2B Fire Sprinklers (Wet Pipe System) Qty Unit Daily Output

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

2B Fire Sprinklers (Wet Pipe System) Qty Unit Daily

Output
Main Building area 200' x 130' or 26,000 sqf
Spacing of sprinklers is 1/130 sqf per sketch
Fast Act glass bulb 135 to 155 degrees sprinklers
1/2" npt brass Sprinkler 200 Ea 16
3" Sch 40 Piping includes couplings & hangers 53 ft
2.5" Sch 40 Piping 80 ft
2" Sch 40 Piping 10 ft
1.5" Sch 40 Piping 800 ft
1" Sch 40 Piping 560 ft

Pipe sub total above 43,969


Pipe waste factor - add 10% to total above
3" - "T"s 11 Ea 6
2.5" - "T"s 8 Ea 9
2" - "T"s 1 Ea 11
1.5" - "T"s 160 Ea 13
1" - "T"s 40 Ea 8
1" pipe plug end caps 40 Ea
90 degree elbows 3" Pipe 1 Ea 10
1.5" - Nipples x 4" Long 140 Ea 24
1" - Nipples x 4" Long 40 Ea 15
3" Pipe Reducer 11 Ea 14
2.5" Pipe Reducer 10 Ea 18
2" Pipe Reducer 1 Ea 21
1.5" Pipe Reducer 40 Ea 24
Cutting & Threading pipe Labor Ea 3" 23 Ea 50
Cutting & Threading pipe Labor Ea 2" 18 Ea 53
Cutting & Threading pipe Labor Ea 1" 400 Ea 73
10% Contingency for Sprinkler est.
Sprinkler Design fee 4% of Sprinkler only cost
A.H.J. permit review fee for this city
15' high Scissor Lift (1 week) 7 Day

Sub Total
Labor Bare Bare Bare Bare Total
Hours Mat Labor Equip Total usd

0.5 23.5 17.3 40.8 10,800


29.5 11.15 51 2,703
23 9.6 41 3,280
14.9 7.5 29 290
11.15 5.95 22 17,600
7.55 5.05 16.6 9,296

4,397
2.7 350 80 430 4,730
1.8 135 53 188 1,504
1.5 66.5 43.5 110 110
1.2 53 36.5 89.5 14,320
1 23 33.5 56.5 2,260
7.7 8.85 23 920
1.6 197 48 245 245
0.7 4.8 19.8 24.6 3,444
0.5 3.24 17.7 20.94 838
1.1 20.5 34 134 1,474
0.9 57 22 107 1,070
0.8 25.5 22.5 65.5 66
0.7 17.7 19.8 52.5 2,100
0.2 5.3 8.8 202
0.2 5.05 8.83 159
0.1 3.65 6 2,400
9,000
3,383
3,500
54 378

100,468

100,468