API 570 Day 5 Book (1 To 130)
API 570 Day 5 Book (1 To 130)
Sections Used
3. Revised edition and addenda of API and ASME Codes may be used
from beginning with date of issue. But they become mandatory from 6
months after issue date.
4. Table A-1B of B 31.3 Code gives weld joint quality factor for
manufactured pipes. The factor can be increased for Electric Fusion
welded pipes by conducting additional radiography (spot or full) as per
Table 302.3.4.
PD
tm = +C
2( SE + PY )
3P
t m = dg +C
16 SE
Where, dg = the inside diameter of gasket
During pneumatic test a pressure relief valve (with set pr ≤ 1.1 x Test
pr.) shall be installed. Pressurization should be in steps. Initially,
pressure shall be slowly increased to 25 psi or 50% of test pressure
(whichever is lower). Check for leakage, if any, and correct them.
10. Hydrostatic test is preferred over Pneumatic test. The butt joints where
Hydro or Pneumatic test can not be performed, 100% RT or UT may
be done on butt welds, and PT or MT may be done on other welds
(branch welds, fillet welds, etc.) as alternative to Leak testing.
a. Value of one specimen is less than average and also less than
minimum for one specimen — Retest
b. Value of two specimen is less than average — Retest
15. In dissimilar pipe joints higher temperature of the two is to be used for
pre-heating.
16. PWHT Table (331.1.1) gives temperature range, minimum time and
maximum hardness values. Hardness survey shall be done for 10%
samples for furnace PWHT, and 100% for local PWHT.
2. Working pressure for flanges and flanged fittings can be read from
pressure-temperature ratings of flange. The hydrostatic test pressure is
taken as 1.5 times the pressure rating at 100º F, rounded to the next
25 psi.
5. API 570 shall not be used for new construction. It shall not violate
jurisdiction requirements.
8. Ultimate responsibility for executing the work as per API 570 rests with
owner/user.
13. Examiner is NDT person who assists the API 570 inspector but does
not decide acceptance / rejection of NDT results.
16. Deadlegs: Stagnant liquids in deadlegs can cause more corrosion than
the active piping in the process.
---------------------------------------End--------------------------------------
12. The two important inspections carried out periodically on piping are:
14. External visual shall include checklist form Appendix D which involves
checking for leaks, misalignments, vibrations pipe support conditions,
external corrosion, condition of insulation/coating/painting.
15. TMLS shall be selected representing suspect areas and shall include
elbows, tees, injection points and S/A interface.
b. External visual:
i. 5 years for Classes 1 and 2
ii. 10 years for Class 3
iii. Injection points and S/A interface — by
class
12. Pipes systems having remaining life more than 10 years and are
adequately protected, need not be included for inspection of
suspect area as above.
2. If corrosion rate is not available for new service, it shall be determined within
3 months of service and shall be confirmed by subsequent measurements.
2 SEt
MAWP = . t = t actual – 2 x corrosion loss up to next insp.
D
For unknown material, assume lowest grade and lowest joint efficiency
permitted by the Construction Code.
7. Any welding done on-stream shall be done in accordance with hot tapping
checklist as per API 2201.
10. Pressure tests are normally required after alterations and major repairs.
However, NDE maybe utilized if Pressure Test is not practical, if accepted
by piping Engineer.
11. The above grade survey of buried piping shall be conducted at an interval of
approximately 6 months.
12. For piping buried in lengths greater that 100 feet and not cathodically
protected (CP), the soil resistivity shall be checked at 5 year interval.
13. For poorly coated pipes or pipes with improper cathodic protection, close-
interval potential survey shall be made every 5 years.
15. Leak testing at minimum pressure = 1.1 x M.O.P. shall be done at half the
above intervals for non-C.P. pipes and same intervals for C.P. pipes.
Pressure shall not drop more than 5% in 4 hours period (Pressure-Decay
Test).
16. Repairs using clamps for buried pipes, the location and date of clamp shall
be shown on the marker (flag) and also on the inspection report. Clamp
shall be replaced by permanent repair at first available opportunity.
17. All fatigue failure take place due to initiation of surface crack and
propagation of crack due to stress fluctuation. There are 3-types of
fatigue failures.
If surface cracks are due to stress concentration, weld undercuts,
notches etc and stress fluctuation due to mechanical reasons
(unbalanced shafts, alternate tension-compression etc.) then it is
Mechanical Fatigue. If stress fluctuation is due to temperature swing, it
is Thermal Fatigue. If stress fluctuation is due to vibrations, water
hammer etc., it is Vibration Fatigue.
---------------------------------------End---------------------------------------
10. For acceptance criteria of production welds refer to Table 341.2.3 of B31.3
for:
• Weld reinforcement
• For radiographic results
• General acceptance of welds
11. Reasons for inspection are to ensure safety, reliability and to meet
regulatory requirements.
15. Flanged fittings and valves are made thicker than pipes. The thickness is
given by:
16. For 4,500 lb rating a factor of 1.35 is used instead of 1.5 in above formula.
17. For retirement thickness of valves and flanged fittings the value of “S” is
selected from stress tables of ASME B31.3.
18. For flanges as per B16.5, the raised face thickness of 1/16” (0.06”) is
included in flange thickness for class 150 and 300 flanges. For flanges of
higher rating raised face is ¼” (0.25”) and is additional to flange thickness.
19. Flanged joints and fittings are hydrostatically tested. Minimum Test
pressure shall be 1.5 times the 100°F rating rounded to next higher 25 psi.
This is also the maximum System-test pressure.
20. To locate the correct pressure temperature ratings for any flange, first
refer to Table 1A of B16.5, which gives which table to refer for which
material.
----------------------------------------End--------------------------------------
2. FOR RT:
b. Backscatter:
Light image of B on dark background - Unacceptable
c. Density Limitations:
3. FOR PT:
a. Control of Contaminants: Sulphur (for Nickel alloys) shall
not exceed 1% of residue. Chlorine + Fluorine (for S.S. and
Titanium) shall not exceed 1% of residue.
b. Temp. shall be between 10oC to 52oC, for standard
procedures.
c. Penetrants are colour (visible) type and fluorescent type.
Each of these have:
water washable
post emulsifying
solvent removable
Thus, total 6 categories of penetrant are available.
d. Emulsifier is applied after applying penetrant and required
dwell time is completed. Lipopholic emulsifier is applied
without pre-rinsing. Hydropholic emulsifier is applied after
pre-rinsing.
e. For dwell time for penetrant and developer refer Table T-
672.
f. After applying developer, interpretation shall be done within
10 to 60 minutes.
g. All penetrant materials should be from same manufacturer.
