International Journal of Engineering & Technology, 7 (3.

10) (2018) 36-39

International Journal of Engineering & Technology


Website: www.sciencepubco.com/index.php/IJET

Research paper

Analyzing Inventory Material Management Control Techniques


on Residential Construction Project Using SPSS
T.Subramani1*, T.Suresh Kumar2
1*
Managing Director, Priyanka Associates (Civil Engineers and Valuers), Salem, TamilNadu, India.
2
CEO, Suresh Associates( Civil Engineers and Valuers), Salem, TamilNadu, India.
*
Corresponding author: E-mail: tsmcivil2007@gmail.com

Abstract

Building Construction materials adopted 50% of cost from the total estimation of the project. Estimated Cost and planned schedule can
be achieved by effective material management. The project team must be understood the goals and efficient material management
techniques for successful project execution. A well planned material management possible by on time delivery and equipment to the job
site and improved workforce planning increased labor productivity, planned schedules and minimum cost. Questionnaire were prepared
for data analysis based on Likert’s scale 25 respondents were answered the questionnaire. Collected data analyzed using SPSS.To reveal
the respondents responses for enhance the analysis results used there are Frequency analysis, Factor analysis, and reliability analysis.
Results will be obtained and also recommendations will be suggested.

Keywords: Analyzing, Inventory, Control Techniques, Project and SPSS.

1. Introduction

1.1. Overview of Material Management

Materials management is a essential factor of the construction


projects. Construction companies should understand the
importance of material management techniques and efficiency of
project execution. Many of the construction projects were
affected by delays and cost overrun. A good material
management decided by such as on time delivery of materials, pre
planned working techniques, Proper scheduling and budgeted
cost construction. It is critical for the contractor to remember that
great distinction within the date that the material turned into
requested or date when the acquisition order become made, and
the time, at which the material could be brought, as a
consequence fabric control is a key of project management.
“Material management is described as the procedure to offer
right fabric at proper region at proper time in proper quantity
with a purpose to limit the price of assignment”. Material
Fig.1: Methodology
management is worried with the planning, identity, procuring,
storage, receiving and distribution of material.
3. Software Used
2. Methodology
3.1. SPSS
Fig.2 shows the methodology adopted in this study.
SPSS is software program for editing and studying all sorts of
statistics. Those statistics may additionally come from basically
any source: medical studies, a patron statistics base, maybe the
server log documents of a site. SPSS can open all record codecs
which are usually used for based data which includes,
Spread sheets from MS Excel or Open office.
• Plain text documents (.txt or .csv).
• Relational (sq.) databases.
Copyright © 2018 Authors. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted
use, distribution, and reproduction in any medium, provided the original work is properly cited.
International Journal of Engineering & Technology 37

• Stata and SAS. 5. Inventory Control


4. Questionnaire Inventory control or manipulate refers back to the management of
idle resources that have future monetary cost. Rather, inventory
1. Do you support the use of lean inventory system in your may be defined as usable but idle assets that have monetary cost.
company? inventory control is one critical issue of the full control of an
 Yes corporation.
 No
2. Is inventory management automated in your company? 6. SPSS Analysis Results
 Yes
 No 6.1. Frequency Analysis
3. Is procurement staff well trained on inventory management?
 Yes Fig.2 shows the inputs for frequency analysis.
 No
4. Do you have procure0ment performance measurement
procedure in your company?
 Yes
 No
5. Does your company follow any analysis for inventory
management?
 Yes
 No
6. If it follows then it is superior to conventional method of
procurement.
 Yes
 No
7. Does your company procure stock when a project is
undertaken?
 Yes
 No
8. Does your company follow safety procedure to store the stock?
 Yes Fig.2: Inputs for frequency analysis
 No
9. How many days before the project start stocks are mobilized? 6.2. Lean Inventory System
 5Days
 10Days Table 1 shows the results for lean inventory system.
 15Days
 1Month Table 1: Results for Lean inventory system
10. Does your company follow EOQ (Economic Order Quantity)
analysis?
 Yes
 No
11. Which type of material management technique used in your
company?
 JIT
 ABC analysis
 Drop shipping
 Cross-docking

