Professional Documents
Culture Documents
Hidden Failures in Protection Systems and Their Impact On Widear
Hidden Failures in Protection Systems and Their Impact On Widear
Abstract: This paper explores Hidden Failures in protection In this reference, five Special Protection Systems (SPS) are
systems, which have been identified as key contributors in the described and analyzed for Hidden Failures as well.
cascading of Power System wide-area disturbances. The original Examples of such failures are included in the paper.
definition of Hidden Failure, which is a failure that remains
undetected and is uncovered by another system eveng is included
A number of wide-area disturbances were analyzed for
as are the developments of Hidden Failure sequence of events and a
Hidden Failures based on the NERC disturbance reports [3].
methodology for Hidden Failure identiilcation. This method is
based on Protection Element Functionality Defects (PEFD). Hidden A methodology for the identification of Hidden Failures on
Failures Modes are developed based on the relaying wide-area disturbances and the mechanisms of the wide-area
implementation for Primary protection, Back-up protection and disturbances were developed and are presented in this paper.
Special Protection Systems. Wide-area disturbances based on North
American Reliability Council (NERC) reports are analyzed and Regions of Vulnerability are identified as Power System
Hidden Failures are identified employing the developed physical regions in which the occurrence of an event will
methodology. The mechanisms in the wide-area disturbances are uncover a Hidden Failure of a nearby protection system [1].
summarized. Regions of Vulnerability and Areas of Consequence
Areas of Consequence are regions of the power system
are important concepts that identi& the critical elements from the
which become vulnerable to Hidden Failures in succession
point of view of Hidden Failures.
as a wide-area disturbance progresses to its final state.
Keywords: Hidden Failures, Blackouts, Wide-area Analysis of regions of Vulnerability and Areas of
disturbances, Primary Protection, Back-up protection, Special Consequence represents the first step towards a possible
Protection Systems. approach to problem solution.
0-7803-6674-3/00/$10.00
0-7803-6672-7/01/$10.00
(C)(C)
2000
2001
IEEE
IEEE 710
as a consequence of another switching event. The local A PEFD-A, which causes the Z 1 contact to close
effect of Hidden Failures is also an important factor since permanently, will not cause a Hidden Failure Mode since the
the circuits tripped by Hidden Failures are a second logic involved with Z 1 PEFD-A does not allow the failure to
contingency coupled to the first contingency. remain undetected. At the instant when Z 1 fails closed, Zone
1 distance relay will trip the line circuit breaker. This indeed
The first step in identifying Hidden Failures is to classify is a relay mis-operation, but not a Hidden Failure.
Hidden Failure Modes for each protection scheme: relay or
relay system used to protect transmission lines, generators, If the PEFD-A takes place in T3 closing the contact
buses, transformers, an Special Protection System, etc. permanently, the logic will allow this PEFD-A to remain
undetected. At the instant when T3 closes its contacts
HIDDEN FAILURE SEQUENCE OF EVENTS nothing will happen in terms of line trips, because both Z3
and T3 are required to close before tripping the line. Thus
The first event in the Hidden Failure mechanism is a PEFD-A will remain Hidden until a fault occurs within
Protection Element Functionality Defect (PEFD). However, Zones 1,2 or 3 of the transmission line. Zone 2 of the
having a PEFD does not automatically result in a Hidden adjacent line will also close its contact but is prevented from
Failure. In general, a PEFD occurs as a random event and as tripping by virtue of the timer T2. For a zone 1 fault, the
a result protection systems are unable to perform their only erroneous effect of the Hidden Failure will be to drop a
designed and expected actions. Usually the defects which zone 3 target as well, while for zones 2 or 3 faults there will
concern us lead to increased insecurity. These defects can be bean instantaneous trip of the line.
present on any of the protection system elements, and may
take the form of hardware failures. outdated settings and In accordance with the Hidden Failure definition [1], a
human negligence or errors. “failure to operate” will not be considered to be a Hidden
Failure. In other words, if there is a PEFD on any of the
Some examples of PEFD are a relay’s contacts that are protective system elements, with the consequence of not
always open or closed, a timer that operates instantaneously clearing a fault, this protection system failure will not be
regardless of its pre-assigned time delay, an outdated setting classified as a Hidden Failure. This is a “failure to operate”
in a relay, a human error in relay coordination, etc. PEFD event, and is not considered a Hidden Failure due to the fact
related to hardware failures are referred to as PEFD-A, and that some other protection systems will react and clear the
PEFD related to relay settings, human errors or negligence fault. Power Systems are biased towards dependability, and
are defined as PEFD-B. one or the other of the duplicated protection systems should
clear all faults.
