51 -11650.65 -230197.38 -29381.09 -29813.52 -140117.13 -204844.95 -204844.95
103
CHAPTER 4
For the current project, the simulator programme used is called Aspen PLUS.
The simulation was carried out for this project to compare the results of manual
calculations and the simulated values to provide assurance that the assumptions and
calculations made were correct and as close as possible to actual plant operations. The
“NRTL” model was used to calculate the phase equilibrium. The components were
added and since the product is in solid form, the main product which is NaHCO3 and
Na2CO3 were set up as solid instead of conventional. Other components such as NaCl,
H2O, NH3, CO2, and NH4Cl were set up as conventional. Several missing parameters
like “DHFORM” which is enthalpy of formation and “DGFORM” which is ideal gas
Gibbs free energy of formation for certain components were added to run the
simulation. The missing parameters were obtained by online or referring to the books.
In simulation environment, the simulation was carried out for individual unit
operation before running a complete process to ensure the output is correct and
minimize the errors. In soda ash production process, 1 rotary filter, 2 reactors, 2
compressors, 2 pumps, 3 separators, 3 mixers and 7 heat exchangers were used to
simulate the complete process. The unit blocks and streams were labelled and the result
data was rearranged accordingly for better analysis. Although it is handy but it may be
time consuming, especially in the separation models since this project involve solid
materials separation.
105
A computer based process simulator such as Aspen Plus is a useful tool for
designers and plant operators in many ways. The ability to imagine and simulate the
operations of one’s own plant is a very crucial part. This simulation that generated by
computer could provide information important for the users to substitute data that are
not readily available from the control instrumentation and literature. Simulations of
the plant could also be used to cross check the actual performance comparing to the
simulated work load and efficiency. Thus, errors and mistakes such as faulty
instruments and instrument could be readily identified and rectified.
4.2 Complete Process Flow Diagram (Aspen Plus)
106
Figure 4.1 Complete process flowsheet of soda ash production simulated using Aspen Plus
107
108
Stream Name 15 16 17 18 19 20 21 22 23 24 25 26 27
Vapor Fraction 0.00 0.00 1.00 0.51 0.00 1.00 1.00 0.80 0.00 0.00 1.00 0.00 0.00
Liquid Fraction 0.00 0.00 0.00 0.49 1.00 0.00 0.00 0.20 1.00 1.00 0.00 1.00 1.00
Solid Fraction 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0
Temperature ( C) 200.00 25.00 200.00 25.00 25.00 25.00 127.59 99.60 100.00 25.00 100.00 25.00 25.07
Pressure (bar) 1.01 1.01 1.01 1.01 1.01 1.01 4.05 1.01 1.01 1.01 1.01 1.01 4.05
Mole Flow (kmol/hr)
NH3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NaCl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.95 71.95 71.95 0.00 0.00 0.00
H2O 0.00 0.00 107.67 107.67 104.30 3.37 3.37 2583.99 0.00 0.00 2583.99 2583.99 2583.99
CO2 0.00 0.00 107.67 107.67 1.62 106.05 106.05 0.07 0.07 0.07 0.00 0.00 0.00
NaHCO3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NH4Cl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 215.34 215.34 215.34 0.00 0.00 0.00
Na2 CO3 107.67 107.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Flow (kmol/hr) 107.67 107.67 215.34 215.34 105.91 109.42 109.42 2871.35 287.36 287.36 2583.99 2583.99 2583.99
Mass Flow (kg/hr)
NH3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NaCl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4204.97 4204.97 4204.97 0.00 0.00 0.00
H2O 0.00 0.00 1939.69 1939.69 1878.95 60.74 60.74 46551.32 0.00 0.00 46551.32 46551.32 46551.32
CO2 0.00 0.00 4738.50 4738.50 71.12 4667.38 4667.38 2.91 2.91 2.91 0.00 0.00 0.00
NaHCO3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18 0.18 0.18 0.00 0.00 0.00
NH4Cl 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11518.57 11518.57 11518.57 0.00 0.00 0.00
Na2 CO3 11411.72 11411.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Flow (kg/hr) 11411.72 11411.72 6678.19 6678.19 1950.07 4728.12 4728.12 62277.94 15726.62 15726.62 46551.32 46551.32 46551.32
Enthalpy (kW) -33127.29 -33771.58 -18608.27 -20278.05 -8459.08 -11818.98 -11696.04 -201540.00 -26962.14 -27639.55 -171260.00 -205140.00 -205140.00
109
110
The comparison is done between manually calculated and simulated mass and
energy balances on stream basis. The comparison is done to justify the manual
calculation where its deviation should not be more than 15%. The complete
comparison data is tabulated in Table 4.3.
𝐸𝑛𝑡ℎ𝑎𝑙𝑝𝑦𝐴𝑠𝑝𝑒𝑛 − 𝐸𝑛𝑡ℎ𝑎𝑙𝑝𝑦𝑀𝑎𝑛𝑢𝑎𝑙
𝐸𝑟𝑟𝑜𝑟 (%) = | | ×100%
𝐸𝑛𝑡ℎ𝑎𝑙𝑝𝑦𝐴𝑠𝑝𝑒𝑛
111
Justification on Deviations
After a detailed analysis on the manual and simulation results, it is found that
the material balances showed a great convergence compared to energy balances. As
displayed in Table 4.3, most streams highlighted least deviation between manual
calculation and simulation for less than 1% except for Stream 8 and Stream 9 which
exceeded 1%. This may due to the recycling error of carbon dioxide in simulation
where minor amount of the selected component might have lost in earlier separation
from water vapor before mixing with fresh feed, thus increasing the feed amount from
4740 to 4812.62 kg/hr.
As for energy balances, almost 21 streams showed deviation less than 2%,
leaving 5 streams with deviation of less than 15%, and followed by 1 stream which
exceeded the limit fixed, Stream 25. Stream 25 carries the vaporized water evaporated
from mixture of NaCl, NH4Cl and water at evaporator which operates at 100℃ and
1atm. Even though the separation in both manual and Aspen showed 100%, but due to
the recycling error of water, the actual amount to be recycled should be 46490 kg/hr
instead of 46551.32 kg/hr. This may cause the calculation in Aspen simulation went
wrong to a higher exothermic value since the difference is considered huge. However,
overall material and energy balances showed a good agreement between manual and
simulation which confirms the correct assumptions and calculation made in process
design.
CHAPTER 5
As shown in figure above, the liquor leaving centrifuge after carbonation tower,
contains ammonium chloride, unreacted NaCl and traces of sodium carbonate which
is ammoniated in ammonia absorber. Then, the ammoniated liquor is sent to a bed of
washed salt in salt dissolver. A refrigeration unit is utilised to cool the liquor at 0℃,
resulting into crystallize out ammonium chloride. The slurry containing ammonium
chloride crystals is thickened and NH4Cl is centrifuged and dried before selling.
114
On the other hand, the liquor obtained after the separation of NH4Cl is further
charged to a series of carbonation towers in which CO2 is passed from bottom in the
counter current flow of liquor. The resulting sodium bicarbonate is thickened in
thickener and centrifuged leaving the unreacted liquor stream to be recycled to
ammonia absorbing tank. The sodium bicarbonate is then calcined into sodium
carbonate as the main product.
There are several modifications have been carried out to ensure the purity of the
product produced, and cheaper and easier process flow. The innovation done in terms
of unit operations are as follows:
Next, latest rotary filter is designed over centrifuge due to its separation ability.
Rotary filter introduces vacuum suction to the mixture containing valuable sodium
bicarbonate, forcing it to be form layers on filter due to tiny pores surrounding the
filter, leaving very low solid content filtrate to bottom. While, centrifuge may lead to
solids accumulation, complexity and even foaming in liquid stream (Letki, 1998).
115
Lastly, crystallizer is replaced with simple evaporator since the process is already
modified where its inlet stream contains sodium chloride besides ammonium chloride
in dissolved manner. Crystallization process involves cooling by refrigeration which
is relatively expensive and the purity of products produced in continuous process is
low (Charles G. Moyers, 1987).
Apart from unit operations, there are several major modifications have been
introduced to the production process. Firstly, the recycling streams in innovated PFD,
Stream 20 and Stream 25 consists of carbon dioxide and water respectively, are not
listed in original PFD. In original PFD, the ammoniated brine which is separated from
sodium bicarbonate is recycled straight to the ammonia absorber and followed by
removal of ammonium chloride by crystallization. In latest PFD, the carbonation
reaction is set at optimum condition to consume fully the valuable carbon dioxide and
ammonia to reduce them to least level in the exit stream. As well, it is ensured that the
ammonium chloride is separated out together with sodium chloride before recycling
water back to the dissolver. By doing so, higher purity of products can be achieved
besides cheaper and easier process is implemented.
CHAPTER 6
HEAT INTEGRATION
6.1 Introduction
Heat integration seeks to utilize the energy in the high temperature streams that
need to be cooled and/ or condensed to heat and/ or vaporize the cold streams (Seider
et al., 2010). To accomplish this, hot process streams are cooled with cold process
streams. When the sum of heating requirements does not equal to the sum of cooling
requirements, it is always necessary to provide heating or cooling through the use of
utilities such as steam and cooling water. The main objective is set to achieve
maximum energy recovery (MER) as well as to minimize utility targets to achieve cost
savings. In conjunction to this, pinch analysis which has been introduced by Linnhoff
(1993) is used as a tool to accomplish the heat integration involving heat exchangers
in the production process.
Pinch analysis is the systematic approach for optimal design and retrofit for
process systems for maximum energy recovery (MER) to meet the demand and
minimize the fresh resources such heat utilities. One of the benefits of applying pinch
technology is it can recover the energy lost from process systems such excess heat
dissipated from a hot stream. Besides, by application of pinch analysis, less
consumption of fresh utilities which eventually reduces the operating costs of the
process. Heat pinch can be done through 2 different methods which are composite
curves method and problem table algorithm (PTA) method to find the minimum energy
targets and pinch temperature. In this project, PTA method is used to represent the heat
117
Based on designed PFD, the very first step in heat integration is to extract the
data of selected streams involving heat exchangers. The streams data is tabulated in
Table 6.1. The assumption is made such that ∆Tmin = 10℃.
Figure 6.1 Problem table algorithm (PTA) approach for heat integration of designed process
118
119
QC, min
Figure 6.2 Heat cascade to evaluate Tpinch, QH, min and QC, min
From the figure, it can be observed that there is no negative value in cumulative
values flowing down the heat cascade, thus it is concluded that minimum hot utility
required, QH, min is 0 kW. Whereas, the final cumulative value is denoted as minimum
cold utility required, QC, min which is equal to 4,211.87 kW. There values obtained are
logical since there are excess hot streams releasing energy to supply to one and only
cold stream, and the remaining hot streams need further cooling in respective amount
as shown in Figure 6.2. Furthermore, the pinch point is also labelled in figure above
which indicates that pinch temperature, Tpinch = 195℃, leaving hot stream pinch
temperature, Tpinch, hot = 200℃ and cold stream pinch Tpinch, cold = 190℃.
120
Figure 6.3 Heat exchanger network design (HEN-D) using grid diagram (1st trial)
Figure 6.4 Heat exchanger network design (HEN-D) using grid diagram (2nd trial)
121
Figure 6.5 Heat exchanger network design (HEN-D) using grid diagram (3rd trial)
Since the supply and target temperatures of all streams are below Tpinch, hot and
Tpinch, cold, therefore heat exchanger matching can only be done for below pinch
temperature. When constructing the grid diagram, there are 3 distinct diagrams
designed and compared based on its suitability and operability. The first one is
displayed in Figure 6.3 which involves only 2 matchings and leaving remaining hot
streams to use external cooling utilities to achieve desired temperature. Whereas, the
second grid diagram is illustrated in Figure 6.4 which involves 3 matching, leaving
remaining hot streams to use external cooling as well. The third one is as illustrated in
Figure 6.5 which involves stream splitting and increase the matching to 5 matchings
and 6 coolers as external utilities requirement.
For the first trial, FCp rule is obeyed such that FCp, out > FCp, in or FCp, hot > FCp, cold
to initiate the first matching. Therefore, the first match is done between H1 and C1
since H1 has the higher FCp than C1 compared to other hot streams. However, the
energy transferred from H1 is insufficient for C1 to achieve the targeted temperature.
Therefore, another matching done between H6 and C1 since only H6 has enough heat
to transfer to C1 to cater the remaining required heat energy which is 1672.83 kW.
While, the remaining hot streams with lower FCp values and H6 as well are cooled
using external cooling using cooling water to achieve desired temperature. Besides, it
is also ensured the temperatures of streams after matching do not violate ∆Tmin which
122
is equal to 10℃. For instance, the temperature of C1 after the matching with H6 is
72.97℃ which does not violate ∆Tmin since the supply temperature of H6 is 100℃,
proven to have difference of more than 10℃. Moreover, the diagram is justified with
recalculation of QH, min and QC, min. Based on the calculation, it is proven that QH, min =
0 kW while QC, min = 4,211.87 kW.
However, the design is still infeasible after a critical analysis is made. The main
reason is the first matching done between H1 and C1. The infeasibility here is such
that the temperature profile of the cold stream, C1 is higher than the hot stream, H1
which needs cooling. In a better explanation, H1 needs cooling from 70℃ to 25℃ but
the supply temperature of C1, 72.97℃ is above the supply temperature of H1 even
though it does not violate ∆Tmin. Supposedly, a cooler stream is required to cool down
stream H1. Therefore, the second trial is initiated and complete monitoring on the
temperature profile is done ensure feasibility of heat exchange.
The second design is made such that the matching is done between H3 and C1,
followed by H4 and C1, and H6 and C1 to supply sufficient energy or heat to the cold
stream. The first matching and following matching clearly violate the FCp rule, but the
feasibility is concerned over the rule since no other than stream H2 or H3 or H4 to
transfer the heat to C1 with high temperature profile. Therefore, H3 is chosen to match
with C1 since it has the highest FCp than the rest. Next, the matching is done between
H4 and C1 instead of H1 and C1 or H6 and C1. H1 and C1 matching failed because it
does not meet the temperature requirement to heat up the cold stream from 89.36℃ to
99.6℃ since the highest temperature of H1 is 70℃ only. While, H6 and C1 matching
failed too even though the matching able to fulfil the temperature requirement and heat
requirement of C1. However, the violation of ∆Tmin occurs between leaving stream of
H6 and entering stream of C1 after the matching. Lastly, the remaining streams are
compensated with coolers to reach the desired temperature as shown in Figure 6.4.
Moreover, the diagram is also justified with recalculation of QH, min and QC, min. Based
on the calculation, it is proven that QH, min = 0 kW while QC, min = 4,211.87 kW. It must
be noted that there are no streams splitting and loop breaking applicable for the both
trials.
123
The third design is the finalised one as previous 2 designs have their own
violation on the temperature profile and FCp rule respectively. To avoid this, the third
design is initiated by obeying the FCp rule and ∆Tmin throughout the matching, as well
as the feasibility of the network is monitored. This is done via the matching between
H1 and C1 and followed by H6 and C1 for lower temperature heating of C1 as a bulk
stream. The modification or enhancement is made here by splitting the cold stream at
high temperature into 3 streams to reduce the FCp and heat requirement instead of the
bulk stream, C1. Now, the hot streams, H2, H3 and H4 with lower FCp can still cater
the energy requirement by each split stream without violating the FCp and ∆Tmin rule.
The hot streams with excess energy are then cooled using coolers to achieve the desired
temperatures. Here, it can be observed that the number of heat exchangers and coolers
increases but the feasibility and the operability of the design is more vital to run a plant.
Conclusively, the third design is approved by the plant manager for external utilities
savings despite of heat exchangers capital costs.
Percentage of hot and cold utility savings are done using formula below:
3,265.08 − 0
%𝑆𝑎𝑣𝑖𝑛𝑔 = | | ×100% = 100% 𝑠𝑎𝑣𝑖𝑛𝑔
3,265.08
7,475.95 − 4,211.87
%𝑆𝑎𝑣𝑖𝑛𝑔 = | | ×100% = 43.66% 𝑠𝑎𝑣𝑖𝑛𝑔
7,475.95
6.7 Modification on PFD After HEN-D
124
Figure 6.7 PFD after modification
125
126
. After finishing the problem table algorithm (PTA), heat cascade and grid
diagram. a new modification on PFD was made based on the plotted grid diagram,
where hot streams are paired with cold streams for all the streams below the pinch.
This pairing of streams is done to ensure a minimum wastage of heat would occur.
Based on the Figure 6.6, the amount of heat exchanger used is seven which is six of
them are coolers (E-1, E-2, E-3, E-4, E-6, E-7) and another one is heater (E-5).
Meanwhile, after modification was made, the amount of heat exchanger has increased
by four units as illustrated in Figure 6.7. One of the heater was removed since the cold
stream can utilize another heat exchangers as a heating source.
Figure 6.7 shows an alternative process used to save energy by using the excess
heat in the form of steam. For this purpose, Heat Exchanger (E-1) and (E-7) are used
as a function of heating process stream 13 from 45℃ to 87.11℃ before the splitting
into 3 streams. Thus, heat exchanger E-5 is removed from PFD since there is an excess
of heat that can be obtained from E-7 and E-1. Then, the first split stream, stream 30
receives heat at E-2, while the second stream, stream 22 receives heat at E-3, whereas
the third stream, stream 32 receives heat at E-4 to achieve the desired temperature of
99.6℃. Later, all these streams join via mixer before entering the evaporator for
further process. As for the hot streams, 6 coolers (E-6, E-8, E-9, E-10, E-11 and E-12)
with different external utilities requirement are installed to achieve the respective
temperature.
Overall, the energy integration is valid since there are huge savings on external
utilities requirement compared to before integration design, even though the number
of units has increased to 11 units. Thus, it can achieve maximum energy recovery
(MER) as well as to reduce cost. Based on the data collected, it is shown that the hot
and cold utilities can save up to 100% and 43.66% respectively, if the pinch technology
is used to recover the plant’s heating and cooling capability.
CHAPTER 7
PROCESS OPTIMIZATION
7.1 Introduction
Optimization does not necessary mean that the process production will increase
or the plant will bring more profit after optimization. Optimization also can bring
changes that lead to reduction of plant cost, increase in management productivity and
make the plant more safety to work with. There are a few advantages in optimization
of selected design parameters. Among the advantages include:
The major equipment chosen for optimization is evaporator, S-2 since there are
some potentials found to improve and optimize. The PFD of the unit operation is
presented as shown in Figure 7.1.
Objectives:
To minimize the total cost consisting the capital and operating cost of the evaporator.
