Professional Documents
Culture Documents
Rencana Angggaran Pelaksanaan (Rap) : Nama Kelas/Nim
Rencana Angggaran Pelaksanaan (Rap) : Nama Kelas/Nim
BAHAN
Rp0.00
ALAT
EXCAVATOR 98.0 1 Rp184,223.52 Rp18,053,904.62
DT 98.0 14 Rp240,423.33 Rp329,860,813.33
ALAT BANTU 98.0 1 Rp500.00 Rp49,000.00
PEKERJAAN : AC-Base
KUANTITAS : 826.4 M3
HARI 5 hr
BAHAN
Agregat kasar m3 826.4 Rp217,353.87 Rp179,621,238.17
Agregat Halus m3 826.4 Rp217,353.87 Rp179,621,238.17
Asb. Pra Campur kg 826.4 Rp5,000.00 Rp4,132,000.00
ALAT
Wheel Loader 35.0 1 Rp5,640,000.00 Rp197,400,000.00
Genset 35.0 1 Rp2,070,000.00 Rp72,450,000.00
Dump Truck 35.0 1 Rp3,600,000.00 Rp126,000,000.00
Asphalt Finisher 35.0 1 Rp2,205,000.00 Rp77,175,000.00
Tandem Roller 35.0 1 Rp900,000.00 Rp31,500,000.00
Asphalt Liquid 35.0 1 Rp1,500,000.00 Rp52,500,000.00
BAHAN
Agregat kasar m3 560 Rp217,353.87 Rp121,718,167.20
Agregat Halus m3 560 Rp217,353.87 Rp121,718,167.20
Asb. Pra Campur kg 560 Rp5,000.00 Rp2,800,000.00
ALAT
Wheel Loader 10.0 1 Rp5,640,000.00 Rp56,400,000.00
Genset 10.0 1 Rp2,070,000.00 Rp20,700,000.00
Dump Truck 10.0 1 Rp3,600,000.00 Rp36,000,000.00
Asphalt Finisher 10.0 1 Rp2,205,000.00 Rp22,050,000.00
Tandem Roller 10.0 1 Rp900,000.00 Rp9,000,000.00
Asphalt Liquid 10.0 1 Rp1,500,000.00 Rp15,000,000.00
PEKERJAAN : LPB
KUANTITAS : 1250 M3
HARI 10 hr
BAHAN
Agregat kasar m3 1250 Rp217,353.87 Rp271,692,337.50
Agregat Halus m3 1250 Rp217,353.87 Rp271,692,337.50
Asb. Pra Campur kg 1250 Rp5,000.00 Rp6,250,000.00
ALAT
Wheel Loader 10.0 1 Rp5,640,000.00 Rp56,400,000.00
Genset 10.0 1 Rp2,070,000.00 Rp20,700,000.00
Dump Truck 10.0 1 Rp3,600,000.00 Rp36,000,000.00
Asphalt Finisher 10.0 1 Rp2,205,000.00 Rp22,050,000.00
Tandem Roller 10.0 1 Rp900,000.00 Rp9,000,000.00
Asphalt Liquid 10.0 1 Rp1,500,000.00 Rp15,000,000.00