4. FOR MT:
a. Prod Technique:
- Use direct (rectified) current for magnetization
- Prod spacing 3” to 8”
- Useful for surface and sub-surface defects.
b. Yoke Technique:
- Use D.C. or A.C. or permanent magnet
- Suitable for surface defects only.
c. Calibration:
5. FOR VT:
7. SE-797 UT MEASUREMENT:
b. Apparatus: 3 types
- CRT read out
- CRT + direct read out
- Direct thickness read out
API RP 578
8. API RP 578 can be used for new and existing piping system. Carbon steel
components are not covered in RP 578.
9. One inspection lot means items taken from one heat only.
11. PMI testing of at least one electrode should be carried out from each lot or
package.
This is the “Open Book” portion of the exam. Feel free to use any of the
following:
MAWP = _____________________
a. 674 psig
b. 323 psig
c. 125 psig
d. Metal loss exceeds the requirements for 5 year inspection interval
MAWP = _______________________
a. 160 psig
b. 550 psig
c. 723 psig
d. 125 psig
10. What is the maximum length allowed for individual slag trapped in a
weld in a Severe Cyclic Condition piping system?
a. > T w X3
b. < T w /3
c. > 12T
d. 3/23”
11. What is the design thickness of NPS 2 ½ A106B pipe that operates at
25psi/200ºF?
a. .275”
b. .100”
c. .002”
d. Not enough information given
13. What is the test pressure of a metallic piping system whose design
temperature is above the test temperature using the following
conditions? NPS 6, A106-B, 100psi/800ºF
a. 150 psi
b. 450 psi
c. 278 psi
d. Test temperatures verses design temperatures are not different.
14. Determine the MAWP of the following piping system, at the next
inspection, based on the following:
Design Pressure/Temperature 100 psig/750ºF
Pipe description: NPS 6, Std 285c EFW,
Straight
Seam (No radiography)
Outside diameter of pipe, D: 6 5/8 in.
Thickness determined from .280 in.
inspection:
Observed corrosion rate: .01 in/year
Next planned inspection: 5 years
MAWP _____________________
a. 522 psig
b. 487 psig
c. 878 psig
d. 125 psig
15. Impact testing of each form of material for any specification shall be
done using procedures and apparatus in accordance with:
a. ASTM A 370
b. ASME Section V
c. API 570
d. AWS D 1.5
16. In the AWS A5.1, What is the designation for a cellulose DCEP
electrode?
a. E7018
b. E7016
c. E6011
d. E6010
17. With respect to a Class 400 NPS 12 slip-on raised face flange, whose
edges of the gasket do not extend to the bolt, what is the outside
diameter of the gasket?
a. 12.75”
b. 15.00”
c. 16.50”
d. 18.00”
18. The base metal is P No.8, the weld metal is A NO.8-9, and the wall
thickness is 1”. What is the hold time for Heat treatment?
a. None
b. 1 hour
c. 2 hours
d. ½ hour for each 1” thickness
19. On a regularly furnished Class 300 raised face flange, what is the height
of the raised face?
a. 0.06”
b. 0.09”
c. 0.19”
d. 0.25”
20. During a welder qualification test on 3/8” plate in the horizontal position,
how many guided bends are required?
a. 6 side bends
b. 2 nick breaks
c. 1 face and 1 root bends
d. 4 tensile specimens
22. A welder who tests on a ½” thick plate, groove weld in the 3G position is
also qualified to weld in which other plate positions?
a. Vertical only
b. Flat and horizontal
c. Flat
d. All plate positions
23. After not bending and forming, heat treatment is required for which P
numbers?
a. 3, 4, 5, 6 and 10A
b. 1, 2 and 7
c. 11ASG1 and 11ASG2
d. 1, 2, 8, 9A and 9B
24. A piping system that operates at a design pressure of 100 psi at 950ºF
was originally built from NPS 20 EFW (100% radiographed), ½ inch wall,
A-516 Grade 70, A-671 material. During the last inspection, the
thickness was determined to be .370 inches. The records indicated the
corrosion rate to be .009 inches per year. What is the MAWP if the next
inspection is planned in 5 years?
a. 126 psi
b. 285.17 psi
c. 98.23 psi
d. Not enough information given
26. When the MAWP is recalculated, the wall thickness used shall be the
actual thickness minus:
a. The estimated corrosion loss before the date of the next inspection
b. Twice the estimated corrosion loss before the date of the next
inspection.
c. Three times the estimated loss after the date of the next inspection
d. The estimated corrosion loss after the date of the next inspection.
27. The base metal is P.No.1, the weld metal is A No.1, and the wall
thickness is 7/8”. What is the holding time at 1100-1200º for heat
treatment?
a. 1 hour
b. 2 hours
c. 3 hours
d. Procedure is not required for this thickness
28. What is the required thickness of straight run pipe subject to internal
pressure only, based on the following conditions: NPS 14, A-285-C, EFW
Spiral seam (No radiography), operating at 216psi/378ºF
a. 0.11”
b. 1.1”
c. 0.06”
d. Not enough information given.
29. The radiograph of a Normal Fluid Service piping weld revealed a crack.
What is the acceptable crack length if the pipe wall was .375?
a. None
b. T/3
c. 3/16”
d. Cracks will not show on radiographs
32. What is the minimum holding time of A-106 Grade B, 1 inch thick
material?
a. 2.4 hours
b. 2 hours
c. 1 hour
d. Not specified
33. What is the working pressure of a 150 Ib. flange, A 350 Gr. LF6 CL1,
used at 400ºF?
a. 230 psig
b. 200 psig
c. 170 psig
d. 140 psig
34. What is the minimum class flange that can be used if the material is A
351 Gr. C F8C, temperature 950ºF and working pressure is 1930 psig.
a. 800
b. 900
c. 1500
d. This material cannot be used at this temperature
35. The preheat zone shall extend beyond each edge of a pipe weld:
a. 1”
b. 2”
c. 2T
d. 3T
36. What is the root face limitation as listed on the attached WPS and PQR?
a. 3/32”
b. 1/8”
c. No limit
d. Not designated
37. If the supporting PQR is used, are the P-no’s correct on the attached
WPS?
a. Yes
b. No
c. Could be if properly preheated
d. Not enough information
40. What should have been the correct number and type of guided bends on
the PQR?
a. 6 side bends
b. 2 face and 2 root bends
c. 1 side, 1 face and 1 root bend
d. 2 face, 2 root and 4 side bends
41. According to API 570, a(n) ________ is a person who assists the
inspector by performing specific NDE testing.