The logic involved around the PEFD will determine if this
first event will result in an operation due to a Hidden The coordination of the different protective schemes on the
Failure. It is important to note that the determining factor for Power System is one of the most critical tasks. Part of the art
an undetected PEFD is the logic of the protection scheme. In of protective relaying is based on the engineering judgment
the following, Hidden Failure Modes are defined depending of the relaying community. Relay settings are the result of
on the logic associated with the specific protection scheme multiple Power System simulations and reflect the expected
being analyzed. harmony of the Power System reactions for all possible
contingencies. Human errors may occur during this process,
111. HIDDEN FAILURE MODES, A THEORETICAL resulting in protective relay mis-coordination. This type of
APPROACH failure is considered a Hidden Failure since its behavior falls
under the Hidden Failure definition and sequence of events.
An example of these ideas is described in Figure 1, which A PEFD, such as mis-coordination, remains undetected until
shows the control circuit of a three zone step distance relay. another event triggers it. A typical example would be a
generator excitation limiter protection, which was,
A PEFD-A, which affects T3 contacts, will result in a
mistakenly, set to trip the generator unit for a value under its
Hidden Failure Mode. It should be noted that a PEFD-A on
overall capacity. This failure will be hidden until an
Z 1 will not result in a Hidden Failure Mode.
increment on the Power System reactive power requirement
Nf’rF produces an unwanted trip of the generator. The effects of
this Hidden Failure may be serious, and will depend on the
system strength and the prevailing system conditions.
Human error also will fit under this category, where the
0-7803-6674-3/00/$10.00
0-7803-6672-7/01/$10.00
(C)(C)
2000
2001
IEEE
IEEE 711
A human error related Hidden Failure was one of the initial Goshen Idaho ~ Wyoming
events registered in the famous New York 1965 blackout
%
[4].
Khrport
“TD
R?nnre
Table T- 1: WSCC-07/02/96, Sequence of initial Events. square
waves
tkxn
ColnNnimtion —
CFand semltQ Trip
Event Time Comment
Jim Bridger-
Kkrport 345-Kv,
1424:37.180
MAST
Line Sag to close to a
Tree. 4)
r-l- —
% OR
Phase to mound P
fault. - -
Jim Bridger- 1424:37.200 HF 1, Faulty ground 0 OR
Goshen 345-kV MAST element at Bridger, LlxaJSqaar?
trip, I PEFD-A. - Whves AND
RAS started, JB 1424:37.200 RAS was correct, 1040 I N
loose 2 lines. \ MAST \ MW Off.. —
Ail Generators \ Freq. Went to 59.9 Hz. I
respond to I 1- 1 Figure 3: Phase comparison relay internal logic schematic.
Generation lack...
Round Up- 1424:39.200 HF2, bad connectors in
LaGrande 345-kV MAST a distance relay, PEFD- The single phase comparison protective scheme receives as
trip. A. inputs the local and remote wave forms, which are compared
Mi[lCreek- 1425:01.052 HF3, unwanted
in order to determine if the fault is external or internal and
Antelope Trip MAST operation of Back-up
relay, PEFD-B decide if a trip signal will be sent to the circuit breaker, see
numbers 1 and 2 in Figure 3. The biggest rectangle shown in
the sketch represents an AND gate, which receives as inputs
Figure 2 shows the fwst fault on the Bridger-Kinport 345-kV three signals. One of these signals is the element with a
line (see number 1), and the circuit breaker unwanted trip PEFD-A (failed in the closed position) shown in bold, see
caused by HF 1 (see number 2). number 3. The remaining two signals are a channel security
check and an Arming Input Current Detectov see numbers 4
and 5 respectively.
