Chirajara - ACI Investigation of The Chirajara Colapse

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Investigation of the

Collapse of the Chirajara


Bridge
A summary of a study conducted by members of ACI Committee 133, Disaster
Reconnaissance

by Santiago Pujol, Michael E. Kreger, Jonathan D. Monical, and Arturo E. Schultz

T
he government of Colombia is conducting an The exterior spans were approximately 80 m (262 ft) long.
expansion of its built infrastructure, including the At the terminal ends of these shorter spans, massive
transportation system, through its Agencia Nacional de abutments were placed to provide reactions against a portion
Infraestructura (National Infrastructure Agency, ANI). The of the loads imposed on the longer center span.
Chirajara Bridge was one of 47 bridges in a project1 to expand The West Tower (at Axis B in Fig. 1) collapsed, claiming
the highway from Bogotá to Villavicencio from two to four
A B C D
lanes, with the bridge carrying two of those lanes. While 80.00 286.30 80.00

under construction, one-half of the Chirajara Bridge collapsed


on January 15, 2018.
The mission of ACI Committee 133, Disaster Reconnaissance,
is to collect information from disasters affecting reinforced
and prestressed concrete structures. The information collected
is used to inform ACI committees that develop code
provisions, design recommendations, and specifications.
Following the collapse, a representative of ACI Committee (a)
133 contacted ANI to request access to the site to collect any
information that could link the collapse to needed A
80.00
B

improvements in design recommendations. This article


summarizes the findings of the investigation.

The Bridge
Overview Stays not in place

The Chirajara Bridge was a cable-stayed bridge, with a


total projected length of 446.3 m (1464 ft), spanning the
8 9 10 11 12 13 14 15
nearly 150 m (500 ft) deep Chirajara gorge. It was supported 7 6 5 4 3 2 1 1 2 3 4 5 6 7

by two reinforced concrete towers, each to have 52 stay 129.5 m completed deck
(b)
cables. Each tower was 107.34 m (301 ft) tall (above a drilled
shaft foundation), and the center-to-center distance between Fig. 1: The Chirajara Bridge was a cable-stayed bridge, with a total
the towers was 286.3 m (938 ft). The stay cables consisted of projected length of 446.3 m (1464 ft), spanning the nearly 150 m
bundles of ASTM A416/A416M Grade 270 (270,000 psi (500 ft) deep Chirajara gorge: (a) schematic of the completed bridge
[1860 MPa] tensile strength) strands. The typical spacing of (viewed from the south); and (b) schematic of the West Tower at the
stay anchorages along the length of the bridge deck was 9.25 m time of the collapse on January 15, 2018 (Note: Dimensions are in m;
(30 ft), shown in Fig. 1. 1 m = 3.3 ft)

