LAMPIRAN

PERHITUNGAN MANUAL

A. Forecast

 Single Exponential Smoothing

{(0,1)362 + (0,9) 373} = 371,9 ≈ 372

{(0,1)329 + (0,9) 371,9} = 367,61 ≈ 368

{(0,1)377 + (0,9) 367,61} = 368,549 ≈ 369

{(0,1)374 + (0,9) 368,549} = 369,0941 ≈ 370

{(0,1)382 + (0,9) 369,0941} = 370,3847 ≈ 371

{(0,1)364 + (0,9) 370,3847} = 369,7462 ≈ 370

{(0,1)347 + (0,9) 369,7462} = 367,4716 ≈ 368

{(0,1)349 + (0,9) 367,4716} = 365,6244 ≈ 366

{(0,1)337 + (0,9) 365,6244} = 362,762 ≈ 363

{(0,1)359 + (0,9) 362,762} = 362,3858 ≈ 363

{(0,1)367 + (0,9) 362,3858} = 362,8472 ≈ 363

 Moving Average

(329+362+373)/3 = 354,6667 ≈ 355

(377+329+362)/3 = 356

(374+377+329)/3 = 360

(382+374+377)/3 = 377,6667 ≈ 378

(364+382+374)/3 = 373,3333 ≈ 374

(347+364+382)/3 = 364,3333 ≈ 365

(349+347+364)/3 = 353,3333 ≈ 354


(337+349+347)/3 = 344,3333 ≈ 345

(359+337+349)/3 = 348,3333 ≈ 349

(367+359+337)/3 = 354,3333 ≈ 355

 Metode Past Data

 Forcast = Produksi Aktual t-1 = 373

 Forcast = Produksi Aktual t-1 = 362

 Forcast = Produksi Aktual t-1 = 329

 Forcast = Produksi Aktual t-1 = 377

 Forcast = Produksi Aktual t-1 = 374

 Forcast = Produksi Aktual t-1 = 382

 Forcast = Produksi Aktual t-1 = 364

 Forcast = Produksi Aktual t-1 = 347

 Forcast = Produksi Aktual t-1 = 349

 Forcast = Produksi Aktual t-1 = 337

 Forcast = Produksi Aktual t-1 = 359

 Forcast = Produksi Aktual t-1 = 367

 Verifikasi

a) Yi-Ẏi

 Yi-Ẏi = 362-373 = -11

 Yi-Ẏi = 329-371,9 = -42,9

 Yi-Ẏi = 377-367,61 = 9,39

 Yi-Ẏi = 374-368,549 = 5,451

 Yi-Ẏi = 382-369,0941 = 12,9059

 Yi-Ẏi = 364-370,3847 = -6,3847


 Yi-Ẏi = 347-369,7462 = -22,7462

 Yi-Ẏi = 349-367,4716 = -18,4716

 Yi-Ẏi = 337-365,6244 = -28,6244

 Yi-Ẏi = 359-362,762 = -3,762

 Yi-Ẏi = 367-362,3858 = 4,6142

b) ̅
M̅ ̅
̅R̅

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |329 − 371,9| − (362 − 373)

= -11

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |377 − 367,61| − (329 − 371,9)

= -42,9

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |374 − 368,549| − ( 377 − 367,61)

= 9,39

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |382 − 369,0941| − ( 374 − 368,549)

= 5,451

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |364 − 370,3847| − (382 − 369,0941)

= 19,2906

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |347 − 369,7462| − ( 364 − 370,3847)

= 16,3615
̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |349 − 367,4716| − ( 347 − 369,7462)

= 4,2746

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |337 − 365,6244| − (349 − 367,4716)

= 10,1528

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |359 − 362,762| − (337 − 365,6244)

= 24,8624

̅M̅ ̅
̅R̅ = |𝑑′𝑡 − 𝑑′𝑖| − ( 𝑑′𝑡−1 − 𝑑′𝑖−1)

= |367 − 362,3858| − ( 359 − 362,762)

