RREIS CY 2017-BITO Revised (Actual Cost)
RREIS CY 2017-BITO Revised (Actual Cost)
RREIS CY 2017-BITO Revised (Actual Cost)
REGION/PMO : REGION 8
PROJECT TITLE : Improvement of Irrigation Facilities
SYSTEMS CATEGORY : Bito RIS
( NIS/CIS, NIP/SIP )
PROJECT DESCRIPTION : Construction of Canal Lining, Check Structures & Fab./Inst of Steelgates
I. GENERAL INFORMATION
1. Project Location 6. Overall Project Cost
a. Region VIII a. Peso Counterpart (PM)
b. Municipality Abuyog b. Loan Procceds (PM)
c. Province Leyte c. Others (Equity)
Total
2. Service Area
a. New Area 7. Physical Target
b. Rehab Area 751 ha. a. New Area
c. Restored b. Restored Area
3. Source of Water Bito Rivers c. Repair Works: (specify for rehab)
c.1. Earth Canal (km.)
4. Type of Irrigation 5. PT of Diversion c.2. Lined Canal (km.)
( Pls. check the type of irrigation) Latitude Longitude c.3. Structures (units)
a. Run-off the River 10 48' 16" 124 55' 50" c.4. Fab./Inst. Of Steelgates (pcs)
b. Reservoir c.5. Concrete Service Road (km)
c. Groundwater Pump c.6. PCCP Pavement Plain (km)
c.7. Other Repair Works (Repair of Diversion
c.8. Rehab Area ha (attribution)
d. Other Activities (Pls. specify)
8. Overall Implementation Period
a. Physical Starting Date
b. Completion Date
9. CONTINGENCIES - -
ESTELITA S. SUMILE
TOTAL FOR ABUYOG, LEYTE 146156.42 146156.42 Acting Division Manage
TOTAL FOR JAVIER, LEYTE 0 0
TOTAL DIRECT COST 146156.42 146156.42
APPROVED :
IV. SOURCE OF FUNDS
Original Revised
146,156.42
146,156.42
1.30
1
Of Steelgates (pcs) 16
ervice Road (km)
ment Plain (km)
air Works (Repair of Diversion Dam)
a ha (attribution)
feb
sept 30
ROGELIO F. BALLESTEROS oct 31
Engineering Assistant A nov 30
dec
Submitted by : 288
Recommending Approval :
ESTELITA S. SUMILE
Acting Division Manager - EOD SANTOS D. MERACAP JR.
NIS Head / Principal Engineer A
APPROVED :
FERMINA B. ALING
Acting Regional Manager
Republika ng Pilipinas
Pambansang Pangasiwaan ng Patubig
(NATIONAL IRRIGATION ADMINISTRATION)
REGION/PMO : REGION 8
PROJECT TITLE : Improvement of Irrigation Facilities
SYSTEMS CATEGORY : Bito RIS
( NIS/CIS, NIP/SIP )
PROJECT DESCRIPTION : Construction of Canal Lining, Check Structures & Fab./Inst of Steelgates
I. GENERAL INFORMATION
1. Project Location 6. Overall Project Cost
a. Region VIII a. Peso Counterpart (PM)
b. Municipality Javier b. Loan Procceds (PM)
c. Province Leyte c. Others (Equity)
Total
2. Service Area
a. New Area 7. Physical Target
b. Rehab Area 851 ha. a. New Area
c. Restored b. Restored Area
3. Source of Water Bito Rivers c. Repair Works: (specify for rehab)
c.1. Earth Canal (km.)
4. Type of Irrigation 5. PT of Diversion c.2. Lined Canal (km.)
( Pls. check the type of irrigation)Latitude Longitude c.3. Structures (units)
a. Run-off the River 10 48' 16" 124 55' 50" c.4. Fab./Inst. Of Steelgates (pcs)
b. Reservoir c.5. Concrete Service Road (km)
c. Groundwater Pump c.6. PCCP Pavement Plain (km)
c.7. Other Repair Works (Repair of Diversion Dam)
c.8. Rehab Area ha (attribution)
d. Other Activities (Pls. specify)
8. Overall Implementation Period
a. Physical Starting Date
b. Completion Date
Original Revised
1,308,000.05
1,308,000.05
1.30
1
16
Original Revised
: February 15, 2017
: Nov. 30, 2017
feb
Submitted by : 288
Recommending Approval :
ESTELITA S. SUMILE
Acting Division Manager - EOD
APPROVED :
FERMINA B. ALING
Acting Regional Manager
ROGELIO F. BALLESTEROS
Engineering Assistant A
MASTERLIST OF ACTIVITIES
STATION Length
PARTICULARS FROM TO (KM) Clearing & Desilting Concrete De
FORCE ACCOUNT WORKS
Bito RIS (Javier)
A. Canal System
Desilting (Manual) @ Main Canal 2+924 3+040 0.116 0 72.21761
0 0 0 0 0
DERIVATION OF UNIT COST, DESILTING, (Manual)
BITO RIVER IRRIGATION SYSTEM
Javier, Leyte
Desilting (Manual)
1) LABOR COST
Crew: 1 Laborer
Capability of one tea 2.5 cu.m./day/man
1 laborer @ 260 per day = 260.00 per day
Unit Cost: 260 per day / 2.5 cu.m./day/man = 104.00 per cu.m.
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 104.00 per cu.m.
C. EQUIPMENT COST = -
TOTAL ESTIMATED DIRECT COST = 104.00 per cu.m.
Desilting (Manual)
1) LABOR COST
Crew: 1 Laborer
Capability of one tea 2.5 cu.m./day/man
1 laborer @ 260 per day = 260.00 per day
Unit Cost: 260 per day / 2.5 cu.m./day/man = 104.00 per cu.m.
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 104.00 per cu.m.
C. EQUIPMENT COST = -
TOTAL ESTIMATED DIRECT COST = 104.00 per cu.m.
4. PARCELLARY MAPPING/SURVEY -
-
13018.91 5000000
0 javier 7510.12 javier
13018.91 5508.79 661887.6
13018.91
feb
Jan
Feb
mar 13
31
apr 30
may 31
jun 30
jul 31
aug 31
oct 31
nov 30
dec
288
2. Package # 2
2.a. Control Gates
Fabrication/Installation of Steel Gates pcs. 9 54884.35 493959.15 74093.8725
Sub-total (Package 2)
Sub-total (Contract works) Abuyog, Leyte
FORCE ACCOUNT
2 WORKS
Canal Desilting
Canal Desilting @ main Canal (Sta 4+900 - 5+045) cu.m. 58.233
Total (FORCE ACCOUNT WORKS)Abuyog
FORCE ACCOUNT
2 WORKS
Canal Desilting
Canal Desilting @ main Canal (Sta 2+924 - 3+040) cu.m. 72.2176
Total (FORCE ACCOUNT WORKS) Javier
Prepared By:
ROSALYN S. DELFIN
Engineer A
Attachment "D"
INDIRECT COST TOTAL
PROFIT VAT TOTAL UNIT COST PROJECT COST
6.76 14489.6544
165.92 38350.75
9728.5 1266650.7
0
73.21 428927.87
13.42 78684.62
1156.72 276340.408
0 0 0 2103444.0124
6.76 578.994
193.06 36374.4346
210 3150
6709.05 3689.9775
10377.4 184645.08
0
73.21 70332.1149
13.43 12902.0667
5936.49 0
3215.55 0
93118.55 93118.55
71668.94 71668.94
1156.72 80045.024
0 0 0 556471.63
6.76 1379.04
165.92 2809.0256
9728.5 137269.135
0
73.21 33163.3979
13.43 6083.6557
1156.72 21193.597348
201897.861548
2861813.503948
104 6056.232
6056.232
35161.91
INDIRECT COST TOTAL
PROFIT VAT TOTAL UNIT COST PROJECT COST
35161.91
105485.72
175809.54
3691999.995948
INDIRECT COST TOTAL
PROFIT VAT TOTAL UNIT COST PROJECT COST
INDIRECT COST TOTAL
PROFIT VAT TOTAL UNIT COST PROJECT COST
7.12 10392.4232
167.45 31145.7
9727.1 791494.127
72.27 264614.4369
12.95 47416.0365
1150.74 93140.8956
0 0 0 1238203.6192
1238203.6192
104 7510.6404
7510.6404
12457.14
12457.14
37371.46
62285.74
1307999.9996
4761904.715548
47619.05
47619.05
142857.18
4999999.995548
4999999.995548
Submitted By:
JOJO A. ARCEŇO
OIC IS / BHHD-BIG-DGM Satellite Office
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
DETAILED BREAKDOWN OF CY 2017 PROGRAM OFWORK (BY ACTIVITIES)
ACTIVITY LABOR TEV SundrieEquipment RentRSB Cement Fuel & Oil Spare Parts Office Supplies Civil Works & Others
A. DIRECT COST
1. CIVIL WORKS
a. Contract Works 4748337.84
b. Force Account Works 13566.87
9. Contingencies
-12775.29625
Prepared by:
-15156.24875
16982.89
ROSALYN S. DELFIN
Engineer A
Attachment "B"
CONTRACT WORKS
4748337.84
13566.87
14285.715 47619.05
47619.05
142857.1838
14285.715 5000000.0038
Submitted by
JOJO A. ARCEŇO
OIC IS / BHHD-BIG-DGM Satellite Office
MASTERLIST OF ACTIVITIES
STATION Length
PARTICULARS FROM TO (KM) Clearing & GDesilting (cu.m.Concrete DeStructure E Str. Backfil 211 KGSC Pl
FORCE ACCOUNT WORKS
Bito RIS (Abuyog)