www.concreteinternational.com | Ci | JUNE 2019 29


the lives of nine workers. At the time, bridge construction was Columns supporting the mast were 6 by 1.6 m (20 by 5.2 ft)
near completion, with the ends of the deck that cantilevered in cross section (solid), with the longer side oriented in the
from each tower being approximately 30 m (98 ft) from one longitudinal direction of the deck. The lower part of the tower
another. No construction activities involving heavy weights or included a 500 mm (20 in.) thick wall acting as a web between
large forces are reported to have been taking place on the the columns (Fig. 3).
collapsed portion at the time of failure. At the top of this web and below the deck was a 6 m wide,
600 mm (24 in.) thick slab (Fig. 4). The slab acted as a tie
Key components, dimensions, and properties between the columns at the elevation with the widest
The deck was a 13 m (43 ft) wide, composite steel-concrete separation between the columns. This element was referred to
structure with two 1500 mm (59 in.) deep steel longitudinal as the “tower slab” in the drawings.
girders and 840 mm (33 in.) deep steel transverse beams The standard to be met by the deformed reinforcing bars
supporting a 200 mm (8 in.) thick reinforced concrete slab was not specified in the design drawings provided to the
every 3 m (9.8 ft). authors. Nevertheless, mill certificates provided to a
Each tower had a hollow 38 m (125 ft) tall mast to anchor supervision company for the highway expansion project listed
the stay cables (Fig. 2). The mast had a rectangular section minimum and maximum yield strengths of 60,000 and
and was supported by a structure with a diamond-shape 78,000 psi (420 and 540 MPa), respectively, with a required
elevation; the widest part of the diamond accommodated the minimum elongation of 14%. This indicates that the bars were
roadway. The specified compressive strength for the tower specified as ASTM A706/A706M Grade 60.
concrete was 35 MPa (5000 psi). Standard cylinder test According to the drawings, longitudinal reinforcement in
reports provided to the supervision company show results each column comprised 146 No. 10 bars (the drawings
exceeding the specified strength. indicated the bar size using ASTM A706/A706M
The outer dimensions of the cross section of the mast were nomenclature), resulting in a reinforcement ratio of 1.2%.
6 m (20 ft) in the longitudinal direction of the deck and 4.6 m The volumetric transverse reinforcement ratio was 0.5%.
(15 ft) in the transverse direction. The corresponding inner Longitudinal (vertical) reinforcement in the mast comprised
dimensions were 4 and 3.8 m (13 and 12.5 ft), respectively. The 156 No. 10 bars near the outer perimeter face of the hollow
walls were therefore 1000 and 400 mm (39 and 16 in.) thick. section and 46 No. 6 bars near the inner perimeter face,
resulting in a reinforcement ratio of 1.1%. The volumetric
ratio of transverse reinforcement in the mast also was 1.1%.
0.60
4.60
0.60
4.60
1.00
6.00 The interior of the mast was lined with steel plates. The plates
1.00 1.00

0.075 15 No. 10 0.075


0.40 at 0.10
38.0

No. 3 crossties

No. 4 tie at 0.20

1.40
70.00

2.15

No. 6 bar at 0.20

No. 8 vertical bar at 0.20 (72 total each face of web)


1.60
32.00

11 No. 4 crossties at 0.20


58 No. 10 at 0.10

0.5
6

13.00
0.050
14.15
17.62
1.60
Tower No. 4 bar at 0.2
slab
37.34
32.34

Web

4.00
0.25
2.38 8.50
5.00

8.50 1.6

Fig. 3: Section through tower column and web (Note: Dimensions are in m; 1 m =
Fig. 2: Schematic views of a bridge tower 3.3 ft; bar sizes are indicated using ASTM A706/A706M nomenclature—
(Note: Dimensions are in m; 1 m = 3.3 ft) roughly, diameters in multiples of 1/8 in.)

30 JUNE 2019 | Ci | www.concreteinternational.com


12 tendons of one (1) 0.60 in. diameter strand
14 tendons of eight (8) 0.60 in. diameter strands

No. 4 at 0.25 L = 2.95


3 No. 4 at 0.30

0.10
No. 4 at 0.25 L = 12.00
0.60 L = 1.75

No. 4 at 0.25 L = 2.95 No. 4 at 0.25 L = 12.00


57 No. 4 at 0.25 L = 5.90 both faces

Column Web Column

Fig. 4: Section through slab that acted as a tie between the columns at the elevation with the widest separation (Note: Dimensions are in m
unless noted otherwise; 1 m = 3.3 ft; 1 in. = 25 mm)

were 20 mm (0.8 in.) thick in the direction of the deck and vertical bar (as shown in Fig. 3). While the drawings also
25 mm (1 in.) thick in the perpendicular direction, and they called for a spacing of 200 mm (8 in.) for both the vertical and
were anchored to the concrete with headed studs. horizontal bars, we observed in the remains of the West Tower
The web connecting the lower columns of the tower was web that the vertical spacing of the No. 4 bars varied between
reinforced with vertical and horizontal bars near each face. 100 and 200 mm (4 and 8 in.). A design section shows that the
The vertical reinforcement comprised No. 8 deformed bars horizontal web reinforcement was terminated at hooks
(1% reinforcement ratio) and the horizontal reinforcement anchored at exterior longitudinal bars in the column (Fig. 3).
comprised No. 4 bars (0.26% reinforcement ratio). The The tower slab reinforcement is shown in Fig. 4.
drawings showed No. 4 crossties at approximately every third Reinforcement anchored in the columns consisted of twelve

