Professional Documents
Culture Documents
Load Calulation
Load Calulation
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
1 Load calculation 1
2 Design 2
5 Design of Footings 4
6 Design of Piles
7 Design of Pilecaps
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
Uniform load due to wall including 16 mm plaster and 40 thk coping 8.89 kN/m
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
Force Coefficient for Low walls or Hoardings as per Table 26 of IS 875 Part-3
b/h 20.18
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
415
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
415.0
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
1 Design of Beams
Breadth B= 250 mm
Depth D= 250 mm
Clear Cover = 30 mm
Md supp / B x d ^2 = 0.72
Pt Provided = 0.29 %
Md supp / B x d ^2 = 0.60
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
415
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
1 Design of Column
Breadth B= 250 mm
Depth D= 250 mm
Clear Cover = 30 mm
Md supp / B x d ^2 = 0.72
Pt Provided = 0.29 %
Md supp / B x d ^2 = 0.60
PROJECT: Execution of 05 Nos of individual rural piped water DOCUMENT NO. DATE
supply projects pertaining to Nuapada district LE180170-C-WS-CW-DC-3474 3/8/2019
TITLE: DESIGNED CHECKED SHEET
Compound Wall
CKP BRJ
415