A. Canal System
Desilting (Manual) @ Main Canal 4+900 5+045 0.145 0 58.23273
0 0
0 0
MASTERLIST OF WORK TO BE DONE
BITO RIVER IRRIGATION SYSTEM
REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM FY-2017
A. FORCE ACCOUNT WORKS
I. CONSTRUCTION SURVEY Ls.
II. IDP Ls.
B. CONTRACT WORKS
BITO RIS
I. CANAL SYSTEM
CANAL LINING
STATIONING RSB
5
8
7
5 71.5 #REF!
3661.47 80.94
AREA
RSB New Rehab
Cutting, Bending Proc./Fab. & Inst.Rubble Ma170 kgsc P Clearing & Fab./InsFab./Ins
kgs. Ls. cu.m. cu.m cu.m. ha. ha.
AREA
RSB New Rehab
5. Procurement of Equipment
& Vehicles
6. Consulting Services
8. Contingencies
1 3
347,264.83 - 418,135.74 - - -
407.01 678.34
11,904.76 47,619.05
11,904.76 47,619.05 - -
- -
35,714.30 71,428.59 - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
407195.6608 585480.778
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey - -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies -
- 2,381,252.08
5,426.75
-
71,428.59
0 2458107.414
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey - -
4. FSSM - -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
0 0
1,417,418.20
5,426.75
-
0 0
- 0 0
0 0
- 0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 1422844.944 0 0 0
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
3. Construction Survey - - -
4. FSSM - - -
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
- -
TOTAL DIRECT COST 355711.236 177855.618
Attachment "C-4"
3 12
0
531,531.82 4748337.84
2,035.03 13566.87
- 47619.05
0
- 47619.05
0
- 142857.18
0
0
0
0
0
0
0
0
0
0
- 0
533566.854 5000000
NATIONAL IRRIGATION ADMINISTRATION
BITO RIS ABUYOG, LEYTE
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT & CASH REQUIREMENT
FY 2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
Attachment "C-5"
No. of
I. MANPOWER REQUIREMENT
Personnel GRAND TOTAL
1. Monthly Personnel
2. Daily Personnel 2
3. Contractual 3
6. Procurement of Equipment
& Vehicles (for FAPs)
7. Consulting Services
9. Contingencies
Prepared By : Submitted By :
I. CONTRACT WORKS
Projected 0 70870.9098 106306.3647 177177.2745 708709.098 531531.8235 531531.8235 354354.549 531531.8235 354354.549 177177.2745
A. CANAL SYSTEM 3543545.49 70.87091 Actual 100
Projected 111294.326 222588.652 166941.489 55647.163
B. CHECK STRUCTUTURES 556471.63 11.129433 Actual 90
Projected 129664.144 259328.288 194496.216 64832.072
C. FAB/INS. OF STEEL GATES 648320.72 12.966414 Actual 80
Projected 0 0 0 0
Actual 70
Projected 271.3374 407.0061 678.3435 2713.374 2035.0305 2035.0305 1356.687 2035.0305 1356.687 678.3435
II FORCE ACCOUNT WORKS 13566.87 Actual 0 0 0 0 0 60
Projected 11904.7625 23809.525 11904.7625
A. INSTITUTIONAL DEVELOPMENT PRO 47619.05 0.952381 Actual 0 0 0 0 0 0 50
Projected 11904.7625 23809.525 11904.7625
B. CONSTRUCTION SURVEY 47619.05 0.952381 Actual 0 0 0 0 0 40
Projected 10000.0026 25714.2924 35714.295 35714.295 25714.2924 10000.0026
III. FSSM 142857.18 2.8571436 Actual 0 0 0 0 0 30
0 Projected 0 0 0 0 0 0 0
IV. CONTENGENCY 0 Actual 20
Projected
Actual 10
Projected 0.67619055 2.884085044 3.316603694 8.70960443 18.027297588 11.943579782 10.63063647 7.08709098 10.63063647 7.08709098 3.54354549 0
5000000 99.728662 Actual
Projected 33809.5276 144204.2522 406788.6547 694808.5095 1095861.0954 662011.0611 531531.8235 354354.549 531531.8235 354354.549 177177.2745 0
TOTAL CY 2016 PROJECT COST 5000000 99.728662 Actual
33809.5276 178013.7798 584802.4345 1279610.944 2375472.0394 3037483.1005 3569014.924 3923369.473 4454901.297 4809255.846 4986433.12
CY FINANCIAL STATUS
CMD FORM Y-1A BITO RIS ABUYOG, LEYTE
FY 2017 IMPLEMENTATION SCHEDULE AND STATUS FY-2017 PROGRAM OF WORK ON REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM,(RREIS-2017)
BITO RIS
NATIONAL IRRIGATION ADMINISTRATION
Prepared By : Checked By
Approved by :
2,077,029.31
1245673.83791
APPROVED BUDGET FOR THE CONTRACT
BITO RIS Abuyog, Leyte
REPAIR/REHAB. OF EXISTING IRRIGATION SYSTEM - 2017
Contract Reference Number :
Name of Contract : Improvement of Irrig. Facilities
BITO RIS Location of the Contract : Bito RIS Abuyog, Leyte
NATIONAL IRRIGATION ADMINISTRATION Contract Duration : 330 Cal. Days
ITEMS OF WORK UNIT QTY. UNIT COST ESTIMATED DIRECTCONTRACTOR'S VATTOTAL COST UNIT COST
(1) (2) (3) (4) (5) (6) (7) (8)
PACKAGE # 1
Bito RIS
a CONSTRUCTION OF CHECKGATE
Check Structures @ Ulhay Creek
Clearing & Grubbing (Manual) sq.m. 85.65 6.76 495.06 154.71 649.76 7.59
Structure Excavation (Manual) cu.m. 188.41 193.06 27,992.34 8,747.61 36,739.95 195.00
Diversion and care of river cu.m. 15.00 210.00 2,400.00 750.00 3,150.00 210.00
170 kscm Plain Concrete cu.m. 0.55 6,709.05 2,812.87 879.02 3,691.89 6,712.53
211 kscm Class A Concrete cu.m. 17.79 10,377.40 140,811.76 44,003.57 184,815.33 10,388.72
RSB - -
Furnishing of RSB kls 960.69 73.21 53,606.50 16,752.03 70,358.53 73.24
Cutting and Bending of Bars kls 960.69 13.43 9,847.07 3,077.21 12,924.28 13.45
Rubble Masonry cu.m. - 5,936.49 - - - #DIV/0!
RCP 18" Diameter pcs - 3,215.55 0 - - #DIV/0!
