Power Shutdown Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Power Shutdown Work Schedule

Start Date 11/20/2021 (Saturday) 1


Work Lead Maintenance Department
8:00 8:15 8:30 8:45 9:00 9:15 9:30 9:45 10:00 10:15 10:30 10:45 11:00 11:15 11:30 11:45 12:00 12:15 12:30 12:45 13:00 13:15 13:30 13:45 14:00 14:15 14:30 14:45 15:00 15:15 15:30 15:45 16:00 16:15 16:30 16:45 17:00 17:15 17:30
%
WBS TASK LEAD START END Time S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S S
DONE
1 Phase 1 Servicing of Normal Power -
1.1 Manpower preparation on site with toolbox meetings Ken Chan 8:00 9:00 1:00 0%
Isolation of all Fire Alarm, informing of Decam regarding shutdown. Homing of ALL
1.2 On Engineer 8:30 9:00 0:30 0%
Passengers, Fireman & Cargo lifts, lifting of carpark barriers
Perform changeover for MB10-EE-EMSB-101 at MB10-EE-MSB-101 to test the genset and ATS
1.3 On Engineer 9:00 9:05 0:05 0%
functionality
1.4 Perform tripped test for all protection relays at MB40-EE-MCC-CH401 (Chiller plant room) On Engineer and Trane 9:00 9:15 0:15 0%
1.5 Perform tripped test for all the protection relays at MB10-EE-MSB-101 On Engineer 9:15 9:25 0:10 0%
Shutdown of 22kV Switchgears and to the outgoing transformers SS10-EE-TX-101 & SS10-EE-
1.6 On Engineer and Power Grid 9:25 9:30 0:05 0%
TX-102
1.7 PowerGrid to de-energise power supplies serving to 22kV Switchgear (7 Chin Bee) On Engineer and Power Grid 9:30 9:40 0:10 0%
Servicing of 22kV Switchgears, Transformers (SS10-EE-TX-101 & SS10-EE-TX-102), MB10-EE-
1.8
MSB-101, AMF Panels and MB40-EE-MCC-CH401
On Engineer and Power Grid 9:40 15:40 6:00 0% Generator is running during this hour - (6 Hours running)
1.9 PowerGrid to re-energise power supplies serving to 22kV Switchgear (7 Chin Bee) On Engineer and Power Grid 15:40 15:50 0:10 0%
Normalise of power supplies to 22kV Switchgears and outgoing Transformers and MB10-EE-
1.10 On Engineer 15:50 15:55 0:05 0%
MSB-101
2 Phase 2 Servicing of Emergency Supply (Generator) -
2.1 IT team standby onsite for UPS before EMSB is shutdowm IT Dept and Finnlayson 15:30 16:00 0:30 0%
Upon approval from IT team, to proceed to perform tripped test for all the protection relays at
2.2 On Engineer and Linear Power 16:00 16:10 0:10 0%
MB10-EE-EMSB-101. Switch isolator to off and isolate generator
2.3 Servicing of MB10-EE-EMSB-101 On Engineer 16:10 16:40 0:30 0% 45 mins. Support Server

Normalise of power supplies at MB10-EE-MSB-101 to MB10-EE-EMSB-101 and all outgoing.


2.4 On Engineer and Linear Power 16:40 16:45 0:05 0%
Normalise of generator, switching isolator to ‘Auto’