Professional Documents
Culture Documents
A Project Report Submited To "QQGPT" in Partial Fulfillment For The Award of The Degree of
A Project Report Submited To "QQGPT" in Partial Fulfillment For The Award of The Degree of
A Project Report Submited To "QQGPT" in Partial Fulfillment For The Award of The Degree of
SUBMITTED BY
SYED AHMED RAZA 16061-C-250
CERTIFICATE
This is to certify that the project entitled “INDUSTRIAL TRAINING REPORT” has been
carried out in Hyderabad .
In partial fulfillment for the award of DIPLOMA IN CIVIL ENGINEERING to the STATE
BOARD OF TECHNICAL EDUCATION AND TRAINING, Hyderabad from 2nd shift
QULI QUTUB SHAH GOVT. POLYTECHNIC Hyderabad during the Academic year 2018-
2019
QQGPT
Hyderabad-500064
ACNOWLEDGEMENT
A Project is never the outcome of a Single Person’s Effect. It
is a Confluence of carried thought process harmoniously
Integrated into a resourceful product. I am Incepted to
several people for having made this project possible. In the
Endeavor to this , Several people have given their valuable
Suggestions and guidance at Every Step.
CONTENTS
TITLE PAGE NO
1) INTRODUCTION 1
2) STUDY AREA 2
2.1 Capacit’e infra projects limited2
2.2 Site safety precautions 3
3) MATERIALS AND MATERIAL TEST 4
3.1 Steel 4
3.2 Concrete 6
3.3 Cement 12
3.4 Fine aggregate 16
4) METHODOLOGY 18
4.1 Excavation 18
4.2 Plain cement concrete 20
4.3 Shuttering materials 21
4.4 Form work 22
4.5 Reinforcement 26
4.6 Concrete 28
4.7 Block work 29
4.8 Plastering 31
5) CONCLUSION 32
6) REFERENCE 33
LIST OF FIGURES
DESCRIPTION FIGURE NO
SITE SAFETY PRECOTIONS 2.2.1
REINFORCEMENT 3.1.1
REINFORCEMENT 3.1.2
POURING OF CONCRETE IN SLAMP COAN 3.2.1
SLUMP COAN 3.2.2
COMPRESSION TEST MACHINE 3.2.3
CEMENT 3.3.1
VICATE APPARATUS 3.3.2
VICATE APPARATUS WITH CEMENT 3.3.3
SEVER 3.4.1
SILT TEST TUBE 3.4.2
EXCAVATION OF SOIL 4.1.1
ROCK CUTTING 4.1.2
SHETTERING FOR SLAB 4.3.1
FORM WORK FOR SLAB 4.4.1
REINFORCEMENT AND FORM WORK 4.4.2
REINFORCEMENT AND FORM WORK FOR FOTTING4.4.3
PLASTERING OF REINFORCEMENT IN SLAB 4.5.1
REINFORCEMENT FOR SALB 4.5.2
CONCRETE POURING IN SLAB 4.6.1
AAC BLOCKS 4.7.1
ABSTRACT:
1.HIGH-RISE BUILDINGS
2.TOWNSHIPS & VILLAS
3.HOTELS & MALLS
4.HOSPITALS & INSTITUTIONAL
5.MULTI-LEVEL CAR PARKS
2.2 Site Safety Precautions
Personal Protective Equipment (PPE):
• Protective footwear must be used.
• Safety glasses are must be used.
• Apron must be used. Ear protection is must be used.
• Hand glouses should be used while doing any electrical work.
• Safety nets should be placed at a certain height.
• Safety belts should be used when the person is at a height more
than 1.8m.
• Fire extinguishers should be used.
3.1.2 REINFORCEMRNT
3.2 CONCRETE
• Concrete is the most versatile material for all types of
construction works and has been used for innumerable
construction works, either as plain concrete or as
reinforced cement concrete or as precast concrete, or pre
stressed concrete or in many other forms.
• The various constituents of concrete are cement, water,
fine aggregate, and coarse, aggregates. In Reinforced
Cement Concrete Steel is also used.
Cement:Properties and various types of cement have already
been discussed previously
Aggregate
• These are the inert or chemically inactive materials
which form the bulk of cement concrete.
• These aggregates are bound together by means of
cement. The aggregates are classified into two
categories, Fine and coarse.