= 8,3762

 Hasil Kesalahan Single Exponential Smoothing

a) Yi-Ẏi

 Yi-Ẏi = 362 – 373 = -11

 Yi-Ẏi = 329 - 371,9 = -42,9

 Yi-Ẏi = 377 - 367,61 = 9,39

 Yi-Ẏi = 374 - 368,549 = 5,451

 Yi-Ẏi = 382 - 369,0941 = 12,9059

 Yi-Ẏi = 364 - 370,3847 = -6,3847

 Yi-Ẏi = 347 - 369,7462 = -22,7462

 Yi-Ẏi = 349 - 367,4716 = -18,4716

 Yi-Ẏi = 337 - 365,6244 = -28,6244

 Yi-Ẏi = 359 - 362,762 = -3,762


 Yi-Ẏi = 367 - 362,3858 = 4,6142

b) 100 x (Yi−Ẏi)
( )
𝑦𝐼

 100 (362−373)
( ) = -3,038674033
x 362

 100 x
(329−371,9)
( ) = -13,03951368
329

 100 x
(377−367,61)
( ) = 2,49071618
377

 100 x
(374−368,549)
( ) = 1,457486631
374

 100 x
(382−369,0941)
( ) = 3,378507853
382

 100 x
(364−370,3847)
( ) = -1,754038462
364

 100 x
(347−369,7462)
( ) = -6,555100865
347

 100 x
(349−367,4716)
( ) = -5,292722063
349

 100 x
(337−365,6244)
( ) = -8,49388724
337

 100 x (359− 362,762)


( ) = -1,047910864
359

 100 x
(367−362,3858)
( ) = 1,257275204
367

 Hasil Kesalahan Single Exponential Smoothing

a) Yi-Ẏi

 Yi-Ẏi = 377 - 354,6667= 22,3333

 Yi-Ẏi = 374 - 356 = 18

 Yi-Ẏi = 382 - 360 = 22

 Yi-Ẏi = 364 - 377,6667 = -13,6667

 Yi-Ẏi = 347 - 373,3333 = -26,3333


 Yi-Ẏi = 349 - 364,3333 = -15,3333
 Yi-Ẏi = 337 - 353,3333 = -16,3333

 Yi-Ẏi = 359 - 344,3333 = 14,6667

 Yi-Ẏi = 367 - 348,3333 = 18,6667

b) 100 x (Yi−Ẏi)
( )
𝑦𝐼

 100 x (377−354,6667)
( ) = 5,923952255
377
 100 x
(374−356)
( ) = 4,812834225
374

 100 x
(382−360)
( ) = 5,759162304
382

 100 x (364−377,6667)
( ) = -3,754587912
364

 100 x (347−373,3333)
( ) = -7,588847262
347
 100 x
(349−364,3333)
( ) = -4,393495702
349

 100 x (337−353,3333)
( ) = -4,846676558
337

 100 x
(359− 344,3333)
( ) = 4,085431755
359

 100 x
(367− 348,3333)
( ) = 5,086294278
367

 Hasil Kesalahan Past Data

a) Yi-Ẏi

 Yi-Ẏi = 362 – 373 = -11

 Yi-Ẏi = 329 - 362 = -33

 Yi-Ẏi = 377 - 329 = 48

 Yi-Ẏi = 374 - 377 = -3

 Yi-Ẏi = 382 - 374 = 8

 Yi-Ẏi = 364 - 382 = -18


 Yi-Ẏi = 347 - 364 = -17

 Yi-Ẏi = 349 - 347 = 2

 Yi-Ẏi = 337 - 349 = -12

 Yi-Ẏi = 359 - 337 = 22

 Yi-Ẏi = 367 - 359 = 8

b) 100 x (Yi−Ẏi)
( )
𝑦𝐼

 100 (362−373)
( ) = -3,038674033
x 362

 100 x
(329 − 362 )
( ) = -10,03039514
329

 100 (377−329)
( ) = 12,73209549
x 377

 100 x (374−3377)
( ) = -0,802139037
374
 100 x
(382−374)
( ) = 3,378507853
382

 100 (364−382)
( ) = 2,094240838
x 364

(347−364)
( ) = -4,899135447
 100 347
x (349−347)

 100
x ( ) = 0,573065903
349

 100 (337−349)
( ) = -3,560830861
x 337

 100 x
(359− 337)
( ) = 6,128133705
359

 100 (367−359)
( ) = 2,179836512
x 367
B. Master Requirement Planning (MRP)

1) MRP Meja Troli Level 0

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (600 – 363)

= 237

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-2

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (237 – 363 + 410)

= 284

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 237)

= 156

d. Schedule Receipt = 0
e. Planned Order Release = 410

 Bulan Ke-3

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (284 – 363 + 410)

= 331

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 284)

= 109

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-4

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (331 – 363 + 410)

= 378

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410
c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 331)

= 62

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-5

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (378 – 363 + 410)

= 425

b. Planned order receipts = 0

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 378)