JOIN TODAY!
ACI CHAPTERS
200+ Professional and Student Chapters
www.concrete.org/chapters

www.concreteinternational.com | Ci | JUNE 2019 31


0.6 in. (15 mm) diameter unbonded
post-tensioning strands. We believe that
these were specified as ASTM A416/
A416M Grade 270 strands. Notice that
the deformed reinforcement was
terminated near each column face.
Because the construction process
resulted in cold joints between the
concrete in the tower slab and the
columns, the deformed bars would
have been incapable of transferring
tension forces between the tower slab
and the columns.
Deformed reinforcing bars were lap
spliced. Splices were located away from
critical sections.

Construction sequence
After the towers and abutments were
constructed, the deck was built from
each abutment to the adjacent tower.
Shoring supported the deck during this
operation. Deck segments were added
from each tower toward the center of the
middle span. These segments were
supported by stay cables, and the weight
of each was balanced by a corresponding
segment on the opposite side of the
Fig. 5: Frames from a video of the collapse of the West Tower, recorded by a nearby security
tower supporting it. Once the initial
camera north of the bridge. The time interval between each frame is approximately 1 second
seven pairs of stay cables were installed
for each tower, additional segments in
the center span were balanced by the concrete had been placed for the 12th Field Assessment
stays anchored in the nearest abutment. and 13th deck segments. The debris
It is also important to review what the The displacements seen in the video
Collapse structure was not experiencing at the simplified the task of identifying and
Reported conditions time of collapse. Neither portion of labeling the structural members in the
For the portion of the bridge that bridge was carrying significant live load, debris field (Fig. 6). Examination of the
collapsed (supported by the West and the concrete deck did not yet have a debris revealed that failure involved
Tower, on Axis B), 13 pairs of stay planned asphalt wearing course. Lastly, separation between the lower columns
cables are reported to have been there were no seismic demands, no and web. Figure 7 shows that the
installed from the tower toward reports of strong winds, and no horizontal No. 4 bars in the web
mid-span, with the total length of deck indication of foundation distress at the fractured at the juncture with a column.
cantilevered approximately 129.5 m base of the towers. Despite the collapse, the remains of the
(425 ft) from the center of the tower web had limited cracking, indicating
(shown in Fig. 1). We understand that Video evidence that strains were concentrated near the
the 200 mm thick reinforced concrete A security camera recorded the West columns, where the horizontal web
deck slab had been cast along this Tower during the collapse. Frames reinforcement fractured. We observed no
entire length. We also understand that extracted from this video are shown in failures in stay-cable anchorages in the
the deck supported by the collapsed Fig. 5. The sequence shows clearly that bridge deck, and we noted that deck
tower contained only small live loads at the dominant feature of the collapse girders fractured at splice locations.
the time of collapse. On the deck carried involved separation between the
by the (remaining) East Tower, 12 pairs columns on opposing sides of the tower, The remaining tower
of stay cables had been installed, and suggesting a tensile failure at or near the On January 25-26, 2018, the East
deck framing had been installed for the tower slab. The other bridge components Tower was still in place as constructed.
13th deck segment. Nevertheless, no fall almost directly downward. We inspected the tower with a powerful