12. Does your company follow ABC analysis?


 Yes
 No

13. How much waste is generated for a medium project (MT)?


 0.1
 0.1– 0.5
 0.5–1
 >1
14. Is there is a separate division for inventory management in Fig.3 shows the graph of various inventory related questionnaires.
your company?
 Yes
 No

Fig.3: Graph of various inventory related Questionnaires


38 International Journal of Engineering & Technology

6.2.1. Frequently Used Material Management Technique Fig.7 shows the inputs for factor analysis.

Table 2 shows the frequently used material management


techniques.

Table 2: Analysis results for material management technique

Fig.4 shows the pie chart of material management techniques. Fig.7: Inputs for factor analysis

Fig.8 shows the inputs for factor analysis.

Fig.4: Pie chart for material management technique

6.2.2. Major Problem of Material Takeoff

Table 3 shows the analysis results for material takeoff. Fig.8: Inputs for factor analysis

Table 3: Analysis results for material takeoff Table 4 shows the correlation matrix.

Table 4: Correlation Matrix

Fig.5 shows the pie chart for material takeoff.

Table 5 shows the total variance explained.

Table 5: Total variance explained

Fig.5: Pie chart shows material takeoff


Table 6 shows the component matrix.
6.3. Factor Analysis Table 6: Component matrix

The important thing concept of element analysis is that more than


one discovered variables have comparable styles of responses
because they're all associated with a latent (i.e. no longer
immediately measured) variable. Any issue with an eigen value
≥1 explains greater variance than a single observed variable.
Fig.6 shows the inputs for component evaluation.

6.4. Reliability Analysis

The evaluation on reliability is referred to as reliability analysis.


Reliability evaluation is determined through obtaining the
percentage of systematic variant in a scale, which may be finished
Fig.6: Inputs for factor analysis through figuring out the association among the ratings acquired
International Journal of Engineering & Technology 39

from distinctive administrations of the dimensions. accordingly, if [4] T.Subramani.,D.S.StephanJabasingh,J.Jayalakshmi. “Analysis Of