The material which is passed through 4.75mm size sieve is
termed as fine Aggregate. Usually natural river sand, issued as
a fine aggregate
Water:
• Water which is used for making concrete should be clean
and free from harmful impurities such as oil, alkali, acid
etc.
• In general water which is fit for drinking should be used
for making concrete.
• It has a tendency to be porous.
Grades of Concrete:
• Concrete as per IS 456 2000 is classified into three groups as
ordinary concrete, Standard concrete and High strength
concrete.
• M10, M15,M20 and M25 are ordinary concrete, M30,
M35,M40, M45, M50 and M55 are grouped as Design Mix
concrete and M60, M70, M75 and M80 are grouped under High
strength concrete.
• The letter ‘M’ refers to the mix and the number indicates the
specified compressive strength of that mix at 28 days expressed
in N/mm2.
• For lean concrete bases and simple foundations for masonry
walls M10 grades of concrete to be used. These mixes need not
be designed
• Grades of concrete lesser than M15 are not to be used in RCC
work.
For general guidance, the nominal mix proportions (volume ratio)
Correspond approximately to the different grades as follows:
• M 10 - 1:3:6
• M 15 - 1:2:4
• M 20 - 1:1.5:3
• M 25 - 1:1:2
• than M25 grade there is no standard nix proportions for
remaining grades. Their proportions are decided by trail & error
method.
Materials to be Mixed in Concrete:
Density:2400kg/m³
There are some types of materials such as water, aggregates,
admixtures, cement, fly ash
1.Aggregates:
These are mixed in a certain proportion in concrete mixture for a
good properties.
Here fine aggregate is sand & coarse aggregate is of 10,12mm.
2.Admixtures:
These type of materials are added to concrete to increase or the
setting time for concrete.
3.Cement:
It is material which have a good binding property.
Proportion of mixing:
• The ingredients are generally mixed in the ratio of two parts of
Calcareous materials and one part argillaceous material.
• Limestone and shale are first crushed and then they are mixed
either in wet state or in dry state by grounding them together.
• The mixture is then burnt in a rotary kiln at a temperature
between 1400°C and l500°C. Pulverized coal, gas or oil being
used as the fuel.
• The clinker so obtained is first cooled and then gypsum (3 to
4%) is added and it is grounded to the required fineness.
3.3.1 CEMENT
Properties of Cement:
1.Fineness:
• It is the degree of grinding of cement.
• The rate of reaction depends upon the fineness of grinding
• For accurate measurement it is measured by surface area, air
permeability method and the unit is cm2/gram of cement.
2.Setting Time:
• Setting of cement is the phenomenon by virtue of which the
green cement changes into hard mass.
• Initial setting is a stage in the process of hardening after which
any crack that may appear will not reunite and the completion of
this process is, known as final setting time.
• The time between water is added in cement and initial setting
takes place is known as Initial Setting Time.
• Cement should not loose its plasticity till the various operations
of mixing, transporting and placing are complete.
• Hence this time is generally kept not less than 30 minutes.
3.Strength:
• The quality of concrete and cement is always judged by strength
and that is only by compressive strength because cement is
weak in tension and for it steel reinforcement is always
provided.
• For this purpose cement and standard sand are mixed in the ratio
of 1:3
4.Soundness:
• Free lime and magnesia present in cement makes the cement
unsound by increasing the volume after setting.
• It is generally measured by Le-Chatlier method or by Autoclave
method.
5.Heat of Hydration:
• Setting of cement is due to chemical reactions between cement
and water and this process is known as Hydration.
• As, this reaction is exothermal process, so sufficient heat is
generated and this process continues for an indefinite period at a
diminishing rate.
3.3.1 Field Tests on Cement:
The colour of cement should be uniform gray with light
greenish shade.
Cement should feel smooth when touched.
If hand is inserted in a bag of cement it should feel cool not
warm.
If a small quantity of cement is thrown in a bucket of water, it
should sink and should not float on the surface.
Cement should be free from any hard lumps.
A sample meant for testing shall be drawn from at least 12
different bags or barrels or containers or from 12 different
positions in a heap if cement is loose. Chemical composition of
cement should be checked for B. I. S. specifications.
Laboratory Tests on Cement
3.4.1 SEAVER
3.4.2 SILT TEST:
Silt canten is a fine material which is less then 150 microne. It is unstable in the
presence of water excessive quntitiy of silt not only reduses the bonding of
cement and fine aggregate but also affects the strngth and durabulity of work
Fine sand, Clay or other material carried by running water and deposited as a
sediment
TEST PROCEDURE:
• To carry out the test,a 250ml measuring cylinder should preferable be
used
• Fill the cylinder approximately uo to the 50ml mark with a salt/water
solution (one teaspoonful of salt to 750ml of water).
