Item Description Unit Qty Status

1 11 KV HT Panel Nos 2 Cable laying and termination completed.

2 Distribution Transformers

Oil Filtration and Oil testing done ,Installed and ready to


2.1 6.6KV/ 0.433 V, 1000 KVA Nos 3 energise. Format III Checklist in progress
2.2 Lighting Transformers Nos 2 Installed and completed testing ,Ready to energise

Installed and completed testing , Bus bar tightness is


done as per Vendor torque recommendation in
3 Bus duct Set 3 presence of .Ready to energise

Installed and completed testing ,Bus bar tightness is


done as per Vendor torque recommendation in
presence of and EIL EIL approved Relay setting yet to
receive from Engg. Ready to energise with default
4 PCC Panel Nos 1 settings. PCC to MCC cable termination complete

Installed and completed testing ,Bus bar tightness is


done as per Vendor torque recommendation in
presence of and approved Relay setting yet to receive
5 EPMC Panel Nos 1 from Engg. Ready to energise with default settings.

Installed and completed testing ,Bus bar tightness is


done as per Vendor torque recommendation in
6 MCC Panel Nos 1 presence of and Ready to energise
Installed and Cable terimination started for recently
7 VFD Panel Nos 23 recd. 7 nos VFD.

Battary Charger Panel ( battarycharger- Erection done including battaary bank .But temporary
1+charger-2+ DCDB Common + 2 set of connection made directly to our DCDB from Client
battary bank for Switchgear -1 set. and DCDB till commissioning of our Battery Charger by
8 Critical DC Lighting - 1 set. set 2 Vendor
UPS Panel (UPS-1 +UPS -2 + ACDB-1 Erection done with battary bank and ACDBs. Waiting
9 +ACDB -2 ) and 2 set of battary bank Nos 1 for Vendor for commissioning
10 SAS Panel Nos 1
11 MLDB/ELDB/ ASB Panel- 01 each Nos 3 Erection done ,Testing done, ready to energise
12 Lighting / Power Panel Nos 8 Lighting DBs are not received
13 LPBS and packages control panel Nos 75 Erected
14 Cable Trays Nos 1380 Check list for Format III in progress
15 Earth Pit Nos 12 Stenciling balance ,Testing done for Earth pit resistance
16 Earth strips ,wires for motors and LPBS Mtrs 3587 Check list for Format III in progress
17 Power & Control Cables Mtrs 63173 Check list for Format III in progress
18 Lighting Poles 9.0 M Height Nos 29 MCBs terminals yet to be receive for termination
19 Lighting Poles 2.5 M Height Nos 96 Check list for Format III in progress
20 Bracket mounted Pipes for fixtures Nos 20 Check list for Format III in progress
21 Lighting Fixtures Nos 305 Check list for Format III in progress
22 Cable Termination Nos 1800 Lighting DBS are not hence termn. Balance
23 EOT Crane / Hoist Nos 3 Vendor need for commissioning and load test
UF Feed pumps -5 ns + UF Backwash pumps -2 nos
24 Motors Nos 78 balance to receive.
25 Cathodic Protection Not in scope

26 Fir Alarm system Lot 1 Free issue from and erection is inscope. Work balance
Rectification of Field Test Reports for
30 PTs, CTs Done and under certification by