Professional Documents
Culture Documents
Basic HIRA (Hazards & Risk Assessment of Solar PV Project)
Basic HIRA (Hazards & Risk Assessment of Solar PV Project)
Hazard Identification:
Hazards identified are as follows
Risk Assessment:
Risk could be calculated by calculating Likelihood and severity.
Hazards Identification:
Hazards identified are as follows:
Risk Assessment:
Risk could be calculated by calculating Likelihood and severity.
6. Handling modules: Here risk is for both, for module and for worker as module is
expensive, module has to be carried and installed as per safe operating procedure,
i.e. 2 worker should handle module. Proper PPE’s is to be used while handling
modules, Proper training is to be provided to the workers as per safe operating
procedures and permit is to be issue to carry out such activity.
7. Muscular stress: Risk can be eliminated by handling the purlins and modules by 2
workers, by carrying out proper manual handling procedure as guided and by
providing training to the workers.
C) Work Activity: Erection of Inverter Room and Transformer.
Working steps for Erection of Inverter Rooms and Transformer:
1. Excavation of 1.5 mtr depth.
2. PCC and bar bending work with shuttering.
3. The concrete mix from the mixer i.e. Ajax, is then used for RCC in the footings of
trafo and ICR.
4. Brick work of the side walls.
5. Erection of ICR and Trafo with the help of Hydra of 16 Ton.
6. Welding of the base plates with the ICR and welding of the cover plates with the
trafo channel.
Hazard Identification:
Hazard identified are as follows:
Risk Assessment
Risk could be calculated by calculating Likelihood and severity.
7. Handling ISMC: Risk can be reduced by using hydra to place the ISMC and using
2 labor to reduce momentum of the ISMC from opposite sides while placing.
8. Shuttering: Risk can be controlled by carrying the activity by a competent person and
using proper PPE’s.
9. Handling planners and other tools: Risk can be controlled by carrying the
activity by a competent person and using proper PPE’s.
10. Erection of ICR and Trafo: Risk can be controlled by first grading and leveling the
area where erection has to be done and issuing work permit. A competent crane
operator and competent rigger person should be used to erect these. The crane
should be fit to use and proper statutory requirements should be ensured before
use. For 16 ton of crane, 1 / 2 crane has to be used to carry the trafo and ICR
positioned diagonal to the 2 adjacent corner of the wide face of the ICR or trafo.
Proper supervision should be there of a competent person.
11. Handling cement: Risk can be controlled by providing training to the workers for safe
handling of cement, using proper PPE’s specially Masks and by issuing work permit.
12. Handling oil: Risk can be controlled by providing proper training to the workers for
handling oil and disposal procedures and using proper PPE’s.
13. Mobile concrete mixer: Risk can be control by ensuring that the vehicle has
competent driver and having back horn all lights and signals are working
appropriately or by using red flag when in operation and by providing vehicle
permit and could use sirens also while mobile.
14. Mobile crane: Risk can be controlled by ensuring that the driver is a competent driver
along with competent rigger helper. The crane has passed fitness test report and its
slings to be used also have passed the fitness test and properly labeled it’s
maximum limit value. There should be a back horn, emergency siren for over
loading and tyres should be guarded properly, after ensuring all the point the crane
should be provided with lifting vehicle permit.
15. Welding: Risk can be controlled by providing hot work permit, ensuring that the area is
properly grounded, ensuring that a fire extinguisher has been placed , welder is a
competent welder, using proper PPPE’s i.e. leather gloves, Face shield with UV
protected glass etc and proper training is to be provided to the welder for any kind of
emergency .
16. Vibrator: Risk is tolerable
17. Cutter: Risk can be controlled by properly guarding the cutter, using proper PPE’s,
ensuring cutter is running below its maximum rpm and properly grounded.
D) Work activity: DC, AC Cable Laying and Termination.
Working steps for DC, AC Cable Laying and Termination:
1. Excavation of 1m depth and 1m width trench.
2. Sand laying into the trench.
3. Cable drums shifting and jacking at some plane surface.
4. Unrolling the cable and laying into the trench.
5. Sand laying above the cable and backfilling the trench.
6. Placing cable trays b/w ICR and trafo.
7. Cutting the cable, fixing lugs, covering with heat sleeves and terminating with the ICR,
SCB’s, Trafo and ICOG’s.
Hazard identification
Hazard identified are as follows:
2. Excel blades: Risk can be reduced by carrying out the cutting activity by a skilled
labor using proper PPE’s.
3. Fixing jacks with cable drums: Risk can be reduced by carrying out the activity with
skilled and trained labor using proper PPE’s and issuing work permit for the work.
4. Lifting vehicle (14 Tons): Risk can be controlled by ensuring that the driver is a
competent driver along with competent rigger helper. The crane has passed fitness
test report and its slings to be used also have passed the fitness test and properly
labeled its maximum limit value. There should be a back horn, emergency siren for
over loading and tyres should be guarded properly, after ensuring all the point
the crane should be provided with lifting vehicle permit.
5. Lug clamping device: Risk is tolerable.
6. Welding machine: Risk can be controlled by providing hot work permit, ensuring
that the area is properly grounded, ensuring that a fire extinguisher has been
placed , welder is a competent welder, using proper PPPE’s i.e. leather gloves,
Face shield with UV protected glass etc and proper training is to be provided to the
welder for any kind of emergency .
7. Heat blower: Risk is controlled by issuing hot work permit, using proper PPE’s and
ensuring proper supply with the help of distribution boards.
