SCOPE OF WORKS DOCUMENT

FM-ENG-PRJ-001

REV
Personal Lockers for Met Team Fabrication
00

WCP A Office Level

Project Owner:
Project Nr.:
Armindo Fortes

Project Manager: Project Name:


Celso Moisés De Jesus Xavier Personal Lockers for Met Team Fabrication

Start Date: Tender closing Date:


On receipt of PO

Site Meeting date: Works Completion or Shutdown date:


On request

NOTE: ONCE COMPLETED, THIS DOCUMENT TO BE SAVED AS A PDF DOCUMENT AND


ATTACHED TO THE RFQ WORKFLOW IN ORB FUSION

1. INTRODUCTION

Unless otherwise expressly provided herein, the CONTRACTOR shall supply all supervision,
labour, equipment, tools, materials, transport, travel, accommodation, fuel and each and
every item of expense necessary to manufacture, deliver and test (Personal Lockers for Met
Team Fabrication), as per detailed fabrication drawings supplied by Kenmare (hereinafter
referred to as WORKS).

2. DESCRIPTION OF WORKS

2.1 WORKS TO BE PERFORMED (Personal Lockers for Met Team Fabrication)

The CONTRACTOR shall perform the WORKS described in clause 1 above, which shall include
but not be limited to:

2.1.1 Civil

 N/A

2.1.2 Structural: The following is required from contracting company -

 Fabricate Personal Lockers for Met Team with 18 compartments according to drawing,
 Paint the locker and

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 1 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

 Transport it to the WCPA office level.

locker Door

LockerDoor Lock
1 [] 2 [] 3 []

Must Have a total of


Note:
18 Doors
[] 5 [] 6 []
4 Measurements For Each
Compartment
Length: 55 Cm
[] [] [] Width: 44 Cm
7 8 9
Height: 33 Cm

10 [] 11 [] 12 []

13 [] 14 [] 15 []

16 [] 17 [] 19 []

2.1.3 Mechanical

 N/A

2.1.4 Piping and Services

 N/A

2.1.5 Electrical & Instrumentation

 N/A

2.1.6 Pre-Commissioning

The CONTRACTOR shall supply all labour and materials to pre-commission the work.

The CONTRACTOR shall allow access to and work closely with Kenmare pre-commissioning
team who shall witness the CONTRACTOR´s activities.

The CONTRACTOR shall prepare and submit to Kenmare for approval his pre-commissioning
procedure, activities and programme at least (indicate number of weeks) prior to the start of
pre-commissioning activities. The results of the CONTRACTOR’s pre-commissioning activities

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 2 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

shall be logged in a pre-commissioning manual. The pre-commissioning manual shall be


submitted to Kenmare at the end of the pre-commissioning activities.

2.1.7 Performance Criteria, Commissioning Testing and Handover

The following performance criteria shall be guaranteed by the CONTRACTOR and shall be
checked during commissioning testing:

 Ensure that a working system is handed over to Kenmare,


 Ensure that all housekeeping is done.

The CONTRACTOR shall supply all the supervisory manpower required to commission the
plant with the assistance of the Kenmare project, operating and maintenance personnel. He
shall also maintain a supervisory and labour workforce of trades’ personnel to repair faulty
equipment or adjust plant design during the commissioning period.

The installation/equipment performance and settings shall be measured, adjusted as


required and recorded for future reference where applicable. This performance testing shall
be conducted in accordance with the commissioning plan.

A Taking over (Handover) Certificate shall be issued for the Works or part thereof on the
successful completion of the performance testing as described above. This will determine
the start of the warranty period.

2.1.8 Training (N/A)

2.1.8.1 General

The CONTRACTOR shall prepare training manuals and shall provide training of Kenmare
personnel for the operation and maintenance of the new asset/plant.

The training tools shall be developed by the CONTRACTOR from the documents prepared for
the project such as:

 Flow sheets
 Drawings
 Manuals - both operational and maintenance
 Functional analysis
 Software programmes.

2.1.8.2 Scope of Training

The training shall include:

 Classroom training of Kenmare operational supervisory personnel (Indicate the number


of people to be trained)

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 3 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

 Classroom training of Kenmare control and instrumentation supervisory personnel


(Indicate the number of people to be trained)
 Classroom training of Kenmare maintenance supervisory personnel (Indicate the
number of people to be trained)
 Hands-on training of Kenmare operation and maintenance personnel.

2.1.9 Spare Parts (N/A)

The CONTRACTOR shall supply a comprehensive spare parts manual and a recommendation
of spares to be carried for two (2) years of operation.

The CONTRACTOR shall supply all commissioning spare parts unless otherwise stated. Other
spares i.e. consumable parts and wearing parts shall be excluded.

2.1.10 General

All works on site that can impact on normal plant production is to take place during planned
maintenance shutdowns and must not impact on ensuring plant start-up.

Shutdowns take place every (Can be done on the run). Longer shutdowns may be arranged
on a case by case basis with careful planning with the Plant.

All other work that does not impact on normal plant production is to take place between
07h00 and 17h00 during weekdays only and between 07h00 and 12h00 on Saturdays.