Fab./inst of Sluice gate pc 1.00 93,118.55 70,982.25 22,181.95 93,164.20 93,164.20
Fab./inst of Intake gate pc 1.00 71,668.94 54,884.35 17,151.36 72,035.71 72,035.71
Structure Backfill w/ compaction (HB) cu.m. 69.20 1,156.72 61,012.72 19,066.47 80,079.19 1,157.21
Sub-total 424,844.93 132,763.93 557,608.85
b CANAL SYSTEM
Canal Lining SFD @ TSAG#3 CLB IA.Sta.0+000 to Sta.0+150(150m),Canal Lining SFD @ TSAG#1, CUL IA,Sta.0+000 to Sta.0+180,(180m)
Canal Lining SFD @ TSAG#8 MACASACA IA.Sta.0+000 to Sta.0+100(100m),Canal Lining SFD @ TSAG#7, SANULMACO IA,Sta.0+000 to Sta.0+120,(120m)
Clearing and Grubbing sq.m. 2,143.44 6.76 12,389.08 3,871.59 16,260.67 7.59
Structure Excavation cu.m. 231.14 165.92 30,047.55 9,389.86 39,437.41 170.63
170 kscm Re-inforced Concrete cu.m. 130.20 9,728.50 965,259.73 301,644.32 1,266,904.04 9,730.67
RSB
Furnishing of RSB kgs 5,858.87 73.21 326,924.67 102,163.96 429,088.63 73.24
Cutting and Bending kgs 5,858.87 13.42 60,053.37 18,766.68 78,820.04 13.45
Structure backfill (HB) cu.m. 238.90 1,156.72 210,634.94 65,823.42 276,458.36 1,157.21
Sub-total 1,605,309.34 501,659.82 2,106,969.16
TOTAL CONTRACT AMOUNT 2,030,154.26 634,423.75 2,664,578.01 -197235.49
7,016,304.99 7,464.99
3,987,577.04 55.64
602,045.94 7.63
4,657,042.25 3,549.40
0 2,143.97
2177.99619048
524,762.54 826.74
17,662,442.28
2,077,029.31
2,682,837.76 2664578.00972
DERIVATION OF UNIT COST
DAGUITAN-GUINARONA-MARABONG RIVER IRRIGATION SYSTEM
JULITA, LEYTE
[CONTRACT WORKS ]
I CONSTRUCTION MATERIALS
A. HAULING OF CEMENT
Ave.Hauling distance: = 45 km.from office to source to warehouse and nearest point accessible
by truck (field bodega)
Utilize: 6-7 tons cargo truck with five laborers
Ave.Hauling Distance: 45.00 kms.
Base Cost of cement: P 260.00 / bag
Capacity of Cargo Truck = 200 bags/trip]
Rental rate= P 851 / hr.(Acel 2009 Edition 24)
Baremonth= P 110,604 / month
= 110,604/baremonth x 1 month / 25 days x 1 day / 8 hrs.
= 553.02 / hr.
Laborer rate @ P 260.00 / day
CYCLE TIME:
EQUIPMENT:
Rental: [ P 851.00 / hr. x 3.96 hr./trip ] / [ 200 bags/trip ]= 16.84 / bag
12% VAT
0.12 x 553.02 / hr. x 3.96 hr./trip ] / [ 200 bags/trip ]= 1.31 / bag
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
CYCLE TIME:
LABOR COST:
Laborer:[5xP 260.00 / day x 4.63 hr./trip ] / [ 8 hrs./day x 250pc/trip]= 3.01 / pc.
LABOR COST…………. 3.01 / pc.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 4.63 hr./trip ] / [ 250 pcs./trip]= 15.74 / pc.
12% VAT
0.12 x 553.02 / hr. x 4.63 hr./trip ] / [ 250 bags/trip ]= 1.23 / pc. OK
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : Plywood G.I.Sheet
A. Base Cost = 750.00 / pc. 310.00 / pc.
B. Labor Cost = 5.07 / pc. 5.07 / pc.
Page 46 of 102
C. Equipment Cost = 15.74 / pc. 15.74 / pc.
D. 12% VAT = 1.59 / pc. 1.59 / pc.
UNIT COST….....= P 772.40 / pc. 332.40 / pc. OK
CYCLE TIME:
LABOR COST:
Laborer:[5xP 260.00 / day x 3.31 hr./trip ] / [ 8 hrs./day x 4000 bd.ft./trip ] = P 0.13 / bd.ft.
LABOR COST…………. 0.13 / bd.ft.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 3.31 hr./trip ] / [ 4000.00 bd.ft./trip 0.70 / bd.ft.
12% VAT
0.12 x 553.02 / hr. x 3.31 hr./trip ] / [ 4000 bags/trip ]= 0.05 / bd.ft. OK
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
CYCLE TIME:
Loading : [ 6000 kgs./trip x 60 min./hr.] /[ 6000 kgs./ hr. = 60.00 min./ trip
Unloading [ 6000 kgs./trip x 60 min./hr.] /[ 7000 kgs./ hr. = 51.43 min./ trip
LABOR COST:
Laborer:[5xP 260.00 / day x 4.48 hr./trip ] / [ 8 hrs./day x 7000.00 0.10 / kgs.
LABOR COST…………. 0.10 / kgs.
EQUIPMENT:
Rental: [ P 851.00 / hr. x 4.48 hr./trip ] / [ 6000.00 kgs./trip 0.64 / kgs.
12% VAT
0.12 x 553.02 / hr. x 4.48 hr./trip ] / [ 6000.00 bags/trip ]= 0.05 / kgs.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : RSB CW NAILS TIE WIRE
A. Base Cost = 55.00 / kg. 75.00 / kg. 75.00 / kg.
B. Labor Cost = 0.44 / kg. 0.44 / kg. 0.44 / kg.
C. Equipment Cost = 0.64 / kg. 0.64 / kg. 0.64 / kg.
D. 12% VAT = 0.06 / kg. 0.06 / kg. 0.06 / kg.
UNIT COST….....= P 56.14 / kg. 76.14 / kg. 76.14 / kg.
LABOR COST:
Laborer:[1xP 260.00 / day x 1.89 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 15.37 / cu.m.
LABOR COST…………. 15.37 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 1.89 hr./trip ] / [ 4.00 cu.m./trip 351.38 / cu.m.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
w/ manual hauling
SUMMARY : SAND GRAVEL
A. Base Cost = 550.00 / cu.m. 850.00 / cu.m.
B. Labor Cost = 15.37 / cu.m. 15.37 / cu.m.
C. Equipment Cost = 351.38 / cu.m. 351.38 / cu.m.
D. Manual Hauling = 173.33 / cu.m. 173.33 / cu.m.
UNIT COST….....= P 1090.08 / cu.m. 1390.08 / cu.m.
b) Common Borrow
Loading : [ 2.5 cu.m/trip x 60 min./hr.] /[ 20 cu.m/ hr. = 7.50 min./ trip
Unloading [ 2.5 cu.m/trip x 60 min./hr.] /[ 25 cu.m/ hr. = 6.00 min./ trip
Loading : [ 4 cu.m/trip x 60 min./hr.] /[ 5 cu.m/ hr. = 48.00 min./ trip
Unloading [ 4 cu.m/trip x 60 min./hr.] /[ 8 cu.m/ hr. = 30.00 min./ trip
Laborer:[1xP 260.00 / day x 1.53 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 12.39 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 1.53 hr./trip ] / [ 4.00 cu.m./trip 283.27 / cu.m.
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
C) Boulders
Loading : [ 2.5 cu.m/trip x 60 min./hr.] /[ 20 cu.m/ hr. = 7.50 min./ trip
Page 48 of 102
Unloading [ 2.5 cu.m/trip x 60 min./hr.] /[ 25 cu.m/ hr. = 6.00 min./ trip
Loading : [ 4 cu.m/trip x 60 min./hr.] /[ 3 cu.m/ hr. = 80.00 min./ trip
Unloading [ 4 cu.m/trip x 60 min./hr.] /[ 4 cu.m/ hr. = 60.00 min./ trip
min./ trip
TOTAL TIME………… 153.50 min./ trip
2.56 hrs./ trip
LABOR COST:
Laborer:[1xP 260.00 / day x 2.56 hr./trip ] / [ 8 hrs/day x 4.00 cu.m./trip 20.79 / cu.m.
LABOR COST…………. 20.79 / cu.m.
EQUIPMENT:
Rental: [ P 743.00 / hr. x 2.56 hr./trip ] / [ 4.00 cu.m./trip 475.21
MANUAL HAULING:
Manual hauling of construction materials from nearest stockpile/field bodega,
considering seven (7) hrs. Effective working time per day, with the assumption
that laborers are traversing along rice paddies,Average hauling distance .15 km.