= 15

d. Schedule Receipt = 0

e. Planned Order Release = 0

 Bulan Ke-6

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (425 – 363)

= 62
b. Planned order receipts = 0

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 425)

= -32 ≈ 0 (Karena bernilai negatif, diubah menjadi 0)

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-7

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (62 – 363 + 410)

= 109

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 62)

= 331

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-8

a. Project on hand
- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (109 – 363 + 410)

= 156

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 109)

= 284

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-9

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (156 – 363 + 410)

= 203

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 156)

= 237
d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-10

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (203 – 363 + 410)

= 250

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 203)

= 190

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-11

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (250 – 363 + 410)

= 297

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410
c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 250)

= 143

d. Schedule Receipt = 0

e. Planned Order Release = 410

 Bulan Ke-12

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (297 – 363)

= 344

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 410

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (363 + 30) – (0 + 297)

= 96

d. Schedule Receipt = 0

e. Planned Order Release = 0

2) MRP Pegangan Level 1

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (700 – 410)
= 290

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-2

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (290 – 410 + 600)

= 480

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 290)

= 370

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-3

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (480 – 410 + 600)


= 670

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = Net requirements = (gross requirement + safety stock) –

(schedule receipt + project on hand sebelumnya)

= (410 + 250) – (0 + 480)

= 180

d. Schedule Receipt = 0

e. Planned Order Release = 0

 Bulan Ke-4

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (670 – 410)

= 260

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0

 Bulan Ke-5

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (260 – 0)

= 260
b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-6

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement

+ lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (260 – 410 + 600)

= 450

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 260)

= 400

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-7

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement

+ lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (450 – 410 + 600)

= 640
b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 450)

= 210

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-8

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement

+ lot sizing) (digunakan apabila Project On Hand tidak memenuhi)

= (640 – 410 + 600)

= 830

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 640)

= 20

d. Schedule Receipt = 0

e. Planned Order Release = 0

 Bulan Ke-9

a. Project on hand
- Project on hand = (project on hand sebelumnya – gross requirement)

= (830 – 410) = 420

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-10

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement

+ lot sizing) (digunakan apabila Project On Hand tidak memenuhi

= (420 – 410 + 600)

= 240

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 420)

= 240

d. Schedule Receipt = 0

e. Planned Order Release = 600

 Bulan Ke-11

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

(digunakan apabila Project On Hand tidak memenuhi)


= (610 – 410 + 600)

= 800

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 600

c. Net requirements = (gross requirement + safety stock) – (schedule receipt +

project on hand sebelumnya)

= (410 + 250) – (0 + 610)

= 50

d. Schedule Receipt = 0

e. Planned Order Release = 0

 Bulan Ke-12

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (800 – 0)

= 800

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0

3) MRP Pipa Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (4000 – 3000)
= 1000

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 3750

4) MRP Tutup Pipa Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (2000 – 1200)

= 800

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 4000

5) MRP Siku Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (9500 – 2400)

= 7100

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0
e. Planned Order Release = 0

6) MRP Badan Meja Level 1

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (700 – 410)

= 290

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 600

7) MRP Triplek Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1650 – 1200)

= 450

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0

8) MRP Tiang Penyangga Level 2

 Bulan Ke-1

a. Project on hand
- Project on hand = (project on hand sebelumnya – gross requirement)

= (2000 – 600)

= 1400

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0

9) MRP Tutup Pipa Level 3

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1500 – 0)

= 1500

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 15000

10) MRP Mur Level 3

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1590 – 0)

= 1590

b. Planned order receipts = 0


c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 50000

11) MRP Baut Level 3

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1590 – 0)

= 1590

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 50000

12) MRP Pipa Level 3

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1590 – 0)

= 1590

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 2000

13) MRP Sambungan T Level 3


 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (1590 – 0)

= 1590

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 6000

14) MRP Roda Level 1

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement)

= (700 – 410)

= 290

b. Planned order receipts = 0

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 600

15) MRP Roda Penggerak Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (Digunakan jika on hand tidak memenuhi)


= (700 – 1200 + 1500)

= 1000

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 1500

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0

16) MRP Roda Statis Level 2

 Bulan Ke-1

a. Project on hand

- Project on hand = (project on hand sebelumnya – gross requirement +

lot sizing) (Digunakan jika on hand tidak memenuhi)

= (700 – 1200 + 1500)

= 1000

b. Planned order receipts = lot size (jika project on hand tidak memenuhi)

= 1500

c. Net requirements = 0

d. Schedule Receipt = 0

e. Planned Order Release = 0