32 JUNE 2019 | Ci | www.concreteinternational.com


scope, cameras with zoom lenses, and Analyses of the Towers mast. We were not provided with
an aerial robot (drone) (Fig. 8(a)), and Simple idealization of the tower records of the cable-stressing
we observed that the cold joints at the as a truss operations. However, we estimated this
ends of the tie (or tower slab) were open The video of the collapse suggests component to be 3600 kN (820,000 lbf)
(Fig. 8(b)). We also noted a large crack that the failure was related to gravity by assuming that the horizontal
in the north side of the web, starting demands. We made the following component and the concrete transition
near the cold joint and extending toward estimate of the vertical load acting on block (discussed in the next paragraph)
the foundation. We estimated the crack the West Tower at the time of the balanced the cantilever load.
to be 8 to 9 m (26 to 30 ft) in length collapse. The deck in the exterior span totaled
(Fig. 8(c)). Figure 9 shows a free-body diagram about 66 m × 13 m × 6.5 kPa = 5600 kN
of the West Tower and deck at the time (1.26 million lbf), where the 66 m (217 ft)
of the collapse. The distributed deck dimension is the approximate length of
load was about 6.5 kPa (135 psf), the deck from the tower center toward
including the concrete slab and stay the abutment. A concrete transition
cables. The deck cantilevered 129.5 m block (about 3 x 3 m [9.8 x 9.8 ft] in
(425 ft) from the West Tower, so this cross section and 15.7 m [51.5 ft] in
deck portion totaled about 129.5 m × 13 m length) had been placed between the
× 6.5 kPa = 11,000 kN (2.5 million lbf). deck and the abutment. This block
Because the 80 m (262 ft) span included voids and weighed about
measured to the outermost stay of the 2220 kN (500,000 lbf), and half of the
exterior span was shorter than the weight was supported by the end of
cantilevered portion, the group of stay the deck.
cables anchored in the abutment must The total force delivered by the stay
have been stressed to balance the cables to the mast atop the West Tower
system. The vertical component of was therefore 11,000 + 3600 + 5600 +
forces in these stays would have added 2220/2 = 21,300 kN (4.79 million lbf).
to the vertical forces acting on the The mast itself weighed nearly
12,000 kN (2.7 million lbf). The total
vertical force introduced by the mast to
the upper columns was therefore
21,300 + 12,000 ≈ 33,300 kN (about
7.49 million lbf). Lastly, the columns in
the upper portion of the tower weighed
nearly 8000 kN (1.8 million lbf) each.
If one idealizes the upper half of the
tower as a simple arch (that is, a
two-element truss), with the weight of
its elements being applied in halves at
Fig. 6: View of collapse site captured using an aerial robot (drone). LCS and LCN indicate element ends, the horizontal component
lower column south and north sides, respectively; and UCS and UCN indicate upper column of the axial force in each of the upper
south and north sides, respectively (images courtesy of Xenital S.A.S.) columns would be approximately

(a) (b) (c)

Fig. 7: Views of the lower column south (LCS), showing the remnants of horizontal No. 4 bars at what had been the junction with the web:
(a) overall view; (b) view of bars that were bent downward as the column fell away from the web; and (c) closeup of bars that necked down
and fractured at the juncture