Page 49 of 102
pcs. per meter
10 3.696 133 491.568 38 395.00416 106.87342 0.616 6 3.696
12 5.328 47 250.416 19 201.22417 37.767298 0.888 6 5.328
16 9.474 19 180.006 14 144.64554 15.267631 1.579
20 14.796 26 384.696 29 309.12614 20.892548 2.466
total 1306.686 100 1050 12.8592
47.527603
105
#REF!
47
180 18.8 60
13 110
60 230
125 110
13 60
60 570 0.8 5.7 9.12
13 5.64 0.3 1.692
100 10.812
80 5.328
80 57.606336
724 5.328
10.812
Page 50 of 102
12.8592
1.1 1.21
2 4
5.21
5.21√
2.2825424
Page 51 of 102
BITO RIVER IRRIGATION SYSTEM
Abuyog,Leyte
CY 2017 POW
(By Contract Works)
Attachment "G"
DERIVATION OF COST OF CONSTRUCTION MATERIALS
LOCAL MINOR CONTRACT
Position Rate per day (P) Position Rate per day (P)
Foreman 400.00 Heavy Equipment Operator 350.00
Carpenter 350.00 Light Equipment Operator 300.00
Mason 350.00 Driver/Bar Cutter 300.00
Steelman/Welder 350.00 Laborer/Helper (per Minimum Wage 260.00
Board as of July 1, 2012)
SUMMARY
A. Base Cost = 270.00 per bag
B. Labor Cost = 0.81 per bag
C. Equipment Cost = 15.40 per bag
Plus 5% VAT (Exc. Mat'l Cost) = 0.81 per bag
TOTAL = 287.02 per bag
CONSTRUCTION MATERIALS RSB, C.W. NAILS, TIE WIRES & ANGLE BARS
Rough Road:
With Load : 0.00 km/trip / 20.00 km./hr. = 0.00 hr./trip
W/o Load : 0.00 km/trip / 25.00 km./hr. = 0.00 hr./trip
2.30 hr./trip
Baremonth = P96564/bare month x 1month /25 days x 1 day / 8hrs. = P 482.82 /hr.
Cycle Time
Concrete Road:
With Load : 15.00 km/trip / 35.00 km./hr. = 0.43 hr./trip
W/o Load : 15.00 km/trip / 45.00 km./hr. = 0.33 hr./trip
= 0.76
Rough Road:
With Load : 5.00 km/trip / 20.00 kms./hr. = 0.25 hr./trip
W/o Load : 5.00 km/trip / 25.00 kms./hr. = 0.20 hr./trip
Loading, Spot & manuver, unloading & delay = 0.20 hr./trip
= 0.65 hr./trip
TOTAL = 1.41 hr./trip
B. LABOR COST
1 Helper x 260.00 /day 1.41 hr./trip
8.00 hrs./day x 4.00 cu.m./trip = 11.46 per cu.m.
5% VAT = 11.46 x 0.05 = 0.57 per cu.m.
C. EQUIPMENT COST
Rental = 743.00 /hr. x 1.41 hr./trip
4.00 cu.m./trip = 261.91 per cu.m.
VAT 0.05 x 743.00 /hr. x 1.41 hr./trip = 13.10 per cu.m.
4.00 cu.m./trip
SUMMARY Boulder
A. Base Cost = 500.00 per cu.m.
B. Labor Cost = 4.17 per cu.m.
C. Equipment Cost = 173.30 per cu.m.
Plus 12% VAT (Exc. Mat'l Cost) = 8.88 per cu.m.
Total = 686.35 per cu.m.
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 5801.28 per cu.m.
B. LABOR COST = 1405.71 per cu.m.
1. Cutting, Bending & Placing of RSB = 0 per cu.m.
2. Fabrication, placing and dismantling of forms = 497.14 per cu.m.
3. Concreting and Curing = 908.57 per cu.m.
C. EQUIPMENT COST = 258 per cu.m.
1. Concrete Mixer = 258 per cu.m.
TOTAL ESTIMATED DIRECT COST = 7464.99 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM (20% OF EDC) = 1493 per cu.m.
B. VAT (12% OF LABOR COST) = 171.93 per cu.m.
1. Labor Cost (Cutting,Bending & Placing, Fabrication, = 168.69 per cu.m.
Placing & Dismantling of forms, Concreting & Curing
2. Labor Cost ( Hauling of Materials ) = 3.24 per cu.m.
C. VAT (12% OF EQUIPMENT RENTAL ) = 61.76 per cu.m.
1. Equipment Rental Cost using ( Concrete Mixer ) = 0 per cu.m.
2. Equipment Rental Cost using ( Hauling of Materials ) = 41.68 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 179.16 per cu.m.
TOTAL INDIRECT COST = 1905.85 per cu.m.
TOTAL UNIT COST = 9370.84 per cu.m.
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 6.50 per sq.m.
C. EQUIPMENT COST = -
TOTAL ESTIMATED DIRECT COST = 6.50 per sq.m.
II. INDIRECT COST
A. PROFIT & OCM (2% OF EDC) = 1.30 per sq.m.
B. VAT (12% OF LABOR COST) = 0.78 per sq.m.
C. VAT (12% OF RENTAL ) = -
D. VAT (12% OF PROFIT & OCM ) = 0.16 per sq.m.
TOTAL INDIRECT COST = 2.24 per sq.m.
TOTAL UNIT COST = 8.736 per sq.m.
SUMMARY :
I. ESTIMATED DIRECT COST
A. MATERIAL COST = -
B. LABOR COST = 140.00 per sq.m.
C. EQUIPMENT COST =
TOTAL ESTIMATED DIRECT COST = 140.00 per sq.m.
II. INDIRECT COST
A. PROFIT & OCM (20% OF EDC) = 28.00 per sq.m.
B. VAT (12% OF LABOR COST) = 16.80 per sq.m.
C. VAT (12% OF RENTAL ) = -
D. VAT (12% OF PROFIT & OCM ) = 3.36 per sq.m.
TOTAL INDIRECT COST = 48.16 per sq.m.
TOTAL UNIT COST = 188.16 per sq.m.
Spreading:
Equipment Used 1-Unit DOZER D60A-11 (155 HP)
Capability = 90.00 cu.m./hr.
Operated Rental Rate P 2,594.00 /hr.
Bare Month P 337,194.00
= 337,194.00 /month /25 days x 1 day / 8hrs.
1,685.97 /hr.
Operated Re2,594.00 /hr / 90.00 cu.m./hr. = 28.82 /cu.m.
I. DIRECT COST
A. MATERIAL COST
1. Material Cost 773.37 per cu.m.
A. EQUIPMENT COST
3. Spreading = 28.82 per cu.m.
4. Compaction = 24.55 per cu.m.
53.37 per cu.m.
TOTAL ESTIMATED DIRECT COST = 826.74 per cu.m.
B. LABOR COST
1. Fabrication, placing and dismantling of forms
1 Carpenter @ 350 per day = 350 per day
1 Laborer @ 260 per day = 260 per day
Total = 610 per day
Capability 4.5 cu.m./day
Labor cost = 135.56 per cu.m.
2. Concreting with curing
Time of Mixer = 7.5bags/cum x 4.5cum/day x 10min/bag = 5.63 hrs/day
60min/hr
a With concrete mixer
1 Foreman @ 400 per day = 400 per day
2 Mason @ 350 per day = 700 per day
8 Laborer @ 260 per day = 2080 per day
Total = 3180 per day
Capability 4.5 cu.m./day
Labor Cost = 706.67 per cu.m.
C. EQUIPMENT COST
Capability 4.5 cu.m./day
Rental = 172 per hr. x 5.25 hrs/day = 200.67 per cu.m.
4.5 cu.m./day
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 3,770.10 per cu.m.
B. LABOR COST = 842.23 per cu.m.
1. Fabrication, placing and dismantling of forms = 135.56 per cu.m.
2. Concreting and Curing = 706.67 per cu.m.
C. EQUIPMENT COST = 200.67 per cu.m.
1. Concrete Mixer = 200.67 per cu.m.
TOTAL ESTIMATED DIRECT COST = 4813 per cu.m.
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 4,562.77 per cu.m.