• Pour in the sand until the level is up to the 100ml mark.
• Add more salt solution until it reaches the 150ml level.
• Shake the mixture well
• Stand the cylendare on a level surface and tap it untill the top of the sand
is level
• Leave the cylindare to stand for three hours
• Measure the volume of the silt layer, and the volume of sand
• If silt is present in sand it will expand and contraction according its
temperature
• Volume of the sand and silt = A
• Volume of the sand = B
Volume of the sand and silt –Volume of the sand X100
Volume of the sand
If it is below 7% then it is ok
3.4.2 SILT TEST TUBE
CHAPTARE-4
METHADOLAGY
4.1 EXCAVATION WORK:
Scope:Excavation for foundations lay to the required bearing strata conforming
to location and dimensions as per drawings.
Procedures:
Obtain work permit before starting blasting & Excavation work.
Provide proper slope as per the soil condition & standards.
Any pit exceeds 1.50m depth must have Hard barrication
Sufficient ladders with a upright extension of 1mt. Min to be provided
(min. one at each 30m. of horizontal distance) for safe access to the pit
whose depth exceeds 1.20mt.
Proper ramp should be provided for the vehicle movement for ingress
and egress, maintaining a safe angle of the ramp.
A distance of 1.5mt or half of the depth of excavated pit or whichever
is more should be maintained from the edge of the excavation and
heavy structures, installations etc
No loose soil or materials should be kept at the edge
Prepare schemes for excavation with the required working space for
foundations as per the drawing
Mark dimensions of limits of excavation with reference to the scheme
prepared
Excavate to required depth, manually or mechanically and check
formation condition by consultant or designer, if required
Record the levels of formation, before laying PCC and maintain the
record
4.1.1 EXCAVETION OF SOIL 4.1.2 ROCK CUTTING
4.1.1 Hard Rock Excavation:
At all stages of excavation, precaution to be taken to preserve the rock
below and beyond the lines specified for the excavation, in the
soundest possible condition
Storage facilities for the explosives to be made as per the rules of
local, state and central government authorities and statuary bodies /
regulation and procedures for storage to be followed as described in
Technical specification for hard rock blasting
Blasting to be carried out during the fixed hours of the day (after the
sunrise and before the sunset) as approved by the client in written
Notification to be given to all companies and public utility companies
having service or structure in proximity to the site of work about the
blasting operation to enable them to protect their property from injure
Required holes as specified to be made by the supervisor (c/c of hole
shall not exceed 2.0m)
Wooden tamping rod with a flat end shall be used to push cartridges in
the hole firmly
After a insertion of explosives to the required depth in the hole, the
balance hole shall be stemmed, consisting of sand or stone dust
Then the blast area to be covered with one layer of sand bags
Over the sand bags (60bags/sqm) MS plate of minimum 6mm thk to
be placed
One row of sand bags to be placed above the steel plate
Precaution to be taken to ensure the blasting circuit is adequately
taped to avoid contact with MS plate
Then the detonation of the explosives to be done electrically
Misfire:
Sufficient time shall be allowed to account for the delayed blast
Inspection to be done in all the charges and determine the missed one
Then the explosive materials to be removed with the help of air
compressor by blowing air through that hole or it may be flooded with
water
4.2 PLAIN CEMENT CONCRETE (PCC) WORK:
Procedure:
Concrete chute to be used to take the concrete to down.Ensure sufficient
lighting before doing the job at night.
Gum Boots & Rubber hand gloves should be provided to the workers.
Clean the excavated / back filled formation level and should be free from
loose material
Take the joint record for bottom of footing/drain with PMC
Complete the anti-termite treatment as per the procedure and allow the
surface to get dried to receive the base concrete
Obtain the approval from the PMC on the Pour Card for concreting
Mark the PCC limits and top level with concrete
Laying and ramming the concrete to the required level as per drawing and
finishing the same uniformly
Cure PCC for 7 days
4.3 SHUTTERING MATERIALS:
RMD Boards.(2700×900mm)(Company maken)
1. Tie rods(15mm,length-3m)
2. PVC pipe.(20mm)
3. Male female jack(or)Vertical prop(1.5,2m)
4. Square tube.(50mm×50mm×2.9mm)(length-6m)
5. Pin joint.
6. PVC cap (to cover the wholes)
7. C-Clamp(800mm)
8. Runner (200×280×25mm)
9. Shuttering oil
10.Plywood(8ft×4ft×18mm-cost=Rs89cost=Rs50.75/sqft) (30kg)(cost(
11.U-Jack
12.Adjustable u-jack
13.Wire Nails(1.5,2,3,4,5inches)
14.Base plate.
