Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

PRABHU A.

R  CONTACT
 arprabhu511@gmail.com
 +919500376723
 2/145,Ottarur,
Uthandiyur(P.O),
Sathyamangalam,
Erode(Dt),
 OBJECTIVE Tamilnadu,
Pincode-638402.

Have an in depth knowledge in Civil Quantity surveying practices  https://www.linkedin.com/in/prabhu-


Also have 8.5 Years of working experience as Quantity Surveyor ar-2557811a4
in India and Malaysia as well.Seeking for a challenging position  https://www.facebook.com/prabhu.ar1
as a CIVIL Quantity Surveyor in construction organization, which
gives me more responsibilites & challanges where I can use my
knowledge and skills in construction and help for grow the  SKILLS
company to achieve its goal.
AutoCAD
 EXPERIENCE MS Office

Tan Bock Kwee and Sons Sdn Bhd,Malaysia MS Project


Augest 2017 - Auguest 2021 ERP
Senior Quantity Surveyor (Experience 4 years) 3ds Max with V-Ray
Preparation of tender documents and procurement of
subcontract packages,including production of bills of  LANGUAGE
quantities as necessory
English
Report on tender submission
Tamil
Preparation of subcontract documentation
Telugu
Carry out take offs for material procurement
Hindi
Assisting in Sub-contract negotiation and letting
Site measurement including material and waste records
 PERSONAL DETAILS
Manage and value variations Date of Birth : 02/08/1990
Preparation and issue of contractual notices to sub- Marital Status : Single
contractors
Nationality : India
Agreement and cerification of sub-contractors interim
valuations and final accounts Passport Number : K 1088214
Assist Project Manager in project forecasting and reporting Father Name : Ravi G (late)
Carryout construction cost estimation and compilation Mother Name : Sumathi R
Carrying material take-off
Compilation of cost for material, manpower, equipment,
and indirect cost
Gathering and maintaining a database of material prices
Assist in Project Scheduling Planning and Reporting
Compile Project progress and forecast cost report
Compilation of Project Cost
Prepration Shop drawings using Auto-cad
Preparation As-built drawings using Auto-cad
Develop Job method statement and participate in the
development of Job Safety Analysis
Senthil Construction Corporation Private Limited,Chennai
April 2013 - May 2017
Quantity Surveyor (Experience 4 year 2 months)
Prepare and Checking RA Bills
Take off quantities for Civil and Infrastructure works
Preparing BOQ for IFC Drawings
Compare the quantities with respect to bill of quanntities
provided by Designer
Quantification of Variations as per IFC Drawings with the
help of RFI & Engineering Instructions
Preparing interim Valuations
Certify sub-contractor's payment invoice
Attend the site progress metting
Prepare daily report and also 3-Week look ahead schedule,
together with resource requirements
Provide estimations of material requirements
Seek to resolve engineering issues with client's
representative
Measurements of the work carried out every fortnight by
labour contractors based on gate entery & daily allocation
reports received from site engineer and gate entry from the
security on daily basis
Involve in Construction Planning, Scheduling, material
selection and procurement advice
Prepare DLR,DPR & MPR Report
Provide Safety induction meeting to new labours
Manthly Safety audit was conducted to all discipline
Others to be stipulated from time to time

 EDUCATION
Bannari Amman Institute of Techology,Sathyamangalm
2013
B.E Civil Engineering
83.5
Nanjaiah Lingammal Polytechnic College,Mettupalayam
2010
Diploma Civil Engineering
94.5
Government Boys Higher Secondary School,Sathyamangam
2008
HSC (12th)
59.2
Government Boys Higher Secondary School,Sathyamangam
2006
SSLC (10th)
80.4
 PROJECTS
Rapid Petronas Project,Pengrang,Johor,Malaysia
The RAPID Pengerang project refinery is designed to
produce gasoline and diesel (Package 3 & 14)
Budjet RM 500 Million (Oil & Gas Sector)

Euro-5 Infrastructure 
Sub-Station & FAR Buildings
Road Culvert
AOC & COC Piple line System
Cooling tower
Pipe rack founations
Steel structures
Duct banks
Cable trenchs
Drainage & Utilities system
ATT Tanjung Bin (ATB/VTTI) Sdn Bhd,Johor,Malaysia
At the heart of the vibrant trading centre for Asia.ATB is part of
the Singapore trading and pricing hub, It has one million m3
of storage, handling gasoline, jet fuel, gasoil, fuel oil
,crude oil and biofuels.
Budjet RM 30 Million (Oil & Gas sector)
Tank foundations
Pump stations
Pump foundations
Steel structure
Bund walls
Pipe Culvert
Road, Pavement & Drainage system
Shiram Onecity, Elite Villas & Infra works,Chennai,(Macro
Enterprices,PSK,SCCPL)
Residential Buildings
Luxury Villas
Apartments
Road & Drainage
Landscaping
Goverment projects
Infra works

You might also like