Percentage Error (%) = (Actual Flowrate - Estimated Flowrate)/ Actual Flowrate ⨯100%
Annualised Total Cost (RM) = Annualised Operating Cost (RM) + Annualised Capital
Cost (RM)
Annualised Operating Cost (RM) = Steam cost (RM/s) × (3600 s)/(1 hr)×(24 hr)/(1
day)×(355 days)/(1 yr)
Annualised Capital Cost (RM) = Bare-module cost (RM) ⨯ (AP, 20%, 15)
(Assuming the capital cost is annualised for 15 years of operation with 20%
interest/year)
Inequality constraint:
1. Temperature of evaporator, 100 ℃ ≤ T ≤ 110 ℃
2. Product mole fraction, 0.3 ≤ XP ≤ 1.0
130
Equality constraint:
1. F = V + L Overall
2. F(1-XF) = V + L(1-XP) Water Balance
3. FXF = LXP Solute Balance
2. Utility Cost
(steam consumed for evaporator to keep the column operates at 100 ℃)
Electric Tariff
(On peak – RM 33.70 per kW for 12 hours)
(Off peak – RM 20.20 per kW for 12 hours)
Water Tariff
(≤ 227 m3 - RM 0.92/m3)
(>227 m3 - RM 0.84/m3)
Steam
∆HV = 2716 kJ/kg at 120℃ steam feed
Steam cost = 0.00084 /kg steam feed (assumed)
Tin = 120℃, Tout = 110℃
Table 7.1 LP method Excel tool along with percentage of flowrate errors and heat duty saving
XP/XF - (1 - % %
XF XP XP/XF XP/XF - (1 - Xp) L (mol/hr) V (mol/hr) Q (kW) % Saving
Xp) + 1 Error Error
0.100057 0.30 3.00 2.30 3.30 870534.00 203.07 2000748.03 22.45 51641.03 14.93
0.100057 0.35 3.50 2.85 3.85 746172.00 159.78 2125110.03 17.63 53461.41 11.93
0.100057 0.40 4.00 3.40 4.40 652900.50 127.30 2218381.53 14.01 54826.70 9.68
0.100057 0.45 4.50 3.95 4.95 580356.00 102.05 2290926.03 11.20 55888.59 7.94
0.100057 0.50 5.00 4.50 5.50 522320.40 81.84 2348961.63 8.95 56738.10 6.54
0.100057 0.55 5.50 5.05 6.05 474836.73 65.31 2396445.30 7.11 57433.16 5.39
0.100057 0.60 6.00 5.60 6.60 435267.00 51.54 2436015.03 5.58 58012.37 4.44
0.100057 0.65 6.50 6.15 7.15 401784.92 39.88 2469497.11 4.28 58502.48 3.63
0.100057 0.70 7.00 6.70 7.70 373086.00 29.89 2498196.03 3.17 58922.56 2.94
0.100057 0.75 7.50 7.25 8.25 348213.60 21.23 2523068.43 2.20 59286.64 2.34
0.100057 0.80 8.00 7.80 8.80 326450.25 13.65 2544831.78 1.36 59605.21 1.81
0.100057 0.85 8.50 8.35 9.35 307247.29 6.97 2564034.74 0.62 59886.30 1.35
0.100057 0.90 8.99 8.89 9.89 290178.00 1.02 2581104.03 0.05 60136.15 0.94
0.100057 0.95 9.49 9.44 10.44 274905.47 4.29 2596376.56 0.64 60359.71 0.57
0.100057 1.00 9.99 9.99 10.99 261160.20 9.08 2610121.83 1.17 60560.91 0.24
131
Table 7.2 Annualised capital cost of evaporator data summary
Purchase Cost, Bare-module Annualised Capital Cost
XP Q (kW) Q (Btu/ hr) A (ft2) CBM (RM)
Cp ($) Cost, CBM ($) (RM/yr)
0.30 51641.03 176352054.60 35931.55 1977768.57 4845532.99 21562621.80 4612244.80
0.35 53461.41 182568590.82 37198.16 2015814.28 4938744.98 21977415.17 4700969.10
0.40 54826.70 187230992.98 38148.12 2043967.28 5007719.84 22284353.28 4766623.17
0.45 55888.59 190857305.78 38886.98 2065646.57 5060834.09 22520711.72 4817180.24
0.50 56738.10 193758356.01 39478.07 2082856.86 5102999.30 22708346.90 4857315.40
0.55 57433.16 196131942.57 39961.68 2096851.93 5137287.23 22860928.16 4889952.53
0.60 58012.37 198109931.37 40364.70 2108456.37 5165718.10 22987445.56 4917014.60
0.65 58502.48 199783614.20 40705.71 2118234.85 5189675.37 23094055.41 4939818.45
0.70 58922.56 201218199.48 40998.00 2126587.10 5210138.39 23185115.82 4959296.27
0.75 59286.64 202461506.72 41251.33 2133804.06 5227819.95 23263798.79 4976126.56
0.80 59605.21 203549400.56 41472.98 2140102.56 5243251.28 23332468.21 4990814.95
0.85 59886.30 204509306.89 41668.56 2145647.50 5256836.37 23392921.84 5003745.98
0.90 60136.15 205362556.96 41842.41 2150566.50 5268887.93 23446551.29 5015217.32
0.95 60359.71 206125991.23 41997.96 2154959.93 5279651.82 23494450.61 5025462.98
1.00 60560.91 206813082.08 42137.95 2158907.75 5289323.99 23537491.78 5034669.49
132
Table 7.3 Annualised operating cost and total cost (utility cost + capital cost)
133
ANNUALISED COST (RM/ YEAR) VERSUS PRODUCT MOLE FRACTION
45.00
Millions
40.00
ANNUALISED COST (RM/ YEAR)
35.00
30.00
25.00
Annualized Operating Cost
20.00 Annualized Capital Cost
10.00
5.00
0.00
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10
PRODUCT MOLE FRACTION
Optimum variable (higher yield with better cost)
Figure 7.2 Graphical illustration of annualised cost versus decision variable (highlighting optimum point)
134
135
Sample Calculation
Given:
At XP = 0.3000,
𝑋𝑃 0.3000
= = 𝟑. 𝟎𝟎
𝑋𝐹 0.100057
𝑋𝑃
⁄𝑋 − (1 − 𝑋𝑃 ) = 3.00 − (1 − 0.3000) = 𝟐. 𝟑𝟎
𝐹
𝑋𝑃
⁄𝑋 − (1 − 𝑋𝑃 ) + 1 = 2.30 + 1 = 𝟑. 𝟑𝟎
𝐹
𝐹 2871282.03
𝐿= = = 𝟖𝟕𝟎, 𝟓𝟑𝟒. 𝟎𝟎 𝒎𝒐𝒍/𝒉𝒓
𝑋𝑃 3.30
⁄𝑋 − (1 − 𝑋𝑃 ) + 1
𝐹
𝐿𝑛𝑒𝑤 − 𝐿𝑖𝑑𝑒𝑎𝑙
%𝐷𝑒𝑣𝑖𝑎𝑡𝑖𝑜𝑛 𝑒𝑟𝑟𝑜𝑟 = | | ×100%
𝐿𝑖𝑑𝑒𝑎𝑙
870534.00 − 287235.94
=| | ×100%
287235.94
= 𝟐𝟎𝟑. 𝟎𝟕%
𝑋
𝑉 = ( 𝑃⁄𝑋 − (1 − 𝑋𝑃 )) ×𝐿 = 2.30×870534.00 = 𝟐, 𝟎𝟎𝟎, 𝟕𝟒𝟖. 𝟎𝟑 𝒎𝒐𝒍/𝒉𝒓
𝐹
136
𝑉𝑛𝑒𝑤 − 𝑉𝑖𝑑𝑒𝑎𝑙
%𝐷𝑒𝑣𝑖𝑎𝑡𝑖𝑜𝑛 𝑒𝑟𝑟𝑜𝑟 = | | ×100%
𝑉𝑖𝑑𝑒𝑎𝑙
2000748.03 − 2579911.2098
=| | ×100%
2579911.2098
= 𝟐𝟐. 𝟒𝟓%
(𝐹 − 𝐿)(𝐻𝑣 − ℎ𝑃 ) − 𝐹(ℎ𝐹 − ℎ𝑃 )
𝐻𝑒𝑎𝑡 𝐷𝑢𝑡𝑦, 𝑄 =
3600
(2871282.03 − 870534.00)( −236.17 − ( −763.13))
−
2871282.03(−1043.41 − ( −763.13))
𝑄=
3600
𝑸 = 𝟓𝟏, 𝟔𝟒𝟏. 𝟎𝟑 𝒌𝑾
𝑄𝑂𝑟𝑖𝑔𝑖𝑛𝑎𝑙 − 𝑄𝑁𝑒𝑤
%𝐸𝑛𝑒𝑟𝑔𝑦 𝑆𝑎𝑣𝑖𝑛𝑔 = | | ×100%
𝑄𝑂𝑟𝑖𝑔𝑖𝑛𝑎𝑙
60,705.60 − 51641.03
=| | ×100%
60,705.60
= 𝟏𝟒. 𝟗𝟑%
𝐵𝑡𝑢
Heat duty, Q = 51641.03 kW = 176352054.60 ℎ𝑟
𝐵𝑡𝑢
Assume overall heat coefficient, U = 150 ℎ𝑟.𝑓𝑡 2 .℉
𝐵𝑡𝑢
𝑞 176352054.60
𝐴𝑇 = = ℎ𝑟
𝑈∆𝑇𝑚 𝐵𝑡𝑢
150 (32.72℉)
ℎ𝑟. 𝑓𝑡 2 . ℉
𝑨𝑻 = 𝟑𝟓, 𝟗𝟑𝟏. 𝟓𝟓 𝒇𝒕𝟐
541.7
Purchase cost, 𝐶𝑝 = 5,700𝐴0.55 = ( 500 ) [5,700(35931.55 )0.55 ]
𝑪𝒑 = $ 𝟏, 𝟗𝟕𝟕, 𝟕𝟔𝟖. 𝟓𝟕
𝑄 51641.03
𝑚𝑠𝑡𝑒𝑎𝑚 = = = 𝟏𝟐𝟑𝟒. 𝟐𝟓 𝒌𝒈/𝒔
𝐶𝑝(∆𝑇) 4.184(10)
𝑅𝑀0.00084 𝑹𝑴𝟏. 𝟎𝟒
𝐶𝑜 = 𝑚𝑠𝑡𝑒𝑎𝑚 × = 1234.25 ×0.00084 =
𝑘𝑔 𝒔
Justification on Optimization
For earlier design, product mole fraction was set at 1.0 at 203.15K. The product
flowrates for bottom stream was 287,291.03 mol/hr while for top stream the flowrate
was 2,583,991.00 mol/hr, which deviated from the ideal values at 0.04% and 0.16%
respectively. The heat duty of the evaporator to vaporize the water in the sodium
chloride-ammonium chloride-water mixture was estimated at 60,705.60 kW. The
annualised operating cost and annualised capital cost were RM 5,041,281.74/yr and
37,381,649.55/yr respectively, summing a total of RM 42,422,931.29/yr.
138
WASTE MANAGEMENT
8.1 Introduction
(Schedule Wastes) Regulations, 1989. The main purpose of this regulation is to prevent
environmental pollution and to provide a long term healthy environment.
As illustrated in the Table 8.1, source reduction and reuse always become the
top priority in waste management. It can be done in several ways, such as reducing
packaging, redesigning products and reducing toxicity. The advantages of source
reduction are to save natural resources, conserve energy, reduce pollution and save
money by reducing waste treatment and disposal cost. Next, recycling and composting
is the second priority. The purpose is to remanufacturing the recycle raw materials into
new products. This can benefit in term of preventing the greenhouse emission and
water pollutants, saving energy and reducing the dependence on new landfills.
Energy recovery would be the third priority because once the energy is
recovered, there is still approximately about 10 percent of the volume remains as ash,
which is commonly sent to a landfill. In addition, energy recovery also called as waste-
to-energy (WTE). Last but not least, treatment and disposal is the last choice in the
waste management hierarchy, as stated in Table 8.1, it helps in reducing the volume
and toxicity of waste, thus it can minimize the amount of waste from dumping in the
landfills. One of the advantages of having landfill is the formation of methane gas from
the decomposition of waste, it can be used as fuel to generate electricity. Thus, it can
help in reducing electricity cost.
In this Soda Ash Production Plant, there are two types of waste generated from
the process which are production waste and schedule waste. Production waste is the
waste generated from a stream that need to be treated and then discharged to the
environment. The treated stream needs to comply with the standard provided.
Meanwhile, schedule waste is any matter, whether in a solid, semi-solid, liquid or in
143
the form of a gas or vapor that are no longer to be used, which may cause pollution if
discharged to the environment in such a volume or composition.
In the production of soda ash via dual process, one waste stream (stream 19) is
discharged as a bottom product after the separation process by using separation drum.
This stream contains a major amount of water and a minor amount of carbon dioxide.
Both are in the liquid phase with 25 oC and at a pressure of 1 atm. The details of the
stream composition are shown in the Table 8.2 below.
Based on Table 8.2, it shows that the discharged water contains minor amount
of carbon dioxide that soluble in the water itself. A suitable treatment needs to undergo
to remove the carbon dioxide from the water before it will be discharged to the
environment. The details of the treatment are discussed in the wastewater treatment
part.
144
Scheduled Wastes
In schedule waste, there are two types of waste that being produced which are
from the water purification process and the boiler system. Since the water supplied
from the Pengurusan Air Pahang Berhad (PAIP) contains only 85% of purity, thus the
water purification process is needed to remove the contaminants of magnesium and
calcium in the water. This is to ensure that the is no impurities along the process and
the desired product can be achieved. In the water purification process, soda ash and
sodium hydroxide will be fed to the water system to remove the magnesium and
calcium ion present in the water. The reaction occurs as shown below:
At the end of the process, there are formed of calcium carbonate and
magnesium hydroxide in a solid form. The solution is filtered and then sludge will be
formed as a bottom product of the clarifier. This sludge is considered as schedule waste
and need to be sent to the waste treatment experts such as Kualiti Alam in Bukit Nenas
Negeri Sembilan. The details of the procedure are explained in schedule waste
treatment part.
In the boiler system, wood chips are used to process steam as the source of
heating system to increase the temperature of a stream and some of the processing
units. The purpose of using wood chip is because their energy requirements are higher
and their demand for energy is steady year-round. During the combustion process, the
fuel (wood chips) is automatically injected into the furnace, combustion air is added
and the fuel burns to produce heat. The hot exhaust gas gases the flow out of the
furnace area and into the heat exchanger. However, there is formation of ash after the
combustion process which will accumulate in certain locations and must be removed
regularly. Once this ash has been removed, it can be classed as a schedule waste and
it will be sent to the waste treatment expert for further treat process. The details of the
procedure are discussed in schedule waste part.
145
Wastewater Treatment
After analysing the composition in the waste water stream, the wastewater
only contains a little amount of carbon dioxide. The calculated concentration of
carbon dioxide as below:
1878.95𝑘𝑔 𝑚3 1000𝐿
× × = 1878.95 𝐿/ℎ𝑟
ℎ𝑟 1000 𝑘𝑔 𝑚3
71.12 𝑘𝑔 1000𝑔 1000𝑚𝑔
× × = 71120000 𝑚𝑔/ℎ𝑟
ℎ𝑟 1𝑘𝑔 1𝑔
71120000𝑚𝑔 ℎ𝑟
÷ = 37850.93 𝑚𝑔/𝐿
ℎ𝑟 1878.95𝐿
It means that the water contains about 37,850.93 ppm of carbon dioxide
which is in quite high amount. The carbon dioxide can be removed by using two
proposed methods which are aeration process and Hollow Fibre membrane contactor.
To select the best method to treat the wastewater produced from propylene
glycol production plant, two current technologies are being reviewed for this purposes:
In the production of soda ash, only liquid waste is produced where the major
component is water with a 98.47% from total amount of the waste. However, this
liquid waste will be referred as wastewater. But after the calculation of concentration
of carbon dioxide, the carbon dioxide must be removed from the water since level of
30 ppm are harmful to the most organisms. While at the ocean the average
concentration of carbon dioxide is about 387 ppm. Water quality criteria based on
present day standards and guides are presented to assist in the establishment of water
147
system performance goals for any plant. Quality criteria are expected to change as new
information on the nature and behaviour of water is revealed.
The trend is toward production of water of higher quality. The quality of raw-
water sources is not expected to improve substantially and indeed may worsen in many
places as greater use is made of streams for waste disposal. The water treatment plant,
therefore, will have an increasingly important role of production of water of high
quality.
The Environmental Quality Act (EQA), 1974 specifies two standards for effluent
discharge:
*The standards are listed in the Third Schedule of the Environmental Quality Act 1974,
under the Environmental Quality (Sewage and Industrial Effluents) Regulation, 1979,
regulations 8 (1), 8 (2) and 8 (3). An extract of the standards is given below:
Aeration (gas addition) and gas stripping (gas removal) are common
wastewater treatment method to remove carbon dioxide from water. This artificially
induced gas transfer aims at the addition of oxygen (O2) and the removal of carbon
dioxide (CO2), methane (CH4), hydrogen sulfide (H2S), and other volatile organic
compounds. But, reducing the carbon dioxide concentration leads to a rise in pH and
a reduction of aggressive carbon dioxide that can disintegrate (concrete) pipes.
Aeration brings water and air in close contact to remove dissolved gases (such
as carbon dioxide) and oxidizes dissolved metals such as iron, hydrogen sulfide, and
volatile organic chemicals (VOCs). Aeration is often the first major process at the
treatment plant. During aeration, constituents are removed or modified before they can
interfere with the treatment processes.
Aeration brings water and air in close contact by exposing drops or thin sheets
of water to the air or by introducing small bubbles of air (the smaller the bubble, the
better) and letting them rise through the water. The scrubbing process caused by the
turbulence of aeration physically removes dissolved gases from solution and allows
them to escape into the surrounding air.
Aerators fall into two categories. They either introduce air to water, or water
to air. The water-in air method is designed to produce small drops of water that fall
through the air. The air-in-water method creates small bubbles of air that are injected
into the water stream. All aerators are designed to create a greater amount of contact
between air and water to enhance the transfer of gases and increase oxidation. Most
aerators can remove carbon dioxide by the physical scrubbing or sweeping action
caused by turbulence. At normal water temperatures, aeration can reduce the carbon
dioxide content of the water to as little as 4.5 mg/L.
149
Justification on Selection
As describe in Figure 8.2, carbon dioxide water is fed at a constant flow rate
from a tank into the lumen side of the contactor. The extractant liquid (aqueous)
diethanolamine (DEA) flows counter-currently at a constant rate on the shell side. The
carbon dioxide depleted exit water is continuously recycled and returned to the tank.
The carbon dioxide molecules are desorbed from water, diffuse into the air-filled pores
of the fibers and exit on the shell side. Maintaining DEA at levels of high
concentration, it is assumed that permeated carbon dioxide molecules instantaneously
react with DEA causing no change in the resistance of the extract phase. Therefore, in
such an arrangement the concentration of carbon dioxide in the tank decreases from
an initial concentration level before exponentially attaining a steady-state level of
concentration.
Figure 8.2 Plant Layout of wastewater treatment
152
153
Per designed process, there are several steams feeding processes such as
calcination and evaporation. The usage of high pressure steam and medium pressure
steam in respective unit operations are generated using boiler system which involves
combustion process in furnace. The boiler feed such as wood chips are used as the fuel
to combust to produce sufficient amount of heat to boils up the water flowing in pipe
in the furnace. The combusted ashes together with gases are carried away from the top
to the ash collector and to the flare system to ensure no harm to environment. Here,
the wood ashes in the collector is considered as scheduled waste for disposal in landfill
(Maker, 2004). Secondly, the water purification system is implemented to purify the
water to highest level before feeding into the production plant. The water typically
contains ions such as magnesium and calcium which require to be removed as it may
affect the production of soda ash (ESAPA, 2004). These ions are removed by reaction
with sodium hydroxide and sodium carbonate respectively, forming sludge containing
calcium carbonate and magnesium hydroxide which is also considered as scheduled
waste for disposal.
Based on the categories, the wastes generated from boiler system and purification
system can be classified as Scheduled Wastes Category 4 (SW4).
There are total of 17 general regulations are implemented (EQA, 2005) as tabulated in
Table 8.5.
According to Regulation (8), it is ensured that the wastes are properly stored
treated on-site, recovered on-site for material or product from such scheduled wastes
or delivered to and received at prescribed premises for treatment, disposal or recovery
of material or product from scheduled wastes. It is ensured that the scheduled wastes
that are subjected to movement or transfer be packaged, labelled and transported in
accordance with the guidelines prescribed by the Director General.
Regulation (12) and Regulation (13) are two main rules or references that needs
attention from the design team to dispose the scheduled wastes properly. The
information provided through copies of forms are closely monitored and updated
following the time frame fixed. The agreement between the design team, contractor
and occupier of premises is clear enough such that the handling, transportation and
disposal are carried out under approval of Director General in accordance with the act.
9.1 Introduction
Equipment sizing and costing is a very important element in plant design project
before the start-up to check the feasibility of plant to run. This is done intensively
considering all features of the plant which covers only the machinery sizing and
costing includes the major equipment such as reactors, absorbers, etc. and auxiliary
equipment such as pumps and compressors. In soda ash production plant, there are 7
major equipment and 15 auxiliary equipment which needs intensive sizing and costing.
Even in the major equipment, there are possibilities to have auxiliary equipment such
as agitator in dissolver. Furthermore, the costing part is vital as it highlights necessary
amount of capital cost needed for a plant start-up. Both the sizing and costing of each
equipment are done based on equations, physical data, and reference tables and figures
available in books written by Felder and Rousseau (2005), Geankoplis (2014), Sinnott
(2005) and Seider et al. (2010), as well as from internet sources for parameters
estimation such as L/D ratio of vessels (ICARUS, 1998), and earlier sections in the
report such as Aspen data. Several assumptions are also made with proper justification
or evidence due to lack of minor data. As for the costing part, the base cost index is
denoted as 500 while the latest base cost index is taken from (Jenkins, 2017), stated as
541.7, average value in 2016. Besides, most calculations are done is English units and
in dollars which is further converted into Ringgit Malaysia for reference of USD:RM
with ratio of = 1:4.45.
158
Mixer 1/ Dissolver
Operating Condition
Maximum allowable 15,000 Retention time, θ 300
stress, S (psi) (sec)
Design pressure, Pd 21.76
(psig)
Cost
Vessel cost, CV ($) 19,660.58 Platform cost, CPL 6,377.40
($)
Agitator cost, CA ($) 13,449.58 Purchase cost, CP 49,955.13
($)
Bare-module cost, CBM (RM)
924,769.36
The packed tower is used to enhance the surface are contact between ammonia
and brine (Zuehlsdorff, 1979). Stainless steel 316 is utilised as it provides the best
corrosion resistance for corrosive medium consisting of ammonia and chloride ions
(Steels, 2013).
Carbonation Reactor
The main reaction of Dual process takes place in carbonation tower in form of
gas absorption process. Stainless steel 316 is used for material construction as the inlet
reactant and outlet product contain chloride ions (IEAGHG, 2010). Bubble-cap plates
161
are used as baffles since it has higher absorption efficiency even though expensive in
terms of cost (MNZIFST, 2014).
Cost
Tower cost, CV ($) 26,253.24 Platform cost, 9,553.39
CPL ($)
Plate/ Tray cost, CT 55,650.07 Purchase cost, 130,371.23
($) CP ($)
Bare-module cost, CBM (RM)
2,413,432.22
Rotary drum filter is an extremely effective solid and liquid separation device
due to its unique methods of handling formed cake solids. The vessel is in the
horizontal shape and it is constructed using stainless steel to prevent corrosion from
the mixture of water and sodium chloride.
The construction material used is stainless steel because it can withstand the
200oC temperature of the furnace. Besides, it is also excellent resistance to corrosion
since the product obtained after the calcination process are water vapor and carbon
dioxide which may cause corrosive to the equipment.
