SUMMARY 

 OF  CONCRETE  CUBE  TEST  RESULTS for period from 10/4/2012 to 19/5/2012 (40 Batches)
Brunei International Airport Project (BIA) ‐ TRCjvSWEE
( Design Mix ‐ GRADE 40 )
Check on Compliance (Clause 6.20)
( I ) ( II )
Individual Cube Results for 28 days  The 
Average  Difference between individual cube 
(N/mm2)
Date of  Strength  average  test result shall not be more than 
Sample  Date of Testing
Concreting for 28 days  strenght of  20% average
(N/mm2)  three 
cubes is  Percentage  Complianc
Cube 1 Cube 2 Cube 3 Difference
not less  Difference e
than the
1 10/4/2012 18/05/2012 53.11 55.11 55.78 54.66667 OK 2.67 4.88% OK
2 10/4/2012 18/05/2012 54 54.67 56 54.89 OK 2 3.64% OK
3 10/4/2012 18/05/2012 46.22 47.11 50.44 47.92333 OK 4.22 8.81% OK
4 27/04/2012 25/05/2012 48.89 50.22 50.89 50 OK 2 4.00% OK
5 1/5/2012 29/05/2012 48.44 51.78 53.78 51.33333 OK 5.34 10.40% OK
6 2/5/2012 30/05/2012 46.00 46.22 51.56 47.92667 OK 5.56 11.60% OK
7 4/5/2012 1/6/2012 44.67 47.33 49.11 47.03667 OK 4.44 9.44% OK
8 5/5/2012 2/6/2012 51.33 52.67 54.89 52.96333 OK 3.56 6.72% OK
9 44.44 50.59 52.89 49.30667 OK 8.45 17.14% OK
10 47.56 50.00 50.22 49.26 OK 2.66 5.40% OK
11 49.56 52.00 52.89 51.48333 OK 3.33 6.47% OK
12 6/5/2012 3/6/2012 50.22 50.67 52.67 51.18667 OK 2.45 4.79% OK
13 9/5/2012 6/6/2012 49.33 50.22 52.89 50.81333 OK 3.56 7.01% OK
14 47.11 50.67 53.11 50.29667 OK 6 11.93% OK
15 45.78 49.78 52.00 49.18667 OK 6.22 12.65% OK
16 45.78 49.33 52.89 49.33333 OK 7.11 14.41% OK
17 10/5/2012 7/6/2012 47.78 50.00 50.22 49.33333 OK 2.44 4.95% OK
18 44.44 47.56 49.33 47.11 OK 4.89 10.38% OK
19 12/5/2012 9/6/2012 49.33 50.22 50.89 50.14667 OK 1.56 3.11% OK
20 15/5/2012 12/6/2012 49.11 52.00 54.44 51.85 OK 5.33 10.28% OK
21 48.67 48.89 50.44 49.33333 OK 1.77 3.59% OK
22 44.89 46.89 47.11 46.29667 OK 2.22 4.80% OK
23 44.44 49.33 49.78 47.85 OK 5.34 11.16% OK
24 44 44
44.44 49 33
49.33 49 78
49.78 47 85
47.85 OK 5 34
5.34 11 16%
11.16% OK
25 42.22 48.22 51.11 47.18333 OK 8.89 18.84% OK
26 47.11 48.22 50.22 48.51667 OK 3.11 6.41% OK
27 17/5/2012 14/6/2012 46.89 49.33 49.78 48.66667 OK 2.89 5.94% OK
28 40.44 43.78 46.89 43.70333 OK 6.45 14.76% OK
29 42.44 43.78 44.67 43.63 OK 2.23 5.11% OK
30 42.89 43.56 44.89 43.78 OK 2 4.57% OK
31 45.56 46.22 46.44 46.07 OK 0.88 1.91% OK
32 44.89 45.33 46.00 45.40667 OK 1.11 2.44% OK
33 46.67 47.33 48.44 47.48 OK 1.77 3.73% OK
34 45.11 46.89 47.33 46.44333 OK 2.22 4.78% OK
35 19/5/2012 16/6/2012 42.22 44.89 45.11 44.07333 OK 2.89 6.56% OK
36 44.22 44.22 44.44 44.29333 OK 0.22 0.50% OK
37 45.33 47.56 49.56 47.48333 OK 4.23 8.91% OK
38 45.33 46.22 46.22 45.92333 OK 0.89 1.94% OK
39 No Result Yet (Assumption  46.52784 48.70054 50.24 48.48946 OK 3.712162 7.66% OK
40 based on average) 46.49632 48.63526 50.13421 48.42193 OK 3.637895 7.51% OK
Count Data 40
Sum 1936.944723
Mean Strength 48.42361807 KN/mm2
Standard Deviation (s) 2.764881796
Statistical Constant (as per MS 1195) 1.64

Current Margin = 2.764882 x 1.64 = 4.534 N/mm2
(but shall not less than 7.5 N/mm 2 , therefore the current margin (4.534 mm 2 ) is not meet requirement

Therefore, Adopt Current Margin = 4.534 N/mm2
( From 40 Sample)

Therefore, Characteristic Strength (fc) achieved = 48.424 ‐ 4.534 = 43.889 N/mm2
2
(which is greater than 40 N/mm .  Thus ok!)

Grade 40 Concrete

60
55
Cube Strength N/mm2

50
45
40
35
30
25
G40P‐c G40P‐b
(Cement Content= 410kg) (Cement Content= 400kg)
20
15
10
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38
Test Number/ Batch
Cube Strength Distribution Characteristic strength = 40 N/mm2 Target Mean Strength = 47.5 N/mm2

Histogram & Normal Distribution Curve


1.64s
10 0.16
9 0.14
8
0.12
Frequency

7
6 0.1
5 0.08
4 0.06
3
0.04
2
1 0.02
0 0
43 44 45 46 47 48 49 50 51 52 53 54
frequency 3 2 2 3 9 4 6 4 4 1 0 2
distribution 0.02107 0.04012 0.06703 0.09826 0.12638 0.14261 0.14119 0.12264 0.09347 0.0625 0.03667 0.01888
Cube Strength