Professional Documents
Culture Documents
Chirajara - ACI Investigation of The Chirajara Colapse
Chirajara - ACI Investigation of The Chirajara Colapse
Chirajara - ACI Investigation of The Chirajara Colapse
T
he government of Colombia is conducting an The exterior spans were approximately 80 m (262 ft) long.
expansion of its built infrastructure, including the At the terminal ends of these shorter spans, massive
transportation system, through its Agencia Nacional de abutments were placed to provide reactions against a portion
Infraestructura (National Infrastructure Agency, ANI). The of the loads imposed on the longer center span.
Chirajara Bridge was one of 47 bridges in a project1 to expand The West Tower (at Axis B in Fig. 1) collapsed, claiming
the highway from Bogotá to Villavicencio from two to four
A B C D
lanes, with the bridge carrying two of those lanes. While 80.00 286.30 80.00
The Bridge
Overview Stays not in place
by two reinforced concrete towers, each to have 52 stay 129.5 m completed deck
(b)
cables. Each tower was 107.34 m (301 ft) tall (above a drilled
shaft foundation), and the center-to-center distance between Fig. 1: The Chirajara Bridge was a cable-stayed bridge, with a total
the towers was 286.3 m (938 ft). The stay cables consisted of projected length of 446.3 m (1464 ft), spanning the nearly 150 m
bundles of ASTM A416/A416M Grade 270 (270,000 psi (500 ft) deep Chirajara gorge: (a) schematic of the completed bridge
[1860 MPa] tensile strength) strands. The typical spacing of (viewed from the south); and (b) schematic of the West Tower at the
stay anchorages along the length of the bridge deck was 9.25 m time of the collapse on January 15, 2018 (Note: Dimensions are in m;
(30 ft), shown in Fig. 1. 1 m = 3.3 ft)
No. 3 crossties
1.40
70.00
2.15
0.5
6
13.00
0.050
14.15
17.62
1.60
Tower No. 4 bar at 0.2
slab
37.34
32.34
Web
4.00
0.25
2.38 8.50
5.00
8.50 1.6
Fig. 3: Section through tower column and web (Note: Dimensions are in m; 1 m =
Fig. 2: Schematic views of a bridge tower 3.3 ft; bar sizes are indicated using ASTM A706/A706M nomenclature—
(Note: Dimensions are in m; 1 m = 3.3 ft) roughly, diameters in multiples of 1/8 in.)
0.10
No. 4 at 0.25 L = 12.00
0.60 L = 1.75
Fig. 4: Section through slab that acted as a tie between the columns at the elevation with the widest separation (Note: Dimensions are in m
unless noted otherwise; 1 m = 3.3 ft; 1 in. = 25 mm)
were 20 mm (0.8 in.) thick in the direction of the deck and vertical bar (as shown in Fig. 3). While the drawings also
25 mm (1 in.) thick in the perpendicular direction, and they called for a spacing of 200 mm (8 in.) for both the vertical and
were anchored to the concrete with headed studs. horizontal bars, we observed in the remains of the West Tower
The web connecting the lower columns of the tower was web that the vertical spacing of the No. 4 bars varied between
reinforced with vertical and horizontal bars near each face. 100 and 200 mm (4 and 8 in.). A design section shows that the
The vertical reinforcement comprised No. 8 deformed bars horizontal web reinforcement was terminated at hooks
(1% reinforcement ratio) and the horizontal reinforcement anchored at exterior longitudinal bars in the column (Fig. 3).
comprised No. 4 bars (0.26% reinforcement ratio). The The tower slab reinforcement is shown in Fig. 4.
drawings showed No. 4 crossties at approximately every third Reinforcement anchored in the columns consisted of twelve
JOIN TODAY!
ACI CHAPTERS
200+ Professional and Student Chapters
www.concrete.org/chapters
Construction sequence
After the towers and abutments were
constructed, the deck was built from
each abutment to the adjacent tower.