Separation Drum
The vertical separator is used for larger flow of carbon dioxide out through
mist eliminator (Svrcek and Monnery, 1993). Stainless steel 304 is strong enough to
resist to the corrosion caused by carbon dioxide (wet) in feed (Standard, 2004).
Evaporator
Operating Condition
Heat Transfer Rate 3,317.86 Heat Transfer 2308.55
(kW) Area (ft2)
Heat Exchangers
Shell and tube heat exchanger is the most commonly type of heat transfer used
in the chemical industries. The type of heat exchanger to be designed is a cooler and
heater. In this current design, only cooler is used in the process flow diagram. Type of
flow arrangements available into the cooler are parallel flow, counter flow and cross
flow. The chosen flow arrangement is counter current flow. The material of
construction factor which is FM are available in book written by Seider et al. (2010).
While, the overall heat coefficient value, U is assumed from book (Sinnott, 2005).
167
Operating Condition
Heat transfer Chilled water Heat Duty 9.4082× 105
medium (Btu/hr)
Log mean 53.20
temperature (˚F)
Purchase cost, CP ($)
10,843.43
Bare-module cost, CBM (RM)
165,719.96
171
Operating Condition
Heat transfer Chilled water Heat Duty 8.3029× 106
medium (Btu/hr)
Log mean 44.44
temperature (˚F)
Purchase cost, CP ($)
22,042.69
Bare-module cost, CBM (RM)
336,878.04
173
Pumps
1.0 based on flow rate range and pump head range which is 496.10 gpm and 50 ft
respectively.
Compressors
10.1 Introduction
As for the designed soda ash plant, control mechanism with complete
instrumentation and automatic control equipment are implemented to overcome the
negative impact that could result from such disturbances. Besides, the instrumentation
is computer monitored for convenience, stability, safety and optimisation.
183
a) Production safety
b) Product quality
To maintain the soda ash purity and composition within the specified quality
standard, which is 99.9%.
c) Production rate
The production rate of soda ash plant is targeted at 100,000 metric tonnes per
annum.
d) Economics
a) Identify and draw in those control loops that are obviously needed for steady
plant operation, such as level control, flow control, pressure control,
temperature control and composition control.
b) Identify the key process variables that need to be controlled to achieve the
specified product quality. Include control loops using direct measurement of
the controlled variable, where possible.
c) Identify and include those additional control loops required for safe operation,
not covered in steps (a) and (b).
d) Decide and show those ancillary instruments needed for the monitoring of the
plant operation by the operators and for trouble-shooting.
Set point
Command Process
input Controller Final Control Unit output
Feedback Measurement
For the ease of recognizing various equipment, instruments, valves and control
loop in the process flow sheet, standard symbols (BS 1646) have been. The commonly
used legends in the Piping and Instrument Diagram (P&ID) are shown the following
Table 10.1.
Dissolver (D – 1)
186
Flowrate of sodium Flowrates of sodium Flowrate of sodium Flowrate of recycled Feedforward Both feed streams must
chloride in feed chloride and recycled chloride in feed water (wild stream) (ratio control) enter the dissolver at fixed
stream water in feed streams stream ratio of 2.7 to ensure better
mixing of brine solution.
187
Ammonia Absorption Tower (V – 1)
188
underflowing and as well
as flooding in the tower.
189
Carbonation Reactor (R – 1)
190
well blocking the feed of
ammoniacal brine at 4 atm.
Control Objective: To control the stoichiometry ratio of the ammoniacal brine to carbon dioxide at 1:1 (set point)
Controlled Manipulated Control
Measured Variable Disturbances Justification
Variable Variable Configuration
Flowrate of carbon Flowrates of Flowrate of carbon Flowrates of Feedforward Both feed streams must enter
dioxide in stream 34 ammoniacal brine dioxide in stream 34 ammoniacal brine (ratio control) the carbonation reactor at
and carbon dioxide (wild stream) fixed stoichiometry ratio of
feed streams 1:1 to ensure complete
consumption of carbon
dioxide and production of
ammonium chloride and
sodium bicarbonate.
191
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Carbonation Reactor (R-1) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Dinesh A/L Arumugam Electric signal
192
Rotary Drum Filter (F – 1)
193
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Rotary Drum Filter (F-1) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Mohamad Hanafi bin Noslan Electric signal
194
Calciner (R – 2)
195
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Furnace (R-2) // Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Mohamad Hanafi bin Noslan Electric signal
196
Separation Drum (S – 1)
197
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Separation Drum (S-1) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Dinesh A/L Arumugam Electric signal
198
Evaporator (S – 2)
199
Controlled Manipulated Control
Measured Variable Disturbances Justification
Variable Variable Configuration
Liquid level Liquid level in Flowrate of liquid in Flowrate of Feedback Liquid level should be
in evaporator evaporator stream 23 stream 37 maintained to prevent from
overflowing or underflowing
of the evaporator
200
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Evaporator (S-2) // Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Mohamad Hanafi bin Noslan Electric signal
201
202
Heat Exchangers
The control system for heat exchanger is designed to operate optimally and for
safety purposes. For heat exchanger in the plant, the control systems are designed as
feedback control system. The outlet temperature of the process stream from the heat
exchanger is controlled by the utility inlet flow rate. It is done to ensure the process
stream reaches the desired temperature and the other processes will not be affected.
Another objective for heat exchanger control design is the safety aspect to keep
the stream temperature from getting too high or too low that will have impact to the
plant operation and indirectly cause the plant operation to be unsafe. In this report,
only 3 selected heat exchangers are discussed as they give significant results in this
design plant.
Heat Exchanger (E – 4)
203
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Heat Exchanger (E-4) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Rizmalinda binti Jamaludin Electric signal
204
Heat Exchanger (E – 9)
205
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Heat Exchanger (E-9) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Rizmalinda binti Jamaludin Electric signal
206
Heat Exchanger (E – 11)
207
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Heat Exchanger (E-11) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Rizmalinda binti Jamaludin Electric signal
208
Pumps
Pump 1 (P – 1)
209
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Pump (P-1) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Nurnaziha Binti Mohd Saad Electric signal
210
Pump 2 (P – 2)
211
Company: Y Chemical Sdn Bhd Indication:
Title: P&ID for Pump (P-2) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Nurnaziha Binti Mohd Saad Electric signal
212
Compressors
Compressor 1 (K – 1)
213
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Compressor (K-1) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Nurnaziha Binti Mohd Saad Electric signal
214
Compressor 2 (K – 2)
215
Company: Y Chemical Sdn. Bhd. Indication:
Title: P&ID for Compressor (K-2) Pneumatic signal
Date: 17/5/2017 Major pipe line
Designer: Nurnaziha Binti Mohd Saad Electric signal
216
CHAPTER 11
11.1 Introduction
Significant advanced technology has been made in chemical process safety since
1950. Today, safety is important to produce and develop scientific disciplines which
include many highly technical and complex theories and practices. The chemical
industry has traditionally devoted considerable attention to safety, beginning with the
research and development of new processes through plant design and construction
(Weinstein, 1997). In chemical plant, the main hazards are toxic and corrosive of
chemicals, explosions, fires and accidents. It is common to all industrial
218
activities. The Occupational Safety and Health Act (OSHA) 1974provided a new legal
administrative framework to promote, simulate and encourage even higher standards
of health and safety at work. Its aim is to promote safety awareness and effective safety
organization and performance in companies. Employers are required to carry out
certain specific duties and employees must co-operate with the employer to comply
with the law and not misuse safety equipment. Every employer must prepare a
statement of policy on health and safety, together with the arrangement for the
implementation of that policy.
As been stated in the introduction part of this chapter, process safety study
plays an important role in designing a chemical plant. In this part, an introduction to
general plant safety such as concept hazard analysis, hazard and operability studies
will be discussed. Due to the chemical substances handled in the plant are hazardous,
the workers in the plant should be thoroughly informed of the safety procedure before
plant start operating.
There are a few basic safety rules, which must be observed when working in
all chemical-manufacturing areas:
i. Each employee is expected to know and observe all safety instructions and
danger signs. It is part of their job safety and correctly. For example, know how
to use all types of fire extinguishers, fire hoses, fire blankets, and the location
of escape routes.
ii. The employer is responsible for their employee’s safety.
iii. No smoking, except in specific areas designated for smoking.
iv. No eating, drinking except of water fountains.
219
Most danger can be avoided if readily recognized and the right corrective
action taken promptly. Some of the ways in the signs of possible hazards may be
recognized (Cook and Cullen, 2014) are as follows:
i. Seeing
Look for warning signs, tags and safety instructions. Smokes, fumes or sparks,
particularly from electrical equipment, is signs of overheating and constitute a fire
hazard. A blue flash may indicate a discharge of static electricity. Observe gauges for
sudden increase in temperature, rapid pressure changes, rise or fall in liquid levels in
tanks and gauge glasses. Look for cracks or other visible damage to equipment,
particularly glassware and glass linings and leaks at valves, gaskets or seals. Keep
watch for physical changes of chemicals, such as a change in color, lumpiness, and
change in crystal form, bubbling or frothing. Do no poke your head into any vessel to
220
see it is clean. Look out for reddening of the skin or rashes: they may indicate contact
with an irritating, corrosive or dermatitis chemical.
ii. Hearing
iii. Feeling
iv. Smelling
Some chemicals may irritate the mucous membranes: some are sweet and
sickly (such as nitrous oxide), others are pungent, and suffocating and may cause
gasping (such as ammonia). A pungent, irritating smell is characteristic of chlorine or
221
bromine: a sweet, scented smell may indicate the organic chemicals called esters (such
as amyl acetate). Organic compounds of benzene give a characteristic aromatic smell,
which is easily recognizable. There are also many chemicals, which give smells
identifiable with common day-to day smells such as hydrogen disulphide (rotten eggs)
or carbon disulphide (decaying vegetables). Even the absence of a smell may, in some
cases, cause one to suspect the identity of a material. In all cases, smell should only be
used to detect from general atmospheric pollution. Never deliberately sniff at a
chemical, under any circumstances.
v. Tasting
Housekeeping
Generally, the efficiency of any industrial plant can be judged by the standard
of its cleanliness and tidiness. In the chemical industry, poor housekeeping is challenge
to safety. Chemicals and volatile flammable liquids must be stored and handled in
authorized and clearly marked containers, which are kept closed. The methods need to
be used for dealing with spillages of particular hazardous liquids and accumulations
of dangerous dust must be clearly stated in the standing instructions and followed
promptly. Operations involving hazardous dusts should only be allowed where there
is proper local exhaust ventilation and other facilities must protect the worker. Besides
that, regular inspection is needed to ensure that well housekeeping and regular cleaning
are enforced. Exits should not be blocked for fast and easy movements during
222
Clear responsibilities for the receipt, storage and issue of materials used in
processes must be established. Proper arrangements for inventory control, records and
security must be made. Materials and supplies used at a plant site should be stored in
a neat and orderly manner at the site to prevent them from falling off of shelves onto
moving equipment. Lastly, junk parts removed from a piece of equipment should be
disposed of in a proper manner.
i. Safety helmets
Many types are now available, all giving protection against the inhalation of
harmful dust. Special absorbent pads are covered by a perforated metal disc or fitted
to a mounded rubber face piece: the pads should be changed regularly and the face
piece cleaned after use. It is most important to remember that dust mask offer no
protection against gases.
Air mask is mainly used as protection against gases and fumes especially when
handling with chemical substances. The most common air masks are the “army gas-
mask” type: a mounded rubber front with two eye ports is held to face by adjustable
elastic straps fitting around the head. Air is drawn through a flexible hose and a non-
return valve, in front of the mouth, from a canister strapped to the body, and is expelled
between the cheeks and the rubber sides of the mask. The canister contains suitable,
absorbent material and it is therefore of vital importance to distinguish the correct
canister for the conditions to be entered. Check with a supervisor, there is a limited life
before the absorbent material is spent and it is susceptible to deterioration, so
immediately area.
Industrial safety shoes and boots, with steel toecaps, are good appearance and
comfortable. Ordinary shoes are unsuitable as they offer little resistance to corrosive
chemicals or to falling objects. Sparks from nailed boots are a source of danger. Rubber
boots are watertight and resistant to most corrosive chemicals, but may be attacked by
many organic solvents.
v. Eye Protectors
protection, but have the advantages that they may be worn for long periods without
discomfort. Some spectacles are fitted with plastic side-shields for added protection.
Perspex goggles, with a surrounding shield of plastic fitting tightly to the face around
the eyes, are particularly useful, not only against chemical splashes, but also in the
presence of dust or gases which affect the eyes. Face shields or visors give full
protection against splashes or sparks, and although they tend to “steam up” under
certain conditions, they may be treated with “demisters”.
i. Adequate protection against the specific hazard(s) to which the worker will be
exposed;
ii. Minimum weight and discomfort compatible with efficient protection.
iii. Flexible but effective attachment to the body;
iv. Weight carried by a part of the body which is able to support it;
v. No restrictions on those body movements and sensory perceptions which are
essential to the job;
vi. Durability;
vii. Clothing should be attractive;
viii. Accessibility of parts which should be maintainable on the premises;
ix. No additional hazards introduced by the PPEs even when they are misused; and
x. Compliance with relevant standards.
Storage of Chemical
The chemical storage is important because it has a huge amount of raw material
or complicated product along with chemicals used for other processes such as water
treatment, cleaning, waste treatment etc. To avoid any form of unnecessary risk, the
storage tank farm should not be situated Adjacent to urban development to eliminate
225
any possibility of Vapor Cloud Explosion (VPE), fireball or toxic cloud drift over
population. To avoid any form of unnecessary risk, the storage tank should not be
situated adjacent to urban development to eliminate any possibility of vapor cloud
explosion, fireball or toxic cloud release. A buffer zone is suggested around the plant.
Transportation
Plant Location
Chemical plant, there is a need to locate the plant far from any housing areas
in order to minimize the probability of harming the public during any explosion fire or
226
order probabilities or release event. For every chemical plant, there is a need to locate
the plant far from any housing areas to minimize the probability of harming the public
in any possible way. Accidents that normally occur can be related to fire, explosion or
vapor cloud and each of these factors can result in a big catastrophe.
Utility
Plants should be designed so that the sudden failure of one or more utility
supplies does not prove disastrous. The routing of service supplies should be as secure
as possible. The position of underground supplies should be clearly marked on
drawings and, where possible, by ground posts. Underground supplies must be
adequately protected from heavy vehicles.
i. Electricity
The use of flameproof and intrinsically safe electrical equipment and conduit
is to reduce the risk of flammable gases, vapors and dusts. A ‘hazardous zone drawing’
is made when all sources of leaks of flammable materials have been identified. This
shows the categories of electrical equipment allowed in each zone.
b) Know how your circuits are labeled so equipment can be de-energized quickly
in an emergency;
c) Never use extension cords as permanent wiring. Unplug them at the end of the
workday;
d) Mount multi-plug adaptors a few inches off the floor to avoid possible water
damage;
e) Never use multi-plug adaptors in series; and
f) Replace any damaged or frayed electrical cords immediately.
Flammability
vapors and of dispersed dusts and liquid droplets, all of which refers to as fuels. The
result of ignition can be a fire or explosion or sometimes both.
Accidental fires and explosions of flammable air mixtures often follow the
escape of combustible materials, which may result from an uncontrolled reaction or an
explosion within the process or storage plant. The constructional materials used in the
process industries are mostly of low flammability, although the plant and structure
used often require fire protection. Flammable gases and vapors of flammable liquids
are in many ways more dangerous than the liquids themselves. This is because they
are invisible, cannot easily be contained and may travel considerable distance before
they reach an ignition source and ignite
Parameters of Flammability
Explosion
Explosion in the vapor spaces of fixed roof storage tanks have been numerous.
The reason for the large number of explosion is that explosive mixtures are present in
the vapor space of many storage tanks. It is almost to be certain that a source of ignition
will never turn up, particularly if the liquid in the tank has a low conductivity so that
static charges can accumulate on the liquid. For this reason, many companies insist
that fixed roof storage tanks containing hydrocarbons above their flash points must be
blanketed with Nitrogen. Other companies insist that such Hydrocarbons are stored
only in floating roof tanks.
First Aid
Personnel Protection
Soda ash is mildly alkaline and will dissolve in human perspiration. This
could lead to mild skin irritation in individuals with sensitive skin,
particularly in hot and humid conditions.
Soda ash piles can cake to give the appearance of a hard crust. This can yield
and engulf a worker. Personnel entering bins or silos containing soda ash must
wear safety belts properly roped to rescue facilities and be physically
observed by someone not on the soda ash pile.
231
Soda ash is friable, so it tends to break into small dusty particles when under
pressure or by abrasion. Dust is commercially undesirable since particle dimension is
critically important, particularly in glass manufacture. To limit dust formation, soda
ash needs to be moved using handling equipment that minimizes grinding during
transportation. Ideal handling equipment includes:
i. grabs
ii. conveyor belts
iii. front-end loaders
iv. belt elevators
v. drag chains
Moreover, Soda ash is not corrosive to steels, but it will readily attack iron
and rust. Painted surfaces other than epoxy resins are undesirable. Refractory surfaces
such as concrete and brick should be smooth and sound and designed so that handling
equipment is unlikely to break off small pieces that can contaminate the soda ash.
Storage Characteristics
i. Helpful when confronting hazards that are difficult to quantify, i.e.: hazards
rooted in human performance and behaviours hazards that are difficult to detect,
analyse, isolate, count, predict, etc.
ii. Built-in brainstorming methodology
iii. Systematic & comprehensive methodology
iv. More simple and intuitive than other commonly used risk management tools
a) Study Nodes
b) Intention
The intention defines how the plant is expected to operate in the absence of
deviations at the study nodes. This can take a number of forms and can either
be descriptive or diagrammatic; e.g., flowsheets, line diagrams, P&IDS.
c) Deviations
These are departures from the intention which are discovered by systematically
applying the guide words (e.g., "more pressure").
d) Causes
These are the reasons why deviations might occur. Once a deviation has been
shown to have a credible cause, it can be treated as a meaningful deviation.
These causes can be hardware failures, human errors, an unanticipated process
state (e.g., change of composition), external disruptions (e.g., loss of power),
etc.
234
e) Consequences
These are the results of the deviations should they occur (e.g., release of toxic
materials). Trivial consequences, relative to the study objective, are dropped.
f) Guide Words
These are simple words which are used to qualify or quantify the intention in
order to guide and stimulate the brainstorming process and so discover
deviations. The guide words shown in the Figure 11.1 are the ones most often
used in a HAZOP. Each guide word is applied to the process variables at the
point in the plant (study node) which is being examined.
g) Action
Dissolver
236
STUDY NODE Stirrer
PARAMETERS GUIDE WORDS POSSIBLE CAUSES POSSIBLE CONSEQUENCES ACTION REQUIRED
1. No mixing, possible
1. Stirrer motor malfunction
No accumulation of unreacted 1. Interlock with feed line
2. Power failure
materials
Agitation
1. Stirrer motor controller
1. The temperature of motor 1. Regular monitoring and
More fails, resulting in higher
might increase rapidly servicing
speed
237
Ammonia Absorption Tower
238
Carbonation Reactor
239
2. Pressure build up in the 2. The decomposition of sodium 2. Regular maintenance or
reactor/tower bicarbonate into valuable soda checking
3. Cascade control failure, ash in tower itself
readings incorrect 3. Loss of product yield
1. Leaking of inlet heating 1. Incomplete reaction at non- 1. Install low temperature
utility optimum temperature indicating alarm
Lower
2. Cascade control failure, 2. Loss of product yield 2. Regular maintenance or
readings incorrect checking on
1. Install pressure low
1. Incomplete reaction at non- indicating alarm
Lower 1. Relief valve fails open optimum pressure 2. Update procedures to
2. Loss of product yield handle relief valve fail
open
Pressure
1. Install high pressure
1. Carbonation tower over
1. Relief valve malfunction alarm
pressure
Higher 2. Temperature build up in the 2. Schedule regular
2. Explosion will occur
tower maintenance of relief
3. Production loss
valve
240
Rotary Drum Filter
241
Calciner
242
2. Instrument failure 2. Install pressure relief valve
3. Plant shutdown
1. Install pressure indicator
1. Inconsistent inlet 1. Loss of product yield
2. Install low temperature
Lower flowrate 2. Temperature drop
alarm
2. Unit leakage 3. Reversible flow
3. Install control valve
243
Separation Drum
244
Evaporator
245
2. Instrument failure 2. Install pressure indicator
3. Plant shutdown
1. Loss of product yield 1. Install pressure indicator
1. Inconsistent inlet flowrate
Lower 2. Temperature drop 2. Install low temperature alarm
2. Unit leakage
3. Reversible flow 3. Install control valve
246
11.5 HAZOP Studies for Auxiliary Equipment
Heat Exchangers
247
1. Control system not
functioning
2. No temperature change at 1. Temperature increases with 1. Install low temperature alarm
Lower the coolant flow stream that condition 2. Schedule regular cleaning of
3. Condensation occurs at 2. Failure of other equipment valves and pipes
the tube of the heat
exchanger
248
Pumps
249
2. Instruct operators and update
procedures to handle relief valve
fail open
1. Pipe blockage 1. Install high pressure alarm
1. Explosion will occur
Higher 2. Relief valve 2. Schedule regular maintenance of
2. Production loss
malfunction relief valve
250
Compressors
251
Relief Valve
252
253
The most difficult and critical time in the operation is during start-up and
shutdown. A small mistake during the procedure could have led to severe destruction
to the equipment or the whole plant. Therefore, commissioning program is necessary
before a new plant start its operation. Start-up procedure should be planned properly
to avoid any possible hazard. The same consideration should be given during plant
shutdown. Failures in identify and eliminate the hazards associated with the shutdown
and start-up of operation units have resulted in serious injury and death to personnel
and costly property damage. Industrialist has devoted much time and effort to improve
the design unit operating procedures to eliminate the hazard. Normally, start-up and
shut down of plant must proceed safely and easily, yet flexible enough to be carried
out in several ways. The operating limits of the plant must not be exceeded and
dangerous mixtures must not be performed. Where necessary introduce additional
equipment, sampling points, instrumentation and lines identify the use on the
engineering line diagram. There are several important things that we must take into
consideration during the start-up and shut down of the plant.
