Calculo de Flete Terrestre

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

FLETE TERRESTRE HUIRONAYCCASA - PACOBAMBA

A. CALCULO POR PESO


MATERIAL UNIDAD CANTIDAD P.U P.T
PETROLEO D-2 gal 724.86 7.00 5,074.04
ALAMBRE NEGRO N° 16 kg 8.82 1.00 8.82
ALAMBRE NEGRO N° 8 kg 3.50 1.00 3.50
ACERO DE
CLAVOS 2" REFUERZO
- 4" fy=4200 kg/cm2 GRADO 60 kg 126.68 1.00 126.68
kg 20.13 1.00 20.13
CLAVOS DE CALAMINA kg 1.00 1.00 1.00
REJILLA METALICA 0.60 m X 0.60 m und 1.00 5.00 5.00
TAPA METÁLICA C/MARCO DE 0.80m x 0.90m, e=1/8" und 2.00 10.00 20.00
ESCALERA METALICA DE 1.50 X 1.60 e=1/16" und 1.00 25.00 25.00
TEE HDPE 90mm und 1.00 5.00 5.00
CODO HDPE 90mm und 2.00 5.00 10.00
TAPON HDPE 90mm und 2.00 5.00 10.00
ADAPTADOR PVC-SAP C/R 2" und 2.00 3.00 6.00
ADAPTADOR PVC-SAP S/P 3" und 2.00 2.00 4.00
CONO DE REBOSE 90MMX110MM und 2.00 2.00 4.00
TUBERIA HDPE NTP ISO 4427 PE-80 PN6, D=90mm m 104.48 2.00 208.95
UNION PVC BRIDA - CAMPANA 3" X 90mm und 2.00 5.00 10.00
CANASTILLA DE SALIDA PVC Ø 90MM und 2.00 1.00 2.00
REDUCCION HDPE 250MM - 200MM und 1.00 2.00 2.00
TEE PVC-SAL 3" und 1.00 2.00 2.00
GEOMEMBRANA HDPE e=1.5mm m2 1,682.55 1.00 1,682.55
GEOTEXTIL NO TEJIDO 200 GRAMOS/CM2 m2 1,780.90 0.80 1,424.72
TUBERIA PVC-U NTP 4435 SN4, D=90MM m 21.00 12.00 252.00
TUBERIA PVC-U NTP 4435 SN4, D=63MM m 10.00 2.00 20.00
CALAMINA pln 20.00 8.00 160.00
CEMENTO PORTLAND TIPO IP (42.5 kg) bol 34.47 42.50 1,464.76
YESO BOLSA 28 kg bol 13.55 15.00 203.31
PERNO HEXAGONALES DE 3/4 X 3 1/2" pza 9.00 0.10 0.90
IMPERMEABILIZANTE gal 0.74 5.00 3.72
MADERA TORNILLO p2 270.00 3.00 810.00
MADERA NACIONAL P/ENCOFRADO-CARP p2 25.98 3.00 77.94
TRIPLAY DE 1.20X2.40 m X 6 mm und 31.50 10.00 315.00
TRIPLAY DE 1.20X2.40 m X 18 mm pln 1.40 10.00 14.01
MADERA CORRIENTE p2 40.66 5.00 203.31
PINTURA ESMALTE gal 3.14 4.00 12.57
NIPLE DE FIERRO GALVANIZADO DE 2" und 2.00 2.00 4.00
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 2" und 2.00 1.00 2.00
VALVULA COMPUERTA DE 2" und 1.00 1.00 1.00
VALVULA COMPUERTA DE 3" und 1.00 1.00 1.00
CODO PVC SAL 2"x90" und 0.00 2.00 0.00
CODO PVC SAL 3"x90" und 1.00 2.00 2.00
TOTAL (KG) 12,202.93
TOTAL (TON) 12.20
FACTOR DE ESPONJAMIENTO 1.10
CAPACIDAD DEL VOLQUETE (M3) 6.00
EFICIENCIA 0.90
RENDIMIENTO 5.45
NUMERO DE VUELTAS 2.00

B. CALCULO POR VOLUMEN - TUBERIA


UNIDAD DE (2.20 M. x 6 M.) DE CARROCERIA, CON H= 2.405 M.
CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML ML DE TUBOS N° DE TUBOS N° DE VIAJES
TUBERIA PVC 6" 6.00 U 15.00 6.00 2.50 0.42
TOTAL NUMERO DE VIAJES 0.42
REDONDEAR NUMERO DE VIAJES 0.00

