Design of pile cap

Fcu = 250 Kg/cm2

Fy = 3600 Kg/cm2

1- Design of column ( Pw = 345 ton)

Pu=1.35 Fcu Ac + .67 Fy As

Let As = 1.5 % Ac
3
345*10 *1.5 = .35*300*Ac + .67*3600*1.5/100 Ac

Ac= 3506.16 cm2

Take b=40 cm and T= Ac/B =88 cm ≈ 90 𝑐𝑚

As = 1.5*40*90/100 = 54cm2 (14 Φ 22)

----------------------------------------------------------------

2- Design of pile

Ppile = Ac * Fco + 0.44 Fy As

345*1000/6 =( πD2/4)*250 + .44 * 3600* 2/100 Ac

Let As = 2% Ac

D2 = 195.26 cm2

D= 13.97 cm +6 cm + 6cm = 25.87 cm ≈ 40 cm

As= 2% * Ac= 18 cm2 ( 8 Φ 18)

-------------------------------------------------------------------
For Check

Case : 1

W= .3 *.3 * 2.5* 1= .225 t/m’

Max B.M=4.275 t.m

α= 0.2 For Beam

K1= 0.193

K2=1215

4.275∗105
d= 0.193 √ = 14.52 cm < 24 cm ok – safe
75

4.275∗105
As= = 14.6 cm2 ( 4Φ22)
1215∗24
Case: 2

Max B.M=5 t.m

α= 0.2 For Beam

K1= 0.193

K2=1215

5∗105
d= 0.193 √ = 15.75 cm < 24 cm ok – safe
75

5∗105
As= = 17.1 cm2 ( 4Φ22)
1215∗24
Design of Pile Cap

Pcol. = 345 ton (40 * 90)cm

Ppile =345/6 = 57.5ton (D=40)cm

S= 120 cm

X1 = 40 cm

X2 = 85 cm

M11= 3*55*.4*.85= 56.1 t.m

M22=2*55 * .85*.85= 79.475 t.m


K1= .313 & K2=1217

79.475∗105
d=0.313 √ = 101 cm
𝐹𝑐=75

t=d+cover = 101+7 ≈ 110 𝑐𝑚

Sec: 1-1
𝑀11 56.1∗105
As= = =44.75 cm2/3.6m =12.43 cm2 /m’ (6 Φ18)
𝐾2∗𝑑 1217∗103

Sec: 2-2
𝑀22 79.4∗105
As= = =63.34 cm2/2.4 =26.4 cm2 /m’ (10 Φ18)
𝐾2∗𝑑 1217∗103

---------------------------------------------------------