Start-up of a new plant is the most dangerous periods and its will presents the
most challenge situation to the chemical engineer. It exposes their all basic education
and experience. Without any experience, it is quite difficult to handle it. Plant start-
ups are very difficult with seemingly impossible tasks, as well as frustrating problems
and failures. Problems may result from equipment failures, inadequate equipment and
process failures. Equipment failures, which include leaking, broken shafts and
impellers, short-circuits and plugged on line. Inadequate equipment which includes
towers that flood at design capacity, drivers that are overloaded at rated capacity of the
compressor, excessive pressure drop in exchangers and corrosion of equipment that
not suitable according to specifications. Process failures generally include those that
result from that incorrect use or interpretation of data from the laboratory and pilot
plant.
254
Problems must be avoided strictly when start-up a new plant. There are several
guidelines on how the chemical engineer can start-up their new plant:
i. Organize - The various groups, crafts and technical personnel who will
participate in the commissioning.
ii. Prepare the detailed plans schedules and budgets.
iii. Train the personnel.
iv. Perform - The pressure tests, the dry runs, the hot tests, the dynamic safe-fluid
tests, the dynamic solvent tests, and the process-fluid tests.
v. Operate the plant to make product.
vi. Trouble shoots and makes performance analysis.
vii. Maintain the plant and make modifications.
i. Pre-commissioning.
ii. Initial start-up
iii. Performance runs.
Pre-commissioning
i. Operating philosophy
Many times, the plant is shut down due to leakages in the process areas. During
pre-commissioning, the foundation for operation philosophy is established and once
set, it is difficult to change. As a precaution, care must be exercised to avoid shortcuts
that could harm the safety of the plant or the workers. Safe plant operation and good
housekeeping practices should be emphasized throughout.
ii. Simulation
The analytical laboratory is often an area that escapes attention until it is too
late. Routine analysis should be started with known product and chemical samples
before pre-commissioning. Lab technicians require a lot of practice. Lab tests
procedures, reports, record keeping, etc, should be reviewed and finalized now.
Several key points must be done at pre-commissioning.
Initial Start-up
to identify problems areas. During initial period, there are natural tendencies for
supervisors to become overly with operations. This is important to control in order to
provide exposure to plant operators.
Performance Runs
Process modifications must be done during the start-up phase and shutdown
may be necessary to handle certain jobs. Eventually, the plant will be ready for a
performance test. Usually, all the following are completed prior to the performance
run.
Before start-up the plant, the following items must be completed in the
processing unit after a turnaround. Below are the prestart-up procedures that should be
followed:
1. Before the manways covers are installed on the towers or vessel, a final
inspection should be made of the interiors of each tower and vessels for
cleanliness and conformance to the design specification.
257
2. Check all the items in the “Turnaround Worklist” whether they have been
completed and all the equipment and the associated lines has correctly
reassembled.
3. If any heat exchangers were opened during the turnaround for inspection,
cleaning and mechanical work, they must be hydrostatically tested after they
have beeb assembled.
4. Check all the instruments control loops that the alarm circuits are functioning
correctly.
5. Check all the level gauge glasses for cleanliness
6. Make sure that all the control valves operable.
7. Check all the orifice plates have been installed properly.
8. Check the pumps for operability
9. Check all the utilities, power, steam and cooling water. Check all the steam
traps are functioning.
10. Make sure that all the safety valves are tested, installed and the block valves
are sealed in their respective operating position.
11. Check all onsite fire protection equipment such as extinguishers, water hoses,
nozzles and steam hoses are in place and ready for immediate use.
12. Check all the drains are unplugged and all the water drained from equipment.
13. Make sure all the flanges and manheads have good gasket and are made up
tight.
14. The safety valve header, the blowdown line and the flare system are
successfully commissioned.
15. All the blinds are required for tightness testing and air freeing equipments are
available, removed or installed.
16. Make all the steam tracing is operable.
17. The supply of chemicals are adequate and at hand.
18. Air freeing and tightness testing.
19. Gas blanketing.
20. Catalyst should be activated and sufficiently warm for reaction to commence
when flow of reactants is started.
258
There are three types of plant shutdown, the normal shutdown for turnaround,
emergency shutdown, trip by the interlock system due to the danger imposed by the
failure of the plant and resulting an automatic shutdown.
1. Cooling and depressurizing units – this is to reduce the heat supply and cut off.
Releasing hydrocarbon gases to a gas collecting system should relieve excess
pressure. If the cooling tends to produce vacuum in units, an inert gas should
be reduced to maintain the pressure close to atmospheric pressure.
2. The “Turnaround Worklist” is to be prepared to include all items for repair,
cleaning, inspection and modification.
3. The detailed plan has the shut-down and turnaround for the day to day and
probably hour by hour schedule of the sequence of the events are to be prepared.
This called the Critical Path Monitoring Chart.
4. Each material should be pumped out to prescribed place. This is following by
the cooling of the units.
5. Removal of residuue hydrocarbon, water and inert gases.
6. Before shutting down the unit, check the following:
The fire fighting equipment are to correctly located the personnel
protective equipment are to available for immediate use.
259
All special precaution that are specific for the shut-down have been taken
care, for examples hoses laid to any critical points and ready for immediate
use.
7. Shut down blinds should be installed in various lines that leave and enter units
to prevent unwanted materials from entering yhe units while it is down.
8. All items that are required during the shut-down of the unit are available. These
items include blinds, hoses for steaming out circuits and equipment, hoses for
draining circuits equipments of liquids, connections for connecting those hoses.
9. Advanced preparation work are to be carried out prior to the shut-down of the
unit, to avoid any delay in mechanical work during the actual shut-down, e.g.
the erection of scaffolding, stringing of steam or fire hoses, placing of
equipment to be used by the Maintenance Section.
i. Loss of utilities such as electrical power, instrument air, steam or cooling water.
ii. Mechanical failure of equipment, which prevents normal operation or result in
a serious fire or leak.
3. Handle the emergency as a localized condition without shutting down the entire
unit.
4. Shut-down the unit using the emergency procedure.
Automatic Shut-Down
Individual Equipment
Dissolver
5. Lastly, the recycling inlet valve and outlet valve can be opened after a
maximum design height in the vessel is achieved by the brine mixture.
1. Make sure all supply lines of feed is blocked or closed, as well as outlet
pipeline.
2. Switch off the agitator to stop the mixing.
3. Then, monitor and remove the vessel remaining emergency outlet, leaving the
empty vessel.
4. The cleaning of vessel may take place periodically.
1. Make sure all control systems and automation mode are available.
2. Open the valve for brine inlet line from top feeding point.
3. Open the fully feed-gas cylinder (NH3). Set the regulator pressure to the desired
setting not exceeding 4 atm.
4. Adjust the rotameters to allow the desired flow of the feed gas into the column.
5. Open the brine inlet valve and adjust the rotameters to obtain the desired flow
into the column. Ensure that no top feed is allowed when the gas feed flowrate
is zero, as the brine may enter to the gas feed line damaging its source.
6. Switch on the differential pressure gauge to measure the pressure drop across
the column. The concentration of feed gas in outlet bottom stream is
continuously monitored.
7. During the operation, ensure that the liquid level is kept at the bottom of the
column to prevent unreacted gas escape, and flooding over packing materials.
8. Lastly, monitor the changes on control panel and responsive according to the
process requirement.
262
1. Firstly, turn off the solvent flow into the column by closing brine inlet valve
completely.
2. Close completely the feed gas cylinder valve.
3. Wait for the feed gas and liquid feed into the column to go to zero on the
rotameter scales, then turn off rotameters.
4. Switch off the pressure gauge.
5. Unplug the power requirement for the column to operate.
6. Lastly, cleaning of tower or packing materials are allowed to be done.
Carbonation Reactor
Since the carbonation reactor involves absorption reaction via tray tower, it
functions almost similar to the ammonia absorption tower.
1. Make sure all control systems and automation mode are available.
2. Open the valve for brine inlet line from top feeding point.
3. Open the fully feed-gas cylinder (CO2). Set the regulator pressure to the
desired setting not exceeding 4 atm.
4. Adjust the rotameters to allow the desired flow of the feed gas into the column.
5. Open the ammoniacal brine inlet valve and adjust the rotameters to obtain the
desired flow into the column. Ensure that no top feed is allowed when the gas
feed flowrate is zero, as the brine may enter to the gas feed line damaging its
source.
6. Switch on the differential pressure gauge to measure the pressure drop across
the column. The concentration of feed gas in outlet bottom stream is
continuously monitored.
7. During the operation, ensure that the liquid level is kept at the bottom of the
column to prevent unreacted gas escape, and flooding over trays.
263
8. Lastly, monitor the changes on control panel and responsive according to the
process requirement.
1. Firstly, turn off the solvent flow into the column by closing brine inlet valve
completely.
2. Close completely the feed gas cylinder valve.
3. Wait for the feed gas and liquid feed into the column to go to zero on the
rotameter scales, then turn off rotameters.
4. Switch off the pressure gauge.
5. Unplug the power requirement for the column to operate.
6. Lastly, cleaning of tower or changing of trays are allowed to be done.
1. Firstly, on the control panel, locate the Agitator “start” button and press
“start”. This will begin the agitator in the slurry tank.
2. Next is to fill the slurry tank to the operational level which is 33%
submergence.
3. After that, the vacuum seal water is turned on. In the control panel, locate the
Vacuum Pump “start” button and press the “start”. This will begin the vacuum
filtration.
4. Then, on the control panel, locate Filtrate Pump “start” button and press it.
5. After that, open the lower parts of filter valves which is the cake-forming part.
6. On the control panel, locate the Filter Drum “start” button and press it.
Starting the rotary drum filter need to be under the direction of the pilot plant
manager. It is compulsory to begin the drum rotation at the lowest possible
rpm setting.
264
7. Next is to open the upper parts of the filter valves which is cake-dewatering
parts.
8. Lastly, adjust the drum rotation speed for desired production conditions.
1. Firstly, close the lower (cake forming) parts of the filter valves.
2. Then, run the remaining cake off the drum filter. On the control panel, locate
the Vacuum Pump “stop” button and press it.
3. After that, locate the Filtrate Pump “stop” button and press it.
4. After the slurry is drained, wash the filter cloth with a hose. Reduce the drum
rotation to the lowest possible rpm.
5. On the control panel, locate the Filter Drum “stop” button and press it.
6. Lastly, locate the Agitator “stop” button on the control panel and press it to
shut down everything.
Calciner
The start-up and shut down of the furnace need to be controlled carefully. It
must follow the standard operating procedures. The procedures are developed in detail
before the commissioning of the furnace. There is a maximum of two planned
shutdowns per year and can be up to 5 in total.
1. The computerised control system for the line will be started up, which will
mean that measurements and interlock system will be in operation.
2. After that, utilities for the plant such as water, electricity, instrument air, the
firewater system and safety system will then be started up.
265
Separation Drum
1. Make sure all control systems and automation mode are available.
2. Open the inlet valve and close the outlet valves on top and bottom of the
vessel.
3. Wait till 30% fill of liquid-gas mixture in the vessel. Ensure that no sudden
increase in temperature and pressure occurs.
4. Once the pressure in vessel shows an increase, may open the top outlet valve
leaving the gas to flow out to next process. Bottom stream outlet valve can be
opened too to release the liquid product to wastewater treatment (incomplete
separation).
5. The conditions and control system on the drum is continuously monitored.
1. Firstly, turn off the solvent flow into the vessel by closing brine inlet valve
completely.
2. Close completely the outlet valves after a while relieving the pressure in the
vessel.
3. The remaining liquid portion in the vessel may be drained out and kept at a
safe place.
4. The cleaning or maintenance work on separation drum can now be done.
Evaporator
1. First and foremost, stick water tank needs to be at least half full of product.
Then vacuum pump will be started.
267
2. After that, cooling tower fan and cooling water pump are started as well as
feed pump.
3. As level is established in the boot of each calandria, start the relevant
circulation and transfer pumps.
4. When level is established in the second effect, start the extraction pump and
allow flow through the extraction pump to return to the feed tank using valve.
5. Next, wait while the vacuum in the condenser climbs to around 80%. During
this time, the levels in the separators should stabilize at operating level and
the liquor should be circulating through each effect.
6. Check the cooling water at the condenser is satisfactory.
7. Then, introduce heat to the first effect by taking temperature set point out of
manual and putting into automatic. The absolute pressure in the first effect
boot should rise to around 85 kPa absolute. This will only be achieved
gradually as the liquor in the effects heats up to evaporation temperature.
8. After that, monitor the concentrate taking samples from the flow ex the
extraction pump and as the concentrate approaches 30% TS then adjust the
concentrate flow control set point and continue monitoring until the
concentrate stabilizes at 30% TS.
9. Then, monitor the vacuum in each effect and adjust the set point to increase
or decrease evaporation. The temperature set point will correlate with vacuum
in the first effect. It is not recommended to increase the temperature set point
to where the vacuum in the first effect is less than 5%. The extraction flow
rate controls the concentration of the extract. This will need to be monitored,
particularly after the temperature set point has been adjusted.
10. Adjust the vent valves, if required. These valves vent the incondensable gases
to the surface condenser and vacuum pump. There is also a loss of steam
through these valves. Air is heavier than steam, so the main adjustment is the
lower vent of each calandria. Adjust the vent valves by cracking open the top
valves.
11. The vacuum should be maintained at least at 88% (12kPa absolute) in the
surface condenser. If the vacuum falls below, It is needed to check the
operation of the vacuum pump, seal water in the tank as well as the cooling
water temperatures. The design assumes water to the condenser is a maximum
of 30°C. The temperature rise should not be more than 15°C.
268
12. Lastly, monitor the level in the feed tank and adjust the temperature set point
to match the liquor production rate. If the level gets too low and the evaporator
is in danger of running out of feed, then hot water should be added to the feed
tank.
1. As the liquor runs out in the feed tank, make up with hot water, adding water
to the feed.
2. Monitor the concentrate TS and as the solids reduce, reduce the temperature
set point and divert the liquor to the drain.
3. The evaporator will then be operating on water at reduced evaporation rate.
4. As the liquor clears then divert the extract back to the feed tank.
5. Break the vacuum at the vacuum break valve adjusting, the vacuum to about
75% which is 250kPa absolute and equivalent to 65C in the surface
condenser.
6. Reduce the temperature set point as necessary to maintain a small amount of
evaporation.
7. After that, add cleaning chemicals to the CIP Tank and introduce to the first
effect using Valve 2 in conjunction with the feed pump. Circulate for the
prescribed time.
8. Divert the chemicals to drain and rinse through with hot water. Repeat the
procedure with different chemicals as appropriate.
9. After the final rinse through, shut off the steam and the waste heat.
10. Turn off the vacuum pump, cooling tower fan and cooling tower pump.
11. Then, turn off circulation pumps, extraction pump, feed pump and condensate
pump.
12. When no vacuum, drain the vessels, if required at the pump inlets.
13. The concentrate tank is cleaned by adding cleaning chemicals to the CIP Tank
and transfer to the concentrate tank directly by closing Valve 1 and opening
Valve 3 in conjunction with running feed pump.
14. The CIP is returned from the concentrate tank by utilising the CIP Return
pump. Circulate for the prescribed time.
269
15. Repeat the procedure with different chemicals as appropriate. To clean the
stickwater feed tank, add cleaning chemicals to the CIP Tank and transfer to
the stickwater tank directly opening V701-03 in conjunction with the feed
pump (P707).
16. Once the CIP chemicals have been transferred, select valve V701- 06 to
recirculate the flow within the stickwater feed tank. Circulate for the
prescribed time.
17. Repeat the procedure with different chemicals as appropriate.
Heat Exchangers
Most problems with heat exchanger occur in plant during initial installation
or shortly thereafter. On initial start-up and shut down, heat exchanger can be subjected
to damaging thermal shock, over pressure or hydraulic hammer. This can lead to leaky
tube-to-tube sheet joints, damaged expansion packing glands because of excessive
axial thermal expansion of tubes or shell. Table 11.12lists the start-up and shut down
procedures of heat exchangers.
b) General comments
i. In all start-up and shut down operations, fluid flows should be regulated to
avoid thermal shocking the unit regardless of whether the unit is of either
a removable or non-removable type construction.
ii. For fixed tube sheet (non-removable bundle) type units where the tube side
fluid cannot be shut down, it is recommended that:
- A bypass arrangement be incorporated in the system
- The tube side fluid is bypassed before the shell side fluid is shut down.
Table 11.12 Start-up and shut down of general heat exchangers
Fluid Location & Relative Temperature
Type of Construction Shell Side Tube Side Start-Up Shut Down
Fluid Type Real Temp. Fluid Type Real Temp.
Start both fluids Shut down both fluids
Liquid Cold Liquid Hot
gradually at same time gradually at same time
Start both fluids Shut down both fluids
Liquid Hot Liquid Cold
gradually at same time gradually at same time
Fixed Tube sheet
Start cold fluid first and Shut off hot fluid first, then
(Non-Removable Liquid Cold Gas Hot
then hot fluid gradually. cold fluid.
Bundle)
Condensing Liquid or Start cold fluid first and Shut off cold fluid first,
Hot Cold
gas (steam) gas then hot fluid gradually. then hot fluid
Start cold fluid first and Shut off cold fluid
Gas Hot Liquid Cold
then hot fluid gradually. gradually, then hot fluid
Start cold fluid first and Shut off hot fluid gradually,
U-Tube Liquid Hot Liquid Cold
then hot fluid gradually then cold fluid
Packed Floating Head
Start cold fluid first and Shut off hot fluid first, then
Internal Floating Head Liquid Cold Liquid Hot
then hot fluid gradually cold fluid
270
(All these types have Start cold fluid first and Shut off hot fluid first, then
Liquid Cold Gas Hot
removable bundles) then hot fluid gradually cold fluid
Shut off cold fluid first,
Condensing Liquid or Start cold fluid first and
Hot Cold then shut down hot fluid
Gas (Steam) Gas then hot fluid gradually
gradually
Start cold fluid first and Shut off hot fluid first, then
Gas Hot Liquid Cold
then hot fluid gradually cold fluid
271
272
Pumps
1. Close the discharge valve and open the suction valve. Except for axial flow
pumps, the almost closed discharge valve creates a minimum load on the
driver when the pump is started. Assuming that the motor inrush current
allows and that the motor will not kick off, the discharge valve may be just
"cracked" --about 1/8 open -- before the pump is started.
2. Be sure the pump is primed. Opening all valves between the product source
and the pump suction should get product to the suction, but does not always
ensure that the pump is primed. Only after ascertaining that fluid emissions
are not hazardous or are routed to a safe area, open the bleeder valve from the
pump casing until all vapors is exhausted and a steady stream of product flows
from the bleeder. It may be necessary to open the bleeder again when the
pump is started, or even to shut down and again bleed off vapor if pump
discharge pressure is erratic.
3. If a minimum flow bypass line is provided, open the bypass. Be sure the
minimum flow bypass is also open on spare pump if it starts automatically.
4. Never operate a centrifugal pump without liquid in it.
5. Check lube oil and seal pot level (assumes dual seals).
6. Start the pump. Confirm that the pump is operating by observing the
discharge pressure gauge. If the discharge pressure does not build up, stop the
pump immediately and determine the cause.
7. Open the discharge valve slowly, watching the pressure gauge. The discharge
pressure will probably drop somewhat, level off and remain steady. If it does
not drop at all, there is probably a valve closed somewhere in the discharge
line. In that case, close the discharge valve. Do not continue operation for
any length of time with discharge valve or line blocked.
8. If the discharge pressure drops to zero or fluctuates widely, the pump is not
primed. Close the discharge valve and again open the bleeder from the casing
to exhaust vapor. If the pump does not pick up at once, as shown by a steady
stream of product from the bleeder and steady discharge pressure, shut down
273
the pump and driver and check for closed valves in the suction line. A dry
pump will rapidly destroy itself.
9. Carefully check the pump for abnormal noise, vibration (using vibration
meter) or other unusual operating conditions. An electrician and machinery
engineer should be present when pumps are started up for the very first time,
i.e. upon being initially commissioned.
10. Be careful not to allow the bearings to overheat. Recheck all lube oil levels.
11. Observe whether the pump seal or stuffing box is leaking.
12. Check the pump nozzle connections and piping for leaks.
13. When steady pumping has been established, close the startup bypass and
chill-down line (if provided) and check that block valves in minimum flow
bypass line are open.