C. CALCULO POR VOLUMEN - AGREGADO


UNIDAD DE (15M3)
CAPACIDAD DEL CAMION EN AGREGADOS / VIAJE CAPACIDAD UND CANTIDAD N° DE VIAJES
PIEDRA CHANCADA 1/2"-3/4" 8.00 8.60 1.07
PIEDRA MEDIANA 8.00 0.26 0.03
ARENA FINA 8.00 0.25 0.03
ARENA GRUESA 8.00 2.81 0.35
HORMIGON SELECCIONADO DE RIO 8.00 0.36 0.05
TOTAL NUMERO DE VIAJES 1.54
FLETE TERRESTRE HUIRONAYCCASA - PACOBAMBA

REDONDEAR NUMERO DE VIAJES 2.00

FLETE TERRESTRE
Por Peso Kg C.U PARCIAL
12,202.93 0.25 3,050.73
Por Volumen N° viajes C.U PARCIAL
TUBERIA 0.00 60.00 0.00
AGREGADO 2.00 1,250.0 2,500.00
TOTAL 5,250.7
FLETE RURAL HUIRONAYCCASA - PACOBAMBA

UNIDAD DE MEDIDA
MATERIAL CANTIDAD PESO UNITARIO PESO TOTAL
(BLS, LATAS, KG, ETC)

PETROLEO D-2 gal 724.86 7.00 5,074.04


ALAMBRE NEGRO N° 16 kg 8.82 1.00 8.82
ALAMBRE NEGRO N° 8 kg 3.50 1.00 3.50
ACERO
CLAVOSDE
2" REFUERZO
- 4" fy=4200 kg/cm2 GRADO 60 kg 126.68 1.00 126.68
kg 20.13 1.00 20.13
CLAVOS DE CALAMINA kg 1.00 1.00 1.00
REJILLA METALICA 0.60 m X 0.60 m und 1.00 5.00 5.00
TAPA METÁLICA C/MARCO DE 0.80m x 0.90m, e=1/8" und 2.00 10.00 20.00
ESCALERA METALICA DE 1.50 X 1.60 e=1/16" und 1.00 25.00 25.00
TEE HDPE 90mm und 1.00 5.00 5.00
CODO HDPE 90mm und 2.00 5.00 10.00
TAPON HDPE 90mm und 2.00 5.00 10.00
ADAPTADOR PVC-SAP C/R 2" und 2.00 3.00 6.00
ADAPTADOR PVC-SAP S/P 3" und 2.00 2.00 4.00
CONO DE REBOSE 90MMX110MM und 2.00 2.00 4.00
TUBERIA HDPE NTP ISO 4427 PE-80 PN6, D=90mm m 104.48 2.00 208.95
UNION PVC BRIDA - CAMPANA 3" X 90mm und 2.00 5.00 10.00
CANASTILLA DE SALIDA PVC Ø 90MM und 2.00 1.00 2.00
REDUCCION HDPE 250MM - 200MM und 1.00 2.00 2.00
TEE PVC-SAL 3" und 1.00 2.00 2.00
GEOMEMBRANA HDPE e=1.5mm m2 1,682.55 1.00 1,682.55
GEOTEXTIL NO TEJIDO 200 GRAMOS/CM2 m2 1,780.90 0.80 1,424.72
TUBERIA PVC-U NTP 4435 SN4, D=90MM m 21.00 12.00 252.00
TUBERIA PVC-U NTP 4435 SN4, D=63MM m 10.00 2.00 20.00
CALAMINA pln 20.00 8.00 160.00
CEMENTO PORTLAND TIPO IP (42.5 kg) bol 34.47 42.50 1,464.76
YESO BOLSA 28 kg bol 13.55 15.00 203.31
PERNO HEXAGONALES DE 3/4 X 3 1/2" pza 9.00 0.10 0.90
IMPERMEABILIZANTE gal 0.74 5.00 3.72
MADERA TORNILLO p2 270.00 3.00 810.00
MADERA NACIONAL P/ENCOFRADO-CARP p2 25.98 3.00 77.94
TRIPLAY DE 1.20X2.40 m X 6 mm und 31.50 10.00 315.00
TRIPLAY DE 1.20X2.40 m X 18 mm pln 1.40 10.00 14.01
MADERA CORRIENTE p2 40.66 5.00 203.31
PINTURA ESMALTE gal 3.14 4.00 12.57
NIPLE DE FIERRO GALVANIZADO DE 2" und 2.00 2.00 4.00
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 2" und 2.00 1.00 2.00
VALVULA COMPUERTA DE 2" und 1.00 1.00 1.00
VALVULA COMPUERTA DE 3" und 1.00 1.00 1.00
CODO PVC SAL 2"x90" und 0.00 2.00 0.00
CODO PVC SAL 3"x90" und 1.00 2.00 2.00
TOTAL 12,202.93

PORCENTAJE DE MATERIALES QUE SERAN TRASLADADOS 50.00%


CAPACIDAD DE CARGA DE PEON (POR VIAJE) 20
COSTO POR VIAJE 5
TOTAL TRASLADADO 6101.46
NUMERO DE VIAJES 305.07
COSTO TOTAL 1525.37

You might also like