B. LABOR COST = 842.23 per cu.m.
1. Cutting, Bending & Placing of RSB = - per cu.m.
2. Fabrication, placing and dismantling of forms = 135.56 per cu.m.
3. Concreting and Curing = 706.67 per cu.m.
C. EQUIPMENT COST = 200.67 per cu.m.
1. Concrete Mixer = 200.67 per cu.m.
TOTAL ESTIMATED DIRECT COST = 5605.67 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM (2% OF EDC) = 1121.13 per cu.m.
B. VAT (12% OF LABOR COST) = 26.14 per cu.m.
1. Labor Cost (Cutting,Bending & Placing, Fabrication, = 101.07 per cu.m.
Placing & Dismantling of forms, Concreting & Curing
2. Labor Cost ( Hauling of Materials ) = 2.94 per cu.m.
C. VAT (12% OF EQUIPMENT RENTAL ) = 55.24 per cu.m.
1. Equipment Rental Cost using ( Concrete Mixer ) = 15.62 per cu.m.
2. Equipment Rental Cost using ( Hauling of Materials ) = 39.62 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 134.54 per cu.m.
TOTAL INDIRECT COST = 1337.05 per cu.m.
TOTAL UNIT COST = 6942.72 per cu.m.
9. RUBBLE MASONRY
A. MATERIAL COST (per cu.m.)
Cement 4.50 bags @ 286.21 per bag = 1,287.95
Gravel 0.45 cu.m. @ 1123.37 per cu.m. = 505.52
Sand 0.225 cu.m. @ 773.37 per cu.m. = 174.01
Boulder 0.95 kgs @ 677.47 per cu.m. = 643.60
Total Material Cost = 2,611.07 per cu.m.
B. LABOR COST
1. Laying of Materials
1 Laborer @ 260.00 per day = 260.00 per day
Total = 260.00 per day
Capability 1.5 cu.m./day
Labor Cost = 173.33 per cu.m.
2. Concreting with curing
Time of Mixer = 4.5bags/cum x 5.0cum/day x 10min/bag = 3.75 hrs/day
60min/hr
a With concrete mixer
1 Foreman @ 400.00 per day = 400.00 per day
2 Mason @ 350.00 per day = 700.00 per day
8 Laborer @ 260.00 per day = 2,080.00 per day
Total = 3,180.00 per day
Labor Cost = 636.00 per cu.m.
Capability 5 cu.m./day
C. EQUIPMENT COST
Capability 5 cu.m./day
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = 2,611.07 per cu.m.
B. LABOR COST = 809.33 per cu.m.
1. Laying of Materials = 173.33 per cu.m.
2. Concreting and Curing = 636.00 per cu.m.
C. EQUIPMENT COST = 129.00 per cu.m.
1. Concrete Mixer = 129.00 per cu.m.
TOTAL ESTIMATED DIRECT COST = 3,549.40 per cu.m.
II. INDIRECT COST
A. PROFIT & OCM 20% OF EDC) = 709.88 per cu.m.
B. VAT (12% OF LABOR COST) = 98.98 per cu.m.
C. VAT (12% OF RENTAL ) = 42.06 per cu.m.
D. VAT (12% OF PROFIT & OCM ) = 85.19 per cu.m.
TOTAL INDIRECT COST = 936.11 per cu.m.
TOTAL UNIT COST = 4485.5051 per cu.m.
A. CONSTRUCTION OF SLPOE PROTECTION WORK @ DAGUITAN DAM DOWNSTREAM RIGHT EMBANKMENT FACING UPSTREAM
STATIONING
FROM TO LENGTH (mAREA (sq.m.) St AREA (sq.m.) BackfAREA (sq.m.) Emb.AREA (sq.m.)AREA (sq.m.) DewLength (l.m.) Clearing & Grub AREA (sq.m.)
Vert. Bars Hor. Bars (12mVolume (cu.m.) St Volume (cu.m.) BVolume (cu.m.) Em
Volume (cu.m.Volume (cu.m.Area (sq.m.) Cl Volume (cu.m.)Vert. Bars Hor. Bars (12mm
DOWNSTREAM RIGHT SIDE EMBANKMENT FACING UPSTREAM
0 + 000 2.00 2.10 0.00 3.04 1.80 15.00 0.47 3.35 53
0 + 000 0 + 003.50 3.5 2.20 11.90 0.00 3.04 1.80 15.00 0.47 3.35 53 7.35 24.50 0.00 10.64 6.30 52.50 1.65 208.24 179.70
0 + 003.5 0 + 009 5.5 5.90 6.30 0.00 3.04 1.80 15.00 0.47 3.35 53 22.28 50.05 0.00 16.72 9.90 82.50 2.59 327.23 282.38
0 + 009 0 + 010 1 2.50 16.10 0.00 3.04 1.80 15.00 0.47 3.35 53 4.20 11.20 0.00 3.04 1.80 15.00 0.47 59.50 51.34
0 + 010 0 + 020 10 4.30 3.30 0.00 3.04 1.80 15.00 0.47 3.35 53 34.00 97.00 0.00 30.40 18.00 150.00 4.70 594.96 513.43
0 + 020 0 + 040 5 12.41 5.80 0.00 3.04 1.80 15.00 0.47 3.35 53 41.76 22.75 0.00 15.20 9.00 75.00 2.35 297.48 256.71
0 + 040 0 + 060 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUB-TOTAL 25 109.59 205.50 0.00 76.00 45.00 375.00 11.75 1,487.40 1,283.56
TOTAL 25 109.59 205.50 0.00 76.00 45.00 375.00 11.75 2770.96363636364
B. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 0 + 340 - 1 + 018 L = 261.15 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.34
L = 261.15 3.04 0.15
V = 0.07*3.34*261.15
V = 61.06 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.34 0.15
L = 261.15
V = 0.07*3.34*261.15 3.04 0.15
V = 61.06 cu.m.
c. Filter Drain
Area = 0.18 sq.m.
L = 261.15
V = 0.18*261.15
V = 47.00 cu.m.
C. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 2 + 501 - 3 + 094 L = 22 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 22 1.98 0.15
V = 0.07*2.28*22
V = 3.51 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 22
V = 0.07*2.28*22 1.98 0.15
V = 3.51 cu.m.
D. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 4 + 552 - 4 + 568 L = 20 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 20 1.98 0.15
V = 0.07*2.28*20
V = 3.19 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 20
V = 0.07*2.28*20 1.98 0.15
V = 3.19 cu.m.
E. REPAIR OF CANAL LINING OF DAGUITAN LATERAL D STA 3 + 972 - 3 + 988 L = 16 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.5
L = 16 3.2 0.15
V = 0.07*3.5*16
V = 3.92 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.5 0.15
L = 16
V = 0.07*3.5*16 3.2 0.15
V = 3.92 cu.m.
Prepared by:
JOJO A. ARCENO
Senior Engineer A
Summary
A.
Program Amount
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Clearing & Grubbing (Mechanized) sq.m. 375.00 12.78 4,792.50
b. Dewatering cu.m. 45.00 618.10 27,814.50
d. Common Excavation-Mechanized cu.m. 461.13 146.17 67,403.46
d. Filter drain cu.m. 11.75 1,715.67 20,159.12
e. 211kgsc. Concrete cu.m. 76.00 11,425.49 868,337.24
f. Furnishing of RSB kgs. 6,650.31 66.91 444,972.24 6650.31
g. Cutting,Bendin & Placing of RSB kgs. 6,054.85 16.14 97,725.28
h. Supply & Installation of Steel Sheet Piles pcs. - - 6054.85
h. Backfill w/ Compaction ( SB )-Mechanized cu.m. 205.50 69.87 14,358.29
i. Emb. Const'n. & Comp. ( ECC ) ( HB )-Mechanized cu.m. - 1,254.54 -
TOTAL 1,545,562.63 1,478,159.17
B.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 55.18 624.93 34,483.64
b. 169kgsc. Plain Concrete cu.m. 55.18 7,974.41 440,027.94
c. Filter drain cu.m. 42.48 1,715.67 72,881.66
TOTAL 547,393.24
c.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.55 624.93 1,593.57
b. 169kgsc. Plain Concrete cu.m. 2.55 7,974.41 20,334.75
TOTAL 21,928.32
d.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.55 624.93 1,593.57
b. 169kgsc. Plain Concrete cu.m. 2.55 7,974.41 20,334.75
TOTAL 21,928.32
E.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 1.96 624.93 1,224.86
b. 169kgsc. Plain Concrete cu.m. 1.96 7,974.41 15,629.84
TOTAL 16,854.71
F.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 2.50 624.93 1,562.33
b. 169kgsc. Plain Concrete cu.m. 2.50 7,974.41 19,936.03
TOTAL 21,498.35
G.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.89
H.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.24 624.93 149.98
b. 169kgsc. Plain Concrete cu.m. 0.24 7,974.41 1,913.86
TOTAL 2,063.84
i.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.89
j.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.16 624.93 99.99
b. 169kgsc. Plain Concrete cu.m. 0.16 7,974.41 1,275.91
TOTAL 1,375.89
k.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Concrete Demolition cu.m. 0.32 624.93 199.98
b. 169kgsc. Plain Concrete cu.m. 0.32 7,974.41 2,551.81
TOTAL 2,751.79
l.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Common Excavation cu.m. 1.50 194.43 291.65
b. 211kgsc. Concrete cu.m. 0.43 11,425.49 4,912.96
c. Furnishing of RSB kgs. 15.18 66.91 1,015.69
d. Cutting,Bendin & Placing of RSB kgs. 15.18 16.14 245.01
e. Backfill w/ Compaction ( HB ) cu.m. 9.00 1,502.70 13,524.30
TOTAL 19,989.60
M.