1. Close the discharge valve. This takes the load off the motor and may prevent
reverse flow through the pump.
2. Shut down the electrical driver.
3. If pump is to be removed for mechanical work, close the suction valve and
open vent lines to flare or drain as provided. Otherwise, leave suction valve
open to keep pump at correct operating temperature.
4. Shut off steam tracing, if any. Continue oil mist lubrication, if provided.
5. Shut off cooling water and sealing oil if pump is to be removed for mechanical
work.
6. At times, an emergency shutdown may be necessary. If you cannot reach the
regular starter station (in case of fire, for example), stop the pump from the
starter box, which is located some distance away, and is usually accessible.
274
Compressors
1. Make sure all lubricating, cooling systems, valves and all control
instruments are working.
2. The importance of clean suction lines from knockout drums to compressor
suctions cannot be overemphasized. Operators must be sure these lines have
been thoroughly cleaned before using compressors to take suction from
knockout drums.
3. Never start compressors with shutdown devices inoperative. Vendor
representatives may install bypass wiring on trips to check machinery;
however, operators should not do this.
4. Ensure the compressors are free of installation dirt, liquid that may damage
the compressors.
5. Performing first inspection no more than 48 hours of operation.
1. Close the service valves and run the compressor for approximately 5 minutes
to allow the compressor to cool down.
2. Press the engine switch to the off position after five minutes.
CHAPTER 12
MECHANICAL DESIGN
12.1 Introduction
i. Vessel function;
ii. Process material and services;
iii. Operating and design temperature and pressure;
iv. Materials of construction;
v. Vessel dimensions and orientation;
vi. Type of vessel heads to be used;
vii. Openings and connections required;
viii. Specification on heating and cooling jackets or coils
276
33.03 ft.
11.01 ft.
Figure 12.2 Sketch mode design of separation drum with dimensions
278
Figure 12.4 Base support system for designed vessel with bottom nozzle
Figure 12.5 Elliptical type headed vessel, with feed and top nozzles
279
Detail ID PLAT: [2 OF 2]
Dist. from "FROM" Node / Offset distance 10.000 ft
Platform Start Angle (degrees) 200.0
Platform End Angle (degrees) 90.0
Platform Wind Area 0.0000 ft²
Platform Weight 0.0000 lbf
283
CHAPTER 13
ECONOMIC ANALYSIS
13.1 Introduction
Throughout the chapter, the equipment cost is calculated in sizing and costing
chapter with the CE index in preliminary 2016, which are 541.7. Finally, profitability
analysis is carried out, by analyzing the discounted cash flow analysis. Through this
study, the most concern factor i.e. payback period (PBP), the discounted break-even
period and net present value (NPV) is determined.
In Chapter 9, the equipment costing has been carried out known as “bare module
cost”. This is for determine the grass-root capital for soda ash plant. Grass-root capital
220
cost make-up the major portion of total fixed capital cost. Basically, GRC is the cost
of equipment installed in the plant. To calculate the GRC, contingency and fees (5%
and 3% of total bare module cost respectively), Auxiliary facilities (30% of total bare
module cost) is added to the initial bare module cost. The bare module cost for all the
equipment of the soda ash plant is depicted in Table 13.1.
P-2 RM 115464.86
K-1 RM 1786398.08
Compressor
K-2 RM 1788193.70
Waste Treatment
RM 10179874.91
Plant
Total Bare Module Cost (CTBM) RM 40,981,925.49
Contingency Cc = 0.05CTBM RM 2049096.27
Fees Cf = 0.03CTBM RM 1229457.76
Total Module Cost Cc + Cf + CTBM RM 44260479.53
Site Development CSD = 0.05CTBM RM 2049096.27
Auxiliary Building CAB = 0.04CTBM RM 1639277.02
Offsite Facilities COS = 0.21CTBM RM 8606204.35
Auxiliary Facilities 0.30CTBM RM 12294577.65
GRC = CBM +
Grass-Root Capital (GRC) RM 56,555,057.18
Auxiliary cost
Fixed capital investment (FCI) represents the capital that is needed to start up
the operation and for the installing process equipment necessary with all auxiliaries
that are needed for complete process operation. It includes direct costs, and indirect
costs. For total capital investment (TCI),
Working capital refer to what must be invested to get the plant into productive
operation; that is, money invested before there is a product to sell. It consists of the
total amount of money invested in raw materials and supplies carried in stock, finished
products in stock and semi-finished products in the process of being manufactured,
account receivable, cash kept on hand for monthly payment of operating expenses, e.g.
222
salaries, wages and raw material purchases. For most chemical plant use in an initial
working capital amounting to 12% of the fixed capital investment whereas startup cost
is 8% out of fixed capital cost. Table 12.2 demonstrates the total capital investment of
soda ash plant.
Material and utilities were categories as the expense to build the plant. The
expenses of the materials are calculated by taking the price for the raw materials and
are multiplied by the feed flowrate. Then by assuming that the plant is operated 24-
hour for the whole year (355 days is estimated), the annual cost for raw materials is
estimated.
The terms utilities include, power, compressed air, pump and chilled water. The
current cost of utilities supplied by the utility companies: electricity and water can be
obtained from local area offices. The material, product and utilities costing is shown
in Table 13.3.
PRODUCT
Price of Product (RM/kg)
Soda Ash, Na2CO3 1.08
Ammonium Chloride,NH4Cl 2.14
Product Amount (kg/hr)
Soda Ash, Na2CO3 11420
Ammonium Chloride,NH4Cl 11520
Total Annual Sales (RM/yr) 315124128.00
UTILITIES
Heat Exchangers Cost (RM/yr)
E-9 1998508.78
E-10 359369.74
E-11 725269.35
E-12 791678.75
E-6 1243535.27
E-8 6986702.53
Pumps Cost (RM/yr)
P-1 46559.03
P-2 21063.24
Compressors Cost (RM/yr)
K-1 356248.2991
K-2 356698.1075
Total Utilities 12885633.10
The labour costing for this 100 000 MTA soda ash plant is shown in Table 13.4.
225
with 24 hours continuously operation. Hence the total operating hour per year is 8520
hour. The manufacturing cost is summarized in Table 13.5 and Table 13.6.
The cash flows in a manufacturing company can be likened to the material flows
in a process plant. The inputs are the cash needed to pay for research and development;
plant design and construction; and plant operation. The outputs are goods for sale; and
cash returns, are recycled, to the organisation from the profits earned. The “net cash
flow” at any time is the difference between the earnings and expenditure.
The profitability analysis is to determine the payback period (PBP) and net
present value (NPV) of soda ash plant. The value stated above can be obtained by
using graphical method as proposed in Ulrich (1984). The total operating period is 20
years, excluding the 3 years for start-up operation with fixed capital cost of RM
228
191,721,643.83. Since this is a new plant, we may meet many problems in production
flow in the beginning of start-up. Hence the production cannot achieve the target as
desired. For the discounted break event period, a different interest rate was calculated.
The after tax rate of return of the plant is about 40%. This is where the NPV become
zero at the end of the 20 years, excluded 3 years’ startup operation. Table 13.8 refers
for different discounted factors.
Payback period is the time that must elapse after startup until cumulative
undiscounted cash flow repays fixed capital investment or it is the time required after
the start of the project to pay off the initial investment from income. In illustration PBP
is the point, where undiscounted cash flow rises to the level of negative working
capital. In order to get the payback period, an undiscounted cash flow is calculated.
With refer to the calculated value in Table 13.1, Table 13.5 and Table 13.6, it can be
summarized that PBP is 3 years for undiscounted rate.
Table 13.7 Undiscounted cash flow analysis (exported from Excel)
Year Annual Capital Investment Sales Income Depreciation Total Expenses plus Depreciation Cash Income Allowances Net Profit Federal Income Taxes Net Profit After Taxes Cash Flow or Net Cash Income Cumulative Cash Flow
AI As ABD ATE - ABD ACI=AS - (ATE-ABD) AA ANP=ACI-ABD AIT=30%ANP ANNP=ANP-AIT ANCI=AI+ABD+AA+ANNP ΣANCI
0 0 0 0
1 -57516493.15 -57516493.15 -57516493.15
2 -80523090.41 -80523090.41 -138039583.6
3 -92026389.04 -92026389.04 -230065972.6
4 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 -139495853.1
5 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 -48925733.52
6 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 41644386.01
7 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 132214505.5
8 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 222784625.1
9 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 313354744.6
10 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 403924864.2
11 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 494494983.7
12 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 585065103.2
13 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 675635222.8
14 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 766205342.3
15 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 856775461.8
16 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 947345581.4
17 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1037915701
18 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1128485820
19 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1219055940
20 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1309626060
21 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1400196179
22 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 90570119.54 1490766299
23 23006597.26 315124128.00 19172164.38 193954884.83 121169243.17 0 101997078.79 30599123.64 71397955.15 113576716.8 1604343015
229
Table 13.8 Discounted factor cash flow analysis for 5% & 20% & 33%
Cash flow or Net Cash Income i= 0.05 i= 0.20 i= 0.33
Completion of year ANCI=AI+ABD+AA+ANNP Discounted Factor, fd Discounted Cash Flow Cumulative Cash Flow Discounted Factor, fd Discounted Cash Flow Cumulative Cash Flow Discounted Factor, fd Discounted Cash Flow Cumulative Cash Flow
fdANCI ΣANCI fdANCI ΣANCI fdANCI ΣANCI
0 0 1 0 0 1 0 0 1 0 0
1 -57516493.15 0.952380952 -54777612.52 -54777612.52 0.833333333 -47930410.96 -47930410.96 0.751879699 -43245483.57 -43245483.57
2 -80523090.41 0.907029478 -73036816.7 -127814429.2 0.694444444 -55918812.78 -103849223.7 0.565323082 -45521561.65 -88767045.22
3 -92026389.04 0.863837599 -79495854.91 -207310284.1 0.578703704 -53256012.17 -157105235.9 0.425054949 -39116272.1 -127883317.3
4 90570119.54 0.822702475 74512261.48 -132798022.6 0.482253086 43677719.68 -113427516.2 0.319590187 28945321.46 -98937995.86
5 90570119.54 0.783526166 70964058.56 -61833964.09 0.401877572 36398099.74 -77029416.49 0.240293374 21763399.59 -77174596.27
6 90570119.54 0.746215397 67584817.67 5750853.587 0.334897977 30331749.78 -46697666.71 0.18067171 16363458.34 -60811137.93
7 90570119.54 0.71068133 64366493.02 70117346.61 0.279081647 25276458.15 -21421208.56 0.135843391 12303352.14 -48507785.8
8 90570119.54 0.676839362 61301421.93 131418768.5 0.232568039 21063715.13 -357493.4396 0.102137888 9250640.703 -39257145.09
9 90570119.54 0.644608916 58382306.6 189801075.1 0.193806699 17553095.94 17195602.5 0.076795404 6955368.95 -32301776.14
10 90570119.54 0.613913254 55602196.76 245403271.9 0.161505583 14627579.95 31823182.45 0.057740906 5229600.714 -27072175.43
11 90570119.54 0.584679289 52954473.1 298357745 0.134587986 12189649.96 44012832.4 0.043414215 3932030.612 -23140144.82
12 90570119.54 0.556837418 50432831.53 348790576.5 0.112156655 10158041.63 54170874.03 0.032642267 2956413.994 -20183730.82
13 90570119.54 0.530321351 48031268.12 396821844.6 0.093463879 8465034.692 62635908.73 0.024543058 2222867.665 -17960863.16
14 90570119.54 0.505067953 45744064.88 442565909.5 0.077886566 7054195.577 69690104.3 0.018453427 1671329.071 -16289534.09
15 90570119.54 0.481017098 43565776.07 486131685.6 0.064905472 5878496.314 75568600.62 0.013874757 1256638.399 -15032895.69
16 90570119.54 0.458111522 41491215.31 527622900.9 0.054087893 4898746.928 80467347.54 0.010432148 944840.9018 -14088054.79
17 90570119.54 0.436296688 39515443.15 567138344 0.045073244 4082289.107 84549636.65 0.00784372 710406.6931 -13377648.09
18 90570119.54 0.415520655 37633755.38 604772099.4 0.037561037 3401907.589 87951544.24 0.005897534 534140.3707 -12843507.72
19 90570119.54 0.395733957 35841671.79 640613771.2 0.031300864 2834922.991 90786467.23 0.004434236 401609.3013 -12441898.42
20 90570119.54 0.376889483 34134925.52 674748696.7 0.026084053 2362435.826 93148903.06 0.003334012 301961.8807 -12139936.54
21 90570119.54 0.358942365 32509452.87 707258149.6 0.021736711 1968696.521 95117599.58 0.002506776 227039.008 -11912897.53
22 90570119.54 0.341849871 30961383.69 738219533.3 0.018113926 1640580.435 96758180.01 0.001884794 170706.0211 -11742191.51
23 90570119.54 0.325571306 29487032.08 767706565.4 0.015094938 1367150.362 98125330.37 0.001417138 128350.3918 -11613841.12
230
Figure 13.1 Undiscounted cash flow diagram (with i = 0%)
231
232
Figure 13.2 Cash flow diagram with varies interest rate
233
From Figure 13.1, the PBP shows 3 years after 3 years of start-up period. This
means at i = 0%, the plant will start earning after the PBP. According to Ulrich (1984),
the PBP lays between the start-up of a plant to the recovery of working capital.
The discounted cash flow rate of return (DCFRR) is the point in which the rate
result a Net Present Value (NPV) of zero. From Figure 13.2, within the period of 20
operating years after start-up in year 3, the NPV will be zero if i ≈ 33%. The DCFRR
point is the maximum interest rate that counted after the taxes. If the rate of interest in
market is 20%, the payback period of this plant is roughly 6 years after the start-up
year. This means that the plant is profitable to construct as it promised short PBP.
After carried out the economic analysis to the soda ash production plant, it has
been meet up a few conclusions:
14. ESAPA 2004. Large Volume Solid Inorganic Chemicals Family Process
Bref for Soda Ash European Soda Ash Producers Association.
15. F, B. W. & D, H. R. 1967. Soda ash compaction. Google Patents.
16. FELDER, R. M. & ROUSSEAU, R. W. 2005. Elementary principles of
chemical processes, Wiley NY etc.
17. GEANKOPLIS, C. 2014. Transport processes and separation process
principles (includes unit operations), Prentice Hall Press.
18. ICARUS 1998. ICARUS REFERENCE. Vessels. Third Edition ed. United
States: ICARUS Corporation.
19. IEAGHG 2010. Corrosion and Material Selection for Carbon Capture and
Storage. United Kingdom: IEA Environmental Projects Ltd. (IEAGHG).
20. J., A. 2013. Site Selection for a Plant / Project – Factors Considered.
21. JENKINS, S. 2017. CURRENT ECONOMIC TRENDS: CEPCI
JANUARY (PRELIM.) AND DECEMBER (FINAL). BUSINESS &
ECONOMICS. New York: Access Intelligence, LLC.
22. KANTARCI, N., BORAK, F. & ULGEN, K. O. 2005. Bubble column
reactors. Process Biochemistry, 40, 2263-2283.
23. KHAN, I. U. 2011. CHEMCAD as a tool when teaching Chemical
Engineering.
24. KLETZ, T. A. 1999. HAZOP and HAZAN: identifying and assessing
process industry hazards, IChemE.
25. LETKI, A. G. 1998. Know when to turn to centrifugal separation. Chemical
engineering progress, 94, 29-44.
26. LEVESON, N. G., HEIMDAHL, M. P. E., HILDRETH, H. & REESE, J. D.
1994. Requirements specification for process-control systems. IEEE
transactions on software engineering, 20, 684-707.
27. LINNHOFF, B. 1993. Pinch analysis: a state-of-the-art overview: Techno-
economic analysis. Chemical engineering research & design, 71, 503-522.
28. MAKER, T. M. 2004. Wood-chip heating systems. A guide for institutional
and commercial biomass installations, 1-93.
29. MARLIN, T. E. 2000. Process control, McGraw-Hill New York.
30. MNZIFST, R. H. M. R. 2014. CARBONATION AND BOTTLING
DEBUGGED.
