02 April 2021
COAL GETTING 300.794,39 12.366,02 4,1% 288.428,37 BRE I 5.013,24 3.814,23 L BRE I 5.040,00 3.778,86 L
COAL HAULING 302.400,00 7.761,36 2,6% 294.638,64 BRE II 5.013,24 4.917,57 L BRE II 5.040,00 - L
STRIPING RATIO 4,00 4,39 110% L TOTAL 10.026,48 8.731,80
L TOTAL 10.080,00 3.778,86 L
19
SHIFT 1
Operator Exavator Plan Overburden Actual OB / MD Plan Coal Getting Act Coal Getting HM WH OB WH CC Plan Prodty Prodty WH Prodty CC Distance Ach WH Remark
RONI HEX-1204 4.576,00 - 9,00 8,17 - 575,00 565,71 - 1.970 98% DISPOSAL CROWDED
DENI HEX-1203 3.212,00 - 6,00 5,87 - 575,00 547,50 - 1.750 95% TUNGGU HD AKIBAT BD BERULANG, DISPOSAL CROWDED
ROHMAN HEX-1202 4.312,00 - 10,00 8,17 - 575,00 538,78 - 2.930 94% FRONT AMBLAS
FRANS HEX-1201 3.740,00 - 9,00 7,83 - 575,00 477,45 - 3.134 83% FRONT BERAIR, FRONT SEMPIT
- HEX-424 132,00 - 8,00 1,83 - 240,00 96,00 - 4.600 40% GENERAL
- HEX-416 20.064,00 - 5.013,24 - 6,50 - - 240,00 - - - GENERAL
- HEX-433 - 2.239,41 8,00 - 7,85 240,00 - 285,28 9.200 119% LOADING COAL + GENERAL
- HEX-432 - 1.574,82 5,50 - 6,42 240,00 - 245,43 7.934 102% LOADING COAL + GENERAL, AKSES TERBATAS
- HEX-425 - - 3,00 - - 240,00 - - -
- EX-450 2.030,00 - - 9,75 - 240,00 190,97 - 3.200 80% HML, DT UNDER
- EX-444 1.204,00 - - 9,00 - 240,00 161,78 - 1.800 67% HML, FRONT BERPASIR, DISPOSAL CROWDED
TOTAL ACHIEVMENT 20.064,00 19.206,00 5.013,24 3.814,23
50,62 14,27 379,44 1.346,21
SHIFT 2
Operator Exavator Plan Overburden Actual OB / MD Plan Coal Getting Act Coal Getting HM WH WH CC Plan Prodty Prodty WH Prodty CC Distance Ach WH Remark
SAIFUDIN JUHRI HEX-1204 4.488,00 - 11,00 8,33 - 575,00 522,72 - 2.000 91% HD KURANG (BD), PERBAIKAN JALAN DISPOSAL
AGUS SALIM HEX-1203 4.356,00 - 10,00 8,57 - 575,00 518,75 - 1.750 90% PERBAIKAN JALAN DISPOSAL
HERFAN HEX-1202 5.280,00 - 11,00 9,87 - 575,00 539,59 - 2.950 94% FRONT LICIN, FRONT MIRING
RICO HEX-1201 5.412,00 - 11,00 9,87 - 575,00 544,05 - 3.050 95% FRONT BERAIR/AMBLAS
LENSON S. HEX-424 2.112,00 - 11,00 9,00 - 240,00 176,00 - 4.600 73%
RASYID HEX-416 - - 10,00 - - 240,00 - - - GENERAL
20.064,00 5.013,24 LOADING COAL
APRIL HEX-433 - 1.791,07 10,00 - 7,50 240,00 - 238,81 7.950 100%
SOKAMTO HEX-432 - - 10,00 - - 240,00 - - - GENERAL
PONIMAN HEX-425 - 2.750,19 10,00 - 8,75 240,00 - 314,31 9.200 131% LOADING COAL
RAHMAN HEX-208 - 376,31 10,00 - 2,50 200,00 - 150,52 7.650 75% LOADING COAL
- EX-450 2.422,00 - - 11,50 - 240,00 203,30 - 3.350 85% HML
- EX-444 2.086,00 - - 11,50 - 240,00 182,61 - 1.950 76% HML
TOTAL ACHIEVMENT 20.064,00 26.156,00 5.013,24 4.917,57 68,63 18,75 381,10 1.394,99
MONITORING START STOP HEX-1204 HEX-1203 HEX-1202 HEX-1201 HEX-424 HEX-416 HEX-433 HEX-432 HEX-425 HEX-450 EX-444
SHIFT 1 START 7:26 8:55 6:35 8:05 16:10 0:00 7:05 0:00 0:00 6:30 0:00
STOP 17:45 17:50 17:50 17:50 17:30 0:00 17:16 0:00 0:00 17:46 0:00
SHIFT 2 START 18:05 18:06 18:08 18:08 18:12 0:00 18:00 0:00 20:00 17:58 0:00
STOP 6:15 6:10 6:15 6:20 5:30 0:00 5:03 0:00 6:00 6:14 0:00
TOTAL HRS
NO EQ. NUM MAINTENANCE LOCATION COMPONENT PROBLEM START BD ESTIMASI RFU START RFU HM AGING DAY TOTAL MINUTES RESPONS TIME
B/D
OPERATIONAL ISSUE
NO. PROBLEM TODAY CORRECTIVE ACTION PIC STATUS
1 PERLUNYA PEMADAMAN TERKAIT BATUBARA SEAM G YANG TERBAKAR MENUNGGU PENGATURAN SETTINGAN DARI ENGINEERING SHE-ENGINEERING OPEN
2 PROGRESS KPI PRODUKSI DIHARAPKAN DAPAT MENAMPILKAN INFO TERKAIT PROGRESS IKH, DEVIASI DARI PLAN, SERTA PRODUCTIVITY, DAN REVIEW START STOP DALAM WAKTU DEKAT PRODUKSI OPEN
3 DEBU BERLEBIH PADA AREA LW HINGGA VIEWPOINT DISEBABKAN WATERFILL TERENDAM, MASIH PROGRESS PERBAIKAN WATERFILL HINGGA 2/04 PROGRESS PERCEPATAN PERBAIKAN AREA WATERFILL PRODUKSI OPEN
PRODUKSI-
4 MATERIAL DUDUKAN FRONT PADA AKHIR SHIFT TETAP DILOADING AGAR DAPAT PROGRESS COAL DAN BLASTING PROBLEM MATERIAL KERAS AKIBAT OFFSET AREA, UNTUK PROBLEM KURANG ALAT SUPPORT DAPAT DIKOMUNIKASIKAN KE TIM OB
ENGINEERING
OPEN
5 PENYIRAMAN TERKENDALA AKIBAT WT-020 BD WAITING PART PROGRESS PERCEPATAN PERBAIKAN WT-020 HML OPEN
6 PERHATIAN PADA PROSES LOADING HD DAN DT COAL PADA SEAM G TETAP PRIORITASKAN KESELAMATAN DAN ALAT BESAR PRODUKSI-SHE OPEN
OPERATIONAL ISSUE
NO. PROBLEM TODAY CORRECTIVE ACTION DUE DATE PIC STATUS
SAFETY ISSUE
NO. PROBLEM TODAY CORRECTIVE ACTION DUE DATE PIC STATUS