Professional Documents
Culture Documents
Pile Jetting
Pile Jetting
Pile Jetting
INTRODUCTION
METHOD
The use of the water jet (sometimes in combination with compressed air)
in a pile-driving operation differs radically in principal from driving with a
hammer or vibrator. In this simple procedure, a stream of water is
discharged near the point or along the sides of the pile, thus loosening the
surrounding soil so that the pile drops through the soil into the underlying
material. Typical pile jetting conditions are shown in Fig. 1.
When using water jets to drive piles into sand, the quantity or flow rate
of the water is a more important factor than the jet velocity. However,
when driving piles into gravel or hard clay, the flow velocity is the more
important consideration. For either procedure to be effective, the velocity
of the water jet must be sufficient to loosen the soil and make it quick, and
the volume of water must be sufficient to force the water to escape by
rising to the surface along the pile's shaft. If the volume of water is
insufficient, air jets may be added to help water travel upwards. It may also
be required, at times, to limit the horizontal radius of the escaping column
of water to about 50 cm, so that adjacent piles are not adversely affected,
particularly wooden piles. Jetting of concrete sheet piles, however, usually
does not affect adjacent, previously driven concrete sheet piles.
In the case of silty sands, pile jetting usually enhances the soil's
properties by removing some of the fine particles, thus increasing the
frictional resistance. If thick layers of clay occur within predominantly
sandy foundations, the return water could be blanketed to prevent it
escaping from the jets. In such cases, the volume of the water and its
velocity must be sufficient to wash loosened clay particles surrounding the
(a) (b) (o)
FIG. 1. Pile Jetting in Different Foundation Soil: (a) Sand; (b) Sand with Clay
Stratum; (c) Sand Stratum Underlayed with Clay: 1—Pile; 2—Jet Pipe; 3—Water
Jet; 4—Sand; 5—Clay; 6— Loose Sand; 7—Jet Hole; 8—Fine Particle Deposition
327
(a) <b)
FIG. 2. Increase in Pile Capacity: (a) Compressed Pile; (b) Anchor (Pull-Out) Pile:
1—Pile; 2—Jet Pipe; 3—Crushed Stone and/or Large Gravel; 4—Loose Sand in Jet
Hole; 5—Water Jet
pile to the surface. This will provide a clear annular space for effective
water return. This is a particularly important consideration when piles are
jetted through a soft clay stratum, ensuring that the soft clay will not close
in around the pile as it is driven. If piles are to be jetted into clay, a
sufficiently thick layer of sand should be placed on the top of the clay so '<
that the piles are driven into the clay foundation through the sand. The
sand particles will then fill the voids produced in the clay foundation by the
water jet. Subsequent dynamic driving, performed to achieve the pile's
final set, will consolidate the sand, filling the voids around the pile's shaft.
However, pile jetting is not always a successful operation for driving
piles. For example, jetting could be prevented by the presence of large
boulders in the foundation soil. During jetting, these boulders will move
down along with the jet, towards the pile's tip. Eventually, the boulders
will interfere with pile movement to the extent that the movement of both
jet pipes and pile are prevented. The presence of large materials in sand
foundations, such as cobbles and coarse gravel, could produce similar
effects. For successful jetting through a soil containing large material, it is
essential that a sufficient quantity of water is used. This phenomenon,
however, can be successfully used to increase pile capacity, by simply
feeding the large materials into the jet hole to allow concentration at
designated locations, such as at the pile tip or the bearing surface of an
anchor pile with widening at the end. This installation procedure is shown
in Fig. 2 and has been discussed by Shestopal (1959) and Tsinker (1972).
It is obvious that the amount of water required for pile driving does not
present any problem if piles are jetted offshore, such as for the construc-
tion of various marine structures. It could, however, create problems when
piles are driven on shore, including the need to dispose of large quantities
328
of water during jetting. In the latter case, sufficient means of water escape
are required.
GENERAL PROCEDURE
Conventional pile jetting requires very simple equipment as detailed in
Figs. 3 and 4. Typically, this consists of a centrifugal pump equipped with
a flow meter and pressure gage, a minimum of two steel jet pipes connected
to the pump by the same diameter flexible pressure hoses, and a winch for
1
4-^
l
FIG. 3. Typical Pile Jetting Setup: 1—Barge; 2—Pump; 3—Pile Handling Winch;
A—Jet Pipe; 5—Flexible Hose; 6—T-Joint; 7—Manometer; 8—Flow Meter;
9—Valve; 10—Pile
(o) (b)
FIG. 5. Pile Jetting; T-Shaped Con- FIG. 6. Typical Structure of Jet Hole:
crete Sheet Piles (Width of Flange 100 1—Jet Area, Soil Liquified and Sus-
cm; Depth of Web 60 cm) and Concrete pended (Zone 1); 2—Rising Flow (Zone
Battered 3:1 Anchor Piles with Widen- 2); 3—Filtration Zone (Zone 3)
ing at Ends (Widening Width 150 cm)
handling the jet pipes. The required jet pipe diameter is usually between
50-100 mm. To increase the velocity of water, the lower end of the pipe is
generally equipped with a nozzle as shown in Fig. 4. The internal diameter
of the nozzle is usually taken as 1/3 or more of the pipe's internal diameter.
