WEEKLY CONSTRUCTION REPORT-3

(Period Des. 22 ,2020 ~ Des. 27, 2020)

PROJECT : Concrete Foundation Crusher CP-03 Bunati

LOCATION : KALIMANTAN SELATAN

INFRASTRUCTURE DEPARTMENT

0 Isued for Information 12/21/2020 Muhtar Angga Lesmana Endi Yulianto Doni Fisco Hary Setiawan
CLIENT
REV. DESCRIPTION DATE PJO CHECKED APPROVED
APPROVED

559747677.xlsx/
PT.MJMS - PT. BIB Page 1 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan

1. PROGRESS KESELURUHAN

Berikut laporan progress keseluruhan proyek Concrete Retaining Wall Crusher CP-03 Bunati
berdasarkan hasil pekerjaan dari tgl 22/12/2020~27/12/2020.
Progress aktual untuk pekerjaan konstruksi adalah (0% ) dari total sesuai S-Curve pembobotan di Sheet 2 ,untuk rincian pekerjaan yang
dilakukan terinci di point 2.

2. AKTIVITAS MINGGU INI :


ITEM PEKERJAAN BOBOT (%)
Cutting Mini Pile 25x25 1.48%

3. RENCANA MINGGU DEPAN :


ITEM PEKERJAAN BOBOT (%)
Lean Concrete K100 5.67%
Concrete K300 26.64%
Concrete Reinforcement 22.07
Anchor L, M10 - 300 mm 0.32
Anchor L, M22 - 500 mm 5.8

TOTAL 28.53
4. Item Penting 5. Problem

- - Cuaca tidak kondusif


- - Terdapat 4 minipile belum bisa di potong Hasil konsultasi dan pertimbangan BPk Hary Setiawan
- -
6. Action Plan
-
-

559747677.xlsx/
PT.MJMS - PT. BIB Page 2 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan

5. SAFETY REPORT
- Man power average consumption this week : 4 Man/day.

- Working hours :

Day Sun Mon Tue Wed Thu Fri SAT


###
24 : PM
###
23 : PM
###
22 : PM
###
21 : PM
###
20 : PM
###
19 : PM
###
18 : PM
###
17 : AM
###
16 : AM
###
15 : AM
###
14 : AM
###
13 : AM
###
12 : AM
###
11 : AM
###
10 : AM
###
9 : AM
###
8 : AM
Hours 6 5 8 7 5 5 7 43

Hours Consumption as of Des 27, 2020 : 172 Man-Hours.

- HSE Statistik :

HSE STATISTIK POJECT WORKSHOP & WAREHOUSE BUNATI 10Ha


Jenis Kecelakaan Lost
No Hari/Tanggal Medical Treatment Case Jenis/Uraian Pekerjaan
Near Miss First Aid Workdays Fatality
(MTC) Case (LTC)
1
Sun, 26 Des 2020
2
Mon,27 Des2020
3
Wed, 22 Des 2020
4
Thu, 23 Des 2020
5
Fri, 24 Des 2020
6
sat,25 Des 2020

Jumlah 0.00 0.00 0.00 0.00 0.00

559747677.xlsx/
PT.MJMS - PT. BIB Page 3 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan

- Struktur Organisasi :

Direkut Utama
H. Muhtarom

Direktur Proyek
Muhtar Angga Lesmana

Project Manager
Endi Yulianto

Safety K3 M&E Site Manager Drafter Administrasi


Hendra Deslianto Ardi Parlan Kurniawan Sidiq Nasib Utomo Ansiha

Mandor 1 Mandor 2
Selamet Sajoko Putut Setiawan

6. LAPORAN KONDISI CUACA

DAY
SA SU MO TU WE TH FR REMARKS
DESCRIPTION
CLEAR

CLOUD

RAINY

7. MASALAH DILAPANGAN
- Cuaca Tidak Kondusif

- Terdapat 4 minipile belum bisa di potong Hasil konsultasi dan pertimbangan BPk Hary Setiawan
-
-
-
-
-
-
-
-
-
-
-
-

559747677.xlsx/
PT.MJMS - PT. BIB Page 4 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan

PHOTOGRAPH REPORT

Kemajuan Pekerjaan Pemotongan Minipile sisa 4 tiang

559747677.xlsx/
PT.MJMS - PT. BIB Page 5 of 7
WEEKLY REPORT (3)
TAHUN 2020
NO URAIAN UN VOL HARGA SATUAN HARGA BOBOT Plan vs BULAN
% Actual DESEMBER
MINGGU KE-1 MINGGU KE-2 MINGGU KE-3 MINGGU KE-4
10-15 16-21 22-27 23-27
1 Pekerjaan Persiapan LS 1 10,000,000 10,000,000 3.15 Plan 3.15
Actual 3.15
2 Cutting Mini Pile 25x25 PCS 47 200,000 9,400,000 2.96 Plan 1.48 1.48
Actual 1.48 1.48
3 Lean Concrete K100 M3 9 2,000,000 18,000,000 5.67 Plan 5.67
Actual
4 Concrete K300 M3 50 3,380,000 169,000,000 53.28 Plan 26.64 26.64
Actual
5 Concrete Reinforcement Kg 2,800 25,000 70,000,000 22.07 Plan 7.35 7.35 7.35
Actual
6 Anchor L, M10 - 300 mm Point 10 100,000 1,000,000 0.32 Plan 0.32
Actual
7 Anchor L, M22 - 500 mm Point 184 200,000 36,800,000 11.60 Plan 5.8 5.8
Actual
8 Grouting Baseplate M3 1.5 2,000,000 3,000,000 0.95 Plan 0.96
Actual
Actual
TOTAL : 317,200,000
PPN (10%) : 31,720,000
GRAND TOTAL : 348,920,000
RENCANA 4.63 47.26 40 8.31
AKUMULASI RENCANA
REALISASI
AKUMULASI REALISASI

Dibuat Oleh :
CV. AMANAH INSANI
Disetujui Oleh
Owner
PT.Borneo Indobara

PJO
MUHTAR ANGGA LESMANA

……………………….
………………………