236
MATERIAL BALANCES
Dissolver/ Mixer 1
NaCl(s)
Brine
Dissolved NaCl(aq)
H2O(l)
H2O(l)
Recycled H2O(l)
NaCl(aq)
H2O(l)
NH3(g)
Ammoniated brine
Dissolved NaCl(aq)
H2O(l)
Absorbed NH3(aq)
Cooler 1
Pump 1
NaCl (aq), H2O (l), NH3 (aq) NaCl (aq), H2O (l), NH3 (aq)
Compressor 1
Process condition: Tin, Pin = 25°C, 1atm, Tout, Pout = 128°C, 4atm
Mixer 2
̇ 𝟗. 𝟒𝟖 𝐦𝐭/𝐡𝐫
ṁCO2out = ṁCO2in + ṁrecycled CO2 = 4.74 + 4.74 =
ṁTout = ṁTin = 4.74 + 4.74 = 𝟗. 𝟒𝟖 𝐦𝐭/𝐡𝐫
Cooler 2
Carbonation Reactor
Ammoniated brine
Dissolved NaCl(aq)
H2O(l)
Absorbed NH3(aq)
NaHCO3(s)
CO2(g) Dissolved NH4Cl(l)
Dissolved NaCl(aq)
H2O(l)
Rotary Filter
NaHCO3(s)
NaHCO3(s)
Dissolved NH4Cl(aq)
Dissolved NaCl(l) H2O(l)
H2O(l) Dissolved NaCl(aq)
Dissolved NH4Cl(l)
Calciner
CO2(g)
H2O(v)
NaHCO3(s) Na2CO3(s)
Cooler 3
Cooler 4
Separation Drum
CO2 (g)
H2O (l)
CO2 (g)
H2O(l)
Compressor 2
Process condition: Tin, Pin = 25°C, 1atm, Tout, Pout = 128°C, 4atm
Heater 1
NaCl (aq), H2O (l), NH4Cl (aq) NaCl (aq), H2O (v), NH4Cl (aq)
in out out
Process conditions: Tin, Pin = 45°C, 1atm ; Tout, Pout = 99.6°C, 1atm
Evaporator
H2O(v)
NaCl(s)
NH4Cl(s)
H2O(l) NaCl(s)
NH4Cl(s)
Cooler 5
Cooler 6
Pump 2
H2O (l)
H2O (l)
Process condition: Tin, Pin = 25°C, 1atm, Tout, Pout = 25°C, 4atm
ENERGY BALANCES
Dissolver/ Mixer 1
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (−411 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
̂𝑓 𝑁𝑎𝐶𝑙 =
𝐻𝑁𝑎𝐶𝑙 𝑖𝑛 = 𝑚̇𝐻 = −𝟑𝟐, 𝟖𝟎𝟎. 𝟒𝟓 𝒌𝑾
3600𝑠
𝑔
3880000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
̂𝑓 𝐻2𝑂 =
𝐻𝐻2𝑂 𝑖𝑛 = 𝑚̇𝐻 = −𝟏𝟕, 𝟎𝟗𝟔. 𝟏𝟐 𝒌𝑾
3600𝑠
̂𝑓 𝐻2𝑂
𝐻𝑟𝑒𝑐𝑦𝑐𝑙𝑒𝑑 𝐻2𝑂 𝑖𝑛 = 𝑚̇𝐻
𝑔
46490000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= = −𝟐𝟎𝟒, 𝟖𝟒𝟒. 𝟗𝟓 𝒌𝑾
3600𝑠
𝑔
50370000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
̂𝑓 𝐻2𝑂 =
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻 = −𝟐𝟐𝟏, 𝟗𝟒𝟏. 𝟎𝟕 𝒌𝑾
3600𝑠
∆𝐻 = (−32,800.45) + (−221,941.07)
−((−32,800.45) + (−17,096.12) + (−204,844.95))
= 𝟎 𝒌𝑾
𝑔
3670000 𝑘𝐽
( ℎ𝑟
𝑔 × (−46.19 𝑚𝑜𝑙 ))
17.03
𝑚𝑜𝑙
̂𝑓 𝑁𝐻3 =
𝐻𝑁𝐻3 𝑖𝑛 = 𝑚̇𝐻 = −𝟐, 𝟕𝟔𝟓. 𝟎𝟏 𝒌𝑾
3600𝑠
70
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 ̂𝑓 𝑁𝑎𝐶𝑙 + 𝑚̇ ∫ 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇
= 𝑚̇𝐻
25
70
= −32,800.45 + 𝑚̇ ∫ 0.0368 𝑑𝑇
25
253
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (1.6556 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −32,800.45 +
3600𝑠
= −𝟑𝟐, 𝟔𝟔𝟖. 𝟑𝟐 𝒌𝑾
70
̂𝑓 𝐻2𝑂 + 𝑚̇ ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻
25
70
= −221,941.07 + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇
25
𝑔
50370000 𝑘𝐽
( ℎ𝑟
𝑔 × (3.393 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= −221,941.07 +
3600𝑠
= −𝟐𝟏𝟗, 𝟑𝟎𝟔. 𝟓𝟕 𝒌𝑾
70
̂𝑓 𝑁𝐻3 + 𝑚̇ ∫ 𝐶𝑝𝑁𝐻3 𝑑𝑇
𝐻𝑁𝐻3 𝑜𝑢𝑡 = 𝑚̇𝐻
25
70 −3 −5 −8
= −2,765.01 + 𝑚̇ ∫ 35.15×10 + 2.954×10 −12+ 0.4421×10 𝑑𝑇
25 −6.686×10
𝑔
3670000 𝑘𝐽
( ℎ𝑟
𝑔 × (1.6444 𝑚𝑜𝑙 ))
17.03
𝑚𝑜𝑙
= −2,765.01 +
3600𝑠
= −𝟐, 𝟔𝟔𝟔. 𝟓𝟕 𝒌𝑾
Cooler 1
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7358 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −32,800.45 +
3600𝑠
= −𝟑𝟐, 𝟕𝟒𝟏. 𝟕𝟑 𝒌𝑾
45
̂𝑓 𝐻2𝑂 + 𝑚̇ ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻
25
45
= −221,941.07 + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇
25
𝑔
50370000 𝑘𝐽
( ℎ𝑟
𝑔 × (1.5080 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= −221,941.07 +
3600𝑠
= −𝟐𝟐𝟎, 𝟕𝟕𝟎. 𝟏𝟖 𝒌𝑾
45
𝐻𝑁𝐻3 𝑜𝑢𝑡 ̂𝑓 𝑁𝐻3 + 𝑚̇ ∫ 𝐶𝑝𝑁𝐻3 𝑑𝑇
= 𝑚̇𝐻
25
255
45 −3 −5 −8
= −2,765.01 + 𝑚̇ ∫ 35.15×10 + 2.954×10 −12+ 0.4421×10 𝑑𝑇
25 −6.686×10
𝑔
3670000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7236 𝑚𝑜𝑙 ))
17.03
𝑚𝑜𝑙
= −2,765.01 +
3600𝑠
= −𝟐, 𝟕𝟐𝟏. 𝟔𝟗 𝒌𝑾
Pump 1
45
̂𝑓 𝑁𝑎𝐶𝑙 + 𝑚̇ ∫ 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇 + 𝑉∆𝑃
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 = 𝑚̇𝐻
25
256
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (411 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙 45
= + 𝑚̇ ∫ 0.0368 𝑑𝑇
3600𝑠 25
𝑔
16790000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
2165000 3
𝑚
+
(1000)(3600𝑠)
( )
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7358 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −32,800.45 + + 6.472×10−6
3600𝑠
= −𝟑𝟐, 𝟕𝟒𝟏. 𝟕𝟑 𝒌𝑾
45
𝐻𝐻2𝑂 𝑜𝑢𝑡 ̂𝑓 𝐻2𝑂 + 𝑚̇ ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇 + 𝑉∆𝑃
= 𝑚̇𝐻
25
𝑔
50370000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
45 1000000 3
𝑚
= −221,941.07 + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇 +
25 (1000)(3600𝑠)
( )
𝑔
50370000 𝑘𝐽
( ℎ𝑟
𝑔 × (1.508 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= −221,941.07 + + 4.197×10−5
3600𝑠
= −𝟐𝟐𝟎, 𝟕𝟕𝟎. 𝟖𝟎 𝒌𝑾
45
̂𝑓 𝑁𝐻3 + 𝑚̇ ∫ 𝐶𝑝𝑁𝐻3 𝑑𝑇 + 𝑉∆𝑃
𝐻𝑁𝐻3 𝑜𝑢𝑡 = 𝑚̇𝐻
25
257
45 −3 −5
+ 0.4421×10−8 𝑑𝑇
= −2,765.01 + 𝑚̇ ∫ 35.15×10 + 2.954×10 −12
25 −6.686×10
𝑔
3670000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
880000 3
𝑚
+
(1000)(3600𝑠)
( )
𝑔
3670000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7236 𝑚𝑜𝑙 ))
17.03
𝑚𝑜𝑙
= −2,765.01 + + 3.472×10−6
3600𝑠
= −𝟐, 𝟕𝟐𝟏. 𝟔𝟗 𝒌𝑾
Compressor 1
Process conditions: Tin = 25℃, Tout = 128℃, Pin = 1 atm, Pout = 4atm
Components:
1. Inlet stream: CO2in (g)
2. Outlet stream: CO2out (g)
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (−393.5 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
̂𝑓 𝐶𝑂2 =
𝐻𝐶𝑂2 𝑖𝑛 = 𝑚̇𝐻 = −𝟏𝟏, 𝟕𝟕𝟐. 𝟓𝟏 𝒌𝑾
3600𝑠
128
𝐻𝐶𝑂2 𝑜𝑢𝑡 ̂𝑓 𝐶𝑂2 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝐶𝑂2 𝑑𝑇
25
258
128
+ 7.4640 X 10−12 T 3 dT
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (4.07 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
= −11772.51 +
3600𝑠
= −𝟏𝟏, 𝟔𝟓𝟎. 𝟕𝟓 𝒌𝑾
∆𝐻 = −11,650.75 − (−11,772.51)
= 𝟏𝟐𝟏. 𝟕𝟔 𝒌𝑾
Mixer 2
128
𝐻𝐶𝑂2 𝑜𝑢𝑡 ̂𝑓 𝐶𝑂2 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝐶𝑂2 𝑑𝑇
25
128
+ 7.4640 X 10−12 T 3 dT
259
𝑔
9480000 𝑘𝐽
( ℎ𝑟
𝑔 × (4.07 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
= −23545.03 +
3600𝑠
= −𝟐𝟑, 𝟑𝟎𝟏. 𝟓𝟎 𝒌𝑾
Cooler 2
45
𝐻𝐶𝑂2 𝑜𝑢𝑡 ̂𝑓 𝐶𝑂2 + 𝑚̇ ∫ 𝐶𝑝𝐶𝑂2 𝑑𝑇
= 𝑚̇𝐻
25
45 −3 −5 −8
= −23,545.03 + 𝑚̇ ∫ 36.11×10 + 4.233×10 −12− 2.887×10 𝑑𝑇
25 +7.464×10
𝑔
9480000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7526 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
= −23,545.03 +
3600𝑠
= −𝟐𝟑, 𝟓𝟎𝟎. 𝟎𝟎 𝒌𝑾
∆𝐻 = (−23,500.00) − (−23,301.50)
= −𝟏𝟗𝟖. 𝟓𝟎 𝒌𝑾
260
Carbonation Reactor
45
̂𝑓 𝑁𝑎𝐶𝑙 + 𝑚̇ ∫ 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇 + 𝑉∆𝑃
𝐻𝑁𝑎𝐶𝑙 𝑖𝑛 = 𝑚̇𝐻
25
𝑔
16790000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
45 2165000 3
𝑚
= −32,800.45 + 𝑚̇ ∫ 0.0368 𝑑𝑇 +
25 (1000)(3600𝑠)
( )
𝑔
16790000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7358 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −32,800.45 + + 6.472×10−6
3600𝑠
= −𝟑𝟐, 𝟕𝟒𝟏. 𝟕𝟑 𝒌𝑾
45
̂𝑓 𝐻2𝑂 + 𝑚̇ ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇 + 𝑉∆𝑃
𝐻𝐻2𝑂 𝑖𝑛 = 𝑚̇𝐻
25
𝑔
50370000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
45 1000000 3
𝑚
= −221,941.07 + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇 +
25 (1000)(3600𝑠)
( )
𝑔
50370000 𝑘𝐽
( ℎ𝑟
𝑔 × (1.508 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= −221,941.07 + + 4.197×10−5
3600𝑠
= −𝟐𝟐𝟎, 𝟕𝟕𝟎. 𝟖𝟎 𝒌𝑾
261
45
̂𝑓 𝑁𝐻3 + 𝑚̇ ∫ 𝐶𝑝𝑁𝐻3 𝑑𝑇 + 𝑉∆𝑃
𝐻𝑁𝐻3 𝑖𝑛 = 𝑚̇𝐻
25
45 −3 −5
+ 0.4421×10−8 𝑑𝑇
= −2,765.01 + 𝑚̇ ∫ 35.15×10 + 2.954×10 −12
25 −6.686×10
𝑔
3670000
( ℎ𝑟
𝑔 ) ×(4 − 1)𝑎𝑡𝑚
880000 3
𝑚
+
(1000)(3600𝑠)
( )
𝑔
3670000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7236 𝑚𝑜𝑙 ))
17.03
𝑚𝑜𝑙
= −2,765.01 + + 3.472×10−6
3600𝑠
= −𝟐, 𝟕𝟐𝟏. 𝟔𝟗 𝒌𝑾
45
̂𝑓 𝐶𝑂2 + 𝑚̇ ∫ 𝐶𝑝𝐶𝑂2 𝑑𝑇
𝐻𝐶𝑂2 𝑖𝑛 = 𝑚̇𝐻
25
𝑔
9480000 𝑘𝐽
( ℎ𝑟
𝑔 × (−393.50 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
=
3600𝑠
45 −3 −5 −8
+ 𝑚̇ ∫ 36.11×10 + 4.233×10 −12− 2.887×10 𝑑𝑇
25 +7.464×10
𝑔
9480000 𝑘𝐽
( ℎ𝑟
𝑔 × (0.7526 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
= −23,545.03 +
3600𝑠
= −𝟐𝟑, 𝟓𝟎𝟎. 𝟎𝟎 𝒌𝑾
45
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 ̂𝑓 𝑁𝑎𝐶𝑙 + ∫ 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇)
= 𝑚̇(𝐻
25
𝑔
4200000
( ℎ𝑟
𝑔 )
58.44 𝑘𝐽 45
𝑚𝑜𝑙
= × (−411 + ∫ 0.0368 𝑑𝑇)
3600𝑠 𝑚𝑜𝑙 25
262
𝑚𝑜𝑙 𝑘𝐽 𝑘𝐽
= 19.9635 × (−411 + 0.7358 )
𝑠 𝑚𝑜𝑙 𝑚𝑜𝑙
= −𝟖, 𝟏𝟗𝟎. 𝟑𝟏 𝒌𝑾
45
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚(̇𝐻
̂𝑓 𝐻2𝑂 + ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇)
25
𝑔
46490000
( ℎ𝑟
𝑔 )
18.02 𝑘𝐽 45
𝑚𝑜𝑙
= × (−285.84 + ∫ 75.4×10−3 𝑑𝑇)
3600𝑠 𝑚𝑜𝑙 25
𝑚𝑜𝑙 𝑘𝐽 𝑘𝐽
= 716.64 × (−285.84 + 1.508 )
𝑠 𝑚𝑜𝑙 𝑚𝑜𝑙
= −𝟐𝟎𝟑, 𝟕𝟔𝟒. 𝟐𝟓 𝒌𝑾
45
𝐻𝑁𝑎𝐻𝐶𝑂3 𝑜𝑢𝑡 = 𝑚(̇𝐻
̂𝑓 𝑁𝑎𝐻𝐶𝑂3 + ∫ 𝐶𝑝𝑁𝑎𝐻𝐶𝑂3 𝑑𝑇)
25
𝑔
18100000
( ℎ𝑟
𝑔 )
84.007 𝑘𝐽 45
𝑚𝑜𝑙
= × (−945.60 + ∫ 0.0876 𝑑𝑇)
3600𝑠 𝑚𝑜𝑙 25
𝑚𝑜𝑙 𝑘𝐽 𝑘𝐽
= 59.85 × (−945.60 + 1.7522 )
𝑠 𝑚𝑜𝑙 𝑚𝑜𝑙
= −𝟓𝟔, 𝟒𝟖𝟖. 𝟖𝟑 𝒌𝑾
45
𝐻𝑁𝐻4𝐶𝑙 𝑜𝑢𝑡 = 𝑚(̇𝐻
̂𝑓 𝑁𝐻4𝐶𝑙 + ∫ 𝐶𝑝𝑁𝐻4𝐶𝑙 𝑑𝑇)
25
𝑔
11520000
( ℎ𝑟
𝑔 )
53.49 𝑘𝐽 45
𝑚𝑜𝑙
= × (−361.20 + ∫ 0.0841 𝑑𝑇)
3600𝑠 𝑚𝑜𝑙 25
𝑚𝑜𝑙 𝑘𝐽 𝑘𝐽
= 59.82 × (−361.20 + 1.6820 )
𝑠 𝑚𝑜𝑙 𝑚𝑜𝑙
= −𝟐𝟏, 𝟓𝟎𝟕. 𝟗𝟎 𝒌𝑾
Rotary Filter
Components:
1. Inlet stream: NaClin (aq), H2Oin (l), NaHCO3in (s) and NH4Clin (aq)
2. Outlet stream: NaClout (aq), H2Oout (l), NaHCO3out (s) and NH4Clout (aq)
45
𝐻𝑁𝑎𝐶𝑙 𝑖𝑛 ̂𝑓 𝑁𝑎𝐶𝑙 + ∫ 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇) = −𝟖, 𝟏𝟗𝟎. 𝟑𝟏 𝒌𝑾
= 𝑚̇(𝐻
25
45
𝐻𝐻2𝑂 𝑖𝑛 = 𝑚(̇𝐻
̂𝑓 𝐻2𝑂 + ∫ 𝐶𝑝𝐻2𝑂 𝑑𝑇) = −𝟐𝟎𝟑, 𝟕𝟔𝟒. 𝟐𝟓 𝒌𝑾
25
45
𝐻𝑁𝑎𝐻𝐶𝑂3 𝑖𝑛 = 𝑚(̇𝐻
̂𝑓 𝑁𝑎𝐻𝐶𝑂3 + ∫ 𝐶𝑝𝑁𝑎𝐻𝐶𝑂3 𝑑𝑇) = −𝟓𝟔, 𝟒𝟖𝟖. 𝟖𝟑 𝒌𝑾
25
45
𝐻𝑁𝐻4𝐶𝑙 𝑖𝑛 = 𝑚(̇𝐻
̂𝑓 𝑁𝐻4𝐶𝑙 + ∫ 𝐶𝑝𝑁𝐻4𝐶𝑙 𝑑𝑇) = −𝟐𝟏, 𝟓𝟎𝟕. 𝟗𝟎 𝒌𝑾
25
Calciner
200
𝐻Na2CO3 out ̂𝑓 Na2CO3 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝Na2CO3 𝑑𝑇
25
200
= -33847.21+ ∫25 0.1123 dT
𝑔
11420000 𝑘𝐽
( ℎ𝑟
𝑔 × (19.65 𝑚𝑜𝑙 ))
105.99
𝑚𝑜𝑙
= −33847.21 +
3600𝑠
= −𝟑𝟑, 𝟐𝟓𝟗. 𝟏𝟎 𝒌𝑾
100 200
̂𝑓 𝐻2𝑂 + 𝑚̇ ∫
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻 𝐶𝑝𝐻2𝑂 𝑑𝑇 + 𝑚̇ ∫ ̂𝑣
𝐶𝑝𝐻2𝑂 𝑑𝑇 + 𝑚̇𝐻
25 100
200
100
= −7231.94 + 𝑚̇ ∫ 75.4000 X 10−3 𝑑𝑇 + 𝑚̇ ∫ 33.4600 X 10−3
25
100
200
̂𝑓 𝐶𝑂2 + 𝑚̇ ∫
𝐻𝐶𝑂2 𝑜𝑢𝑡 = 𝑚̇𝐻 𝐶𝑝𝐶𝑂2 𝑑𝑇
25
200
+ 7.4640 X 10−12 T 3 dT
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (7.23 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
= −11772.51 +
3600𝑠
= −𝟏𝟏, 𝟓𝟓𝟔. 𝟐𝟏 𝒌𝑾
Cooler 3
𝐻𝐻2𝑂 𝑖𝑛 = −5,744.17 𝒌𝑾
̂𝑓 𝐻2𝑂
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻
𝑔
1940000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
=
3600𝑠
= −𝟖, 𝟓𝟒𝟖. 𝟎𝟔 𝒌𝑾
266
̂𝑓 𝐶𝑂2
𝐻𝐶𝑂2 𝑜𝑢𝑡 = 𝑚̇𝐻
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (−393.50 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
=
3600𝑠
= −𝟏𝟏, 𝟕𝟕𝟐. 𝟓𝟏 𝒌𝑾
Cooler 4
̂𝑓 𝑁𝑎2𝐶𝑂3
𝐻𝑁𝑎2𝐶𝑂3 𝑜𝑢𝑡 = 𝑚̇𝐻
𝑔
11420000 𝑘𝐽
( ℎ𝑟
𝑔 × (−1130.90 𝑚𝑜𝑙 ))
105.99
𝑚𝑜𝑙
=
3600𝑠
= −𝟑𝟑, 𝟖𝟒𝟕. 𝟐𝟏 𝒌𝑾
∆𝐻 = (−33,847.21) − (−33,259.10)
= −𝟓𝟖𝟖. 𝟏𝟏 𝒌𝑾
267
Separation Drum
Compressor 2
Process conditions: Tin = 25℃, Tout = 128℃, Pin = 1 atm, Pout = 4atm
Components:
1. Inlet stream: CO2in (g)
2. Outlet stream: CO2out (g)
128
𝐻𝐶𝑂2 𝑜𝑢𝑡 ̂𝑓 𝐶𝑂2 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝐶𝑂2 𝑑𝑇 + 𝑉∆𝑃
25
268
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (−393.50 𝑚𝑜𝑙 ))
44.01
𝑚𝑜𝑙
=
3600𝑠
128
+ 𝑚̇ ∫ 36.11×10−3 + 4.233×10−5 − 2.887×10−8 𝑑𝑇
25 +7.464×10−12
4740 𝑘𝑔 𝑚3
( ×( ))
ℎ𝑟 1.977 𝑘𝑔
+ · 3 𝑎𝑡𝑚
3600𝑠
𝑔
4740000 𝑘𝐽
( ℎ𝑟
𝑔 × (4.0734 𝑚𝑜𝑙 )) 𝐽
44.01 7192.716
𝑚𝑜𝑙 ℎ𝑟
= −11,772.51 + +
3600𝑠 3600𝑠
= −𝟏𝟏, 𝟔𝟓𝟎. 𝟕𝟓 𝒌𝑾
∆𝐻 = −11,650.75 − (−11,772.51)
= 𝟏𝟐𝟏. 𝟕𝟔 𝒌𝑾
Heater 1
99.6
̂𝑓 𝑁𝑎𝐶𝑙 + 𝑚̇ ∫
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 = 𝑚̇𝐻 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇
25
𝑔
4200000 𝑘𝐽
( ℎ𝑟
𝑔 × (−411 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙 99.6
= + 𝑚̇ ∫ 0.0368 𝑑𝑇
3600𝑠 25
𝑔
4200000 𝑘𝐽
( ℎ𝑟
𝑔 × (2.7445 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −8,204.99 +
3600𝑠
= −𝟖, 𝟏𝟓𝟎. 𝟐𝟎 𝒌𝑾
99.6
𝐻𝐻2𝑂 𝑜𝑢𝑡 ̂𝑓 𝐻2𝑂 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝐻2𝑂 𝑑𝑇
25
𝑔
46490000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙 99.6
= + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇
3600𝑠 25
𝑔
46490000 𝑘𝐽
( ℎ𝑟
𝑔 × (5.62 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
= −204,844.95 +
3600𝑠
= −𝟐𝟎𝟎, 𝟖𝟏𝟕. 𝟒𝟐 𝒌𝑾
99.6
𝐻𝑁𝐻4𝐶𝑙 𝑜𝑢𝑡 ̂𝑓 𝑁𝐻4𝐶𝑙 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝑁𝐻4𝐶𝑙 𝑑𝑇
25
𝑔
11520000 𝑘𝐽
( ℎ𝑟
𝑔 × (−361.2 𝑚𝑜𝑙 ))
53.49
𝑚𝑜𝑙 99.6
= + 𝑚̇ ∫ 0.0841 𝑑𝑇
3600𝑠 25
𝑔
11520000 𝑘𝐽
( ℎ𝑟
𝑔 × (6.2739 𝑚𝑜𝑙 ))
53.49
𝑚𝑜𝑙
= −21,608.52 +
3600𝑠
= −𝟐𝟏, 𝟐𝟑𝟑. 𝟏𝟗 𝒌𝑾
270
Evaporator
100
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 ̂𝑓 𝑁𝑎𝐶𝑙 + 𝑚̇ ∫
= 𝑚̇𝐻 𝐶𝑝𝑁𝑎𝐶𝑙 𝑑𝑇
25
100
= -8205.00 + 𝑚̇ ∫25 0.0368 𝑑𝑇
𝑔
4200000 𝑘𝐽
( ℎ𝑟
𝑔 × (2.76 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
= −8205.00 +
3600𝑠
= −𝟖, 𝟏𝟒𝟗. 𝟗𝟏 𝒌𝑾
100
̂𝑓 𝐻2𝑂 + 𝑚̇ ∫
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻 𝐶𝑝𝐻2𝑂 𝑑𝑇 + 𝑚̇∆𝐻𝑣
25
271
𝑔
46490000 𝑘𝐽
( ℎ𝑟
𝑔 × (−241.83 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙 100
𝑘𝐽
= + 𝑚̇ ∫ 75.4×10−3 𝑑𝑇 + 𝑚̇(40.66 )
3600𝑠 25 𝑚𝑜𝑙
𝑔 𝑔
46490000 𝑘𝐽 46490000 𝑘𝐽
( ℎ𝑟 ( ℎ𝑟
𝑔 ×(5.6550𝑚𝑜𝑙)) 𝑔 ×(40.66𝑚𝑜𝑙))
18.02 18.02
𝑚𝑜𝑙 𝑚𝑜𝑙
= −173,305.54 + +
3600𝑠 3600𝑠
= −𝟏𝟒𝟎, 𝟏𝟏𝟒. 𝟐𝟕 𝒌𝑾
100
̂𝑓 𝑁𝐻4𝐶𝑙 + 𝑚̇ ∫
𝐻𝑁𝐻4𝐶𝑙 𝑜𝑢𝑡 = 𝑚̇𝐻 𝐶𝑝𝑁𝐻4𝐶𝑙 𝑑𝑇
25
100
= -21608.52 + 𝑚̇ ∫25 0.0841 𝑑𝑇
𝑔
11520000 𝑘𝐽
( ℎ𝑟
𝑔 × (6.31 𝑚𝑜𝑙 ))
53.49
𝑚𝑜𝑙
= −21608.52 +
3600𝑠
= −𝟐𝟏, 𝟐𝟑𝟏. 𝟎𝟑 𝒌𝑾
Cooler 5
̂𝑓 𝑁𝑎𝐶𝑙
𝐻𝑁𝑎𝐶𝑙 𝑜𝑢𝑡 = 𝑚̇𝐻
𝑔
4200000 𝑘𝐽
( ℎ𝑟
𝑔 × (−411.0 𝑚𝑜𝑙 ))
58.44
𝑚𝑜𝑙
=
3600𝑠
= −𝟖, 𝟐𝟎𝟓. 𝟎𝟎 𝒌𝑾
̂𝑓 𝑁𝐻4𝐶𝑙
𝐻𝑁𝐻4𝐶𝑙 𝑜𝑢𝑡 = 𝑚̇𝐻
𝑔
11520000 𝑘𝐽
( ℎ𝑟
𝑔 × (−361.20 𝑚𝑜𝑙 ))
53.49
𝑚𝑜𝑙
=
3600𝑠
= −𝟐𝟏, 𝟔𝟎𝟖. 𝟓𝟐 𝒌𝑾
Cooler 6
̂𝑓 𝐻2𝑂
𝐻𝐻2𝑂 𝑜𝑢𝑡 = 𝑚̇𝐻
273
𝑔
46490000 𝑘𝐽
( ℎ𝑟
𝑔 × (−285.84 𝑚𝑜𝑙 ))
18.02
𝑚𝑜𝑙
=
3600𝑠
= −𝟐𝟎𝟒, 𝟖𝟒𝟒. 𝟗𝟓 𝒌𝑾
∆𝐻 = (−204,844.95) − (−140,114.27)
= −𝟔𝟒, 𝟕𝟑𝟎. 𝟔𝟖 𝒌𝑾
Pump 2
Process condition: Tin, Pin = 25°C, 1atm, Tout, Pout = 25°C, 4atm
Components:
1. Inlet stream: H2Oin (l)
2. Outlet stream: H2Oout (l)
( )
= −204,844.95 + 3.89×10−5
= −𝟐𝟎𝟒, 𝟖𝟒𝟒. 𝟗𝟓 𝒌𝑾
∆𝐻 = (−204,844.95) − (−204,844.95)
= 𝟑. 𝟖𝟗×𝟏𝟎−𝟓 𝒌𝑾
APPENDIX C
Mixer 1/ Dissolver
Vessel sizing
a) Vessel volume, V
𝑓𝑡 3
𝑉 = 36.05 ×5𝑚𝑖𝑛
𝑚𝑖𝑛
𝑽 = 𝟏𝟖𝟎. 𝟐𝟓 𝒇𝒕𝟑
b) Vessel diameter, D
𝜋𝐷2 3𝜋𝐷3
𝑉= ∙𝐿 =
4 4
4𝑉 1/3 4×180.25 1/3
𝐷=( ) =( )
3𝜋 3𝜋
𝑫 = 𝟒. 𝟐𝟓 𝒇𝒕
c) Vessel height, L
𝐿 = 3𝐷 = 3×4.25 𝑓𝑡
𝑳 = 𝟏𝟐. 𝟕𝟓 𝒇𝒕
d) Cross-sectional area, A
𝜋𝐷²
A= 4
𝜋(4.25)2
A= 4
𝑨 = 𝟏𝟒. 𝟏𝟗 𝒇𝒕𝟐
276
Vessel costing
b) Vessel Cost, CV
𝑫𝒊 (ft) 𝒕𝒑 (in.)
