Professional Documents
Culture Documents
Tutorial 5 Capital Budgeting
Tutorial 5 Capital Budgeting
Tutorial 5 Capital Budgeting
my/Umcced
Tutorial 5
Financial Management
Question 1
Smart Bhd involved in agriculture project. Company still consider investing or not in cocoa
plantation. Your team and you are assigned to evaluate either the project is profitable or not
and when Smart Bhd will get their investment back.
The project required cost of capital at 8% per year with expected project life span of 4 years.
Management estimates the following cash flows from the project with initial investment of
RM6,000,000.
Year Cash Flow
RM
0 6,000,000
1 2,000,000
2 3,000,000
3 2,800,000
4 1,600,000
Question 2
Lela Media Company is in the process of deciding the purchase of an electronic casting
system. Provided below is the after tax cash flow for both systems.
The company’s cost of capital is 10% and these projects are mutually exclusive.
a. Calculate the following for both system :
i. Payback period
ii. Discounted Payback Period
iii. Net present value
iv. Profitability Index
v. Interest Rate Return - KIV
b. Which project would be selected and state your reasons.
UDE1010/CH7/T5 amiroh@um.edu.my/Umcced
Question 3
Hook Industries is considering the replacement of one of its old drill presses. Two alternative
replacement presses are under consideration. The relevant cash flows associated with each
drill presses are shown in the following table. The firm’s cost of capital is 15%.
Calculate the project based on the following capital budgeting techniques and make the
decisions for each technique below:
a) Payback period.
b) Discounted Payback period
c) Net Present Value (NPV)
d) Profitability Index (PI)
Suggested answer:
Project Jebat
= 0.1 (RM30,000) + 0.4(RM40,000) + 0.4(RM35,000) + 0.1(RM25,000)
= RM35,500
Project Tuah
= 0.1 (RM25,000) + 0.2(RM50,000) + 0.4(RM20,000) + 0.3(RM40,000)
= RM32,500
UDE1010/CH7/T5 amiroh@um.edu.my/Umcced
Project Jebat
= 0.1(RM30,000-RM35,500)2 + 0.4(RM40,000-RM35,500)2 +
0.4(RM35,000-RM35,500)2 + 0.1(RM25,000-RM35,500)2
= RM4,717
Project Tuah
= 0.1(RM25,000-RM32,500)2 + 0.2(RM50,000-RM32,500)2 +
= 0.4(RM20,000-RM32,500)2 + 0.3(RM40,000-RM32,500)2 +
= RM12,093
Suggested Answer :
b. Which project is more risky and calculate the net present value of each
project. Which project would the company undertake? Why?
Based on both project, you need to compare the answer from (iii). P.Jebat
(0.13) less than P.Tuah (0.37). So it shows that Project Tuah has a higher
coefficient of variation. Therefore Project Tuah is more risky compare to the
Project Jebat.
Based on the information given, it was mention that both project are mutually
exclusive project. If mutually ex, meaning that if let say u have 10 project, but
you are allowed to choose one which most the best in term of higher NPV.
You not allowed to choose more than one because the project is mutually
exc.
Different with independent project (refer answer on c below).
c. If the projects are independent projects, should the company accept both?
Why?
Independent projects mean (you can choose or accept many project as you
can as long as it can give POSITIVE NPV.
Based on the answer from B, both project give positive NPV, so if the project
is independent, company may choose BOTH project or one Project. If
company want to choose one project only which give higher NPV also
acceptable. No limit. Its up to your judgement.
But, if the question say, the project are mutually exclusive (Refer on B) on
third point.
Question 5
Banau Berhad is evaluating two mutually exclusive capital budgeting projects. Both projects
require the same amount of initial outlay totalling RM15 million. Both projects are expected
to have a useful life of five years. However, the annual differential cash flows of the two
projects are highly uncertainty, depending on economic performance. The forecasted annual
tax differential cash flows over the projects’ lives are as follows:
Based on the above information, calculate the following for each of the project:
i. Expected return
ii. Standard deviation
iii. Coefficient of variation
UDE1010/CH7/T5 amiroh@um.edu.my/Umcced
b) If the company decided to use 15% for the less risky project and 24% for the higher
risk project, calculate the net present value of each project. Which project would the
company undertake? Why?
c) If the projects are independent projects, should the company accept both? Why?
Question 6
Billionaire Berhad is analyzing two mutually exclusive capital budgeting projects. Project 1
will require an initial outlay of RM25 million, while Project 2 would require RM28 million. Both
projects are expected to have a useful life of four years. The annual differential after tax cash
flows of the two projects depend highly on the forecasted economic performance. The cash
flows of the projects are as follows:
a. Based on the above information, calculate the following for each of the project:
i. Expected annual after tax differential cash flow
ii. Standard deviation
iii. Coefficient of variation
b. If the company decided to use 13% for the less risky project and 20% for the higher
risk project, calculate the net present value of each project. Which project would the
company undertake? Why?
c. If the projects are independent projects, should the company accept both? Why?