Operations Management 475 - Short Answers Question 2

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

E

5 wks
G I
A.
6 wks 6 wks
B C
8 wks 3 wks F
7 wks
Start A H
5 wks 8 wks J Finish

D 5 wks
4 wks

B.

TASK EARLY START EARLY FINISH LATE START LATE FINISH SLACK TIME
A 0 5 0 5 0
B 5 13 5 13 0
C 13 16 13 16 0
D 5 9 17 21 12
E 16 21 16 21 0
F 16 23 18 25 2
G 21 27 21 27 0
H 23 31 25 33 2
I 27 33 27 33 0
J 33 38 33 38 0

C.

Path 1 = A+B+C+E+G+I+J = 38 weeks

Path 2 = A+B+C+F+H+J = 36 Weeks

Path 3 = A+D+G+I+J = 26 weeks

The Critical Path in this case would be Path 1 which is 38 weeks