a. NDE technician
b. Inspector assistant
c. Level II inspector
d. Examiner
48. API 570 applies to piping systems for process fluids such as:
a. Firewater
b. Plumbing, sanitary sewers and storm sewers
c. Raw, intermediate, and finished products
d. Piping systems on trucks, ships and barges
56. The downstream limit of the injection point circuit is the second change
in flow direction past the injection point or:
a. 25 feet beyond the first change
b. 50 feet beyond the first change
c. 100 feet, if the pipe is straight run
d. No downstream requirement
58. Piping subject to CUI includes piping insulated for personnel protection,
especially:
a. Plastic piping
b. Glass lined piping
c. Carbon steel piping systems
d. Carbon steel piping systems operating between 25ºF - 250ºF
59. A leak test was performed on a buried piping system. The system was
repressured to 125 psi four hours into the test. Sometime during the
final four hours, the gauge fell 5 psi.
a. The piping system failed
b. The piping system passed
c. The test must be repeated
d. The piping system must be visually inspected.
62. Excessive cyclic stresses that are well below the static yield strength of
the material results in ______
a. Material failure
b. Fatigue cracking
c. Failure cracking
d. Creep cracking
65. What classification does the majority of unit process piping fall into?
a. CLASS 3
b. CLASS 2
c. CLASS 1
d. Owner/user designated system
68. A weld is changed from multipass per side to single pass per side. How
does this effect the PWHT limitation?
a. This limitation does not apply when a WPS is qualified with a PWHT
above the upper transformation temperature
b. This limitation does not apply when a WPS is qualified with a PWHT
below the upper transformation temperature
c. The PWHT is not a consideration
d. The PWHT must be performed per ASME IX and time increased by
one hour
70. Which of the following methods can be used to join cast iron pipe/
a. Welding
b. Compression
c. Epoxy resin
d. Bell and spigot
72. In a piping circuit, which of the following does not routinely have
thickness measurement taken?
a. Valves
b. Straight Run Pipe
c. Fitting
d. Deadlegs
73. What is the maximum measurement for open defects in the weld or heat
affect zone for a guided bend specimen?
a. 1/16”
b. 1/8”
c. 3/16”
d. No open defects are allowed
77. An operator notices a pipe off its support, what should be done?
a. Ignore the situation
b. Report the situation to engineering or inspection personnel
c. Keep a record or the situation for future reference
d. Contact maintenance personnel for immediate repair
78. When heat treating welded joints between dissimilar ferritic metals, the
temperature range shall be for which metal?
a. The one with the higher temperature range
b. The one with the lower temperature range
c. The average of both materials
d. Either one may be used
80. When a welder has not welded with a process during a period of
_______________ his qualifications for that process shall expire
a. 3 months or more
b. 6 months or more
c. 9 months or more
d. 12 months or more
81. Rerating piping systems may be allowed only if the calculations are
performed by ______________
a. The piping engineer or the inspector
b. The plant manager.
c. An out-side engineering firm
d. A third party inspection organization.
90. The letter ‘ B “ is placed on radiographic film holder for what reason ?
a. To determine if back scatter radiation is exposing the film
b. To show the distance from the source of radiation to the weld
c. To function as a location marker for the radiograph
d. To designate whether the penetrameter is on the film side or the back
side.
92. Piping systems that are not located in high activity areas and do not
significantly vaporize are designed as ______________.
a. Class 3
b. Class 2
c. Class 1
d. Owner / user designed system
93. Of the following examples, which one may cause a leak in a threaded
joint?
a. Back – welded the fitting
b. Lack of thread lubricant
c. Under – pressuring the part
d. Changing the direction of flow in the piping system
94. Pentrameters are normally placed on the _____________ side of the part
being examined.
a. Source
b. Film
c. Weld
d. Reverse
96. Exemptions for preheating and post weld heat treatment must be
approved by the _____________
a. Piping engineer
b. Inspector
c. Applicable standard, API 570
d. Repair procedure
97. A welder qualified to weld in accordance with one qualified WPS is also
qualified to weld ____________
a. Using the same welding process within the limits of the essential
variables
b. Any other qualified weld procedure
c. Using a different welding process of a qualified weld procedure
d. Any WPS developed and tested by the welder’s employer.
99. What document may be used as a guide when examiners are being
qualified their employer?
a. ASME Section IX
b. ASME Section V
c. ASNT SNT-TC-1A
d. API 570
102. Why should a leaking threaded joint not be tightened while the
system is in service?
a. The craftsman should not be near the threaded connection
b. Rust or corrosion might be holding the pressure
c. The joint might be unscrewed
d. A crack in a thread root might fail
111. The repair organization shall use welders and welding operators
qualified in accordance with the code to which the piping was built or
alternatively ___________
a. ASME B 31.3
b. ASME Section V
c. AWS D 1.1
d. API 1104
112. When an entire piping assembly is to be treated, but it will not fit into
the furnace , what action should be taken ?
a. Heat treat in more than one heat, with a 1’ overlap
b. Heat treat as much as possible and hardness test the untreated area
c. Radiograph the untreated area
d. MT the untreated area.
113. What is the maximum allowable deviation for the ammeter on each
piece of magnetizing equipment?
a. 30%
b. 10%
c. 20%
d. 15%
117. All piping systems repair and alteration welding shall be done in
accordance with:
a. ASME BPV IX
b. ASME B31.G
c. API 570
d. ASME B- 3.3 or The code to which then system was built
118. A piping system started with a wall thickness of .375 inches. Over a
five year period the wall thickness is now. 1 inch, What is the long term
corrosion rate ?
a. .055 inches per year
b. .005 inches per year
c. .550 inches per year
d. Not enough information given.
119. Given the above information, what is the short term corrosion rate of
the above piping system?
a. .055 inches per year
b. .005 inches per year
c. .550 inches per year
d. Not enough information given.
