Software Project Management Digital Assignment – I

Name: Chandan Kumar


Registration Number: 21MCA0106

Earliest Start – ES
Earliest Finish – EF
Latest Start – LS
Latest Finish - LF

Activity Span = LF – ES
Free Float – The time by which an activity can be delayed without affecting
any subsequent activity.
Free Float (FF) = Minimum ES Successor – ES Activity – Duration
Activity Interfering float (IF) = Difference between Total float – free float
Activity Span = LF – ES
Free Float – The time by which an activity can be delayed without affecting
any subsequent activity.
Free Float (FF) = Minimum ES Successor – ES Activity – Duration Activity

Interfering float (IF) = Difference between Total float – free float

Activity Diagram shown below


FF = 0 IF=0 FF = 0 IF=0 FF = 7 IF=0

3 wks 4 wks 2 wks


3 3 7 7 9
0
A 3 C 14
F 16
0 3 7

0 wks 4 wks 0 wks 9 wks 7 wks


3 wks

IF=2
FF = 0 FF = 0 IF=0
6 wks
5 wks
3 9 7 12 Finish
Start 5 B E
11 7 12

8 wks 2 wks 5 wks 0 wks

FF = 2 IF=0 FF = 0 IF=0 FF = 0 IF=0

1 wks 4 wks 3 wks


9 12 16 19
10 16
D 12 G 16 H 19
11 12 16
3 wks 2 wks 4 wks 0 wks 3 wks 0 wks

Critical Path -->