Professional Documents
Culture Documents
Exam Notes 2017
Exam Notes 2017
Exam Notes 2017
5 - Role and
responsibility of
employer, contractor
and architect
DEC 2015 a)+ve and –ve of a) Contractor case of Pembinaan - liquidated damages
-4q ab contract with BQ selection by direct Leow Tuck Chui v Dr. - difference between
b)characteristic for negotiation – Leela and Hickmans contract sum, pc
- fixed price lump situation v Roberts sum and
sum b) right to time and provisional sum
- cost money extension
reimbursement of delay due to
- employer fault
- contractor fault
- fault of neither
JUNE 2016 a)+ve and –ve of a) Contractor a) right to time and case of Pembinaan
-4q ab contract with BQ selection by direct money extension Leow Tuck Chui v Dr.
b)characteristic for negotiation – of delay due to Leela and Hickmans
- fixed price lump situation - employer fault v Roberts
sum b)process of - contractor fault
- cost tendering - fault of neither
reimbursement b) 5 RE for EOT
DEC 2016 a) Process of a) Contractor a) 5 RE for EOT - liquidated damages
-2q abcd tendering selection by b) right to time and - variation order
b) Role and negotiation or money extension - difference between
responsibility competition of delay due to contract sum, pc
-employer situation n effect - employer fault sum and
-contractor b) Comparison - contractor fault provisional sum
-architect contract with bq - fault of neither
and without bq
JUNE 2017 Process of tendering +ve and –ve of EOT and RE contract sum, pc
-4q Role n responsibility contract with BQ sum and provisional
sum, LD, VO
PAST EXAM QUESTIONS
Process of Tendering
- With aid of flow chart, illustrate and explain the process of tendering and evaluation
- Dec 2016 (10m), June 2016 (15m), June 2015 (15m)
Selection of Tender
- Analyze the circumstances and effect of employing each method (negotiation / competition) Dec 2016 (15m)
- Explain under what circumstances would you advice the client to negotiate directly with a particular contractor
instead of advertising for tenders (10-15m) June 2016, Dec 2015, June 2015, Dec 2014
Sum, LD, VO
- Elaborate the following statements:
- a) the purpose and operation of liquidated damages
- b) the requirement for a valid variation order to the works in construction
- c) the distinction between contract sum, prime cost sum and provisional sum
- Dec 2016 -15m, Dec 2015 -25m (a,c), Jun 2015 -12m, Dec 2014 -25m
Retention Sum
- Maybe similar to Sum, LD, VO
- X pernah keluar
Precedent Case
- Based on the precedent cases of Pembinaan Leow Tuck Chui v Dr. Leela, and Hickmans v Roberts, analyze the
cases in regard to certification and interference in the contract administration
- 20-25m June 2016, Dec 2015, June 2014
ROLE AND RESPONSIBILITIES
- Identify and analyze the roles and responsibilities of the project participants in building contract
- (15m) -Dec 2016
- a)The Employer b)The Contractor c)The Architect
Answer :
- Client
- The design consultant (architect, surveyor, QS etc…)
- The builder (contractor, SC, supplier etc…)
- Provide a brief to define the content, requirement and function of the building.
- Issues instructions through the architect or superintending officer (SO).
- Commission the construction project and pays the cost of work (certified by the architect, SO,
contract document.
- Make decision- ultimate decision maker over all facets of the project (type,size,cost).
- Finance the project – employer’s own fund / borrowing.
Architect (5m)
- Responsible for design, inspection of the works during construction and certification
- Interpret client’s brief, prepares preliminary and detail design.
- Obtaining planning permission from the local authority
- Securing the remedying of defects at the end of defect liability period (DLP)
- Certifying payment & final account
Contractor (5m)
Client
Contractor
Answer :
Contractual
relationship
diagram
SELECTION OF TENDER
NEGOTIATION COMPETITION
1. A method to select tender without a call for 1. Consists of open tendering and selective tendering
competition 2. Open -The tenders are selected through
2. The client selects a contractor directly and then competition via public advertisement in website or
negotiates with terms of agreement and form of newspaper over specified period
payment 3. Selective – suitable firms are invited from client’s
3. Client can invite a contractor to prepare a budget approved list singled out by reputation and
quotation for the work based on limited information recommendation
QUESTION B: Rights to time and money extensions because of delay due to: (15 m)
Legend:
RE – Relevant events LD – Liquidated damages CNC – Certificated of non-completion
EOT – Extension of time LE – Loss and expenses
EOT and LE are claimed by contractor
LD are claimed by employer/client, bear by contractor