120. When testing cast iron pipe, which of the following methods should
not be used?
a. Radiographic test
b. Leak test
c. Ultrasonic testing
d. Hammer test
125. In lieu of the required heat treatment after welding, what may be used
as an alternative?
a. Normalizing/annealing
b. Quenching
c. Air Hardening
d. Strain Harmonics
126. A piping system has a corrosion rate of .074 inches per year; the
actual wall thickness is .370 inches and the minimum required thickness
is .1 inch. What is the remaining life?
a. 36.48 years
b. 364.8 years
c. 3.6 years
d. 3.6 months
127. The inspection shall approve all repair and alteration work at
designated times, referred to as
a. Hold points
b. Work stop points
c. Inspection delay points
d. Inspector’s discretion
142. When can welding procedures qualified by other than the employer
be used?
a. When there is specific approval of the inspector
b. When the job contract gives authorization
c. When the procedure is used only one time
d. When the production weld is radiographed
146. Without the benefit of an impact test, what is the minimum operating
temperature for A-106 Grade B material used in a Category D Fluid
Service?
a. -29ºF
b. -20ºC
c. -20ºF
d. 0ºF
150. The three well-known methods of determining soil resistivity are, soil
bar, soil box and ________________
a. A-c Bridge
b. Six pin method
c. Holiday pipe survey
d. Wenner (4-pin) method
ANSWER KEY
Solution: 2SEt/D
(40,000) (.08)
20
3,200
20
160
(19,200) (.180)
6.625
3,456
6.625
MAWP = 2SEt/D
= 2 (4,500) (1) (.370 – [(2 x .045)]
20
MAWP = 2 (4,500) (1) (.370 – .09)
20
MAWP = 2 (1260)
20
MAWP = 2520
20
MAWP = 2SEt/D
MAWP = 2 (1017)
20
MAWP = 2034
20
1. What is the height of the raised face on regularly furnished class 300
Raised Face Flanges?
a. 0.06
b. 0.09
c. 0.19
d. 0.25 alone 300 class 1.524 mm
14. The preheat zone shall extend at least _____________ beyond each
edge of the weld
a. 6T
b. 12 inches ( 30cm)
c. Wall thickness divided by 3
d. 25mm (1 inch )
27. TMLs can be eliminated for piping systems with which of the following
characteristics:
a. High potential for creating an emergency in the event of a leak.
b. Extremely corrosive systems
c. Low potential for creating an emergency in the event of a leak
d. Piping systems in cyclic condition at high pressure and temperatures
28. When determining the corrosion rate, the formulas from API 570 may be
used or:
a. Published data on piping system in comparable service
b. Owner/User’s experience
c. Budget restraints
d. Both A and B
30. When the corrosion rate for a piping circuit cannot be determined, the
initial thickness measurement determination shall be made after no
more than:
a. 1 year
b. 6 months
c. 3 months
d. 30 days.
33. The location markers which are to appear as radiographic images on the
film shall be placed on the _________________
a. Part
b. Film holder/cassette
c. Film side only
d. IQI
34. What is the required tolerance for the flange thks for NPS 16 inch
a. + or – 3mm
b. +3 mm, - 0 mm
c. +5, -5 mm
d +5,-3 mm
Section/page ____7.4_____ Reference Publication B16.5
35. If the soil resistivity is 6,500 ohm-cm, what is the inspection interval for
buried piping without cathodic protection?
a. 10years
b. 15 years
c. 5 years
d. Whenever a leak is suspected.
36. The ammeter on each piece of magnetizing equipment shall not deviate
by more than _______________
a. 30%
b. 10%
c. 20%
d. 15%
37. A welder is tested on ½ inch thick pipe in the 5G position. How many
face bends are required for this test?
a. 1
b. 2
c. 3
d. 4
Section/page QW 452.1(or) one face bend and one root bend Reference
Publication sec IX.
40. A welder is tested on ½ inch thick plate, how many face are required for
this test?
a. 1
b. 2
c. 3
d. 4
Section/page QW-452.1(or) one face & one root Reference Publication sec
IX.
41. During the final four hours of buried piping test, which was re-pressured
to 125 PSI, the gauge fell 5 PSI.
a. The piping system failed
b. The piping system passed.
c. The test must be repeated
d. The piping system must be visually inspected
43. A steel that hardens during cooling in air from a temperature above its
transformation range is ________________
a. Quenched and tempered steel
b. Annealed steel
c. Air-hardened steel
d. Normalized steel
44. A pipe welder successfully passes a 6G pipe test. The welder can weld
in which of the following positions?
a. 1G
b. 2G
c. 5G
d. All positions
47. Material in the form of ring used to support molten metal is called _____
a. Backing gas.
b. Cold wire slug
c. Consumable insert
d. Backing ring.
49. Who shall have the overall responsibility for compliance with API 570
and for establishing requirements for inspection, repair, alteration and
rerating?
a. Piping engineer
b. Repair organization
c. Inspector
d. Owner / user
50. During a procedure qualification test on pipe that is 3/8 inches thick,
how many side bends are required if the face and root bends are
acceptable?
a. 1
b. 2
c. 4
d. None
53. Excess water washable penetrant shall be removed with a water spray.
The water pressure shall not exceed _________________
a. 110 PSI
b. 90PSI
c. 50PSI
d. 20PSI
55. Flushing the surface with solvent, following the application of the
penetrant and prior to developing is _____________________
a. The average PT technique
b. Allowed if sufficient solvent is available
c. Not mentioned in ASME Section V
d. Prohibited.
56. Welding terms not specifically referred in ASME B31.3 can be found in
what document?
a. ASME Section IX
b. ASME Section V
c. AWS A 2.4
d. AWS A 3.0
57. How many tensile test are required to quality a ¼” plate groove weld?
a. 2
b. 3
c. 4
d. 6
59. ______________ may not be performed on the root pass or final pass of
a weld.
a. Peening
b. Cleaning
c. Stress relieving
d. Painting
62. Determine the MAWP , at the next inspection , of the piping system
based on the following
MAWP = ________________
a. 263 PSIG
b. 329 PSIG
c. 732 PSIG
d. 125 PSIG
66. Wet magnetic particle examination shall not be performed if the surface
temperature of the part exceeds _______________
a. 100ºF
b. 40ºF
c. Manufacturer’s temperature limitations
d. 135ºF
72. When valve body and/ or closure tests are performed after servicing ,
they should conducted in accordance with:
a. API 598
b. API 798
c. NACE RP 0169
d. ASME B 31.3
76. Services that are flammable but do not significantly vaporize when they
leak and not located in high- activity areas are labeled ____________
a. Class 1
b. Class 2
c. Class 3
d. Class 4
77. During PT test, final interpretation shall be made within what time
range?
a. 7 to 60 min
b. 30 to 60 min
c. 60 to 120 min
d. Any time after 24 hours
78. Who shall provide the materials, equipments, quality control, and work
man ship necessary to maintain and repair the piping systems in
accordance with the requirements of API 570?
a. Piping engineer
b. Repair organization
c. Inspector
d. Operator.
