Quality Requirement
----Quality Team
EHS self-check report
For whom?
Everybody involved in working at site level
When working on site, Must wear proper PPE: Helmet, Visiable vest, Safety shoes, Full
body harness.
×
EHS check COVID-19 prevention instructions
1.Wear a mask
2.Stay 1 meter away from others
3.Wash your hands often
4.Cover coughs and sneezes
5.Clean and disinfect
6.Monitor your health daily
-Be alert for symptoms. Watch for fever, cough,
shortness of breath, or other symptoms of COVID-
19
-Take your temperature, if the temperature is high
please inform the RPM immediately
EHS Tower climbing
When workers climbing up and down the tower, Please must make sure at least one full
body harness hook lock on the tower. Two hooks alternate up and down.
√
EHS Fire extinguisher
× √
EHS self-check report
Before Subcontractor start installation on site, Team leader need to take all members
learning ECC together on site.
Must take a reading photo and submit to the EPMS, The team memebers must face to the
ECC paper.
EHS self-check report
2. Take a photo of site ID on site, Clear to see the site ID, No blurred.
Wireless Closed BTS view
At least take 2 photos of Antenna&RRU port View(Waterproofing & Lable) within 0.5m,
1. At least one photo for Antenna port, One photo for RRU port.
2. All used ports must bound 1+3+3 waterproofing, Unused ports bound with 1+1+1 tape.
3. All jumper connector use torque wrench fasten,For 7/16 DIN: 25Nm,4.3-10: 5Nm
4. The jumpers need to keep at least 200mm-300mm straight,Then bend.
5. All labels clear to read;
6. Clearly to see RRU unit window screw closed well;
Wireless Azimuth & M-tilt(Antenna swap)
Open the covers show the cable inside, Take a photo of cables within 0.5m
1. The power cables install one by one, No cable cross and fly;
2. Clearly to find all label inside;
Wireless New site Power system Grounding (inside & outside cabinet)
Take photos of cable&jumper entry points into cabinet in each sector within 0.5m
1. Show each sector of cable&jumper entry points;
2. After install complete, seal the cable hole;
EHS self-check report
Make sure before installation, you must check with ZTE BSC
representative for the alarm status, If there is any alarm before
installation, must be escalated to ZTE rollout manager/engineer for
further action.
Before site installation, Must do ECC learning and EHS check, And submit ECC self check
report and EHS self check report immediately on site,
For quality self-check report must submit within 1 day after site on air.
1. ZTE will assign quality self check task and EHS self check task; Partner team build ECC
report task from iEPMS APP.
2. Partner company manager assign quality self check task and EHS self check task to team
leader(At web site: My team);
Submit 1 ECC report, 1 EHS self check report and 1 quality self-check report in each site.
Thanks