Professional Documents
Culture Documents
Weekly Report 3
Weekly Report 3
Weekly Report 3
INFRASTRUCTURE DEPARTMENT
0 Isued for Information 12/21/2020 Muhtar Angga Lesmana Endi Yulianto Doni Fisco Hary Setiawan
CLIENT
REV. DESCRIPTION DATE PJO CHECKED APPROVED
APPROVED
559747677.xlsx/
PT.MJMS - PT. BIB Page 1 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan
1. PROGRESS KESELURUHAN
Berikut laporan progress keseluruhan proyek Concrete Retaining Wall Crusher CP-03 Bunati
berdasarkan hasil pekerjaan dari tgl 22/12/2020~27/12/2020.
Progress aktual untuk pekerjaan konstruksi adalah (0% ) dari total sesuai S-Curve pembobotan di Sheet 2 ,untuk rincian pekerjaan yang
dilakukan terinci di point 2.
TOTAL 28.53
4. Item Penting 5. Problem
559747677.xlsx/
PT.MJMS - PT. BIB Page 2 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan
5. SAFETY REPORT
- Man power average consumption this week : 4 Man/day.
- Working hours :
- HSE Statistik :
559747677.xlsx/
PT.MJMS - PT. BIB Page 3 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan
- Struktur Organisasi :
Direkut Utama
H. Muhtarom
Direktur Proyek
Muhtar Angga Lesmana
Project Manager
Endi Yulianto
Mandor 1 Mandor 2
Selamet Sajoko Putut Setiawan
DAY
SA SU MO TU WE TH FR REMARKS
DESCRIPTION
CLEAR
CLOUD
RAINY
7. MASALAH DILAPANGAN
- Cuaca Tidak Kondusif
- Terdapat 4 minipile belum bisa di potong Hasil konsultasi dan pertimbangan BPk Hary Setiawan
-
-
-
-
-
-
-
-
-
-
-
-
559747677.xlsx/
PT.MJMS - PT. BIB Page 4 of 7
WEEKLY REPORT (3)
REV
CPP PROJECT DEPT
WEEKLY CONSTRUCTION REPORT-3 0
DOC. NO. :
(Period Des. 22 ,2020 ~ Des. 27, 2020)
DATE PJO CHKD APVD
12/21/2020 Muhtar Angga Lesmana Doni Fisco Hary Setiawan
PHOTOGRAPH REPORT
559747677.xlsx/
PT.MJMS - PT. BIB Page 5 of 7
WEEKLY REPORT (3)
TAHUN 2020
NO URAIAN UN VOL HARGA SATUAN HARGA BOBOT Plan vs BULAN
% Actual DESEMBER
MINGGU KE-1 MINGGU KE-2 MINGGU KE-3 MINGGU KE-4
10-15 16-21 22-27 23-27
1 Pekerjaan Persiapan LS 1 10,000,000 10,000,000 3.15 Plan 3.15
Actual 3.15
2 Cutting Mini Pile 25x25 PCS 47 200,000 9,400,000 2.96 Plan 1.48 1.48
Actual 1.48 1.48
3 Lean Concrete K100 M3 9 2,000,000 18,000,000 5.67 Plan 5.67
Actual
4 Concrete K300 M3 50 3,380,000 169,000,000 53.28 Plan 26.64 26.64
Actual
5 Concrete Reinforcement Kg 2,800 25,000 70,000,000 22.07 Plan 7.35 7.35 7.35
Actual
6 Anchor L, M10 - 300 mm Point 10 100,000 1,000,000 0.32 Plan 0.32
Actual
7 Anchor L, M22 - 500 mm Point 184 200,000 36,800,000 11.60 Plan 5.8 5.8
Actual
8 Grouting Baseplate M3 1.5 2,000,000 3,000,000 0.95 Plan 0.96
Actual
Actual
TOTAL : 317,200,000
PPN (10%) : 31,720,000
GRAND TOTAL : 348,920,000
RENCANA 4.63 47.26 40 8.31
AKUMULASI RENCANA
REALISASI
AKUMULASI REALISASI
Dibuat Oleh :
CV. AMANAH INSANI
Disetujui Oleh
Owner
PT.Borneo Indobara
PJO
MUHTAR ANGGA LESMANA
……………………….
………………………