82. In compliance with API 570, portable water follows U.S practice which
allows
a. 2,500 parts per million maximum chloride
b. Less than I part per million maximum chloride.
c. 250 parts per million maximum chloride requirement
d. There is no maximum chloride requirement.
83. When the United States coast guard requires a system to be pressured
tested, care should be taken to avoid ______________, if the system is
subjected to thermal expansion.
a. Under pressure
b. Excessive pressure
c. Pneumatic pressure testing is required in this situation
d. Pipe “Shrinkage”.
85. The owner of buried piping should conduct surveys of the surface
conditions on adjacent to each pipe line path every ______________
a. 6 months
b. 12 months
c. Yearly
d. 5 years.
88. Filler metals, for piping welds, shall confirm to the requirements of?
a. AWS A5.1
b. ASME Section IX
c. ASME Section V
d. API 570
89. During the inspection of S/A interface, excavation was required, what is
the minimum depth required?
a. 1 inch to 5 inch
b. 6 inch to 12 inch
c. 13 inch to 19 inches
d. Inspector desecration
91. A point in the repair or alternation process beyond which work may not
proceed until the required inspection has been performed and
documented is called a(n) _______________________
a. Hold point
b. Inspection point
c. Wait for the inspector and charge extra period
d. Thickness measurement.
92. The exposed surface of a weld on the side from which the welding was
done is called the weld _______________
a. Cap
b. Toe
c. Face
d. Root
Section/page __fig A5______________ Reference Publication
___577____________
95. The person responsible to the owner – user for activities involving
design, engineering review, analysis or evaluation of systems covered
by API 570 is a(n) __________________
a. Piping engineer
b. Repair engineer
c. API authorized piping inspector
d. Operator.
Section/page 3.1.66 Reference Publication 570.
96. The person responsible to the owner – user for determining that the
requirements of API 570 for Inspection, examination, and testing are met
is a(n).__________
a. Piping engineer
b. Repair engineer
c. API authorized piping inspector
d. Operator.
Section/page 3.1.7 Reference Publication 570.
97. In compliance with API 570, who has control of the activities relating,
repair, and alternation of its piping systems?
a. Repair organization
b. Operations
c. Owner- user inspection organization
d. Maintenance crafts men.
98. Terminology for weld metal in excess of the specified weld size.
a. Weld reinforcement
b. Good weld technique
c. Weld toe
d. Weld throat
106. What % of all suspect areas and areas damaged insulation should be
inspected for a Class 3 system that is within susceptible temperature
ranges?
a. 100%
b. 75%
c. 50%
d. 10%
107. What is the heat treatment holding time based on hour per inch of
carbon steel 1 ¼” thick?
a. 2.4 hr/in
b. 1.5hr/in
c. 1.0hr/in
d. 0.5hr/in
Section/page Table 331.1.1 Reference Publication B31.3.
110. What is the minimum required thickness of the system listed above?
a. 1.312”
b. 1.112”
c. 0.997”
d. 0.650”
111. Calculate the long term corrosion rate of the system listed above
based on : 5 year interval : third cycle
a. 0.023”
b. 0.021”
c. 0.112”
d. 0.997”
112. Calculate the short term corrosion rate of the system listed above,
based on
T previous =1.112”
T last = 0.997”
5 year interval: third cycle
a. 0.023”
b. 0.021
c. 0.112”
d. 0.997”
115. What is the outside diameter of a gasket type E-2 for fitting in
questions 114?
a. 10.62”
b. 8.62”
c. 12.12”
d. 12.62”
120. What is the position designation for welding pipe in the horizontal
fixed position?
a. 2G
b. 3G
c. 5G
d. 6G
ANSWER KEY
MAWP = _____________________
a. 674 psig
b. 323 psig
c. 125 psig
d. Metal loss exceeds the requirements for 5 year inspection interval
10. What is the maximum length allowed for individual slag trapped in a
weld in a Severe Cyclic Condition piping system? ( Table 341.3.2 – B
31.3 )
a. > T w X3
b. < T w /3
c. > 12T
d. 3/23”
11. What is the design thickness of NPS 2 ½ A106B pipe that operates at
25psi/200ºF? Table A 1 of B 31.3 & 11.2 of API 574)
a. .275”
b. .100”
c. .002”
d. Not enough information given
13. What is the test pressure of a metallic piping system whose design
temperature is above the test temperature using the following
conditions? NPS 6, A106-B, 100psi/800ºF (, Par. 345.4.2) ASME B31.3
a. 150 psi
b. 450 psi
c. 278 psi
d. Test temperatures verses design temperatures are not different.
14. Determine the MAWP of the following piping system, at the next
inspection, based on the following: Table 4 of API 570
MAWP _____________________
a. 522 psig
b. 487 psig
c. 878 psig
d. 125 psig
15. Impact testing of each form of material for any specification shall be
done using procedures and apparatus in accordance with:
a. ASTM A 370
b. ASME Section V
c. API 570
d. AWS D 1.5
16. In the AWS A5.1, What is the designation for a cellulose DCEP
electrode?
a. E7018
b. E7016
c. E6011
d. E6010
17. With respect to a Class 400 NPS 12 slip-on raised face flange, whose
edges of the gasket do not extend to the bolt, what is the outside
diameter of the gasket? ( Out side the Syllabus)
a. 12.75”
b. 15.00”
c. 16.50”
d. 18.00”
18. The base metal is P No.8, the weld metal is A NO.8-9, and the wall
thickness is 1”. What is the hold time for Heat treatment?
a. None
b. 1 hour
c. 2 hours
d. ½ hour for each 1” thickness
19. On a regularly furnished Class 300 raised face flange, what is the height
of the raised face? ( Fig 11-7 –B 16.5)
a. 0.06”
b. 0.09”
c. 0.19”
d. 0.25”
20. During a welder qualification test on 3/8” plate in the horizontal position,
how many guided bends are required?
a. 6 side bends
b. 2 nick breaks
c. 1 face and 1 root bends
d. 4 tensile specimens
22. A welder who tests on a ½” thick plate, groove weld in the 3G position is
also qualified to weld in which other plate positions?
a. Vertical only
b. Flat and horizontal
c. Flat
d. All plate positions
23. After hot bending and forming, heat treatment is required for which P
numbers?
a. 3, 4, 5, 6 and 10A
b. 1, 2 and 7
c. 11ASG1 and 11ASG2
d. 1, 2, 8, 9A and 9B
24. A piping system that operates at a design pressure of 100 psi at 950ºF
was originally built from NPS 20 EFW (100% radiographed), ½ inch wall,
A-516 Grade 70, A-671 material. During the last inspection, the
thickness was determined to be .370 inches. The records indicated the
corrosion rate to be .009 inches per year. What is the MAWP if the next
inspection is planned in 5 years?
a. 126 psi
b. 285.17 psi
c. 98.23 psi
d. Not enough information given
26. When the MAWP is recalculated, the wall thickness used shall be the
actual thickness minus:
a. The estimated corrosion loss before the date of the next inspection
b. Twice the estimated corrosion loss before the date of the next
inspection.
c. Three times the estimated loss after the date of the next inspection
d. The estimated corrosion loss after the date of the next inspection.
