Bhopal Metro Rail Project

Package BH-06

Sr. Tender Clause/Sub- Clause Description (relevant portion) as Clause Description (relevant portion) as
No. Document Clause/Para existing in the Tender Documents amended now to be read as
Reference (Page No)

(140 of 324) of the Engineer as specified in Section 37.6 of


Volume IV [TS]

32 Volume III, 18.4.3, (17) New sub clause added The Contractor shall carry out the Reliability,
ER (new) Availability, Maintainability & Safety (RAMS) study
for all MEP Equipment and submit for the approval
(140 of 324)
of the Engineer as specified in Section 37.6 of
Volume IV [TS]

33 Volume III, 18.6.2, last line The payment for relocation/shifting/removal for The payment for relocation/shifting/removal for
ER (143 of 324) these utilities shall be included under Schedule ‘A’ these utilities shall be entitled under Schedule ‘E’
Provisional Sum. Provisional Sum.

34 Volume III, 18.6.4, (4) Schedule of Rates of MP Electricity Board (MPEB). Schedule of Rates of MP Power Management Co.
ER (144 of 324) Ltd. (MPPMCL).

35 Volume III, Appendix IV New appendix added Refer Attachment – 10 to Corrigendum – 2 for newly
ER (new) added “Project Interface Matrix”.
(324 of 324)

36 Volume III, Appendix V New appendix added Refer Attachment – 11 to Corrigendum – 2 for newly
ER (new) added “BIM Manual”.
(324 of 324)

Corrigendum – 2, Date: 10.11.2021 Page 12 of 80