Up to 4 1/4
4–6 5/16
6–8 3/8
8 – 10 7/16
10 - 12 1/2
1
Hence, 𝑡𝑝 = 4 𝑖𝑛 = 0.25 𝑖𝑛.
0.22(53.50+18)1532
𝑡𝑤 = 15000(53.50)2
𝑡𝑤 = 0.0086 𝑖𝑛.
𝑡𝑝 + 𝑡𝑤 0.25 + 0.0086
𝑡𝑣 = = = 0.1293 𝑖𝑛.
2 2
d) Purchase cost, Cp
𝐶𝑃 = 𝐹𝑀 𝐶𝑉 + 𝐶𝑃𝐿
541.7
𝐶𝑃 = ( ) [(1.2×(19,660.58 + 13,449.58)) + 6,377.40]
500
𝑪𝑷 = $ 𝟒𝟗, 𝟗𝟓𝟓. 𝟏𝟑
Tower sizing
83.33𝑚𝑚𝐻2 𝑂/𝑚
∆𝑃𝑓𝑙𝑜𝑜𝑑 = 0.115𝐹𝑝 0.7 = 0.115(650.7 ) ( )
𝑖𝑛. 𝐻2 𝑂/𝑓𝑡
∆𝑷𝒇𝒍𝒐𝒐𝒅 = 𝟏𝟕𝟖. 𝟎𝟓 𝒎𝒎𝑯𝟐 𝑶/𝒎
b) Flooding velocity, Uf
𝐹𝐿𝐺 = 0.4978
𝑈𝑓 2 𝐹𝑝 𝜌𝐺
𝑌= (𝜌 ) 𝑓{𝜌𝐿 }𝑓{𝜇𝐿 }
𝑔 𝐻2𝑂
𝑈𝑓 2 (65) 0.00086
0.0469 = ( ) (0.9557)(0.8912)
32.2 1
𝑈𝑓 2 = 31.72
𝑼𝒇 = 𝟓. 𝟔𝟑 𝒇𝒕/𝒔
c) Tower diameter, DT
d) Cross-sectional area, A
𝜋(𝐷)2
A= 4
𝜋(3.68)2
A= 4
𝑨 = 𝟏𝟎. 𝟔𝟒 𝒇𝒕𝟐
e) Tower height, 𝑧
100 100
𝐻𝐸𝑇𝑃 = + 0.333 = + 0.333
𝑎 28
𝑯𝑬𝑻𝑷 = 𝟑. 𝟗𝟎 𝒇𝒕
𝑦 − 𝐻𝑥 1 1
𝑙𝑛 [(𝑦 𝑖𝑛 − 𝐻𝑥𝑖𝑛 ) (1 − 𝐴) + 𝐴]
𝑜𝑢𝑡 𝑖𝑛
𝑁𝑂𝐺 =
1
1−𝐴
Since the concentration of ammonia in inlet brine is almost zero and dilute,
𝑦 1 1
𝑙𝑛 [(𝑦 𝑖𝑛 ) (1 − 𝐴) + 𝐴]
𝑜𝑢𝑡
𝑁𝑂𝐺 =
1
1−
𝐴
And, absorption factor, A is computed by:
kg
𝑚̇𝑏𝑟𝑖𝑛𝑒 67160.02
𝐴= = hr = 19.28
0.95𝑚̇𝑁𝐻3 kg
0.95(3667.37 )
hr
𝑁𝑂𝐺 = 4.80
𝑧 = 𝐻𝐸𝑇𝑃(𝑁𝑂𝐺 ) = 3.90(4.80)
𝒛 = 𝟏𝟖. 𝟕𝟐 𝒇𝒕
f) Residence time, θ
𝑧 18.72 𝑓𝑡
𝜃= =
𝑔𝑎𝑠 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 3100.81 𝑓𝑡 3 /min
( )
10.64 𝑓𝑡 2
𝜽 = 𝟎. 𝟎𝟔 𝒎𝒊𝒏 = 𝟑. 𝟖𝟓 𝒔𝒆𝒄
282
Tower costing
b) Tower Cost, CV
Since the wall thickness calculated is too small due to low pressure, hence,
1
𝑡𝑝 = 𝑖𝑛 = 0.25 𝑖𝑛.
4
Assuming a wall thickness of 1.25 in., L = 224.64 in. and 𝐷𝑖 = 44.16 in.
𝐷𝑜 = 44.16 + 1.25(2) = 46.66 𝑖𝑛.
𝑡𝑝 + 𝑡𝑤 0.25 + 0.011
𝑡𝑣 = = = 0.1305 𝑖𝑛.
2 2
Based on installation cost table, CPK = 19 $/ft3 for ceramic Raschig rings.
d) Purchase cost, Cp
𝐶𝑃 = 𝐹𝑀 𝐶𝑉 + 𝐶𝑃𝐿 + 𝐶𝑃𝑎𝑐𝑘𝑖𝑛𝑔𝑠
541.7
𝐶𝑃 = ( ) [(2.1×(28,261.35) + 7,187.66 + 5,112.61]
500
𝑪𝑷 = $ 𝟕𝟕, 𝟔𝟐𝟒. 𝟔𝟒
Carbonation Reactor
Tower sizing
a) Flooding velocity, Uf
𝜌𝐿 − 𝜌𝐺 1/2
𝑈𝑓 = 𝐶 ( )
𝜌𝐺
𝐶 = 𝐶𝑆𝐵 𝐹𝑆𝑇 𝐹𝐹 𝐹𝐻𝐴
Referring to flooding correlation graph of CSB versus FLG, with plate spacing of
18 in., CSB = 0.16 ft/s.
𝜎𝑚𝑖𝑥𝑡𝑢𝑟𝑒 0.20
𝐹𝑆𝑇 = ( )
20
𝜎𝑚𝑖𝑥𝑡𝑢𝑟𝑒 = 𝜎𝑏𝑟𝑖𝑛𝑒 𝑥𝑏𝑟𝑖𝑛𝑒 + 𝜎𝑁𝐻3 𝑥𝑁𝐻3
𝑃𝑐ℎ (𝜌𝐿 − 𝜌𝑉 ) 4
𝜎𝑖 = [ ] ×10−12
𝑀𝑊
where, 𝑃𝑐ℎ is Sugden’s parachor for organic compounds obtained from Chemical
Engineering Vol 6, reference book.
Assuming 𝜌𝑉 = 0,
𝜎𝑏𝑟𝑖𝑛𝑒 = 72 𝑑𝑦𝑛𝑒/𝑐𝑚
286
4
(12.5 + (11.3×3))(0.73) 𝑚𝐽
𝜎𝑁𝐻3 =[ ] ×10−12 = 15.65 2 = 15.65 𝑑𝑦𝑛𝑒/𝑐𝑚
17.03 𝑚
𝜎𝑚𝑖𝑥𝑡𝑢𝑟𝑒 = 72(0.95) + 15.65(0.05) = 69.18 𝑑𝑦𝑛𝑒/𝑐𝑚
69.18 0.20
𝐹𝑆𝑇 =( ) = 1.28
20
𝑚
𝑓𝑡 𝑠
𝐶 = 𝐶𝑆𝐵 𝐹𝑆𝑇 𝐹𝐹 𝐹𝐻𝐴 = (0.16 ×0.3048 𝑓𝑡 ) (1.28)(0.75)(1) = 0.0468 𝑚/𝑠
𝑠
𝑠
b) Tower diameter, DT
4𝐺
𝐷𝑇 = [ ]
𝐴
(𝑓𝑈𝑓) )𝜋 (1 − 𝐴𝑑 ) 𝜌𝐺
𝑇
c) Cross-sectional area, A
𝜋(𝐷)2
𝐴=
4
𝜋(3.90)2
𝐴=
4
𝑨 = 𝟏𝟏. 𝟗𝟓 𝒇𝒕𝟐
d) Tower height, 𝑧
𝑦 − 𝐻𝑥 1 1
𝑙𝑛 [(𝑦 𝑖𝑛 − 𝐻𝑥𝑖𝑛 ) (1 − 𝐴) + 𝐴]
𝑜𝑢𝑡 𝑖𝑛
𝑁𝑂𝐺 =
1
1−𝐴
Since the concentration of carbon dioxide in inlet ammoniated brine is almost zero
and dilute,
𝑦 1 1
𝑙𝑛 [(𝑦 𝑖𝑛 ) (1 − 𝐴) + 𝐴]
𝑜𝑢𝑡
𝑁𝑂𝐺 =
1
1−𝐴
e) Residence time, θ
𝑧 25.5 𝑓𝑡
𝜃= =
𝑔𝑎𝑠 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 840.41 𝑓𝑡 3 /min
( )
11.95 𝑓𝑡 2
𝜽 = 𝟎. 𝟑𝟔 𝒎𝒊𝒏 = 𝟐𝟏. 𝟕𝟔 𝒔𝒆𝒄
Tower costing
b) Vessel Cost, CV
𝑫𝒊 (ft) 𝒕𝒑 (in.)
Up to 4 1/4
4–6 5/16
6–8 3/8
8 – 10 7/16
10 - 12 1/2
1
Hence, 𝑡𝑝 = 4 𝑖𝑛 = 0.25 𝑖𝑛.
Assuming a wall thickness of 1.25 in., L = 306 in. and 𝐷𝑖 = 46.80 in.
𝐷𝑜 = 46.8 + 1.25(2) = 49.30 𝑖𝑛.
𝑡𝑝 + 𝑡𝑤 0.25 + 0.0192
𝑡𝑣 = = = 0.1346 𝑖𝑛.
2 2
Rounding up to the nearest increment, via increment 1/16 in. from 3/16 in.
290
𝒕𝒔 = 𝟎. 𝟑𝟏𝟐𝟓 𝒊𝒏.
c) Tray cost, CT
𝑁𝑇 = 17 𝑡𝑟𝑎𝑦𝑠
2.25 2.25
𝐹𝑁𝑇 = 𝑁𝑇
= = 1.13
1.0414 1.041417
d) Purchase cost, Cp
𝐶𝑃 = 𝐹𝑀 𝐶𝑉 + 𝐶𝑃𝐿 + 𝐶𝑇
541.7
𝐶𝑃 = ( ) [(2.1×(26,253.24)) + 9,553.39 + 55,650.07]
500
𝑪𝑷 = $ 𝟏𝟑𝟎, 𝟑𝟕𝟏. 𝟐𝟑
Assumptions/additional information:
Vessel Sizing
a) Vessel volume, V
𝐿
𝑉̇ = 1483.15
𝑚𝑖𝑛
292
b) Diameter inside, Di
𝑉 1
𝐷 = ( )3
𝜋
261.88 𝑓𝑡 3 1
𝐷 =( )3
𝜋
𝑫 = 𝟒. 𝟑𝟕 𝒇𝒕
c) Length of filter
𝐿 = 4𝐷 = 4(4.37)
𝑳 = 𝟏𝟕. 𝟒𝟖 𝒇𝒕
d) Cross-sectional area, A
𝐷
𝐴 = 𝜋( )2
2
4.37 2
𝐴 = 𝜋( )
2
𝑨 = 𝟏𝟓 𝒇𝒕𝟐
Filter Costing
a) Purchase cost, Cp
𝑪𝒑 = $ 𝟏𝟏𝟑, 𝟔𝟎𝟔. 𝟕𝟗
𝐹𝐵𝑀 = 2.32
𝐶𝐵𝑀 = 𝐶𝑝 𝐹𝐵𝑀
𝐶𝐵𝑀 = $ 113,606.79 (2.32)
𝑪𝑩𝑴 = $ 𝟐𝟔𝟑, 𝟓𝟔𝟕. 𝟕𝟒 = 𝑹𝑴 𝟏, 𝟏𝟕𝟐, 𝟖𝟕𝟔. 𝟒𝟕
Calciner sizing
𝑄𝑅
𝐴𝑅 =
𝑞
where QR is the radiant duty, and q is the average radiant flux. Assuming an
average radiant flux of 20,000 Btu/(hr.ft2).
294
QR = 5929.35 KW
𝐽 3600 𝑠 9.486×10−4 𝐵𝑡𝑢
= 5929.35 ( )( ) ×1000
𝑠 1 ℎ𝑟 1𝐽
𝐵𝑡𝑢
= 20,248,493.08 ℎ𝑟
𝐵𝑡𝑢
20,248,493.08
𝐴𝑅 = ℎ𝑟
𝐵𝑡𝑢
20,000
ℎ𝑟. 𝑓𝑡 2
𝑨𝑹 = 𝟏𝟎𝟏𝟐. 𝟒𝟐 𝒇𝒕𝟐
𝐷𝑟 2
𝐿= = = 277.56 𝑓𝑡
1 1 1 1
0.52𝜌(𝑇 − 𝑇 ) 0.52(2.2)(113 − 392)
𝑎 𝑔𝑎
𝑘𝑔
𝑚̇𝑓𝑙𝑢𝑒 𝑔𝑎𝑠 = 𝑚̇𝐻2𝑂 + 𝑚̇𝐶𝑂2 = 1939.89 + 4739 = 6678.89
ℎ𝑟
𝐼𝑏
= 14,721.16
ℎ𝑟
𝑖𝑏
16𝑚̇𝑓𝑙𝑢𝑒 𝑔𝑎𝑠 𝑇𝑔𝑎 0.2 16 (14,721.16 ) (392℉)
𝑑𝑜 = ( ) =( ℎ𝑟 )0.2 = 5.6 𝑓𝑡
211,000𝜋 2 𝑓 211,000𝜋 2 (0.008)
𝐼𝑏
𝑚̇𝑓𝑙𝑢𝑒 𝑔𝑎𝑠 14,721.16 1ℎ𝑟 𝐼𝑏
𝑔= = ℎ𝑟 ( ) = 0.1660
𝜋𝑑𝑜 2 /4 𝜋(5.6 𝑓𝑡)2 3600𝑠 𝑠. 𝑓𝑡 2
4
𝐼𝑏 0.6 0.28
2.14𝑔0.6 𝑇𝑔𝑎 0.28 2.14(0.1660 𝑠. 𝑓𝑡 2 ) (392 ℉) 𝐵𝑡𝑢
ℎ𝑐 = = = 1.94
𝑑𝑜 0.4 (5.6)0.4 𝐼𝑏. ℉
1 1 ℎ𝑟℉𝑓𝑡 2
𝑅𝑐 = = = 0.00086
𝑔ℎ𝑐 (0.1660 𝐼𝑏 )(1.94 𝐵𝑡𝑢 )(3600𝑠 ) 𝐵𝑡𝑢
𝑠. 𝑓𝑡 2 𝐼𝑏. ℉ 1ℎ𝑟
Assume, Ri and Ro,
Ri = 0.011 hr.ft2.oF/Btu
Ro = 0.00181 hr.ft2.oF/Btu
295
𝐵𝑡𝑢
𝑄𝐻𝑒𝑎𝑡 𝐸𝑥𝑐ℎ𝑎𝑛𝑔𝑒𝑟 20,248,493.08
𝐴𝐻𝑋 = = ℎ𝑟
𝑈∆𝑇𝐿𝑀 𝐵𝑡𝑢
(150 ) (392℉ − 113℉)
ℎ𝑟℉𝑓𝑡 2
𝑨𝑯𝑿 = 𝟒𝟖𝟑. 𝟖𝟑 𝒇𝒕𝟐
Furnace costing
a) Purchase cost, Cp
𝐶𝑃 = 0.650𝑄 0.81
541.7 𝑏𝑡𝑢 0.81
𝐶𝑃 = ( ) [0.650 (20,248,493.08 ) ]
500 ℎ𝑟
𝑪𝑷 = $ 𝟓𝟖𝟑, 𝟐𝟖𝟒. 𝟐𝟗
Separation Drum
Vessel sizing
a) Vessel volume, V
𝑓𝑡 3
𝑉 = 1576.82 ×2𝑚𝑖𝑛
𝑚𝑖𝑛
𝑽 = 𝟑𝟏𝟓𝟑. 𝟔𝟒 𝒇𝒕𝟑
b) Vessel diameter, D
𝜋𝐷2 3𝜋𝐷3
𝑉= ∙𝐿 =
4 4
4𝑉 1/3 4(3153.64) 1/3
𝐷=( ) =( )
3𝜋 3𝜋
𝑫 = 𝟏𝟏. 𝟎𝟐 𝒇𝒕
297
c) Vessel length, L
𝐿 = 3𝐷 = 3×11.02 𝑓𝑡
𝑳 = 𝟑𝟑. 𝟎𝟔 𝒇𝒕
d) Cross-sectional area, A
𝜋𝐷²
A= 4
𝜋(11.02)2
A= 4
𝑨 = 𝟗𝟓. 𝟑𝟖 𝒇𝒕𝟐
Vessel costing
b) Vessel Cost, CV
Since the wall thickness calculated is too small due to low pressure, hence,
1
𝑡𝑝 = 𝑖𝑛 = 0.50 𝑖𝑛.
2
Assuming a wall thickness of 1.25 in., L = 396.72 in. and 𝐷𝑖 = 132.24 in.
𝐷𝑜 = 132.24 + 1.25(2) = 134.74 𝑖𝑛.
