Professional Documents
Culture Documents
TAL SMZVN MS E 0010 WMS E 07 Busway Installation and Connection Work
TAL SMZVN MS E 0010 WMS E 07 Busway Installation and Connection Work
RcCEIVED
Your submission for approval is subject to following conditions : (Dan a~ trinh phe duy~t c6 ket qua nhll'
sau):
Approved (Chap thu~n) Approved on condition as noted (Chap thu~n v&i dieu ki~n ghi
chu)
~ mend and resubmit(SU'a va trinh lli!i) Not approved as noted (Khong chap thu;;in v&i ghi chu )
I. ! r f ~
Name (Ten): Name (Ten): ~f Name (Ten): Bui Truong San M
Position (ChLl'c v1,1): Position (ChLl'c v1,1): Position (ChLl'c v1,1): Project Manager
Date (Ngay): Date (Ngay): r
A2 - oJ . J Date (Ngay):
METHOD STATEMENT
GUIDANCE NOTES
Where this page is over-stamped with the words "Controlled Copy" this means:
a] Distribution is centralized - in this case of this document from the M&E Manager;
b) Each copy is issued to a particular person or organization. If the document is no longer
required it should be returned to the relevant person;
c) It is not to be photocopied either in whole or in part. Additional copies are available upon
request;
d) Copy holders will be automatically issued with any amendments. Responsibility for
incorporating such amendments rests with the copy holder.
1
~
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev .: 00
CONNECTION WORK
TABLE OF CONTENTS
l. General 3
l. l Description 3
2. Methodology 3
5. Quality control 9
7. Equipment List 10
8. Safety management 10
APPENDICES
2
~
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev.: 00
CONNECTION WORK
1. GENERAL
1.1 Description
This method statement describes the procedure, quality control, environment management
and safety control aspects of busway installation & connection work.
1.2 .Scope of work:
Installation location should follow builder grid line for locating and elevation reference
Consultant: Permit and hand over plan to Shimizu.
Inspection work items fo llow ITP.
Shimizu:
+ Shimizu will present installation method statement, preparation work, Job analysis and risk
easement before executing any works
+Works will be supervised to make sure that all work is carried out in compliance with
approved documentation.
+ Invite consultant inspection before and after finished work.
1.3. Material use:
Manufacturer/Country
Detail of Spec.
No. Materials of origin Category
Remarks
l Busway 5000A, 3P+N+PE Schneider /China
2. METHODOLOGY
2.1. Preparation works:
- The temporary works as: material stock, fabrication, hand tools will be prepared in advance.
- Confirmation of working drawing and preparation of working at workshop shall be done prior
to work. Materials and machineries/equipment necessary for the work shall be set up.
- Clearing the site before realize the work.
2.2: Sequence of works:
Preparation work
Installation work
•
Survey and mark the location
Consultant inspection
4
+
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev.: 00
CONNECTION WORK
- Upon material delivery, internal inspection must be carried out by NS & SMZ.
- Check and prepare technical specification document of material same as approved.
2.3.1.2.2 CM ( construction management) inspection.
5
~
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev.: 00
CONNECTION WORK
- All information and testing result will be recorded in document for hand-over later.
- Before realizing termination work, the phase and size of cable terminal and MCCB terminal must
be checked carefully.
- Only the qualified personnel must be allowed to do termination work.
- Strip cable cover to bring out the cores and exposed conductors, for the minimum length
required for connection, to leave no exposed length of conductor after termination. Ensure that
strands are not damaged when stripping cable cover. Do not reduce number of conductor
strands. Secure all strands at terminals.
- All cable connections shall be made with approved cable lugs, pressing-type together with the
usage of proprietary tools.
- Use cable gland for cable incoming to end tap box, plug in unit and production panel.
- Pay attention to tighten the bolts of lug and marking. The tightening torque depends on bolt size.
- Installing name tags at each end of all cables to identify each cable.
- Checking the connection point comply with specification.
- Checking the strongly of connection among termination.
2.3.3. Installation inspection.
2.3.3.2 CM inspection.
- Request CM for inspection installation work.