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
a. Common Excavation cu.m. 1.50 194.43 291.65
b. 211kgsc. Concrete cu.m. 0.43 11,425.49 4,912.96
c. Furnishing of RSB kgs. 15.18 66.91 1,015.69
d. Cutting,Bendin & Placing of RSB kgs. 15.18 16.14 245.01
e. Backfill w/ Compaction ( HB ) cu.m. 3.60 1,502.70 5,409.72
TOTAL 11,875.02 2,148,570.04
(1,351,329.96)
Prepared by: 2,215,973.50252 -9244.91999179
3,499,900.0000
1,283,926.4974815100000
JOJO A. ARCENO 8,783.7894060443800
Senior Engineer A 9,244.9199917904
DESCRIPTION OF WORK UNIT QUANTITY UNIT COST AMOUNT
#REF!
DETAILED COMPUTATION
Construction of downstream slope protection L/S facing downstream of Daguitan Dam
Sta 0 + 000 + 0 + 026
Brgy. Cantimawa, Burauen, Leyte
I. DIVERSION WORKS
A. Clearing & Grubbing ( Mechanized )
STATIONING Width Thickness No. of Area
FROM TO Name of Canal LENGTH (m) (m) Units (sq.m.)
0 + 000 0 + 026 Daguitan Dam 26 15 390
E. Filter Drain
STATIONING Width Thickness No. of Area
FROM TO Name of Canal LENGTH (m) (m) Units (sq.m.)
0 + 000 0 + 003.5 Daguitan Dam 3.5 0.47
0 + 003.5 0 + 009 Daguitan Dam 5.5 0.47
0 + 009 0 + 010 Daguitan Dam 1 0.47
0 + 010 0 + 026 Daguitan Dam 16 0.47
Total Volume for Filter Drain 26
a b c d
Bar Size Bar Section Length per cut bars (m)
b
a
b
a
a
c
12 mm dia Deformed Ba 0.3 0.76 0.04 1.1
a
12 mm dia Deformed Ba 27 27
c. Filter Drain
Area = 0.18 sq.m.
L = 261.15
V = 0.18*261.15
V = 47.00 cu.m.
B. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 2 + 501 - 3 + 094 L = 22 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 22 1.98 0.15
V = 0.07*2.28*22
V = 3.51 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 22
V = 0.07*2.28*22 1.98 0.15
V = 3.51 cu.m.
C. REPAIR OF CANAL LINING OF DAGUITAN MAIN CANAL STA 4 + 552 - 4 + 568 L = 20 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 2.28
L = 20 1.98 0.15
V = 0.07*2.28*20
V = 3.19 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 2.28 0.15
L = 20
V = 0.07*2.28*20 1.98 0.15
V = 3.19 cu.m.
D. REPAIR OF CANAL LINING OF DAGUITAN LATERAL D STA 3 + 972 - 3 + 988 L = 16 l.m. ( Selected Portion Only)
a. Concrete Demolition ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m. 0.15
w = 3.5
L = 16 3.2 0.15
V = 0.07*3.5*16
V = 3.92 cu.m.
b. Plain Concrete, 169kgsc. ( See Attached Plan and Section Side Slope Only )
t = 0.07 l.m.
w = 3.5 0.15
L = 16
V = 0.07*3.5*16 3.2 0.15
V = 3.92 cu.m.
Volume Remarks
(cu.m.)
inclined wall
VOLUME Remarks
FILL
Volume Remarks
(cu.m.)
80.60 inclined wall
4.29 cut-off wall
84.89
Volume Remarks
(cu.m.)
1.65 inclined wall
2.59 inclined wall
0.47 inclined wall
7.52 inclined wall
12.22
Volume Remarks
(cu.m.)
cut-off wall
No of pcs. Total Length (m) Unit weight of RS Total No. of Kil Remarks
1. Surveying:
Profile:
Capability per team = 5 km/day
Cross-Section:
Capability per team = 3 km/day
Traverse:
Capability per team = 3 km/day
Equipment Cost:
Particulars Rate/trip No. km/day Cost
Equipment Rental = 3,220.40 3 = 1,073.47
Driver = 636.36 3 = 212.12
Fuel = 284.00 3 = 94.67
Oil 30% of Fuel Cost = 28.40
Total Equipment Cost per kilometers = 1,408.65 km
DERIVATION OF UNIT COST
BITO RIS, ABUYOG, LEYTE
Institutional Development Program
1. Personnel Services
1 - IDO = 19,047.62
Sub-Total 19,047.62
2. MOOE
2.a. Office Supplies = 4,761.91
2.b. Fuel & Oil = 2,380.95
2.c. Equipment Rental = 4,761.91
2.d. Spare Parts = 2,380.95
2.e. Trainings = 14,285.72
Sub-Total 28,571.43
SUB-TOTAL 27,823.29 3,000.00 2,225.86 3,338.79 2,150.00 262.50 150.00 - - - 38,950.45 111,293.16 12,000.00 8,903.45 13,355.18 600.00 1,050.00 600.00 11,774.43 5,000.00 164,576.22 203,526.67
COS Employees
1 Jonathan G. Setosta Survey Aide RREIS - DGM RIS - CS 6 587.31 74,001.06 - - - 600.00 - - - - 74,601.06 587.31 74,001.06 - - - - 600.00 - - - 74,601.06 149,202.12
2 Romwell Ogana Survey Aide RREIS - DGM RIS - CS 6 587.31 74,001.06 600.00 74,601.06 587.31 74,001.06 600.00 74,601.06 149,202.12
3 Louie A. Tonido WRFT Tender A RREIS - DGM RIS - SUBSIDY 5 546.31 68,835.06 600.00 69,435.06 546.31 68,835.06 600.00 69,435.06 138,870.12
4 Domingo Simborios Driver Mechanic B RREIS - DGM RIS - SUBSIDY 7 631.36 79,551.36 600.00 80,151.36 631.36 79,551.36 600.00 80,151.36 160,302.72
5 Andres Dela Cruz Driver Mechanic B RREIS - DGM RIS - SUBSIDY 7 631.36 79,551.36 600.00 80,151.36 631.36 79,551.36 600.00 80,151.36 160,302.72
6 Constanti Advincula Utility Worker A RREIS - DGM RIS - SUBSIDY 4 472.77 59,569.02 600.00 60,169.02 472.77 59,569.02 600.00 60,169.02 120,338.04
7 Jessie Leuterio Utility Worker A RREIS - DGM RIS - CS 4 472.77 59,569.02 600.00 60,169.02 472.77 59,569.02 600.00 60,169.02 120,338.04
8 Rico Agner Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
9 Ruel C. Verzosa Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
10 Danilo Tuang Utility Worker B RREIS - DGM RIS - CS 3 409.09 51,545.34 600.00 52,145.34 409.09 51,545.34 600.00 52,145.34 104,290.68
11 Melchor Abbe Natulla RAB RREIS - DGM RIS - IDP 8 678.68 85,513.68 600.00 86,113.68 678.68 85,513.68 600.00 86,113.68 172,227.36
12 Mia Lee T. Planillo RAB RREIS - DGM RIS - IDP 8 678.68 85,513.68 600.00 86,113.68 678.68 85,513.68 600.00 86,113.68 172,227.36
SUB-TOTAL 939,879.36 - - - - 11,400.00 - - - - 951,279.36 939,879.36 - - - - 11,400.00 - - - 951,279.36 1,902,558.72
GRANDTOTAL 967,702.65 3,000.00 2,225.86 3,338.79 2,150.00 11,662.50 150.00 - - - 990,229.81 1,051,172.52 12,000.00 8,903.45 13,355.18 600.00 12,450.00 600.00 11,774.43 5,000.00 1,115,855.58 2,106,085.39
b. Labor Cost
b.1 Cutting, Grinding and Laying of Frame
Crew: 2- Welder ; 2- Laborers
Capability: 2.80 days/unit
b.2 Drilling of Anchor bolts & Retainer bolts, molding of Lifting Stem guide.
