PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN

SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

PACKAGE 2B
Membina dan Menyiapkan Kuarters Kakitangan Di Loji Rawatan
Air Langat 2
Contract No: PAAB/B001-P2B/W/B/K/03/19
Progress for period ending 09 October 2021:

Rev.0 Rev.1

PLANNED 100.00% 91.56 %

PHYSICAL PROGRESS ACTUAL 74.95% 74.95%

(25.05%) (16.61%)
AHEAD/(DELAY)
(175 day)

PLANNED 100.00% 91.37%

OVERALL PROGRESS ACTUAL 74.20% 74.20%

AHEAD/ (DELAY) (25.80%) (17.17%)

Page 1 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

05/10/2021
P2B- HSSE: weekly toolbox meeting

05/10/2021
P2B- HSSE: Sanitizing CSRK site office for Covid-19 prevention & SOP

Page 2 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Infrastructure: Installation blank flange for pressure test

09/10/2021
P2B- TNB Substation: Overall view.

Page 3 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

04/10/2021
P2B- Refuse Centre: Fixing reinforcement bar & formworks for roof beam in progress

05/10/2021
P2B- Refuse Centre: Concreting works for roof beam in progress

Page 4 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

07/10/2021
P2B- Refuse Centre: Dismantle formworks at roof beam in progress

09/10/2021
P2B- Refuse Centre: Overall view.

Page 5 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

04/10/2021
P2B- Block Dewan: Plastering works for external wall at ground level in progress

05/10/2021
P2B- Block Dewan: Installation insulation system at upper roof in progress

Page 6 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

06/10/2021
P2B- Block Dewan: Plastering works for RC gutter coping at entrance in progress.

07/10/2021
P2B- Block Dewan: Plastering works for external column in progress

Page 7 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

07/10/2021
P2B- Block Dewan: Installation roof cover at upper roof in progress

09/10/2021
P2B- Block Dewan: Overall view.

Page 8 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

04/10/2021
P2B- Block Surau: Moisture test using Protimeter before applying under coat paint.

05/10/2021
P2B- Block Surau: Installation conduit & trunking at AV room in progress

Page 9 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

06/10/2021
P2B- Block Surau: Applying under coat at coping in progress

07/10/2021
P2B- Block Surau: Screeding works at ablution in progress

Page 10 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

07/10/2021
P2B- Block Surau: Applying under coat for external wall in progress

08/10/2021
P2B- Block Surau: Laying cable at prayer area in progress.

Page 11 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Block Surau: Installation AWC at male toilet in progress

09/10/2021
P2B- Block Surau: Overall view.

Page 12 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Block F1: Overall view.

05/10/2021
rd
P2B- Block F2: Tiling works for kitchen at 3 floor progress.

Page 13 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

05/10/2021
P2B- Block F2: Tiling works for balcony 3rd floor in progress

09/10/2021
P2B- Block F2: Overall view.

Page 14 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

06/10/2021
P2B- Block F3: Installation IC cover for riser at ground floor in progress

08/10/2021
P2B- Block F3: Concreting works for apron slab in progress

Page 15 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Block F3: Overall view.

09/10/2021
P2B- Block F4: Fixing reinforcement bar & formwork for car park footing in progress.

Page 16 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Block F4: Overall view.

04/10/2021
nd
P2B- Block E1: Tiling works for bathroom & bedroom at 2 floor in progress

Page 17 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

09/10/2021
P2B- Block E1: Overall view.

05/10/2021
P2B- Block E2: Fixing reinforcement bar & formworks for apron slab in progress.

Page 18 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

06/10/2021
st
P2B- Block E2: Tiling works for kitchen at 1 floor in progress.

07/10/2021
P2B- Block E2: Plaster ceiling for bathroom at ground floor in progress

Page 19 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

08/10/2021
P2B- Block E2: Concreting works for apron slab in progress.

09/10/2021
P2B- Block E2: Overall view.

Page 20 of 21
PROPOSED DEVELOPMENT OF LANGAT 2 WATER TREATMENT PLANT AND WATER RETICULATION SYSTEM IN
SELANGOR DARUL EHSAN / WILAYAH PERSEKUTUAN KUALA LUMPUR

Weekly Progress Photos – Period Ending: 09 October 2021

06/10/2021
st
P2B- Block E3: Installation door leaf & door closer for riser at 1 floor in progress

09/10/2021
P2B- Block E3: Overall view.

Page 21 of 21