ASSOUMOU KOUAME Dr COULIBALY WALLAMATIEN

COFFI JEAN OPERATION MANAGEMENT


TETE MARC

HOMEWORK 3

1) *CPM/PERT NETWORK FOR MOORE HOUSE CONTRACTORS ( see paper )

2
Activity T σ ES EF LS LF S
a 4.2 0.25 0 4.2 0 4.2 0
b 3.2 0.25 4.2 7.4 4.2 7.4 0
c 3.8 0.25 7.4 11.2 8 11.8 0.6
d 2.2 0.25 7.4 9.6 33.9 36.1 26.5
e 2 0.11 7.4 9.4 7.4 9.4 0
f 3.8 0.25 11.2 15 11.8 15.6 0.6
g 3.2 0.25 9.4 12.6 9.4 12.6 0
h 4.2 0.69 9.4 13.6 13.6 17.8 4.2
I 2.8 0.25 15 17.8 21.2 24 6.2
j 2.2 0.25 15 17.2 15.6 17.8 0.6
k 5.2 0.69 12.6 17.8 12.6 17.8 0
l 6.5 0.69 17.8 24.3 24 30.5 6.2
m 8.3 1 17.8 26.1 17.8 26.1 0
n 3.3 0.44 24.3 27.6 30.5 33.8 6.2
o 2.3 0.44 27.6 29.9 33.8 36.1 6.2
p 3.5 0.69 29.9 33.4 36.1 39.6 6.2
q 4.2 0.25 26.1 30.3 26.1 30.3 0
r 6.3 1 33.4 39.7 39.6 45.9 6.2
s 5.8 2.25 30.3 36.1 35.1 40.9 4.8
t 4.3 1 30.3 34.6 30.3 34.6 0
CRITICALT
u PATH FOR MOORE 3.3 CONTRACTORS
0.44 30.3 33.6 31.3 34.6 1
v 6.3 1 34.6 40.9 34.6 40.9 0
 Critical
w path : a, b,
5 e, g, k, m, q, t,
1 v, w40.9 45.9 40.9 45.9 0
x 2.8 0.25 40.9 43.7 43.1 45.9 2.2
 Critical path duration= 4.2 + 3.2 + 2 + 3.2 + 5.2 + 8.3 + 4.2 + 4.3 + 6.3 + 5 = 45.9

 Variance of critical path= 0.25 + 0.25 + 0.11 + 0.25 + 0.69 + 1 + 0.25 + 1 + 1 + 1= 5.81
 Standard devision critical path = 5.81 = 2.41

 The z-score for x = 45 :

Z= (x-t) / 

Z=(45-45.9)/2.41

Z= - 0.37

 Probability correspond Z is 0.1443

P ( z ≤45) = 0.500 – 0.1443

P ( z ≤45) = 0.3557 or 35.57 %


It appear that the Moores migth increase their bid to compensate for potential penalties
because 35.57% is not a very high probability that the contractor will complete a house
within 45 days.

2)

The project activities Moore House contractor should be particularly diligent to keep on
schedule are the activities on the critical path . and the activities which are not in the critical
path must pull the ressources with slack .some of the worker on the activities such as h, i , l
, n , o , r , s will be difficultly transferrable to work on the critical path activities .