Crew: 1- Machinest ; 2- Laborers
Capability: 2.40 days/unit
b.3 Assembling & Welding of Frame
Crew: 2- Welder ; 3- Laborers
Capability: 3.00 days/unit
b.4 Fabrication of Lifting Mechanism / Pedestal Guide
Crew: 2- Machinest ; 3- Laborers
Capability: 3.00 days/unit
b.5 Assembling of Gates
Crew: 2- Welder ; 2- Laborers
Capability: 4.00 days/unit
b.6 Cleaning of Materials / Paints Works
Crew: 1- Painter ; 2- Laborers
Capability: 1.60 days/unit
Rate Labor
Personnel
per
Involved
Cutting, Grinding and Laying of Frame Drilling of Anchor bolts & Retainer bAssembling & Welding of Frame
Day No. COST No. COST No. COST
Machinest 400.00 1 400
Welder 350.00 2 700.00 2 700
Painter 350
Laborer 253.00 2 506.00 2 506 3 759
Total Cost 1,206.00 906 1459
Unit Cost 3,376.80 2174.4 4377
Rate Labor
per
Personnel Inv Fabrication of Lifting Mechanism / Pedestal Guide Assembling of Gates Cleaning of Materials / Paints Works
Day No. COST No. COST No. COST
Machinest 400.00 2 800
Welder 350.00 2 700
Painter 350 1 350
Laborer 253.00 3 759 2 506 2 506
Total Cost 1559 1206 856
Unit Cost 4677 4824 1369.6
Sub-Total Unit Cost (For Labor) 20798.8
c. Equipment Cost
c.1 Equipment to be used: Power Rental: P180.00 /hr.
TIME OF POWER SAW
Status Using No. of hours to bhrs./ days/
Power Saw used per unit day unit
25 8 3.125
Installation
b. Hauling Cost
Average hauling distance is 185.35 kms. from Maasin to jobsite
Type of Road: Concrete Road = 180.00 kms.
Poor Maintained Road = 0.30 kms.
Utilized 6-7 tonner Cargo Truck w/ 4 laborers
Rental: P851.00 / hr.
Cycle Time
Status kms. min. kms. min.
using per trip per hr. per hr. per trip
Concrete Road
w/ load 180 * 60 / 35 = 308.57
w/o load 180 * 60 / 45 = 240.00
Poor maintained gravel road
w/ load 0.3 * 60 / 20 = 0.90
w/o load 0.3 * 60 / 25 = 0.72
Manual Hauling, Loading & Unloading = 30.00
TOTAL 580.19 min./trip
9.67 hrs./trip
1.21 day/trip
Labor Cost:
Personnel Peso day unit Peso
Involved per day per trip per trip per unit
1-Driver @
320.00 320.00 * 1.21 * 1 = 386.79
4-Laborer @
253.00 1,012.00 * 1.21 * 1 = 1223.24
TOTAL 1,610.03 /unit
Equipment Cost:
Cost/ Hrs./ Liter/ Cost/ unit/ Cost/
Particulars hr. day hr. liter day unit
Fuel 9.67 * 10.00 * 58.37 * ### = 5,644.30
Oil 30% of Fuel Cost = 1,693.29
Rental 851.00 * 9.67 * ### = 8,229.05
SUMMARY
Materials = 77471 = 77,471.00
Labor = 20,798.80 + 1,362.00 + 1,610.03 = 23,770.83
Equipment = 54,140.00 = 54,140.00
Fuel = 5,644.30 + 1,693.29 = 7,337.58
Rental = 8,229.05 = 8,229.05
Total Estimated Cost P170,948.46
9% O.C.M. P15,385.36
8% Profit P13,675.89
TOTAL P200,009.70
12% VAT P11,217.30
Total Unit Cost P211,227.00
Unit Cost for Proc./Fab. & Inst. of Steel Gate at Intake and Back to River (1.00 m. X 1.15 m.) P211,227.00 / unit
SUMMARY
I. DIRECT COST
A. MATERIAL COST P0.00 / unit
1. Without Fabrication 0.00
2. With Fabrication 0.00
700
759
1459
4377
s / Paints Works
COST
350
506
856
1369.6
20798.8
APPROVED BUDGET FOR THE CONTRACT
BITO RIS Abuyog, Leyte
REPAIR/REHAB OF EXISTING IRRIGATION SYSTEM - 2017
ITEMS OF WORK UNIT QTY. UNIT COST ESTIMATED DIRECT COSCONTRACTOR'S VAT & TOTAL COST UNIT COST
(1) (2) (3) (4) (5) (6) (7) (8) (9)
PACKAGE # 2
BITO RIS
A CONTROL FACILITIES
AT MTO,Portion (1.20m x 0.50m)
Fabrication/Installation of gate set 9.00 72,035.71 493959.15 154,362.23 648,321.38 72,035.71
Sub-total 493,959.15 154,362.23 648,321.38
TOTAL CONTRACT AMOUNT 493,959.15 154,362.23 648,321.38
2017
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
I. PACKAGE #1
1. CONSTRUCTION OF CHECKGATE
Check Structures @ Ulhay Creek
Clearing & Grubbing (Manual) 649.7623125 0.0002439 14
Structure Excavation (Manual) 36739.95 0.0137883 35
Diversion and care of river 3150 0.0011822 35
170 kscm Plain Concrete 3691.8915 0.0013855 14
211 kscm Class A Concrete 184815.3288 0.0693601 77
Furnishing of RSB 70358.533875 0.0264051 21
Cutting and Bending of Bars 12924.2826563 0.0048504 63
Rubble Masonry 0 0 56
RCP 18" Diameter 0 0 14
Fab./inst of Sluice gate 93164.203125 0.034964 21
Fab./inst of Intake gate 72035.709375 0.0270346 21
Structure Backfill w/ compaction (HB 80079.1915 0.0300532 70
Sub-total 557608.85314 0.2092672 90
2. CANAL LINING @ SUPLLEMENTARY FARMDITCHES & LAT. CANAL
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capabilit 11.00 pcs. /day
Rate
Personnel per Labor
Day No. Cost
Foreman 400.00 1 400
Mason 350.00 1 350
L.E. Opera 320.00 1 320
Steelman 300.00 1 300
Laborer 253.00 12 3036
Total Cost 4406
Unit Cost 400.545455
0.12 VAT 48.0654545
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 11 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
Fuel Consumption : 1.25 liters/hr.
Fuel Cost : P55.28 /liter
= 102.9 /hr.
TIME OF MIXER/DAY
Status Usi pcs./ bags/ min./ min./ hrs./
Mixer day pc. bag hr. day
11 * 1.22 * 10 / 60 = 2.23666667
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capabilit 14.00 pcs. /day
Rate
Personnel per Labor
Day No. Cost
Foreman 400.00 1 400
Mason 350.00 1 350
L.E. Opera 320.00 1 320
Steelman 300.00 1 300
Laborer 253.00 12 3036
Total Cost 4406
Unit Cost 314.714286
0.12 VAT 37.7657143
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 14 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
Fuel Consumption : 1.25 liters/hr.
Fuel Cost : P55.28 /liter
= 102.9 /hr.