27. The base metal is P.No.1, the weld metal is A No.1, and the wall
thickness is 7/8”. What is the holding time at 1100-1200º for heat
treatment?
a. 1 hour
b. 2 hours
c. 3 hours
d. Procedure is not required for this thickness
28. What is the required thickness of straight run pipe subject to internal
pressure only, based on the following conditions: NPS 14, A-285-C, EFW
Spiral seam (No radiography), operating at 216psi/378ºF
a. 0.11”
b. 1.1”
c. 0.06”
d. Not enough information given.
29. The radiograph of a Normal Fluid Service piping weld revealed a crack.
What is the acceptable crack length if the pipe wall was .375?
a. None
b. T/3
c. 3/16”
d. Cracks will not show on radiographs
32. What is the minimum holding time of A-106 Grade B, 1 inch thick
material?
a. 2.4 hours
b. 2 hours
c. 1 hour
d. Not specified
33. What is the working pressure of a 150 Ib. flange, A 350 Gr. LF6 Cl, used
at 400ºF?
a. 230 psig
b. 200 psig
c. 170 psig
d. 140 psig
34. What is the minimum class flange that can be used if the material is A
351 Gr. C F8C, temperature 950ºF and working pressure is 1930 psig.
a. 800
b. 900
c. 1500
d. This material cannot be used at this temperature
35. The preheat zone shall extend beyond each edge of a pipe weld:
a. 1”
b. 2”
c. 2T
d. 3T
36. What is the root face limitation as listed on the attached WPS and PQR?
PQR will be given
a. 3/32”
b. 1/8”
c. No limit
d. Not designated
37. If the supporting PQR is used, are the P-no’s correct on the attached
WPS? PQR will be given
a. Yes
b. No
c. Could be if properly preheated
d. Not enough information
40. What should have been the correct number and type of guided bends on
the PQR?
a. 6 side bends
b. 2 face and 2 root bends
c. 1 side, 1 face and 1 root bend
d. 2 face, 2 root and 4 side bends
43. When will be the next inspection schedule from now on for external
inspection for pipe in Q.1?
a. 10 years
b. 8 years
c. 5 years
d. none of the above
44. The pipe in Q.1 above has an insulated area of 200 sq. ft., which is
exposed to susceptible temperature and mist spray of cooling tower.
According to API 570, how much of minimum area is recommended for
NDT survey for CUI during external inspection?
a. 100 square feet
b. 50 square feet
c. 66 square feet
d. 150 square feet
45. A PQR is to be qualified using 5/8 inch thick test coupon. It can qualify
thickness:
a. 1/8” to 1-1/4”
b. 1/16” to 5/8”
c. 1/16” to 1-1/4”
d. None of the above
46. The recommended minimum Dwell time (Penetrant Testing) allowed for
a material made of high temperature alloy is:
a. 5 min
b. 10 min
c. 7 min
d. 6 min
47. A radiograph was having density near the penetrameter equal to 3.0.
Hence the acceptable density range of the radiograph is:
a. 1.7 to 4
b. 2.55 to 3.9
c. 2.0 to 4.0
d. None of the above
48. For piping buried in soil with resistivity of 5000-ohm cm and not
cathodically protected, evaluations of pipe thickness should be
performed at:
a. 10 year interval
b. 5 year interval
c. 3 year interval
d. None of the above
49. For a certain Natural gas piping system, which is in operation for 16
years, it is estimated that it has remaining life of 12 years. Considering
the stipulation of API 570, which of the following will determine
maximum interval for next proposed date for thickness measurement
examination and visual examination?
a. 6 years and 5 years respectively
b. 3 years and 10 years respectively
c. 10 years and 5 years respectively
d. 6 years and 6 years respectively
51. A PRD installed should have the set pressure for the test pressure of
600 psi will be:
a. 660 psi
b. 650 psi
c. 300, 330,360,390,420,450
d. none of above
52. What would you expect to happen if you were taking UT readings on
piping that was operated higher than 200 degrees F?
a. The thickness readings could be lower.
b. The thickness readings would not be influenced.
c. The thickness readings could be about 1% higher for each 100
degrees F rise of temperature.
d. The thickness readings may be higher or lower depending on couplant.
54. The document referenced in API 570 for determining “fitness for
service” of piping system is:
a. API 579
b. API 574
c. ASME B 31.1
d. None of the above
55. During impact testing of A 106 grB (Deoxidised) and A53 grB pipes
(non-deoxidised), following absorbed energy values in ft-lb were
observed:
56. A PQR test was made on A 106 grade C pipe. This will qualify which of
the following sets of materials: Refer Table A1
a. A 106 gr B, A36 , A 182 F1
b. A 105, A516 gr 60, A516 gr 70
c. 515 gr 70, A 285 gr C, A 335 P 11
d. None of the above set is fully qualified by this PQR.
59. A PRD installed should have the set pressure for the test pressure of
600 psi will be:
a. 660 psi
b. 650 psi
c. 300, 330,360,390,420,450
d. none of above
60. Select suitable Hole type (source side) penetrameter for following weld
joint:
a. No 20
b. No 25
c. No 30
d. None of the above
62. For steel plates and welds to be checked by LPI, what shall be the
penetration time for penetrant?
a. 10 min for weld, 5 min for plate
b. 5 min for both
c. 10 min for both
d. 5 min for weld, 10 min for plate
63. After applying the developer the examiner checked four welds for
surface defects after following period, weld A – after 5 minute, weld B
after 10 minutes, weld C was checked after 30 minutes and welds D
after 65 minutes. Which of the welds were checked wrongly?
a. Weld A and B
b. Weld C and D
c. Weld D only
d. Weld A and D
64. In a certain PQR for SMAW, the electrodes used for all passes were of
AWS classification (E 7018). Corresponding WPS also showed filler
materials as E 7018. Now the manufacturer proposes to change the filler
material in WPS to E 7015. Will you ask manufacturer to:
a. Qualify new PQR with E 7015 electrodes.
b. Revise only WPS showing the change from E 7018 to E 7015 and
submit WPS as a new revision.
c. Revise only the PQR document showing the change and resubmit for
approval.
d. Revise both WPS and PQR showing the change and resubmit for
approval.