8. DG set: Risk can be reduced by properly checking the DG as per check list and
ensuring that proper earthing is provided to the DG, MCB is used in the supply unit,
proper wire clamps are there, the silencer is positioned at acceptable height as per
the norms and wires are connected properly and insulated well.
9. Excessive temperature: Risk can be controlled by providing training to the workers
on how to be protected from heat strokes, providing glucose water, Suggesting
increase water consumption by the body, wear light color clothes
10. Dehydration: Risk can be reduced by training the workers for consuming more
and more water, taking rest in shelters when the temperature is more than 42
degree.
11. Falling into the trench: Risk can be reduced by properly barricading the area by 2
layers of caution tapes and using sign board of excavation specialy near the approach
roads.
12. Inadequate access: Risk is tolerable the worker should know the site map.
13. Shifting cable drums: Risk can be reduced by not directly handling the cable drums,
just tying rope and directing the moment of cable drums with the help of 2 labors and
14. Laying cable: Risk can be reduced by using trained labor and proper planning before
carrying out the work and using proper PPE’s.
15. Handling tools: Risk can be reduced by properly maintaining tool kit and using proper
PPE’s.
16. Handling cable trays: Risk can be reduced by ensuring proper PPE’s usage.
17. Muscular stress: Risk can be reduced by carrying out proper manual handling
procedure as guided and by providing training to the workers.
E) Work activity: MCR and Switch Yard Foundation
Working steps for MCR and Switch Yard Foundation are as follows:
1. Excavation of 2 to 3 meters below the NGL.
2. PCC and laying steel mash and binding the steel bars for the column foundation.
3. Shuttering of the steel work for concreting.
4. RCC using concrete mixers.
5. Placing ICMC and steel rail.
6. Placing Base plates into the column and bolts for the super structures.
Hazard identification
Hazard identified are as follows:
6. Handling ISMC channel: Risk can be reduced by using hydra to place the ISMC
and using 2 labor to reduce momentum of the ISMC from opposite sides while placing.
7. Handling steel rail: Risk can be reduced by carrying out lifting operation with
the help of lifting equipment like a crane and controlling its moment with the
help of rope with 2 workers and issuing work permit for that.
8. Handling shuttering plates and fixing: Risk can be controlled by carrying the
activity by a competent person and using proper PPE’s.
9. Handling nails, tools etc: Risk can be controlled by using proper PPE’s.
10. Handling concrete: Risk can be controlled by providing training to the workers for safe
handling of cement, using proper PPE’s specially Masks and by issuing work permit.
11. Welding: Risk can be controlled by providing hot work permit, ensuring that the
area is properly grounded, ensuring that a fire extinguisher has been placed ,
welder is a competent welder, using proper PPPE’s i.e. leather gloves, Face shield
with UV protected glass etc and proper training is to be provided to the welder for
any kind of emergency .
12. Mobile concrete mixer: Risk can be control by ensuring that the vehicle has
competent driver and having back horn all lights and signals are working
appropriately or by using red flag when in operation and by providing vehicle
permit and could use sirens also while mobile.
13. Mobile crane: Risk can be controlled by ensuring that the driver is a competent
driver along with competent rigger helper. The crane has passed fitness test report
and its slings to be used also have passed the fitness test and properly labeled its
maximum limit value. There should be a back horn, emergency siren for over
loading and tyres should be guarded properly, after ensuring all the point the crane
should be provided with lifting vehicle permit.
F) Work activity: Erection of Structures, Isolators, Panels,
CT, PT, LA, BPI, Trafo and Pre Fabricated MCR.
Hazard Identification
Hazard identified are as follows:
Risk Assessment
Risk could be calculated by calculating Likelihood and severity.
8. Handling nut, bolts, tools: Risk is tolerable, then also PPE’s are must.
9. Erecting trafo with the help of 60 Ton crane: Risk can be controlled by first
grading and leveling the area where erection has to be done and issuing work
permit. A competent crane operator and competent rigger person should be used to
erect these. The crane should be fit to use and proper statutory requirements should
be ensured before use. Proper supervision should be there of a competent person
and to control its moment 4 ropes is to be tied at 4 corner then trafo has to be
handled from distance.
10. Handling and erecting electrical instruments: All electrical instrument are delicate
as having porcelain material and they are quite heavy also thus need to be placed
with the help of a crane thus its moment could be controlled by tying 2 ropes at its
end, The worker erecting the instruments should also be competent and should use
proper PPE’s and safety harness while erecting them on the structures.
11. Ergonomics: Risk can be controlled by ensuring work is carried by a competent
person only and it should be carried out in shifts and there should be proper use of
safety harness.
12. Handling stringing wire: Risk can be controlled by using proper PPE’s specially
gloves.
13. Crane 14 and 60 Tons: Risk can be controlled by ensuring that the driver is a
competent driver along with competent rigger helper. The crane has passed fitness
test report and its slings to be used also have passed the fitness test and properly
labeled it’s maximum limit value. There should be a back horn, emergency siren for
over loading and tyres should be guarded properly, its base should also be fixed at
proper levels, after ensuring all the point the crane should be provided with lifting
vehicle permit.
14. Welding: Risk can be controlled by providing hot work permit, ensuring that the
area is properly grounded, ensuring that a fire extinguisher has been placed , welder
is a competent welder, using proper PPPE’s i.e. leather gloves, Face shield with UV
protected glass etc and proper training is to be provided to the welder for any kind of
emergency .
15. Cutter m/c: Risk can be controlled by properly guarding the cutter, using proper
PPE’s, ensuring cutter is running below its maximum rpm and properly grounded.
16. Silicon filling: Silicon is chemically hazardous thus it has to be handled carefully by
using proper PPE’s and special mask.