0.22(134.74+18)396.722
𝑡𝑤 = 29732.70(134.74)2
𝑡𝑤 = 0.0098 𝑖𝑛.
𝑡𝑝 + 𝑡𝑤 0.50 + 0.0098
𝑡𝑣 = = = 0.2549 𝑖𝑛.
2 2
c) Purchase cost, Cp
𝐶𝑃 = 𝐹𝑀 𝐶𝑉 + 𝐶𝑃𝐿
541.7
𝐶𝑃 = ( ) [(1.7×(64,629.13)) + 3,262.98]
500
𝑪𝑷 = $ 𝟏𝟐𝟐, 𝟓𝟔𝟕. 𝟕𝟓
Evaporator
Assumptions/additional information:
Evaporator Sizing
a) Vessel volume, V
𝑉̇ = 1391.22 𝐿/𝑚𝑖𝑛
1391 𝐿 1 𝑚3 35.3145 𝑓𝑡 3
𝑉= (1000 𝐿) ( ) (5 𝑚𝑖𝑛)
𝑚𝑖𝑛 1 𝑚3
300
𝑽 = 𝟐𝟒𝟓. 𝟔𝟏 𝒇𝒕𝟑
b) Vessel diameter, D
𝐿 = 3𝐷
𝑉 = 𝐴𝐿
𝐷
𝐴 = 𝜋( )2
2
𝑉 = 3𝐴𝐷
𝐷
𝑉 = 3𝜋( )2 𝐷
2
3
𝑉 = 𝜋𝐷3
4
4𝑉 1
𝐷 = ( )3
3𝜋
4(245.61 𝑓𝑡 3 ) 1
𝐷 =( )3
3𝜋
𝑫 = 𝟒. 𝟕𝟏 𝒇𝒕
c) Length of vessel
𝐿 = 3𝐷 = 3(4.71)
𝑳 = 𝟏𝟒. 𝟏𝟑 𝒇𝒕
d) Cross-sectional area, A
𝐷
𝐴 = 𝜋( )2
2
4.28 2
𝐴 = 𝜋( )
2
𝑨 = 𝟏𝟕. 𝟒𝟐 𝒇𝒕𝟐
301
𝑘𝐽 𝐵𝑡𝑢
Heat duty, Q = 3,317.86 kW = 3,317.86 = 11,330,359.19
𝑠 ℎ𝑟
𝐵𝑡𝑢
𝑞 11,330,359.19
𝐴𝑇 = = ℎ𝑟
𝑈∆𝑇𝑚 𝐵𝑡𝑢
150 (32.72℉)
ℎ𝑟. 𝑓𝑡 2 . ℉
𝑨𝑻 = 𝟐𝟑𝟎𝟖. 𝟓𝟓 𝒇𝒕𝟐
Evaporator Costing
a) Purchase cost, Cp
541.7
𝐶𝑝 = 5,700𝐴0.55 = ( ) [5,700(2308.55)0.55 ]
500
𝑪𝒑 = $ 𝟒𝟑𝟕, 𝟎𝟏𝟖. 𝟗𝟖
𝐶𝐵𝑀 = 𝐶𝑝 𝐹𝐵𝑀
𝐶𝐵𝑀 = $ 437,018.98(2.45)
𝑪𝑩𝑴 = $ 𝟏, 𝟎𝟕𝟎, 𝟔𝟗𝟔. 𝟓𝟎 = 𝑹𝑴 𝟒, 𝟕𝟔𝟒, 𝟓𝟗𝟗. 𝟒𝟎
302
Heat Exchangers
Heat Exchanger 1
TCout = 24.38°C
TCin = 10°C
Q = 695.49 kW
Q = 2375070.53 Btu/hr
303
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
35 − 31.54
∆𝑇𝐿𝑀 =
35
ln( )
31.54
∆𝑻𝑳𝑴 = 33.24 °C
U = 720 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C
3
1
𝐴 = 695.49 ×10 𝑊× ×
720 𝑊 33.24℃
10.76𝑓𝑡 2
2
𝐴 = 29.06𝑚 ×
1𝑚2
𝑨 = 𝟑𝟏𝟐. 𝟔𝟗 𝒇𝒕𝟐
304
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
Based on Table 22.25 (product and process design principles book), the material
factor, FM: a=5.20, b=0.16;
𝐴 𝑏
𝐹𝑀 = 𝑎 + ( )
100
312.69 0.16
𝐹𝑀 = 5.20 + ( )
100
𝐹𝑀 = 6.40
CP = FPFMFLCB
CP = 0.9803 x 6.40 x 1.00 x 8165.59
CP = $ 51,230.26
305
CBM = FBM × CP × CE
CBM = 3.17 x 51230.26x 541.7/500
CBM = $ 175,944.08 = RM 782,951.16
Heat Exchanger 2
TCout = 26.03 ℃
TCin = 24.38℃
Q = 125.06 kW
125.06 ×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
𝑸 = 𝟒𝟐𝟕𝟎𝟕𝟒. 𝟗𝟎 𝐁𝐭𝐮/𝐡𝐫
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
20.62 − 71.08
∆𝑇𝐿𝑀 =
20.62
ln( 71.08 )
∆𝑻𝑳𝑴 = 40.77°C
307
U = 300 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 125.06×103 𝑊× ×
300 𝑊 40.77℃
10.76𝑓𝑡 2
𝐴 = 10.22 𝑚2 ×
1 𝑚2
𝑨 = 𝟏𝟎𝟗. 𝟗𝟕 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
44.1 44.1 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.989
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.989 x 1.00 x 1.00 x 7300.04
CP = $ 7,219.74
CBM = FBM x CP x CE
CBM = 3.17 x 7219.74 x (541.7/500)
CBM = $ 24,795.32= RM 110,339.17
Heat Exchanger 3
Chilled Water(17000kg/hr)
TCout = 81.95℃
Chilled Water(17000kg/hr)
TCin = 10℃
309
Q = 252.39bkW
Q = 861901.75 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
310
15 − 15.16
∆𝑇𝐿𝑀 =
15
ln( )
15.16
∆𝑻𝑳𝑴 = 15.08°C
U = 300 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C
3
1
𝐴 = 252.39×10 𝑊× ×
300 𝑊 15.08°𝐶
10.76𝑓𝑡 2
𝐴 = 55.79𝑚2 ×
1𝑚2
𝑨 = 𝟔𝟎𝟎. 𝟑𝟎 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 3.01 x 1.00 x 23884.01
CP = $ 70,474.62
CBM = FBM x CP x CE
CBM = 3.17 x 70474.62 x (541.7/500)
CBM = $ 242,036.48 = RM 1,077,062.34
312
Heat Exchanger 4
TCout = 97.93℃
Chilled Water
(2800kg/hr)
TCin = 10℃
Q = 275.5 kW
Q = 940821.48 Btu/hr
313
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
15 − 9.06
∆𝑇𝐿𝑀 =
15
ln(9.06)
∆𝑻𝑳𝑴 = 11.78°C
U = 300 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 275.5 ×103 𝑊× ×
300 𝑊 11.78℃
10.76𝑓𝑡 2
2
𝐴 = 77.96 𝑚 ×
1𝑚2
𝑨 = 𝟖𝟑𝟖. 𝟖𝟓 𝒇𝒕𝟐
314
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803x 1.00 x 1.00 x 11061.34
CP = $ 10,843.43
315
CBM = FBM x CP x CE
CBM = 3.17 x 10843.43 x (541.7/500)
CBM = $ 37,240.44 = RM 165,719.96
Heat Exchanger 5
TCout = 19.40℃
Chilled Water
(50000kg/hr)
TCin = 10℃
Q = 432.75 kW
Q = 1477823.94 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
15 − 80.60
∆𝑇𝐿𝑀 =
15
ln( 80.60)
∆𝑻𝑳𝑴 = 39.01 °C
U = 500 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
317
𝑚2 . °C 1
𝐴 = 432.75×103 𝑊× ×
500 𝑊 39.01 ℃
10.76𝑓𝑡 2
𝐴 = 22.19 𝑚2 ×
1𝑚2
𝑨 = 𝟐𝟑𝟖. 𝟕𝟑 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 6.35 x 1.00 x 7770.65
CP = $ 48,371.56
CBM = FBM x CP x CE
CBM = 3.17 x 48371.56 x (541.7/500)
CBM = $ 166,126.22 = RM 739,261.68
Heat Exchanger 6
TCout =61.58°C
TCin = 19.40°C
319
Q = 2431.35 kW
2431.35 ×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
Q = 8302962.99 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
5.6 − 8.42
∆𝑇𝐿𝑀 =
5.6
ln(8.42)
320
∆𝑻𝑳𝑴 = 6.91°C
U = 1500 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 2431.35 ×103 𝑊× ×
1200 𝑊 6.91℃
10.76𝑓𝑡 2
2
𝐴 = 293.22𝑚 ×
1𝑚2
𝑨 = 𝟑𝟏𝟓𝟓. 𝟎𝟓 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
𝐴 𝑏
𝐹𝑀 = 𝑎 + ( )
100
3155.05 0.00
𝐹𝑀 = 0.00 + ( )
100
𝐹𝑀 = 1.00
CP = FPFMFLCB
CP = 0.9803x 1.00 x 1.00 x 22485.66
CP = $ 22,042.69
CBM = FBM × CP × CE
CBM = 3.17 x 22042.69x (541.7/500)
CBM = $ 75,702.93 = RM 336,878.04
Heat Exchanger 7
TCin = 45°C
322
Q = 897 kW
897×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
Q = 3063219.12 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
10.92 − 10
∆𝑇𝐿𝑀 =
10.92
ln( 10 )
∆𝑻𝑳𝑴 = 10.45°C
323
U = 300 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 897×103 𝑊× ×
300 𝑊 10.45℃
10.76𝑓𝑡 2
𝐴 = 286.12𝑚2 ×
1𝑚2
𝑨 = 𝟑𝟎𝟕𝟖. 𝟔𝟗 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 10.83 x 1.00 x 22123.06
CP = $ 234,872.76
CBM = FBM × CP × CE
CBM = 3.17 x 234872.76 x (541.7/500)
CBM = $ 806,641.84 = RM 3,589,556.19
Heat Exchanger 8
NH4Cl (11520 kg/hr)
NaCl (4200 kg/hr)
Water (46490 kg/hr)
TCout = 88.35°C
CO2 (4740 kg/hr) CO2 (4740 kg/hr)
TCout = 87.11°C
325
Q = 74.14 kW
Q = 253185.13 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
326
9.89 − 39.65
∆𝑇𝐿𝑀 =
9.89
ln( )
39.65
∆𝑻𝑳𝑴 = 21.43°C
U = 250 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 74.14×103 𝑊× ×
250 𝑊 21.43℃
10.76𝑓𝑡 2
𝐴 = 12.29𝑚2 ×
1𝑚2
𝑨 = 𝟏𝟑𝟐. 𝟐𝟒 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
44.1 44.1 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.989
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.989 x 6.25 x 1.00 x 7330.21
CP = $ 45,309.86
CBM = FBM x CP x CE
CBM = 3.17 x 45309.86 x (541.7/500)
CBM = $ 155,611.19 = RM 692,469.78
Heat Exchanger 9
NH4Cl (11520 kg/hr)
NaCl (4200 kg/hr)
Water (46490 kg/hr)
CO2 (4740 kg/hr) CO2 (4740 kg/hr)
H2O (1940 kg/hr) TCout = 94.37°C H2O (1940 kg/hr)
TCin =88.35°C
328
Q = 360.12kW
360.12×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
Q= 1229795.40 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
8.76 − 105.63
∆𝑇𝐿𝑀 =
8.76
ln( )
105.63
∆𝑻𝑳𝑴 = 38.91°C
329
U = 250 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 360.12×103 𝑊× ×
250 𝑊 38.91°𝐶
10.76𝑓𝑡 2
𝐴 = 37.02𝑚2 ×
1𝑚2
𝑨 = 𝟑𝟗𝟖. 𝟑𝟒 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 4.42 x 1.00 x 21606.57
CP = $ 93,619.67
CBM = FBM x CP x CE
CBM = 3.17 x 93619.67 x (541.7/500)
CBM = $ 321,525.34 = RM 1,430,787.74
Heat Exchanger 10
TCout = 94.37°C
TCin =99.6°C
331
Q = 312.5 kW
312.5 ×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
Q = 1067175 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
7.39 − 105.63
∆𝑇𝐿𝑀 =
7.39
ln( )
105.63
332
∆𝑻𝑳𝑴 = 36.93°C
U = 300 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 312.5 ×103 𝑊× ×
300 𝑊 36.93℃
10.76𝑓𝑡 2
2
𝐴 = 28.21𝑚 ×
1𝑚2
𝑨 = 𝟑𝟎𝟑. 𝟓𝟒 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 4.4 x 1.00 x 8115.46
CP = $ 35,004.58
CBM = FBM x CP x CE
CBM = 3.17 x 35004.58 x (541.7/500)
CBM = $ 120,218.96 = RM 534,974.37
Heat Exchanger 11
TCin =60°C
334
iii. Monel tubes, 20 ft long, on square pitch in a Monel shell and fixed head
Q = 1620.9 kW
1620.9 ×103 𝐽 9.486×10−4 𝐵𝑡𝑢 3600𝑠
𝑄= × ×
𝑠 𝐽 ℎ𝑟
Q = 5535308.66 Btu/hr
Sizing
∆𝑇1 − ∆𝑇2
∆𝑇𝐿𝑀 =
∆𝑇
ln(∆𝑇1 )
2
335
10 − 12.89
∆𝑇𝐿𝑀 =
10
ln(12.89)
∆𝑻𝑳𝑴 = 11.38°C
U = 1200 W/𝑚2 . °C
𝑄
𝐴=
𝑈∆𝑇𝐿𝑀
𝑚2 . °C 1
𝐴 = 1620.9 ×103 𝑊× ×
1200 𝑊 11.38℃
10.76𝑓𝑡 2
2
𝐴 = 118.70𝑚 ×
1𝑚2
𝑨 = 𝟏𝟐𝟕𝟕. 𝟏𝟔 𝒇𝒕𝟐
c) Pressure factor, FP
𝑃 𝑃 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
0 0 2
𝐹𝑝 = 0.9803 + 0.018( ) + 0.0017( )
100 100
𝑭𝒑 = 0.9803
Costing
a) Base cost, CB
b) Purchase cost, CP
CP = FPFMFLCB
CP = 0.9803 x 4.53 x 1.00 x 13344.18
CP = $ 59,258.29
CBM = FBM × CP × CE
CBM = 3.17 x 59258.29 x (541.7/500)
CBM = $ 203,515.37 = RM 905,643.40
Pumps
Pump 1
i. Centrifugal pump
ii. FM = 2 (Stainless steel)
iii. FT = 1.8 (Explosion proof enclosure for electric motor)
iv. FBM = 3.30 (Pump and drivers)
337
Pump Sizing
a) Pressure Drop
∆𝑃 = 58.7838 − 14.6959
∆𝑷 = 𝟒𝟒. 𝟎𝟖𝟕𝟗 𝒑𝒔𝒊𝒈
b) Pump Head, H
c) Size Factor, S
a) Theoretical horsepower, PT
𝑔𝑎𝑙 𝑙𝑏𝑓
𝑄. 𝐻. 𝜌 496.1022 ×50 𝑓𝑡 ×18.0995
𝑚𝑖𝑛 𝑔𝑎𝑙
𝑃𝑇 = =
33000 33000
𝑷𝑻 = 𝟏𝟑. 𝟔𝟎𝟒𝟗 𝑯𝒑
𝑃𝑇 13.6049 𝐻𝑝
P𝐵 = =
𝜂𝑝 0.7127
𝐏𝑩 = 𝟏𝟗. 𝟎𝟖𝟗𝟐 𝑩𝑯𝒑
e) Power Consumption, Pc
𝑃𝑇 13.6049
P𝑐 = =
𝜂𝑃 𝜂𝑀 (0.7127)(0.8782)
𝐏𝒄 = 𝟐𝟏. 𝟕𝟑𝟔𝟖 𝑯𝒑
Costing
𝐶𝑃 = 𝐹𝑇 𝐹𝑀 𝐶𝐵
𝐶𝑃 = (1.00)(2.00)(3874.1197)
𝑪𝑷 = $ 𝟕, 𝟕𝟒𝟖. 𝟐𝟒
𝐶𝑃 = 𝐹𝑇 𝐶𝐵
𝐶𝑃 = (1.8)(1410.2186)
𝑪𝑷 = $ 𝟐, 𝟓𝟑𝟖. 𝟑𝟗
𝐼
𝐶𝐵𝑀 = 𝐶𝑃 𝐹𝑀
𝐼𝐵𝐴𝑆𝐸
541.7
𝐶𝐵𝑀 = (10286.6294) ( ) (3.30)
500
𝑪𝑩𝑴 = $ 𝟑𝟔, 𝟕𝟕𝟔. 𝟗𝟔 = 𝑹𝑴 𝟏𝟔𝟑, 𝟔𝟓𝟕. 𝟒𝟗
Pump 2
i. Centrifugal pump
ii. FM = 1 (Cast iron)
iii. FT = 1.8 (Explosion proof enclosure for electric motor)
iv. FBM = 3.30 (Pump and drivers)
341
Pump Sizing
a) Pressure Drop
∆𝑃 = 58.7838 − 14.6959
∆𝑷 = 𝟒𝟒. 𝟎𝟖𝟕𝟗 𝒑𝒔𝒊𝒈
b) Pump Head, H
c) Size Factor, S
a) Theoretical horsepower, PT
𝑔𝑎𝑙 𝑙𝑏𝑓
𝑄. 𝐻. 𝜌 204.6893 ×101.6617 𝑓𝑡 ×8.3454
𝑚𝑖𝑛 𝑔𝑎𝑙
𝑃𝑇 = =
33000 33000
342
𝑷𝑻 = 𝟓. 𝟐𝟔𝟐𝟒 𝑯𝒑
𝑃𝑇 5.2624 𝐻𝑝
P𝐵 = =
𝜂𝑝 0.6224
𝐏𝑩 = 𝟖. 𝟒𝟓𝟓𝟎 𝑩𝑯𝒑
e) Power Consumption, Pc
𝑃𝑇 5.2624
P𝑐 = =
𝜂𝑃 𝜂𝑀 (0.6224)(0.8598)
𝐏𝒄 = 𝟗. 𝟖𝟑𝟑𝟕 𝑯𝒑
343
Costing
𝐶𝑃 = 𝐹𝑇 𝐹𝑀 𝐶𝐵
𝐶𝑃 = (1.70)(1.00)(3451.2823)
𝑪𝑷 = $ 𝟓, 𝟖𝟔𝟕. 𝟏𝟖
𝐶𝑃 = 𝐹𝑇 𝐶𝐵
𝐶𝑃 = (1.8)(772.3980)
𝑪𝑷 = $ 𝟏, 𝟑𝟗𝟎. 𝟑𝟐
344
𝐼
𝐶𝐵𝑀 = 𝐶𝑃 𝐹𝑀
𝐼𝐵𝐴𝑆𝐸
541.7
𝐶𝐵𝑀 = (7257.50) ( ) (3.30)
500
𝑪𝑩𝑴 = $ 𝟐𝟓, 𝟗𝟒𝟕. 𝟏𝟔 = 𝑹𝑴 𝟏𝟏𝟓, 𝟒𝟔𝟒. 𝟖𝟔
Compressors
Compressor 1
i. Reciprocating compressor
ii. Material factor, FM = 1.00 (Assume cast iron)
iii. Drive factor, FD = 1.00 (Assume electric motor drive)
Costing
𝐶𝑃 = 𝐹𝐷 𝐹𝑀 𝐶𝐵
𝐶𝑃 = (1.0)(1.0)(172341.9261)
𝑪𝑷 = $ 𝟏𝟕𝟐, 𝟑𝟒𝟏. 𝟗𝟑
𝐼
𝐶𝐵𝑀 = 𝐶𝑃 𝐹𝑀
𝐼𝐵𝐴𝑆𝐸
541.7
𝐶𝐵𝑀 = (172341.9261) ( ) (2.15)
500
𝑪𝑩𝑴 = $ 𝟒𝟎𝟏, 𝟒𝟑𝟕. 𝟕𝟕 = 𝑹𝑴 𝟏, 𝟕𝟖𝟔 𝟑𝟗𝟖. 𝟎𝟖
Compressor 2
i. Reciprocating compressor
ii. Material factor, FM = 1.00 (Assume cast iron)
346
Costing
𝐶𝑃 = 𝐹𝐷 𝐹𝑀 𝐶𝐵
𝐶𝑃 = (1.0)(1.0)(172515.1571)
𝑪𝑷 = $ 𝟏𝟕𝟐, 𝟓𝟏𝟓. 𝟏𝟔
𝐼
𝐶𝐵𝑀 = 𝐶𝑃 𝐹𝑀
𝐼𝐵𝐴𝑆𝐸
541.7
𝐶𝐵𝑀 = (172515.1571) ( ) (2.15)
500
𝑪𝑩𝑴 = $ 𝟒𝟎𝟏, 𝟖𝟒𝟏. 𝟐𝟖 = 𝑹𝑴 𝟏, 𝟕𝟖𝟖 𝟏𝟗𝟑. 𝟕𝟎
APPENDIX D
There are total of three MSDSs included as this section as described below: