I. Structural Deficiencies
1. Install seismic bracing at top of masonry block walls.
2. Remove flux from structural welds and retest welds.
3. Break un-sheared off ends of TC bolts and torque the connection.
4. Weld moment plates as required.
5. Place required re-bars at negative moments at pile caps.
6. Grout column bearing plates.
7. Install the required additional re-bars at slab & wall openings.
8. Remove debris from expansion joints.
9. Complete the return on welded connections.
10. Provide test reports for controlled backfill material.