65. Actual thickness measured at a TML was 0.4 inch. The corrosion rate is
10 mpy. If next planned thickness inspection is after 6 years, what
thickness will be used for MAWP calculation?
a. 0.4 inch
b. 0.34 inch
c. 0.28 inch
d. None of the above
67. Suggest suitable construction materials for caustic service having 40%
Na0H concentration (by weight) operating at 2400F 571-4.3.10.6C
a. Carbon steel with PWHT
b. Carbon Steel, but PWHT is not required
c. Carbon steels with quenched and tempering treatment
d. Consider Use of high Nickel alloys.
70. While observing radiographic film for weld with SMAW process showed
indication of following description. “A localized darker density with
fuzzy edges, in the center of the width of weld image.” This indication
most likely represents:
a. Excessive penetration
b. Lack of penetration
c. Cluster porosity
d. Burn through
ANSWER KEY
Solution: 2SEt/D
(40,000) (.08)
20
3,200
20
160
(19,200) (.180)
6.625
3,456
6.625
MAWP = 2SEt/D
= 2 (4,500) (1) (.370 – [(2 x .045)]
20
MAWP = 2 (4,500) (1) (.370 – .09)
20
MAWP = 2 (1260)
20
MAWP = 2520
20
MAWP = 2SEt/D
MAWP = 2 (1017)
20
MAWP = 2034
20
Answer: b
Answer: b
Answer: a
Answer: a
Answer: a
51 b, B 31.3- 345.5.2
Answer: c
Answer: b
Answer: a
12.5 + 13.5 + 12
Average for A106 grB = = 12.5 < 13 (For
3
Oxidized)
11 + 11.5 + 9
Average for A53 grB = = 10.5 > 10 ft lb( for
3
deoxidized)
56 A 106 grC pipe belongs to P No. 1 material. So it will qualify only P No. 1
materials. A 105, A 516 gr60 and A516 gr70 are P No. 1 materials.
Refer Table QW-422 from ASME Sec. IX. Better look in to the table A1 to
find P no of all material Only same P no can be used for PQR, Alternative
P nos are only for welder qualification
Answer: a
Answer: a
Answer: c
Answer: b
Answer: d
Answer: d
Answer: d
Answer: b
65 Refer API 570 7-2, Last para for MAWP thickness used shall be Actual
Thickness minus twice the corrosion loss up to next inspection.
Answer: c
Answer is: B
Answer is: D
Answer is: C
Answer is: A
Answer is: D
API 570 CODE- Inspection, repair & Alteration of the piping system in
service
API 571 RP Damage Mechanism in fixed equipment in refining industry
API 574 RP – For whole piping system components
B 31.3 – Code Process piping and Pressure piping, New Construction
B 16.5 –Standard- For Flange and flange fittings
API 577 – RP – Welding inspection and metallurgy
API 578 –RP-Material verification. It Is Retroactive. It is for AS pipes for
New Construction and for AAS pipes in service
Only API 578 is retro active. Others are not retro Active
8. API 570 applies to piping systems for process fluids such as:
a. Firewater
b. Plumbing, sanitary sewers and storm sewers
c. Raw, intermediate, and finished products
d. Piping systems on trucks, ships and barges
16. The downstream limit of the injection point circuit is the second change
in flow direction past the injection point or:
a. 25 feet beyond the first change
b. 50 feet beyond the first change
c. 100 feet, if the pipe is straight run
d. No downstream requirement
18. Piping subject to CUI includes piping insulated for personnel protection,
especially:
a. Plastic piping
b. Glass lined piping
c. Carbon steel piping systems
d. Carbon steel piping systems operating between 25ºF - 250ºF
19. A leak test was performed on a buried piping system. The system was
re-pressured to 125 psi four hours into the test. Sometime during the
final four hours, the gauge fell 5 psi.
a. The piping system failed
b. The piping system passed
c. The test must be repeated
d. The piping system must be visually inspected.
22. Excessive cyclic stresses that are well below the static yield strength of
the material results in ______
a. Material failure
b. Fatigue cracking
c. Failure cracking
d. Creep cracking
Temp Dapa 2
Atmospheric corrosion increases up to 250 Deg F
CUI is present 25 Deg F to 250 Deg F. But More severe from 100Deg
C to 121 Deg C.
Chloride SCC – from 150 Deg F to 400 Deg F
Suulphidisatiion _ Above 500 deg F
Creep – above 900 Deg F
Heat treatment __ 1100 Deg F to 1250 Deg F
25. What classification does the majority of unit process piping fall into?
a. CLASS 3
b. CLASS 2
c. CLASS 1
d. Owner/user designated system
28. A weld is changed from multipass per side to single pass per side. How
does this effect the PWHT limitation?
a. This limitation does not apply when a WPS is qualified with a PWHT
above the upper transformation temperature
b. This limitation does not apply when a WPS is qualified with a PWHT
below the upper transformation temperature
c. The PWHT is not a consideration
d. The PWHT must be performed per ASME IX and time increased by
one hour
30. Which of the following methods can be used to join cast iron pipe/
a. Welding
b. Compression
c. Epoxy resin
d. Bell and spigot
32. In a piping circuit, which of the following does not routinely have
thickness measurement taken?
a. Valves
b. Straight Run Pipe
c. Fitting
d. Deadlegs
33. What is the maximum measurement for open defects in the weld or heat
affect zone for a guided bend specimen?
a. 1/16”
b. 1/8”
c. 3/16”
d. No open defects are allowed
Long crack may expand. So full encirclement weld split sleeve is not
preferred. . But it can be done if piping engineer approves. and he is
confident that longitudinal crack will not spread. For this purpose
piping engineer can consult fracture specialist. Other wise follow the
usual cut repair and grind procedure after putting holes at the ends
of the crack to arrest crack growth.
37. An Inspector notices a pipe off its support, what should be done?
a. Ignore the situation
b. Discuss the situation to Piping engineer
c. Keep a record or the situation for future reference
d. Contact maintenance personnel for immediate repair
38. When heat treating welded joints between dissimilar ferritic metals, the
temperature range shall be for which metal?
a. The one with the higher temperature range
b. The one with the lower temperature range
c. The average of both materials
d. Either one may be used
40. When a welder has not welded with a process during a period of
_______________ his qualifications for that process shall expire
a. 3 months or more
b. 6 months or more
c. 9 months or more
d. 12 months or more
41. Rerating piping systems may be allowed only if the calculations are
performed by ______________
a. The piping engineer or the inspector
b. The plant manager.
c. An out-side engineering firm
d. A third party inspection organization.