2.2 FURNISHED BY CONTRACTOR


The CONTRACTOR shall supply, maintain and remove at its expense items to complete the
above said WORKS that shall include but not necessarily be limited to the following:

 Site Visits costs for Request for Quotation Meetings


 Staff travelling (flight tickets and/or road transport)
 Onsite staff accommodation, food and laundry services
 Site offices, lockable containers, onsite transport and communications
 All fuel, unless otherwise stated
 All workforce required

2.3 FURNISHED BY KENMARE:


Kenmare will supply without costs to the CONTRACTOR:
 Scaffolding
 Touch-up painting
 Electric power (220V single phase & 380V 3-phase, 50Hz)
 Potable drinking water at existing points of supply
 Materials and consumables

2.4 EXCLUDED WORKS:

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 4 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

 Scaffolding erection and dismantling


 Corrosion protection (touch-up paint) of new welds and area surrounding repairs unless
otherwise stated.
 (Add any other items that the scope explicitly excludes)

3. DRAWINGS, SPECIFICATIONS, LAWS, CODES AND STANDARDS

3.1 DRAWINGS (N/A)

The CONTRACTOR shall perform the works in strict accordance with the drawings and other
documents listed below:

NUMBER REVISION TITLE

3.2 SPECIFICATIONS

The CONTRACTOR shall perform the works in strict accordance with the specifications and
other documents listed below:

NUMBER REVISIO TITLE


N
SOP-0029 03 Contractors Management Procedure

PRO-0007 03 Personal Protective Equipment

PRO-0029 03 Hand tool Procedure

PRO- 0055 05 Hot Work Procedure

PRO-0089 04 Lifting Machines And Lifting Tackle Procedure

SOP-ENG-SRV-0002 03 Isolation & lockout Management Procedure:

SOP-ENG-MIN-0012 00 Grating, Guardrails, Pontoon Hatch Cover & Floor Plate


Removal.

SANS 1200 AH, H &HA Structural Steel

AWS D1.1 Welding

6857-00000-B50- 01 Engineering Specification for Corrosion Protection


0004.00-01

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 5 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

3.3 LAWS, CODES AND STANDARDS

All design, procedures, materials, tests and analysis shall be in accordance with the latest
editions of National and International codes, standards and specifications, including all
amendments and revisions, all relevant Kenmare Standard Operating Procedures and best
engineering practice.

All works shall comply with the State of Mozambique General Regulations on Occupational
Health and Safety in Industrial Premises, Statute No 48/73 and both the South African
Occupational Health and Safety Act No. 85 of 1993 and Mine Health and Safety Act No. 29
of 1996, and all amendments thereafter.

The CONTRACTOR must strictly follow the applicable Legal Legislations in Health and Safety,
Employee contracting, Labour, Immigration and other related Legislation.

4. SITE CONDITIONS

 Kenmare Moma Sands is situated in the Northern part of Mozambique at the coast next
to Topuito. Nampula is the largest city in the region and is situated approximately 150
km North of Topuito.

 Kenmare site is situated at: Latitude - 160 33’ 02.52’’ S, Longitude - 39° 37’ 14.04’’ E

 Road between Nampula and the mine is a dirt road and not in a good condition. Average
5-6hrs travel by LDV between site and Nampula

 Ambient temperatures are generally hot and humid during summer months. Malaria is
prevalent in this area.

 Allow approximately 3 weeks for equipment delivery to site.

 Accommodation (with 3 meals per day), laundry services and a tuck shop (with basic
supplies) are available onsite at a cost.

 Kenmare operates two flights per week to/from site with limited seats and with 12,5kg
weight limits per pax associated to luggage and personal items. Commercial flights to
Nampula are also available.

 On Mondays/Thursdays the charter flies Lanseria-Maputo-Beira-Site-Nampula-Site and


on Tuesdays & Fridays the route is Site-Beira-Maputo-Lanseria.

5. SAFETY, PRODUCTIVITY & QUALITY

 Safety, productivity and quality is of utmost importance for this project. Therefore, it is
important to ensure that all personnel offered to assist with this project is properly
skilled and experienced.

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 6 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

 Prior mobilizing project personnel to site, the CONTRACTOR shall ensure that medical
examinations to Kenmare´s standard are conducted for every team member and sent to
site for approval. Also, the CONTRACTOR shall ensure its personnel attend to exit
medical examinations onsite before final departure (at the end of project site works).
“Fit for Work” (FFW) certificate will be required for each person and includes the
following:
 Audiometry exam
 Spirometry test
 Vision tests
 Chest X-Ray
 Detailed occupational health medical questionnaire
 Blood tests, urine tests, and drug tests, where applicable

 All CONTRACTOR´S employees (including casual labour and sub-contractors) who will
require access to site must attend a 2-days safety induction course before being allowed
to site.

 Before commencement of any site work, the CONTRACTOR shall submit its SHE Plan for
Kenmare approval and shall ensure that his personnel are issued with the required
Personal Protective Clothing/Equipment (PPC/E).

 The CONTRACTOR shall be aware of and abide by the requirements as set out in the
standards, specifications and drawings. No deviation from the standards, specifications
or drawings will be allowed, unless approved by Kenmare in writing.

