Procedure of Redosing of admixture at site ( IS :4926-2000)

 Admixture redosing should be done carefully at site.

 Same Admixture should be added, which is batched at plant.

 If 1 litre of admixture is added, 3 litres of water should be added immediately

 The TM drum is rotated at MIXING SPEED for atleast 30 revolutions or 2 minutes.

 Then concrete slump is again checked and then concrete is unloaded.

 There should be no addition of admixture or water into the pump.