Inspection Test Plan For Fabrication PDF Free
Inspection Test Plan For Fabrication PDF Free
References Legend
W : Witness Point
M : Monitoring
R : Review Document
RI : Report Issuance
NSF Procedures: RT : Radiographic Test
UT : Ultrasonic Test
NSF- MAT- 001 Store control MT : Magnetic Particle Test
NSF-PRO- 001 Weld control PT : Liquid Penetrant Test
NSF-QCD-008 N.D.T control HV : Hardness Test
NSF -QCD-005 Ultra sonic Examination VT : Visual Test
NSF-TEC-001 Handling and Packing DT : Dimensional Check
NSF-QCD-007 Magnetic particle Examination HT : Hydrostatic Test
NSF-PRO-003 Painting Control DFT : Dry Film Thickness check
NSF-GEN-001 Fabrication PWHT : Postweld Heat Treatment
NSF-QCD-004 Radiographic Examination WPS : Welding Procedure Specification
PQR : Procedure Qualification Record
WPQ : Welder Performance Qualification
TG : Tightening Check
AI : Authorized Inspector
Name
Signature
Date
Date : 5/10/2012
ITP No. : GC-ITP-000
INSPECTION AND TEST PLAN Rev. : 0
Page : of
Inspection
Ser. #
Remarks &
Activity Description % Acceptance Criteria Verifying Document Sign Sign Sign
Type A B C Reports No.
Date Date Date
I APPROVAL
II MATERIAL PREPARATION
1 100% Material check for confirmity and visual 100% EN 10025 Material Certificate VT&DT H
WPS&Approved
2 Marking,Cutting,Rolling and Edge preparation 100% Drawings
ITP DT M
WPS&Approved
1 Correct Joint design 100% Drawings,AWS D1.1
ITP VT&DT H
IV NDT
1 Visual check for Complete welds(Dynamic or static ) 100% AWS D1.1(table 6.1) visual Report VT&DT H
Inspection
Ser. #
Remarks &
Activity Description % Acceptance Criteria Verifying Document Sign Sign Sign
Type A B C Reports No.
Date Date Date
FOR DOUBLE WALL CJP < 8MM AT TWO STAGES : 1st step
100% MT AFTER ROOT PASS DIRECTLY MAX 3 MM -2nd step 100% AWS D1.1 MT Report MT H&RI
100% MT( AFTER FILLING + CAP )(Dynamic or static )
2 Surface preperation for painting 100% Client Specs painting report VT H&RI
VT& D.F.T
3 Painting check 100% Client Specs painting report H&RI
check
VT& D.F.T
4 Galvanizing check 100% Client Specs Galvanizing Report H&RI
check
5 Documentation check 100% Client Specs ITP H
7 Final release for shipment 100% Client Specs Final Release H&RI