- Check quality of installed busway on site.
- Check busway and supports installed based on approved shop drawing and design
specification.
- Upon inspection request CM to sign the document.
7
~
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev.: 00
CONNECTION WORK
...
SMZ-Site Manager
Mr. Boan
SMZ-safety officer I•
"
Ill SMZ-Site Engineer • .., SMZ-QA/QC Engineer
1
Mr.Toan Mr. Nguyen Danh Thai Mr. Duong
... •
...
M&E Contractor: North Star NS-Site Manager I~ 1 1 Safety Officer
..,
...
NS-Site Engineer QA/QC Engineer
1
... ...
Unloading & transferring Installation work (Team)
work (Team)
'
Worker: 10
Worker: 10
8
+
Rev date: METHOD STATEM ENT
WMS-E-07 : BUS WAY INST ALLATl ON &
Rev.: 00
CONN ECTION WORK
4. 1 Description of duty:
SHIMIZU main contractor:
1: Shimizu - M&E Manager:
Generally manage a ll ME work and to ensure that proposed working schedule followed.
2: Shimizu-M&E Coordinator:
Support M&E manager about Schedule , Procurement and coordinate with employer,
consultant
To get information related to M&E works.
3: Shimizu - Site engineer:
+ Check preparation works and documentation can commence on schedule. Arrange to
Facilitate correction of any documents outstanding.
+ Supervise to make sure that all work must be carried out follow method statement and
Drawing approved by consultant and client
+ Coordinate w ith QC engineer for inspection work (internal and Consultant/ Client inspection.
4: Shimizu - QC engineer:
+ Daily checking on site, instruct to Subcontractor if not follow installation specification
+ Coordinate with Subcontractor QC engineer for internal inspection and Consultant/client for
official Inspection.
5: Shimizu - safety engineer:
+ Daily checking on site, instruct to subcontractor if not follow safety regulation
+ Safety engineer can stop subcontractor working if they proceed unsafely
Northstar subcontractor
+ Follow all instruction from Shimizu Site engineer, QC engineer, Safety officer to directly
Execute at site to make sure all work shall carry out safety, quality and finish on time.
+ Subcontractor must execute al l step as mention method statement
+ Inform to main contractor for inspection after complete .
5. Quality control :
+ Shimizu, consultant, subcontractor must check working plan condition before working.
Subcontractor can execute just as Shimizu a nd consu ltant accepted.
+ Inform consultant to check al l working pla n after installation, connection and cleaning.
6. Detailed schedule/ Manpower Requirement:
(Refer to attached schedule for detail)
9
+
Rev date: METHOD STATEMENT
WMS-E-07: BUSWAY INSTALLATION &
Rev .: 00
CONNECTION WORK
7. EQUIPMENT LIST
7 Scaffoldinos 2 sets
8. SAFETY MANAGEMENT
Prior to start installation work, the following matters w ill be thoroughly constructed to all personal
working on construction site in order to complete the works in accordance with the approval
documents and procedures.
8.1. Joint meeting:
'
Prior to start any activity, a meeting with member directly join on work will be held for purpose of
explanation whole content of work and point all potential risk may occur during construction work
and inform schedule power off for owner factory.
8.2. Instruction:
For new staff join the works, a safety course will be held by Shimizu.
The instruction will be explained same content as above meeting item.
8.3. Prevention of Accident by Heavy Machine
Only skilled operators shall be allowed to operate the heavy machines on site. In case of new
operators , a test of skill shall be conducted first prior to allow him. Maintenance check shall be
done regularly at site prior to full operation. The excavator range must be indicated by safety
barricade and place warning sign;
8.4. Prevention of Accident of Electrocution
10
+
Rev date: METHOD STATEMENT
WMS-E-07 : BUS WAY INSTALLATION &
Rev.: 00
CONNECTION WORK
Equipment use electric power shall be properly protected and properly installed with earth
connection. Electric wires shall be connected with electrical tapes to prevent electric leakage.
Only skilled operator shall be allowed to operate equipment on site.