 The CONTRACTOR is required to submit Method Statements together with associated


Risk Assessments, including mitigations, for the execution of the works.

 Access, Hot Work and Confined Space Permits will be issued daily prior to commencing
any work.

 The CONTRACTOR shall ensure that their personnel are supervised full-time to ensure
that there are no safety violations or transgressions issues.

 Kenmare’s safety rules and regulations apply full time on site. For more detail, refer to
procedure SOP-0029 Contractors Management Procedure

6. PRICE BREAK DOWN IN THE RATE CARD

The attached rate card will be used when submitting quotations for all Engineering projects
by Kenmare during the term of the Engineering Services Agreement.

Suppliers will use the agreed rate cards

When Submitting quotations, using the Rate Card the following information will be included:

 Whether local or overseas employees

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 7 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

 Number of trades to be used

 Number of hours for each trade

 Overall timeline to complete the services

 Commencement and finish time

 Material costs must be submitted attaching the material costs (with no mark-up).

 Material delivery costs must be submitted separately (with no mark-up).

 Lead times must clearly indicate material delivery lead time, service starting date and
completion date.

 Travel to and from site (where applicable), accommodation (where applicable), food,
travel on site, transportation on site, material costs and transportation to site (where
applicable).

 When submitting the invoice, and in order for Kenmare to reimburse the travel,
accommodation and food costs, copies of the proof of such expenses must be submitted
separately from the Rates.

 Requirements for Purchase Order variations costs must be signed off by the Requestor a
separate Variation Purchase Order will be created based on a new quotation which
refers to the existing Purchase Order.

 Any other costs with a comprehensive explanation.

 Prices should be broken down in sufficient detail to form a clear understanding of the
cost structure.

 Foreign contractors work on site (labour cost only) will invite withholding tax (WHT) of
approximately 20% and needs to reflect on quotations. Contact the commercial liaison
to determine more information if required.

7. QUOTATION SUBMISSION, PURCHASE ORDER & INVOICE CURRENCY

The supplier must always refer to the agreed rate card prices & submit the quotation in
Meticais (preferred) using the agreed prevailing exchange of the month. The currency of the
Request for Quotation, Purchase Order and Invoice will be preferred in Meticais, unless
arrangements to an agreed foreign currency is achieved with the commercial liaison.

8. PERFORMANCE SCHEDULE

Before COMMENCEMENT with the WORKS, the CONTRACTOR shall submit a schedule that
must be approved by Kenmare Engineer. No changes on the approved schedule will be
permitted without the consent of the Engineer or his nominated representative.

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 8 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

The performance schedule shall make provision for but not be limited to the following:

 Mobilisation time required by CONTRACTOR in respect of labour and equipment


 Date of material deliveries to site
 Shop fabrication time
 Incremental completion dates in respect of major equipment
 Start and completion dates for each phase of the project
 Other as agreed by the CONTRACTOR with Engineer or his nominated representative

9. WARRANTIES & DEFECT LIABILITY

The CONTRACTOR must acquaint itself with the warranties as specified in the Kenmare
General Terms and Conditions for rendering services, which shall be the minimum warranty
acceptable to Kenmare.

Warranty period: 12 months from approval of Take Over Certificate (C1)

Defect Liability period: 12 months from Practical Completion date (C2)

10. REPORTING REQUIREMENTS

The CONTRACTOR shall submit reports and schedules as requested by the Kenmare Engineer
or his nominated representative, which may include the following but not be limited to:

 Progress report
 Quality control plans
 Critical path schedule
 Daily report
 Monthly report

11. CLARIFICATIONS AND QUERIES

Should the CONTRACTOR have any queries with regards to this tender, the following people
may be contacted for clarification purposes:

Technical queries:
Name: CELSO XAVIER
Mobile: +258 844066938
Phone: Extensio: 180
Email: cxavier@kenmare.com

Procurement queries:

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 9 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

Name: Insert info


Mobile: Insert info
Phone: Insert info
Email: Insert info

12. APPROVAL

TITLE NAME SIGNATURE DATE


SCOPE AUTHOR Celso Xavier
/PROJECT OWNER Armindo Fortes
ENG PROJ. SUPT.

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 10 of 11
SCOPE OF WORKS DOCUMENT
FM-ENG-PRJ-001

INTERNAL NOTE TO PROCUREMENT

1. Projects, Requisitions and or Purchase Orders Related to this Scope of Services:

2. Level of Urgency:
a. Very Urgent _______
b. Urgent _____X__
c. Not Urgent _______

3. Latest Start and end Dates Allowed:


Start Date: On receipt of PO
Termination Date:
Please Justify:

4. Are bidders required to visit Site to better understand the requirement? (YES / NO)
4. The Complexity level of this Requirement is (marked X)

High (A Suppliers for Engineering Services)

Medium (B Suppliers for Engineering Services)

Low (C Suppliers for Engineering Services)


x

DOCUMENT NO. REVISION REF. DOC. ISSUE DATE PAGE


FM-ENG-PRJ-001 01 FM-ENG-PRJ-001 11/23/2021 11 of 11