the affiliation in reliability evaluation is high, the size yields Cost Controlling In Construction Industries By Earned Value
regular outcomes and is consequently reliable. Table 7 shows the Method Using Primavera”, International Journal of Engineering
Research and Applications, Volume. 4, Issue. 6 (Version 5), pp 145
reliability analysis.
-153, 2014.
[5] T.Subramani.T, P.T. Lishitha., M.Kavitha., “Time Overrun And
Table 7: Reliability analysis Cost Effectiveness In The Construction Industry”, International
Journal of Engineering Research and Applications, Volume. 4,
Issue. 6 (Version 5), pp 111- 116, 2014.
[6] T.Subramani. , R.Lordsonmillar., “Safety Management Analysis In
Construction Industry”, International Journal of Engineering
Research and Applications, Volume. 4, Issue. 6 (Version 5), pp
117- 120, 2014.
[7] T.Subramani., A.Sarkunam.A, J.Jayalakshmi. “Planning And
Scheduling Of High Rise Building Using Primavera” , International
Journal of Engineering Research and Applications, Volume. 4,
Issue. 6 (Version 5), pp 134 - 144, 2014.
Table 8 shows the inter-item correlation matrix. [8] T.Subramani.,P.S.Sruthi., M.Kavitha. “Causes Of Cost Overrun In
Construction”, IOSR Journal of Engineering, Volume. 4, Issue. 6
Table 8: Inter-Item correlation matrix (Version 3), pp 1 - 7, 2014
[9] T.Subramani, M.Sekar , " Preplanning And Scheduling Of Road
Construction By Using PPM" , International Journal of Application
or Innovation in Engineering & Management (IJAIEM) , Volume 4,
Issue 5, pp. 234-244 , 2015
[10] T.Subramani, V.Jayaraman , " Analysis Of Construction Workers
Migrate From Industries" , International Journal of Application or
Innovation in Engineering & Management (IJAIEM) , Volume 4,
Issue 5, pp. 274-283 , 2015
[11] T.Subramani, S.Tamizhanban , " Supply Chain Management In
Construction Site By Using SPSS Software" , International Journal
of Emerging Trends & Technology in Computer Science
(IJETTCS) , Volume 5, Issue 3, pp. 182-193 , 2016.
7. Results & Discussions [12] T.Subramani, S.R.Rajiv , " Improving Construction Efficiency And
Productivity Of Industry Using SPSS" , International Journal of
Application or Innovation in Engineering & Management (IJAIEM)
The attitude of owners, consultants, and contractors were found
, Volume 5, Issue 5, pp. 239-250 , 2016 .
by using a questionnaire-based survey towards factors affecting [13] T.Subramani, K.Chinnadurai , " Construction Management And
the performance of construction projects. Based on respondent’s Scheduling Of Residential Building Using Primavera" International
response, frequently used material management technique is JIT Journal of Application or Innovation in Engineering &
analysis 60.0 % positive most of the contractors are accepted JIT Management (IJAIEM) , Volume 4, Issue 5, pp. 188-198 , 2015
analysis gives better result compared to other techniques. From [14] T.Subramani, Kurian Jacob , " Analysis Of Risk, Threshold And
above results major factor affecting material take off is lack of Issues And Monitoring Schedule Of Building Construction Using
communication - 66.7 %.Project undertaken per year (Standard PPM Software" , International Journal of Emerging Trends &
Technology in Computer Science (IJETTCS) , Volume 5, Issue 3,
deviation = 1.18, mean = 3.13), major difficulties when handling
pp. 171-181 , 2016.
material on-site (Standard deviation = 0.45, mean = 1.26). [15] T.Subramani, M. Muhammed Ansar, S.Priyanka , " Impact Of
Prefabricated Technology And Equipment On The Profitability
8. Conclusion Using Primavera " , International Journal of Emerging Trends &
Technology in Computer Science (IJETTCS), Volume 6, Issue 3,
May - June 2017 , pp. 176-185 , ISSN 2278-6856.
From this investigation, material quality plays an important role. [16] T.Subramani, V.Annamalai , S.Priyanka , " Management
Enhance it’s based on cost, time, and quality performance. Information And Communication Technology In Construction
Remedies found for above stated problems regarding material Engineering Of Structures Using Primavera " , International Journal
management through implementing inventory management such of Emerging Trends & Technology in Computer Science
as inventory list & purchase list, material usage calculation, (IJETTCS), Volume 6, Issue 3, May - June 2017 , pp. 186-197 ,
safety storage. This is due to the fact bad coping with of ISSN 2278-6856.
[17] T.Subramani, V.Bhaskaran Nair, A.David, B.Mohamed Ghouse,
production substances influences the overall performance of N.Siva Kumar , " A Study Of Inventory Management System In
creation tasks in terms of time, budget (cost), pleasant and Construction Industry " , International Journal of Application or
productiveness. The total cost of material can also be 50 percent Innovation in Engineering & Management (IJAIEM), Volume 6,
of overall value; in order that it is critical for contractor to Issue 5, May 2017 , pp. 304-311 , ISSN 2319 - 4847.
consider that timely availability of material in project site.

References
[1] T.Subramani., ”Cost Estimation and Identification of Transport
Infrastructure facility Projects in Salem”, International Journal of
Engineering and Technology, Vol.2, No.5, Pp 859 – 867,2012.
[2] T.Subramani., P.Anitha., S.Sekar., “Health-Care Waste
Management System”, International Journal of Engineering
Research and Applications, Vol. 4, Issue 6( Version 2), pp.255-258,
2014.
[3] T.Subramani., N.Kanthasamy., “High End Solution For Advanced
Civil Engineering Projects”, International Journal of Modern
Engineering Research, Volume. 4, Issue. 6 (Version 3), pp 49-53,
2014.