8.5. Prevention of Accident in Night Shift Works
Sufficient quantity of lighting system shall be provided for night shift works especially installed at
working area. If necessary all of the surrounding working area shall be lighted up.
Beside of the above action, all the activities on site must be follow approved "Project Environment
Plan" and the entire related Environment's current regulation of the Vietnam Government.
11
~
Rev date: M ETHOD STATEM ENT
WMS-E-07: BUSWAY INSTALLATION &
Rev.: 00
CONN ECTION WORK
BUS.VAY P.'CX.la
ON PM.lff
SlfE1Y SUP1Ji',1SOR
PVC SHffiS
SUSWAY PIICK,!l;E
'HOOD P.ILLEl
'.%
12
+
Rev date: METHOD STATEMENT
WMS-E-07 : BUSWA Y INSTALLATION &
Rev.: 00
CONNECTION WORK
Seo ffoldinq
safety harness
::::::::::::::::i!i!iii!i!i!i!i!i!iti}i!if::::::::::::::::::::::::
::::::!:t:J:::::::;:::::::!:::::::::::::::::::::::::::::::g:::::::
1po9:>;op~;o909090:0909090909090;090;0Qo90Qo;o;o;o;o;o909090Q0Qo;o
13
~
Rev date: M ETHOD STATEM ENT
WMS-E-07: BUSWAY INSTALLATION &
Rev. : 00
CONN ECTION WORK
Scaffolld1n
safely narness
FFL
14
~
Rev date: M ETHO D STATEM ENT
WMS-E-07: BUSWAY INSTA LLATION &
Rev.: 00
CONN ECTION WORK
Scaffol~in
safety 111arness
o "'o
o ..o o""o"'o"o"o"'o
o o o o o ...o o"'o"'o-o-o"'o
o o o o oa.o ..o-o-o"o"'o~o-o-o
a o o o o o o ....
o.o'"'o"'o-o-o"'o
o o o o o .. o o"'o'"o-o"o
o o o o
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
g~g~g~g:g:g:g:g:g:i:g~g:g:::g:g:g:g:g:g~g:g:g:g:g:g:g:g:g:g~g:g:g
g:g~g:::g:::g:g:g:g:g:g:g:::g:g!g~g:g:g:g:g:g:g:g:g:g:g:g:g:g:g:g
0o o o o o o o o o
0 0 0 0 0 o o o o o o o
0 o o o o o o o o o o
0 0 0 0 0 0 0 0 0 0S!.
0 0 0 9 0 0 9 9 9 9 9 9 0 9 0 0 0 0 0 2 9
FLOOR
15
LAM Vl~C TREN CAO ~'\.
f Royal
HaskoningDHV
Giay phep nay dlJ'Q'C treo a vi tri de !hay l,;!i khu Vl,J'C lam vi$c/khu VlJ'C cong tac. iN°.!Jft(,,1~ 5«~, •Dgtttff
r''
8 C6 li:!p dat h$ thong day CLJ'U sinh ? PHAN D: CAP PHEP
9 Cong nhan lam vi$c ten cao da dlJ'Q'C huan luy$n? 13
Giay phep c6ng tac nay cho phep ngll'ai thl,)'C hi$n dlJ'Q'C
10
ThiOt bi bao hQ tao I lien hanh Cong tac !,;ii khu VlJ'C lam Vi$c nhll' da de c;ap.