15.Adjucost=Rs50.75/sqft) (30kg)(cost
16.U-Jack
17.Adjustable u-jack
18.Wire Nails(1.5,2,3, & 4,inches)
19.Base plate.
20.Adjustable base plate.
21.Props:
Male-female props (or) telescopic prop:3m,4m
Cup-lock system:
Cup to Cup distance-500mm
Cup dia-80mm
Bracing(vertical)=2m,2.5m
Ledger (or) bracing-1.5m,2m,2.5m
Channels=length-3m
Square tube=length-6m,thick-2.9mm,50x50x50mm
U-Heads=depth-75mm,width-120mm,length-10mm
Base jacks=thick-6mm,150mm-width
Estimation for formwork:
Approximate slab area=100sq.m
Shuttering area=70% of slab area-1700sq.m
Requirement of ply:
Each ply of standard size=1.22mx2.44m=2. 976sq.m
Noof ply required=1700/2.976=571nos
Noof repitations considered=571/10=57 nos
Types of woods for Runner:
1.Silver wood
2.Fine wood
For footings, gap between side ply and PCC shall be sealed to make
joints leak proof. For vertical members, a platform shall be erected not
touching the side forms of vertical members for concrete purpose.
For all concrete works, forms shall be kept above concrete level and
inside of forms shall be marked to indicate concrete level. For casting of
columns, shear walls, lift pardi forms shall be kept projecting at least 4”
above concrete level so that next pour can be cast with a leak proof joint.
For all erected formwork, levels shall be checked with auto level or level
tube. Fine correction shall be done in level through adjustable steel props
or adjustable prop heads. It is recommended that Site Engineer.
After placing of reinforcement in position, form surface shall be cleaned
before concreting. Wooden planks shall be provided over reinforcement
as walkways to carry concrete to edged beams.
In no case part of column below beam bottom level should be cast along
with slab / beam concreting. All columns must be cast exactly up to beam
bottom level. If small top portion of column concreting is balance then
the same should be concreted separately before taking up beam bottom
shuttering.
Spacing between wailers of sides of beams or columns should be within
9” to 12”.
For external columns and beams and crank beam of staircase, the
alignment should be maintained by using turn-buckle with wire rope
only.
Checking of shuttering for slab Level marking should be transferred on
column dowels at 2’ height, line Dori should be fixed up and level of slab
to be checked in three dimensions i.e. Length, Breath & diagonally25mm
thick wooden dhar phalli shall be minimum 4” width all around slab gala,
i.e. along periphery of all internal beam sides so that one side will rest on
internal beam side and other side on 3” X 3” chavis having prop supports
at 2’ – 0” c/c.
Shuttering for peripheral / external elevation beams
(a) 3” X 3” cantilever chavi should be provided through beam bottom @
18” c/c. on which platform with 2nos of 9” wide plank should be fixed
all along the peripheral beams as a working platform.
b) 3” X 2” or 3” to 4” X 1 ½” or 2 ½” dia props pieces as racker support
should be provided at 18” c/c with thesi or continuous chavi support fixed
on cantilever chavi.
c) 3” to 4” X 1 ½” wooden chance lafa will be provided connecting both
beam sides at top to keep straight and at required beam width.
To avoid leakages of slurry from shuttering at column / beam junctions,
studs / struts from beam sides should be taken down over the column side
and should be gripped between two horizontal chavi, on both sides of
columns with bolts, nuts and clamps. No nailing is permitted. Refer
Drawing for the same as below.
Spacing between wailing of sides of beams or columns should be within
9” to 12”.
B) Procedures to be followed after erecting formwork:
Just prior to concreting all levels shall be rechecked. It shall be ensured
that all fittings are tight. All tolerances in form work shall fall within the
limits mentioned in acceptance criteria.
During concreting, strict supervision shall be maintained on overall
erected formwork. If any sinking or displacement is observed during
concreting, remedial measures shall be adopted immediately.