Shoring supported the deck during this
operation. Deck segments were added
from each tower toward the center of the
middle span. These segments were
supported by stay cables, and the weight
of each was balanced by a corresponding
segment on the opposite side of the
Fig. 5: Frames from a video of the collapse of the West Tower, recorded by a nearby security
tower supporting it. Once the initial
camera north of the bridge. The time interval between each frame is approximately 1 second
seven pairs of stay cables were installed
for each tower, additional segments in
the center span were balanced by the concrete had been placed for the 12th Field Assessment
stays anchored in the nearest abutment. and 13th deck segments. The debris
It is also important to review what the The displacements seen in the video
Collapse structure was not experiencing at the simplified the task of identifying and
Reported conditions time of collapse. Neither portion of labeling the structural members in the
For the portion of the bridge that bridge was carrying significant live load, debris field (Fig. 6). Examination of the
collapsed (supported by the West and the concrete deck did not yet have a debris revealed that failure involved
Tower, on Axis B), 13 pairs of stay planned asphalt wearing course. Lastly, separation between the lower columns
cables are reported to have been there were no seismic demands, no and web. Figure 7 shows that the
installed from the tower toward reports of strong winds, and no horizontal No. 4 bars in the web
mid-span, with the total length of deck indication of foundation distress at the fractured at the juncture with a column.
cantilevered approximately 129.5 m base of the towers. Despite the collapse, the remains of the
(425 ft) from the center of the tower web had limited cracking, indicating
(shown in Fig. 1). We understand that Video evidence that strains were concentrated near the
the 200 mm thick reinforced concrete A security camera recorded the West columns, where the horizontal web
deck slab had been cast along this Tower during the collapse. Frames reinforcement fractured. We observed no
entire length. We also understand that extracted from this video are shown in failures in stay-cable anchorages in the
the deck supported by the collapsed Fig. 5. The sequence shows clearly that bridge deck, and we noted that deck
tower contained only small live loads at the dominant feature of the collapse girders fractured at splice locations.
the time of collapse. On the deck carried involved separation between the
by the (remaining) East Tower, 12 pairs columns on opposing sides of the tower, The remaining tower
of stay cables had been installed, and suggesting a tensile failure at or near the On January 25-26, 2018, the East
deck framing had been installed for the tower slab. The other bridge components Tower was still in place as constructed.
13th deck segment. Nevertheless, no fall almost directly downward. We inspected the tower with a powerful
Fig. 7: Views of the lower column south (LCS), showing the remnants of horizontal No. 4 bars at what had been the junction with the web:
(a) overall view; (b) view of bars that were bent downward as the column fell away from the web; and (c) closeup of bars that necked down
and fractured at the juncture
Fig. 10: Plots of stress in horizontal reinforcement in the web, determined using a finite element model of the tower (the full tower was
modeled, but columns are truncated in the illustration). Stress in horizontal reinforcement at the column-web joint varied significantly with
clamping force: (a) clamping force P = 700,000 lbf (3100 kN); (b) P = 800,000 lbf (3560 kN); and (c) P = 1 million lbf (4450 kN)
DISCOUNTED RATE
ACI student members also receive discounts on:
• ACI Committee Documents • Seminar Course Manuals • Workbooks
• ACI Education Online • Symposium Papers • ACI Convention Registration
Learning Courses
Get student pricing on ACI 318 by Become an ACI Student Member. It’s free Don’t miss the opportunity to apply for ACI
and gives access to ACI journals, internship Foundation Fellowships and Scholarships.
becoming an ACI Student Member. opportunities, and the ACI Career Center.
+1.248.848.3800 | www.concrete.org | |
Disclaimer
This article contains the opinions and observations solely of the writers. Arturo E. Schultz is a Professor of civil
It does not reflect the views of any organization with which they are engineering and Director of Hybrid
associated. The writers shall not assume any responsibility related to use Simulation at the Department of Civil,
of their opinions by others. Environmental, and Geo- Engineering
at the University of Minnesota, Twin
References Cities, Minneapolis, MN. His research
1. ANI website, Agencia Nacional de Infraestructura (National interests include the seismic design and
Infrastructure Agency), Colombia, www.ani.gov.co/proyecto/carretero/ performance of concrete and masonry
bogota-villavicencio-21255. (last accessed Feb. 2019) structures. He is a member of Joint ACI-
2. SAP2000, “Integrated Software for Structural Analysis and ASCE Committees 335, Composite and
Design,” Computers & Structures, Inc. (CSI), 2018. Hybrid Structures, and 441, Reinforced Concrete Columns.