47. Tubings are mostly seamless and it’s stated size is OD in inches 7 Not
the NPS. Exception to this is
a. Riveted tube
b. ASTM B 88 tubes
c. API -5L - tubes
d. Tubes more than 4 inch size
50. The letter ‘ B “ is placed on radiographic film holder for what reason ?
a. To determine if back scatter radiation is exposing the film
b. To show the distance from the source of radiation to the weld
c. To function as a location marker for the radiograph
d. To designate whether the penetrameter is on the film side or the back
side.
52. Piping systems that are not located in high activity areas and do not
significantly vaporize are designed as ______________.
a. Class 3
b. Class 2
c. Class 1
d. Owner / user designed system
53. Of the following examples, which one may cause a leak in a threaded
joint?
a. Back – welded the fitting
b. Lack of thread lubricant
c. Under – pressuring the part
d. Changing the direction of flow in the piping system
54. Pentrameters are normally placed on the _____________ side of the part
being examined.
a. Source
b. Film
c. Weld
d. Reverse
56. Exemptions for preheating and post weld heat treatment must be
approved by the _____________
a. Piping engineer
b. Inspector
c. Applicable standard, API 570
d. Repair procedure
API 570-8.2.2.1
57. A welder qualified to weld in accordance with one qualified WPS is also
qualified to weld ____________
a. Using the same welding process within the limits of the essential
variables
b. Any other qualified weld procedure
c. Using a different welding process of a qualified weld procedure
d. Any WPS developed and tested by the welder’s employer.
59. What document may be used as a guide when examiners are being
qualified their employer?
a. ASME Section IX
b. ASME Section V
c. ASNT SNT-TC-1A
d. API 570
62. Why should a leaking threaded joint not be tightened while the system
is in service?
a. The craftsman should not be near the threaded connection
b. Rust or corrosion might be holding the pressure
c. The joint might be unscrewed
d. A crack in a thread root might fail
64. A transverse crack was discovered in the root pass of a completed weld
on the outside of a Category D Fluid Service piping system during a PT
test. Which of the following statement is most accurate?
a. The weld is acceptable
b. The PT test should be repeated
c. The welder should be requalified
d. The PT test will not show this type of discontinuity from the outside
65. The transmitted film density through the radiographic image of the body
of the appropriate hole penetrameter and the area of interest shall be
__________ minimum for radiographs made with a gamma ray source
a. 1.8
b. 2.0
c. 2.2
d. 2.6
68. An area defined by a circle having a diameter not greater than 2 inches for
a line diameter not exceeding 10 inches, in which thickness readings may
be averaged is;
a. TML
b. WFMT
c. Test point
d. Averaging point
71. The repair organization shall use welders and welding operators
qualified in accordance with the code to which the piping was built or
alternatively ___________
a. ASME B 31.3
b. ASME Section V
c. AWS D 1.1
d. API 1104
Either B 31.3 or ASME SEC IX
72. When an entire piping assembly is to be treated, but it will not fit into
the furnace, what action should be taken?
a. Heat treat in more than one heat, with a 1’ overlap
b. Heat treat as much as possible and hardness test the untreated area
c. Radiograph the untreated area
d. MT the untreated area.
73. What is the maximum allowable deviation for the ammeter on each piece
of magnetizing equipment ?
a. 30%
b. 10%
c. 20%
d. 15%
77. All piping systems repair and alteration welding shall be done in
accordance with:
a. ASME BPV IX
b. ASME B31.G
c. API 570
d. ASME B- 3.3 or The code to which then system was built
78. A piping system started with a wall thickness of .375 inches. Over a five
year period the wall thickness is now. 1 inch, What is the long term
corrosion rate ?
a. .055 inches per year
b. .005 inches per year
c. .550 inches per year
d. Not enough information given.
79. Given the above information, what is the short term corrosion rate of the
above piping system?
a. .055 inches per year
b. .005 inches per year
c. .550 inches per year
d. Not enough information given.
80. When testing cast iron pipe, which of the following methods should not
be used?
a. Radiographic test
b. Leak test
c. Ultrasonic testing
d. Hammer test
83. The minimum required pipe wall thickness or retirement thickness shall
be based on pressure, mechanical and structural considerations using
the appropriate design formula and ______________
a. Code allowable stress
b. Assumption stress
c. Nil-weight ductility stress
d. CTOD stress
85. In lieu of the required heat treatment after welding, what may be used as
an alternative?
a. Normalizing/annealing
b. Quenching
c. Air Hardening
d. Strain Harmonics
86. A piping system has a corrosion rate of .074 inches per year; the actual
wall thickness is .370 inches and the minimum required thickness is .1
inch. What is the remaining life?
a. 36.48 years
b. 364.8 years
c. 3.6 years
d. 3.6 months
87. The inspection shall approve all repair and alteration work at designated
times, referred to as
a. Hold points
b. Work stop points
c. Inspection delay points
d. Inspector’s discretion
90. Size of the socket weld is limited to Inch nPS fore severe cyclic
condition
a. 0.5 Inch
b. 1 inch
c. 2 inch
d. 4 inch
Code can function as a standard. But reverse is not true
We know it is a code. But API 574 consider this as the industry standard.
Again all codes are industry standards first and then only it become codes
by the Legal acceptance
102. When can welding procedures qualified by other than the employer
be used?
a. When there is specific approval of the inspector
b. When the job contract gives authorization
c. When the procedure is used only one time
d. When the production weld is radiographed
106. Without the benefit of an impact test, what is the minimum operating
temperature for A-106 Grade B material used in a Category D Fluid
Service?
a. -29ºF
b. -20ºC
c. -20ºF
d. 0ºF
109. In piping systems, the one problem that can become severe from the
ordinary loss of containment to a sudden hazard for the investigative
personnel
a. Pipe wall thickness
b. Pipe wall thinness
c. Pipe coating condition
d. Leaks
110. The three well-known methods of determining soil resistivity are, soil
bar, soil box and ________________
a. A-c Bridge
b. Six pin method
c. Holiday pipe survey
d. Wenner (4-pin) method
Wenneer - 4 pin ,
Soli box , soil Bar – 2 pins
Wennner method is not OK for parallel lines or lines with intersection. So
here we use soli box or oli bar
ANSWER
t
initial - tactual / time (yrs) between initial and actual inspections