www.concreteinternational.com | Ci | JUNE 2019 33


Resisting a critical tensile force of nearly 1 million lbf
  8000 kN   1 1
33,300 kN + 2  2
  × × = 4130 kN ≈ 928, 000 lbf (4450 kN)—designing mechanisms to transfer it from one
   2 5 element to another, ensuring reliable long-term capacity, and
The factor 1/2 is the inverse of the number of columns in prohibiting cracking in concrete—would require extreme care
the tower. The factor 1/5 is approximately the tangent of the in the design and meticulous detailing of the reinforcement.
angle between the column and the vertical. The weight of Idealizing the entire tower as a truss (that is, ignoring the
8000 kN is multiplied by 2 because there were two columns, web) would nearly double the estimated axial force in the slab
and it is divided by 2 to follow the common and stated that acted as a tie near tower mid-height (to almost 2 million
assumption that the weight of a truss element can be assigned lbf [8900 kN]). In contrast, the only continuous reinforcement
in halves to the nodes at its ends. in this element comprised twelve 0.6 in. diameter, Grade 270
The estimated force had to be resisted mostly by the tower unbonded strands. The nominal strength of these strands
slab that acted as a horizontal tie between the columns. The would have been about 12 × 0.217 in.2 × 270 ksi = 0.7 million lbf
deck itself did not help resist this tension because the only (3100 kN), which is much less than the 1 to 2 million lbf
direct connection with the tower occurred through bearing tensile force needed to hold the two columns in position at the
pads meant to support at least a fraction of the deck segment widest point in the tower.
directly over the tower. In the estimates given previously, it Therein lies the most glaring issue that may explain the
was assumed that this fraction was negligible relative to the collapse. The tower slab—the element that acted as a tie at
other weights involved. mid-height of the tower—did not have sufficient reinforcement.
The load on the bridge was smaller
than what was expected at service.
There was no reason for any stresses in
the system to be remotely close to
limiting values. Yet, statics and the
simple bridge representation described
previously show that the mid-height
tower slab acting as a tie to resist a
force did not have adequate capacity.
From that point of view, the reason for
the collapse should not be difficult to
(a) (b) (c)
understand.
Fig. 8: The East Tower was inspected using an aerial robot: (a) view of the joints between the
tower column, slab, and web; (b) magnified, lightened, and clarified detail showing opened Linear idealization of the tower
cold joint between tower column and slab; and (c) magnified, lightened, and clarified detail and web
showing large crack in the web We also made a linear idealization of
the tower, including a membrane to
B Vertical component of force imposed represent the web joining the columns of
Line of action of stays
anchored to abutment
by stays anchored to abutment = 3600 kN the lower half of the tower. This model
4200 kN resulted in a tensile force in the critical
Mast weight = 12,000 kN tower tie of about 1.5 million lbf
Upper column weight = 2(8000 kN) (6670 kN). Again, this force exceeds the
capacity of the tower slab. The number
98.5 m
6.5 kPa(13 m) = 84.5 kN/m of strands required to resist this tension
(working at strength) is 26 (many more
than the 12 strands provided). Including
factors of safety and accounting for
40°
loads not acting at the time of collapse,
7 6 5 4 3 2 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
one would expect this number to nearly
1110 kN
triple (to ~78 strands). Interestingly,
66 m 129.5 m
practically zero tension would be
expected in the transverse direction of
Lower column and web weight
the tower slab (longitudinal direction of
the deck). Nevertheless, the slab
Foundation reactions drawings show 14 tendons, each
Fig. 9: A free-body diagram of the West Tower and deck at the time of the collapse (Note: 1 m = containing eight strands, for a total of
3.3 ft; 1 kN = 225 lbf; 1 kPa = 21 psf) 112 strands in that direction.

34 JUNE 2019 | Ci | www.concreteinternational.com


Finite element model of the tower and web tensile strength of the 12 unbonded strands in the tower slab.
What is more difficult to explain is why the West Tower The other clamping forces were 3560 and 4450 kN. Analyses
supported loads for as long as it did and why the East Tower were made in U.S. customary units (clamping forces of
remained standing after the collapse of the West Tower. We 700,000; 800,000; and 1 million lbf). At the highest clamping
believe that failure did not occur earlier during construction force, no yielding was calculated in the horizontal web
because the structure was able to accommodate some force reinforcement. For the lower clamping force values of 3100
redistribution through cracking and yielding of reinforcement and 3560 kN, yielding and concentrated strains were
in the web of the tower. calculated at the column-web joint. Figure 10 shows
To explore the issue further, we developed an approximate horizontal reinforcement stress for the three analyses. Note
model of the tower using SAP2000,2 based on the following that stresses in the slab were also observed to be below the
assumptions: expected tensile strength of concrete in direct tension (which
•• The tower was idealized as frame elements, with moments can be as low as 1.4 to 2.1 MPa [200 to 300 psi]).
Strain concentration, leading to brittle response, could be
transferred at column joints but with no moment or axial
load transferred at the connection between the columns and expected at the web-column connection because the cracking
the tower slab. In other words, the cold joints between the stress of the concrete in direct tension was about the same as the
slab and columns were represented by axial and moment gross stress over the concrete section at yield of the horizontal
releases, uncoupling the corresponding degrees of freedom reinforcement in the web. With a horizontal web reinforcement
between the slab and columns; ratio of 0.26%, the gross stress in the concrete can be calculated
•• The tower slab and columns were modeled using linear as 0.26% × 480 MPa = 1.25 MPa (180 psi). This condition
will result in limited cracking, as strain will be concentrated at
beam elements, with an assumed elastic modulus of
25,000 MPa (3.6 million psi); initial cracks. Further, the unreinforced cold joint at the slab
•• The tower web between the lower columns was modeled ends would have acted as a crack initiator. Heavier web
reinforcement would have produced a more ductile structure
using nonlinear layered shell elements, with reinforcing
bars having a yield stress of 480 MPa and concrete having and possibly provided more time to react to the failure.
a tensile strength of 1.7 MPa (250 psi). The tower slab Cracking observed in the remaining (East) tower (shown in
acted as a stiffener at the web top; and Fig. 8) supports the hypothesis that strains concentrated at the
•• The force applied by the 0.6 in. diameter unbonded strands cold joint at the slab level and near the web-column
connection. Why did the remaining tower not collapse? Here
in the tower slab was modeled as an external clamping force.
Three analyses were made using different clamping forces. are a few plausible reasons:
The lowest force was 3100 kN, which is approximately the •• Because concrete had not yet been placed in the two most