0-7803-6674-3/00/$10.00
0-7803-6672-7/01/$10.00
(C)(C)
2000
2001
IEEE
IEEE 712
gate were satisfied, the Arming Input Current Detector, the conforms to the PEFD-A definition and in this case it is
sanity checks and the PEFD-A (which was already with related to the relay connectors and lugs.
“positive signal”). Consequently the relay system sent a trip
signal to the Jim Bridgercircuit breaker,and second An excerpt from [7] states “Jim Bridger Remedial Action
contingency was caused by the Hidden Failure in the Scheme should have ensured stability and prevented further
protection scheme. outages. Several near simultaneous switching events,
however, had some detrimental effects: A 230 kV line
The Jim Bridger SPS was immediately activated, due to the relayed in Eastern Oregon”. This 230 kV line is the Round
fact that Jim-Bridger generation plant had lost 2 Up – LaGrande, which was tripped due to HF2.
transmission lines. This SPS operation was appropriate and
did work as designed, disconnecting 2 units from the Jim- HF3 will be described next, which is related to the
Bridger plant. Generators from the entire WSCC MillCreek-Antelope 230 kV transmission line, where the
intercomection responded to the ffequency deviation, 59.9 MillCreek station breaker had an unwanted trip. This is a
Hz. Almost 2 seconds after the first event, another relay- Hidden Failure occurring over a Back-up protection system;
unwanted trip disconnected the Round Up-LaGrande 230 kV in fact it can be cataloged as an unwanted operation of a
transmission line. This event is cataloged as HF2. Back-up relay. An excerpt from [7] states: “Relays installed
to detect short circuits must not operate for mild overload
The defective relay was identified as an electro-mechanical and mild voltage depression”. The relay did not do anything
distance relay. Figure 4 describes HF2 sequence of events. wrong, it tripped because the Power System conditions
The relay operation is based upon a balance between changed and the apparent impedance encroached under the
operating and restraining forces created by the current and zone 3 of the distance relay. The relay reacted to the low
voltage inputs [6]. For distance relays, the restraint force apparent impedance resulting from the Power System
overcomes the operating force during out-of-zone faults. In conditions.
the present instance, corrosion under the voltage restraint
crimp-on lug produced a poor connection, reducing the The PEFD associated with HF3 is a PEFD-B. This Hidden
restraint force. In time the corrosion was complete and the Failure is related to human error in relay settings, in the
restraint force was practically eliminated and the distance sense that these Power System conditions presented on the
relay (mis)operated, closing its contacts. July 2, 1996 disturbance were not previously considered in
the contingency analysis studies. This line trip and the 300
v MW interruption caused power swings leading to rapid
overload, voltage collapse and angular instability [7].
& DISTURBANCES
@F
protection scheme. Hidden Failures occur when this
protection scheme is “armed” by the PEFD-A on one of the
relays, closing its contacts permanently
...............
Figure 4: HF2, Sequence of Events.
Toother
‘1
logic,.,
--r “
The time when the corrosion caused the distance relay to
T
R2, with a PEFD
operate is unknown. This relay condition remained
undetected due to the fact that a fault detector supervises this
relay, i.e., some others conditions are required before
sending a tripping signal to the circuit breaker. From the
time when the distance relay was defective due to corrosion
until the time the Round Up-LaGrande 230 kV line was
4
L
T
Trip Coil
52a
0-7803-6674-3/00/$10.00
0-7803-6672-7/01/$10.00
(C)(C)
2000
2001
IEEE
IEEE 713
Table T-2: Mechanisms into the Wide-area Disturbances, Application, VIII. ACKNOWLEDGMENTS
Scheme R1 R2 Application This work is partially supported by a grant from EPRUDOD.
Primarv I Fault I Directional I Transmission line
Ix. REFERENCES
0-7803-6674-3/00/$10.00
0-7803-6672-7/01/$10.00
(C)(C)
2000
2001
IEEE
IEEE 714