C) De-shuttering of formwork:
De-shuttering shall be done only with the prior approval of QA Department.
Recommended de shuttering periods. But this may vary depending on type of
cement being used, strength of concrete achieved on the day of de-shuttering,
type of form used Stripping Time Check For De-shuttering of Slab
a) Beam bottom span up to 6 m - 14 days.
b) Beam Spanning over 6m -21 days.
C) One way of soffit of slab up to 4.5 m - 7 days.
d) Two way soffit of slab span above 4.5 m - 10 days.
2) Sequence of removal of props and other components shall be done as per
instruction of QA Department’s recommendation
4.4.1 Form work for slab
PROCEDURE:
1.Safety Points:
Every day before starting the bar bending and cutting m/c, ensure that the
limit switches are in working conditions
Use hand gloves while doing cutting, bending, shifting and tying of
reinforcement
While manual shifting of "C" or "L" type rod, tie the "L" portion of rods
if it is more than 1 no.
While shifting of rod by means of crane, ensure the quantity of
reinforcement to be shifted by crane is within the crane capacity and
allowable reach
5.Unload and stack the materials diameter wise and consignment wise
separately by placing the identification and traceability board with details of
receipt
6.Distribute copies of BBS to the Sub contractor & Billing Engineer.
7.Cut the reinforcement as per BBS and bend to the requirement
8.Make the Front/ Job ready for receiving reinforcement with Center-lines and
Level markings
9.Give clearance for shifting and tying reinforcements.
10.Check the reinforcements tied as per drawing and record laps and extra
reinforcementprovided
4.5.2 reinforcement
4.6
CONCRETE WORK:
Following procedure shall be adopted for Concrete.
This work procedure should be adopted for the following activities –
RCC Work:
Procedures to be followed before and during erecting formwork:
Mix Design and trials of mix shall be carried out as per the requirements
of IS 456:2008 to check workability, setting time, actual density,
strength and cement consumption (yield) whether it is site produced
concrete or ready mix concrete.
Workability at the pump point as measured by slump test shall be
between 120(+/-) 30 mm, so that after pumping to the desired location
the slump is minimum120 mm.
Retention for concrete shall be considered for 3.5 hrs.
Re-dozing or split dosing (1:3 of admixture and water) shall be allowed
subject to the increase workability/slump by trained technicians and
Engineers PIL.
Any concrete poured should get finally set within maximum 24 hours.
Any concrete of a specified Grade shall meet the characteristic strength
in 28 days. Non Destructed Test (NDT) will be performed in case 28days
strength less than acceptance criteria.
4.8PLASTERING WORKS:
Procedure:
Sufficient lighting to be provided at night work
All walkway platforms are 600mm (min.) and tied both sides
Hack any exposed faces of concrete which form substrate for
plastering
Fix all conduits, chases with chicken wire mesh 150mm wide
Fix sub frames for all doors and window openings
Prepare scaffold to ensure access to all locations. Ensure safety of
scaffolding and provide lighting of adequate intensity
Fix plaster thickness reference by mortar pads with respect to sub-
frames using thread line
Wet all substrate minimum of 2 hours before application of plaster
Provide chicken mesh in double layer of 100mm wide wherever block
masonry joins with the concrete surface using U nails
Use GI sheets at bottom for mixing the cement mortars and measuring
box for measuring the fine aggregate
Making the grooves at the junction of concrete and masonry and as
per the architectural drawing
Always stop a day's work at corner
Follow the check list no.:26 for plastering work
4.9PLASTERING:
As per IS code:383
Zone-1:15-45(it is rejected)
Zone-2:45-60(Block work)
Genarally in academic area there will be a plane area for levelling, but
in the site we had learnt levelling at different places where it is not a
plane area.
CHAPTER-6
REFERENCES
1. As per IS 456:2000 we had tested the slump test and compressive test for
concrete.
2. We had followed MS SHETTY textbook of concrete technology for that.
3. As per IS383 we had done the test for sand which is to be used in
plastering.
4. As per IS: 3025 water should pass both chemical and physical test.
5. As per IS1786 we had tested tolerance’s for steel
6. As pre IS269 we had done physical and chemical test and compression
test for cement
7. As per IS2185 we had done compression test and water absorption test
for AAC blocks
8. These IS specifications and the total knowledge what we have are given
by site manager.