(a) (b) (c)

Fig. 10: Plots of stress in horizontal reinforcement in the web, determined using a finite element model of the tower (the full tower was
modeled, but columns are truncated in the illustration). Stress in horizontal reinforcement at the column-web joint varied significantly with
clamping force: (a) clamping force P = 700,000 lbf (3100 kN); (b) P = 800,000 lbf (3560 kN); and (c) P = 1 million lbf (4450 kN)

www.concreteinternational.com | Ci | JUNE 2019 35


distant segments in the cantilever of the East Tower, the by a controlled detonation in July 2018.)
East Tower had lower loads. The 200 mm thick concrete The concentration of strains described previously implies
deck resulted in a uniform load of 4.7 kPa applied over the that the wall web reinforcement was likely to fracture early in
13 m wide deck area. Thus, relative to the West Tower, the the collapse process. That failure would not necessarily lead
total stay force in the cantilever side could have been to collapse if the remaining structure had sufficient capacity. A
reduced by 61 kN/m × 2 × 9.25 m = 1100 kN. Further, the limit analysis of a failure mechanism that did not include web
horizontal force in the stays anchored to the abutment yielding provided an estimated resistance smaller than the
could have been reduced by 1340 kN to balance the estimated demand. For safe operation, the demand should be
cantilever, resulting in a plausible reduction in the stay much less than the resistance. Given the brittleness of the
force in the tower of 1100 + 1340 × tan(40) = 2220 kN web, it is unlikely that both web and columns (working as
(a 10% reduction); parts of a plastic mechanism) reached their capacities at the
•• Post-tensioning in the tower slab of the East Tower same time.
might have been more effective than in the collapsed
West Tower; Conclusions
•• The East Tower might have had more web reinforcement; or In our opinion, the West Tower of the Chirajara Bridge
•• Initial shrinkage cracks might have distributed strains collapsed because post-tensioned reinforcement placed in a
better and reduced brittleness in the standing tower. slab meant to act as a tie between columns was insufficient by
The answer may involve one or several of these plausible a large margin. In contrast, in the perpendicular direction (that
reasons. In any case, it is clear that the East Tower was near is, in the direction of the deck), where no large stresses would
its limit. (Following a detailed study by a consulting firm, the have been expected, this slab tie (or tower slab) was provided
remaining portion of the Chirajara Bridge was brought down with nine times more reinforcement. Had the provided

Become an ACI Student Member


ORDER ACI 318-14
ACI’S STUDENT
AT

DISCOUNTED RATE
ACI student members also receive discounts on:
• ACI Committee Documents • Seminar Course Manuals • Workbooks
• ACI Education Online • Symposium Papers • ACI Convention Registration
Learning Courses

  
Get student pricing on ACI 318 by Become an ACI Student Member. It’s free Don’t miss the opportunity to apply for ACI
and gives access to ACI journals, internship Foundation Fellowships and Scholarships.
becoming an ACI Student Member. opportunities, and the ACI Career Center.