TIME OF MIXER/DAY
Status Usi pcs./ bags/ min./ min./ hrs./
Mixer day pc. bag hr. day
14 * 0.45 * 10 / 60 = 1.05
SUMMARY
I. DIRECT COST
A. MATERIAL COST = 445.00 /pc.
1. Materials Cost = 445.00 /pc
B. LABOR COST = 314.71 /pc.
1. Installation of RCP = 314.71 /pc
C. EQUIPMENT COST = 12.90 /pc.
1. Concrete Mixer = 12.90 /pc
TOTAL ESTIMATED DIRECT COST = 772.61 /pc. ###
II. INDIRECT COST
A. PROFIT & OCM 17% OF EDC) = 131.34 /pc
B. VAT (12% OF LABOR COST) = 98.98 /pc
C. VAT (12% OF RENTAL ) = 42.06 /pc
D. VAT (12% OF PROFIT & OCM ) = 15.76 /pc
TOTAL INDIRECT COST = 288.15 /pc. ###
Unit Cost for Installation of 18" dia. RCP = 1,060.76 /pc.
b. Labor Cost
b.1 Cutting, Grinding and Laying of Frame
Crew: 2- Welder ; 2- Laborers
Capability: 2.80 days/unit
b.2 Drilling of Anchor bolts & Retainer bolts, molding of Lifting Stem guide.
Crew: 1- Machinest ; 2- Laborers
Capability: 2.40 days/unit
b.3 Assembling & Welding of Frame
Crew: 2- Welder ; 3- Laborers
Capability: 3.00 days/unit
b.4 Fabrication of Lifting Mechanism / Pedestal Guide
Crew: 2- Machinest ; 3- Laborers
Capability: 3.00 days/unit
b.5 Assembling of Gates
Crew: 2- Welder ; 2- Laborers
Capability: 4.00 days/unit
b.6 Cleaning of Materials / Paints Works
Crew: 1- Painter ; 2- Laborers
Capability: 1.60 days/unit
Rate Labor
Personnel
per
Involved
Cutting, Grinding and Laying of Frame Drilling of Anchor bolts & Retainer bolts, moAssembling & Welding of Frame
Day No. COST No. COST No. COST
Machinest 400.00 1 400
Welder 350.00 2 700.00 2 700
Painter 350
Laborer 253.00 2 506.00 2 506 3 759
Total Cost 1,206.00 906 1459
Unit Cost 3,376.80 2174.4 4377
Rate Labor
Personnel
per
Involved
Fabrication of Lifting Mechanism / PedestalAssembling of Gates Cleaning of Materials / Paints W
Day No. COST No. COST No. COST
Machinest 400.00 2 800
Welder 350.00 2 700
Painter 350 1 350
Laborer 253.00 3 759 2 506 2 506
Total Cost 1559 1206 856
Unit Cost 4677 4824 1369.6
Sub-Total Unit Cost (For Labor) 20798.8
c. Equipment Cost
c.1 Equipment to be used: Power Saw Rental: P180.00 /hr.
TIME OF POWER SAW
Status Using No. of hours to be hrs./ days/
Power Saw used per unit day unit
25 8 3.125
Installation
b. Hauling Cost
Average hauling distance is 185.35 kms. from Maasin to jobsite
Type of Road: Concrete Road = 180.00 kms.
Poor Maintained Road = 0.30 kms.
Utilized 6-7 tonner Cargo Truck w/ 4 laborers
Rental: P851.00 / hr.
Cycle Time
Status kms. min. kms. min.
using per trip per hr. per hr. per trip
Concrete Road
w/ load 180 * 60 / 35 = 308.57
w/o load 180 * 60 / 45 = 240.00
Poor maintained gravel road
w/ load 0.3 * 60 / 20 = 0.90
w/o load 0.3 * 60 / 25 = 0.72
Manual Hauling, Loading & Unloading = 30.00
TOTAL 580.19 min./trip
9.67 hrs./trip
1.21 day/trip
Labor Cost:
Personnel Peso day unit Peso
Involved per day per trip per trip per unit
1-Driver @
320.00 320.00 * 1.21 * 1 = 386.79
4-Laborer @
253.00 1,012.00 * 1.21 * 1 = 1223.24
TOTAL 1,610.03 /unit
Equipment Cost:
Cost/ Hrs./ Liter/ Cost/ unit/ Cost/
Particulars hr. day hr. liter day unit
Fuel 9.67 * 10.00 * 58.37 * 1.00 = 5,644.30
Oil 30% of Fuel Cost = 1,693.29
Rental 851.00 * 9.67 * 1.00 = 8,229.05
SUMMARY
I. DIRECT COST
A. MATERIAL COST 152409.8 / unit
1. Without Fabrication 77471
2. With Fabrication 74938.8
= 102.9 /hr.
TIME OF MIXER/DAY
Status Using pcs./ bags/ min./ min./ hrs./
SUMMARY
Labor
12% VAT Rental
OCM
Unit Cost for Fabrication and Installation of 18" RCP #REF! + #REF! =
5. FILTER DRAIN
A. MATERIAL COST (per cu.m.)
2" dia. PV 0.15 cu.m. @ Err:509 per cu.m. = Err:509
Fine Sand 0.65 cu.m. @ Err:509 per cu.m. = Err:509
SUMMARY
I. DIRECT COST
A. MATERIAL COST
1. Materials Cost = Err:509 per cu.m.
B. LABOR COST = Err:509 per cu.m.
1. Laying of Materials = Err:509 per cu.m.
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability 14.00 pcs. /day
Rate
Personnel Involved per Labor
Day No. Cost
Foreman 400.00 1 400.00
Mason 350.00 1 350.00
L.E. Operat 320.00 1 320.00
Steelman 300.00 1 300.00
Laborer 253.00 12 3,036.00
Total Cost 4,406.00
Unit Cost 314.71
#REF!
#REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF! #REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! /pc.
ok
0.08 86.08
0.00 17.29
0.07 224.33
0.00 3.32
0.16 331.02
Proc./Fab. & Inst of 18" dia. RCP
I Fabrication
a. Materials Cost
Hauling from Source to Jobsite
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability: 11.00 pcs. /day
Rate
per Labor
Personnel Involved Day No. Cost
Foreman 500.00 1 500
Mason 450.00 1 450
Steelman 300.00 1 300
Laborer 260.00 12 3120
Total Cost 4370
Unit Cost 397.272727272727
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 11 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
SUMMARY
I. ESTIMATED DIRECT COST
A. MATERIAL COST = 972.1
B. LABOR COST
1. Fabrication of RCP = 434.308227272727
C. EQUIPMENT COST
1. Concrete Mixer = 158.333709090909
TOTAL ESTIMATED DIRECT COST = 1564.74193636364
II. INDIRECT COST
A. OCM (15% OF EDC) = 234.711290454545
B. PROFIT (10% OF EDC) = 156.474193636364
C. VAT (5% OF EDC + PROFIT + OCM) = 97.7963710227273
TOTAL INDIRECT COST = 488.981855113636
Unit Cost for Fabrication of 18" dia. RCP = 2053.72379147727
II Installation
a. Materials Cost
Hauling from Source to Jobsite
b. Labor Cost
Crew: 1- Foreman ; 1-Mason ; 1-L.E. Operator ; 1- Steelman; 12-Laborers
Capability: 14.00 pcs. /day
Rate
per Labor
Personnel Involved Day No. Cost
Foreman 500 1 500
Mason 450 1 450
Steelman 300 1 300
Laborer 260 12 3120
Total Cost 4370
Unit Cost 312.142857142857
c. Equipment Cost
c.1 Equipment to be used: 1- Bagger Concrete Mixer
Capability: 14 pcs./day
Operated Rental Rate : 172 /hr. (Based on ACEL 2009 Editon 24)
SUMMARY
I. DIRECT COST
A. MATERIAL COST = 450.75
B. LABOR COST
1. Installation of RCP = 330.250157142857
C. EQUIPMENT COST
1. Concrete Mixer = 111.662414285714
TOTAL ESTIMATED DIRECT COST = 892.662571428571
II. INDIRECT COST
A. OCM (15% OF EDC) = 133.899385714286
B. PROFIT (10% OF EDC) = 89.2662571428572
C. VAT (5% OF EDC+PROFIT+OCM ) = 55.79
TOTAL INDIRECT COST = 278.955642857143
Unit Cost for Installation of 18" dia. RCP = 1171.61821428571
Unit Cost for Fabrication and Installation of 18" RCP = 3,225.34 /pc
###
###
2,457.40
368.61
245.74
153.59
767.94
3225.342