STATUS UPDATE OF PHASE II WORKS (GIRISH PARK TO GANESH TALKIES)

Progress made so far


TOTA Cutting of 3.0m concrete portion, removal of end cross girders, welding of stiffeners
COMPONENT COMPLETED PENDING Stage #1
L and closing of access holes
18 Erection of supports, beams, strand jacks, assembling, raising up the lifting beam and
SUPERSTRUCTURES 22 nos. 4 nos. Stage #2
fitting with girder bottoms
PIER CAPS 21 nos. 2 nos. 19 Testing of jacks by lifting up the superstructure, cutting of long girders, lowering
Stage #3
down of span
PIERS 22 nos. 1 nos. 20
Stage #4 Dismantling and removal of debris of slab & girder
Stage #5 Dismantling and removal of debris of pier and pier cap

T-25.10.21 T-12.12.21 T-08.12.21 T-04.12.21 T-30.11.21 T-26.11.21 T-09.09.21


A- A- A- A- A- A- A-11.09.21

P41 P42 P43 P44 P45 P46 P47 P48 P49 P50 P51

Presence of 3 Porticos
Presence of 1 Portico

T-09.09.21
T-26.11.21
T-30.11.21
T-25.10.21

T-12.12.21

T-08.12.21

T-04.12.21
T-06.11.21
T-24.11.21

T-24.11.21

T-14.11.21

25m 35m 35m 25m 30m 32m 24.5m 24.5m 24.5m 24.5m

T-29.10.21

T-11.10.21

T-21.09.21
T-25.09.21
T-03.10.21

T-17.09.21

T-13.09.21
T-29.10.21 T-11.10.21 T-03.10.21 T-25.09.21 T-21.09.21 T-17.09.21 T-13.09.21
A- A- A- A- A- A-15.0921 A-12.09.21

T-14.11.21 T-06.11.21 T-29.10.21 T- 21.10.21 T-08.12.21 T-04.12.21 T-30.11.21 T-26.11.21 T-22.11.21 T-05.09.21
A- A- A- A- A- A- A- A- A- A-05.09.21
T-03.10.21 T-25.09.21
T-02.11.21 T-25.10.21 A- A-
T-18.11.21 T-10.11.21
A- A-
A- A- T-07.10.21 T-29.09.21 T-21.09.21 T-17.09.21 T-13.09.21 T-09.09.21
A- A- A- A-16.09.21 A-12.09.21 A-09.09.21

* 07.10.21- 11.10.21 (Modification of Beam) &12.10.21 to 15.10.21 (Durga Puja)


T-Target Date of Completion, A-Actual Date of Completion
Tentative Date of Activitiesof lowering down of each carriageway
Stages
P50-P51 P49-P50 P48-P49 P47-P48 P46-P47
N c/w S c/w N c/w S c/w N c/w S c/w N c/w S c/w N c/w C c/w S c/w
Stage #1
T 01/09 05/09 18/11 09/09 22/11 13/09 26/11 17/09 30/11 21/09 25/09
A 03/09 08/09 09/09 13/09
Stage #2
T 03/09 07/09 20/11 11/09 24/11 15/09 28/11 19/09 02/12 23/09 27/09
A 04/09 09/09 12/09 16/09
Stage #3
T 05/09 09/09 22/11 13/09 26/11 17/09 30/11 21/09 04/12 25/09 29/09
A 05/09 09/09 12/09 16/09
Stage #4
T 07/09 11/09 24/11 15/09 28/11 19/09 02/12 23/09 06/12 27/09 01/10
A 06/09 12/09 15/09
Stage #5
T 09/09 13/09 26/11 17/09 30/11 21/09 04/12 25/09 08/12 29/09 03/10
A 11/09 12/09 In Progress

*N - Northern Carriageway, S - Southern Carriageway, C - Central Carriageway


Stages
P45-P46 P44-P45 P43-P44 P42-P43 P41-P42
N c/w C c/w S c/w N c/w S c/w N c/w S c/w N c/w S c/w N c/w S c/w
Stage #1
T 04/12 29/09 03/10 17/10 21/10 25/10 29/10 02/11 06/11 10/11 14/11
A
Stage #2
T 06/12 01/10 05/10 19/10 23/10 27/10 31/10 04/11 08/11 12/11 16/11
A
Stage #3
T 08/12 03/10 07/10 21/10 25/10 29/10 02/11 06/11 10/11 14/11 18/11
A
Stage #4
T 10/12 05/10 09/10 23/10 27/10 31/10 04/11 08/11 12/11 16/11 20/11
A
Stage #5
T 12/12 07/10 11/10 25/10 29/10 06/11 14/11 24/11
A
Summary:
Phase I: Start Date: 15.06.2021; Status: Completed; Completion Date: 31.08.2021.
 Demolition works of Phase I (approx. 300m) along Strand Road from P1-P14 has been completed; 12 superstructures, 9 pier caps and 14 piers
were demolished;
Phase II: Start Date: 31.08.2021; Status: In Progress; Completion Date: ………………..
 Demolition works of Phase II {approx. 347m (280m structure + 67m retaining wall}from Girish Park to Ganesh Talkies from Piers P51-P41 has been
started from 31.08.2021. The stretch has total of 22 superstructures, 21 pier caps and 22 piers. Target is to complete the works within 30.11.2021. The
schedule may get extended till 31.12.2021 due to monsoon andPuja vacation.
 134m (i.e. 67m each on both Northern and southern side of road) of concrete retaining wall has already been demolished.4 carriageways and 2pier
already demolished.
Status of works on the current superstructure and immediately previous
Southern Carriageway (P48-P49) Southern Carriageway (P49-P50)

1. Stage #1: Cutting of 3.0m concrete portion, removal of end cross girders, welding of stiffeners and 1. Stage #1: Cutting of 3.0m concrete portion, removal of end cross girders, welding of stiffeners and
closing of access holes closing of access holes

Target Date:13.09.21 Target Date:09.09.21

Actual Date:13.09.2021 Actual Date:09.09.21

2. Stage #2: Erection of supports, beams, strand jacks, assembling, raising up the lifting beam and fitting 2. Stage #2: Erection of supports, beams, strand jacks, assembling, raising up the lifting beam and fitting
with girder bottoms with girder bottoms

Target Date:15.09.21 Target Date:11.09.21

Actual Date:16.09.21 Actual Date:12.09.21

3. Stage #3:Testing of jacks by lifting up the superstructure, cutting of long girders, lowering down of span 3. Stage #3: Testing of jacks by lifting up the superstructure, cutting of long girders, lowering down of span

Target Date:17.09.21 Target Date:13.09.21

Actual Date:16.09.21 Actual Date:12.09.21

4. Stage #4:Dismantling and removal of debris of slab & girder 4. Stage #4: Dismantling and removal of debris of slab & girder

Target Date:19.09.21 Target Date:15.09.21

Actual Date:In Progress Actual Date:15.09.21

5. Stage #4: Dismantling and removal of debris of pier 5. Stage #4: Dismantling and removal of debris of pier

Target Date:21.09.21 Target Date:17.09.21

Actual Date: Actual Date:


Lowering of carriageway P49-50(S) completed
Dismantling of Pier P50(S) in Progress
Strand Jack Erection for P47-48(S) in progress