B
D Ung bao ho
Gang tay
Giay bao ho D
N6n bao ho
Mat n,;1 han
Kfnh bao ho
D
D
Thiel bi bit tai
Day an toan
11 Mot so bien phap ph6ng ngLYa can thl,l'C hi$n: ChCt ki cua nqll'6'i d,;1i di$n Haskoninq
PHAN E: CHAP THU~N
14 Toi hieu rang c6ng vi$c phai dlJ'Q'C thl,)'C hi$n di doi v&i
cac bi$n phap an loan. Toi dong y va chap thuan tat ca
cac qui trinh va se dLYng c6ng vi$c neu cong vi$c khong
I
ChC, ki cua nQU'O'i VhlJ'C hi$n: Giam sat thi conq
PHAN F: Kl:.TTHUC
1s Ket thuc/Huy bo
Toi cam ket nhQ>ng cong vi$c tren da dlJ'Q'C c:::J E)a hoan thanh
D ChlJ'a bi:!t dau
(Banh dau vao 6 c6ng tac) D Bi:!t dau nhll'ng ChlJ'a hoan thanh
Va khU Vl,l'C cong tac da dlJ'Q'C thu dQn gQn gang, ngan ni:!p vatrong dieU ki$n an loan
copy1 :fJ~t f?i khu vvc lam vi~c copy2: LU'U ho sa copy3: Gui b¢ phfin an toan
~ Job title: WMS-E-07 Busway installation & JSA No: 007 Page: 01 IDate:
Royal connection work
Job location: Team: Mr. Tinh, Mr.Hung, Mr.Son, Mr.Tran, Mr.Thanh, Mr.Hung , Mr.Quynh, Mr.Quy,
HaskoningOHV Mr.Quy
fnh;Jr~ " 'f/ \l>(itly To.Jt l lU', Project: TAL Garment
3.1 Trapped hand 3.1 Apply the working at height permit to work Engineers & Safety officer
3.2 Slip/trip/fall 3.2 Check electrical power before working Supervisors
3.3 Working at height 3.3 Cover by Temporary Barrier & install sign boards information all around working area Workers
3.4 Dropped object, loose items may fall height 3.4 Workers use PPE full
3.5 Scaffolding drop 3.5 Equipment & Tools hand must inspection before working
3.6 Collapse of scaffolds - improper base plate or 3.6 Install access.platform.handrail ,pipe support scaffolding for workers when working at height
3.7 soft ground/not flat ground, fl oor 3.7 Barricade the surrounding working area.To pause the surrounding activities near the working area and while
3.8 Working with Drilling machine work er is working above.
3.9 Elec trical shock 3.8 Inspection scaffolding and hang tag scaffolding safety to you
3.10 Dust 3.9 Dant stand under when have worker working at height
Step 3: t nstallation works
3 3.11 Materials falle n and spit out to eye 3.10 Just accepted scaffolding have full checklist & card
(Use Scaffolding ... )
3.12 Hit by th e crane and lift up 3.11 Ensure scaffold is on soil level footing
3.13 3.12 No person is to be on the scaffold whilst it is moved
3.13 Equipment and materials must be either removed from the scaffold or secured to prevent anything from falling
from the scaffold during the move
3.14 The ground conditions of the new working area must be inspected prior to the move to ensure it is free of
obstructi ons and is suitable to carry the load of the scaffold
3.15 Working carefully
4.1 Slip/trip/fall 4.1 Engineers. supervisor and worker must use PPE Supervisors
4 Step 4: Inspection 4.2 Install sign board s information around inspection area
5.1 Oust 5.1 Remove unnecessary material, remove waste Engineers & Safety officer
5.2 Slip/trip 5.2 Good housekeeping before, during & aft er working Supervisors
5 Step 5: Housekeeping 5.3 Access must be clear at all time for emergency exiU purpose Workers
I ISE-08-JSA Fo rm
I-ISE Man ual
Pa i.t,c I of l
SCHEDULE INSTALLATION BUSWAY
I Al GARMENT FACTORY
J-rrH~~
No. TASK SUB·CON DURATIONS (DAYS) 10 II 12 13 14 IS 16 11 18 19 2i.l 21 22 2} 24 25 26 27 21 29 10 JI 32 Jl Jc!
3
Submit permil form
Preparation works
NS
NS
- -
3
4
- - - - - - -1----+ - - - l -----l
-fm,m~fdafrovli_
I -
Pre ara1on w rks
-
j 2
I
Setup safety barricade NS Set p sa ty b rica e
Install busway NS 5
Termination \NOrk NS 5 8
1-- - - - - - - - - - - 4 - - - - - - - - - - l- - - - -
5 Tesling works NS
lea n ng & torage
6 Clean & Restoration NS 2
I
20
Manpower Requirement
15
LO
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24. 25 26 27 28 29 30 31