Side holes of 6-10-mm diameter help to loosen the soil around the nozzle.
In the case of concrete piles, one centrally located jet pipe is sometimes
used. During the pile-driving process, the jet pipes are usually pushed into
the ground by hand, then moved up and down along the pile to obtain a
"lubricating" effect.
To obtain good results, the operator(s) shoves the jet down first, hauls it
up and down several times, then while keeping the jet down, drops the pile.
This sequence of pile driving is repeated until the pile reaches the desired
depth. Then, as stated previously, regular piles are driven the last meter or
so of depth without jetting by dynamic methods. This, however, does not
apply to sheet piles designed to resist side thrust only, such as sheet-pile
bulkheads. These techniques apply to the driving of both vertical and
battered piles.
During the past 30 years, thousands of vertical and battered concrete
piles of regular construction, and anchor piles with widening at the ends
(sometimes quite large), have been jetted into both cohesive and cohesive-
less soils. A typical example is shown in Fig. 5.
Few known investigations concerning pile jetting have been conducted
to date. The most comprehensive test results published were conducted by
Shestopal (1959) and Tsinker (1972, 1977). Shestopal basically considered
the jetting of steel pipes, while Tsinker tested concrete piles of regular
construction and anchor piles with widening at the end, jetted into sand
330
foundations. Significant results of these investigation are summarized as
follows:
WATER REQUIREMENTS
On the basis of numerous field tests, Shestopal (1959) suggested that the
following empirical equations may be used to determine the quantity of
water required for pile jetting into a sandy soil:
For a dry sand stratum (water table located below pile tip):
331
For a saturated sand stratum:
where Q = flow rate of water required for pile jetting in m3/h; D = pile
diameter, or width in m; d50 = average size of sand particles in mm; / =
designed submerged length of pile in m; and k = filtration coefficient in
m/day.
In the case of pile jetting through several soil strata, the average
coefficient of filtration can be determined from
ZiKn /„
where kn and ln = the filtration coefficient and lengths, respectively, for soil
!
[ layer n.
i Extensive experience in jetting of different kinds of concrete piles in
Eastern European countries, and particularly in the U.S.S.R., suggests the
11
water requirements and jet sizes presented in Table 1 for successful pile
driving.
For determination of the required pump's capacity, head loss in the
water-supply hoses can be computed using the following:
Q\
H=~ (3)
Ay
j where Q is the same as in Eqs. 1 and 2;lh = total length of the water supply
| hoses in m; and KT = empirical coefficient dependent upon hose material
, obtained from Table 2.
The pressure loss in the jet pipes and in the manifold can be determined
using the data given in Table 3. If pressure loss in jet pipes is excessive and
1
velocity exceeds 5 m/s, then it is necessary to increase the number and/or
[ diameter of jet pipes. Selection of jet pipe diameter and pump capacity
TABLE 1. Volume of Water and Head Required for Pile Jetting (Marine Structures
Handbook 1972)
PILE SECTION (DIAMETER)
30-50 cm 50-70 cm
Head at Jet pipe Flow Jet pipe Flow
Depth tip of internal rate of internal rate of
of pile nozzle diameter water diameter water
Soil driving (MPa) (mm) (m3/min) (mm) (m3/mln)
(1) (2) (3) (4) (5) (6) (7)
Silt; silty sand; 5-15 0.4-0.8 37 0.4-1 50 1-1.5
fine sand; soft 15-25 0.8-1.0 68 1-1.5 80 1.5-2
clay; sand
Sand and hard 5-12 0.6-1.0 50 1-1.5 68 1.5-2.0
sand loam
Sand with gravel 15-25 1.0-1.5 80 1.5-2.5 106 2-3
332
TABLE 2. Factor KT Value for Different Hoses (Marine Structures Handbook 1972)
Hose Material
Jet pipe internal diameter (mm) Rubberized Rubber
0) (2) (3)
33 33 50
50 133 200
65 567 850
76 1,333 2,000
ACKNOWLEDGMENTS
APPENDIX I. REFERENCES
334