+1.248.848.3800 | www.concrete.org | |

36 JUNE 2019 | Ci | www.concreteinternational.com


reinforcement been rotated 90 degrees, the collapse would not
have occurred.
The insufficient lateral restraint offered by the Santiago Pujol, FACI, is a Professor of
civil engineering at the Lyles School of
reinforcement in the tower slab—a critical component that
Civil Engineering at Purdue University,
acted as a tie between columns—forced the reinforced
West Lafayette, IN. His research
concrete web between the columns to work in tension. Two
interests include seismic vulnerability
factors played a critical role in the response of the web to
of structures, response of structures
this tension:
••
to impulsive loads, structural health
The web had minimum tensile reinforcement (with a monitoring, repair, and strengthening
horizontal web reinforcement ratio of 0.26%). Its strength of structures. He is a member of ACI
was comparable to the expected cracking stress of the Committees 133, Disaster Reconnaissance, and 314, Simplified
concrete in direct tension. When cracking stress and Design of Concrete Buildings; ACI Subcommittee 318-R, High
reinforcement strength are similar, deformations Strength Reinforcement; and Joint ACI-ASCE Committees 441,
concentrate at a single or few cracks and tend to result in Reinforced Concrete Columns, and 445, Shear and Torsion.
brittle failure; and
•• The cold joint formed at the connection between the tower
slab and the columns created a discontinuity, forcing Michael E. Kreger, FACI, is the Garry
further concentration of strain and increasing the brittleness Neil Drummond Endowed Chair in
of the system. Civil Engineering and Director of the
Large-Scale Structures Laboratory in
Critical elements required to work in tension should be
the Department of Civil, Construction
reinforced with amounts of reinforcement exceeding the code
and Environmental Engineering at the
minima to avoid brittleness. The brittleness of the web
University of Alabama, Tuscaloosa,
prevented better redistribution of forces, which could have
AL. He is a member of the ACI Board
delayed the collapse.
of Direction and ACI Committees 133,
This tragic example emphasizes once again the importance Disaster Reconnaissance; 318, Structural Concrete Building
of peer review of all projects—especially projects with large Code; and 374, Performance-Based Seismic Design of Concrete
and complex structures. Buildings; ACI Subcommittees 318-C, Safety, Serviceability, and
Analysis; and 318-J, Joints and Connections; and Joint ACI-ASCE
Acknowledgments Committees 352, Joints and Connections in Monolithic Concrete
Our deepest condolences are expressed to the families of the workers Structures, and 441, Reinforced Concrete Columns.
who lost their lives in this tragedy. The only purpose of our work is to
avoid similar tragedies in the future.
Xenital S.A.S., under the direction of Sebastian Uribe, assisted the Jonathan D. Monical is pursuing his PhD
team in the inspection of the bridge using a drone-mounted camera. at the Lyles School of Civil Engineering
The Agencia Nacional de Infraestructura (ANI), Fiscalia General, and at Purdue University, where he received
his BSCE in 2016 and his MSCE in
Ministerio de Transporte, all government agencies in Colombia, are
structural engineering in 2017. He is a
thanked for their assistance in our investigation.
recipient of the school’s 2017 John E.
Special gratitude is expressed to Ron Burg and Matthew Senecal of ACI,
Goldberg Fellowship.
Luis Fernando Mejia of ANI, Luís E. Garcia, and Omar D. Cardona.
Their support and assistance were indispensable.

Disclaimer
This article contains the opinions and observations solely of the writers. Arturo E. Schultz is a Professor of civil
It does not reflect the views of any organization with which they are engineering and Director of Hybrid
associated. The writers shall not assume any responsibility related to use Simulation at the Department of Civil,
of their opinions by others. Environmental, and Geo- Engineering
at the University of Minnesota, Twin
References Cities, Minneapolis, MN. His research
1. ANI website, Agencia Nacional de Infraestructura (National interests include the seismic design and
Infrastructure Agency), Colombia, www.ani.gov.co/proyecto/carretero/ performance of concrete and masonry
bogota-villavicencio-21255. (last accessed Feb. 2019) structures. He is a member of Joint ACI-
2. SAP2000, “Integrated Software for Structural Analysis and ASCE Committees 335, Composite and
Design,” Computers & Structures, Inc. (CSI), 2018. Hybrid Structures, and 441, Reinforced Concrete Columns.

Selected for reader interest by the editors.

www.concreteinternational.com | Ci | JUNE 2019 37

You might also like