Planned PS Under REZ-66 5GW Connectivity LTA Details

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Details of Connectivity/LTA and PPA associated with 66.5GW REZ Schemes As on 30.09.

2021

Potential REZs Status of Stage-II connectivity Status of LTA


Substation name & Transformation Total (GW) PPA Signed
State/Area Taluk/Tehsil
details Capacity (in GW)
Granted Agreed for Grant (in Granted Agreed for Grant
W+S
(in GW) GW) (in GW) (in GW)
Gujarat
2x1500MVA, 765/400
Kutch Bhuj Bhuj-II PS
4x500MVA, 400/220
2 1.05 0 0.75 0.3 1.05
4x1500MVA, 765/400
Kutch Existing S/s - Bhuj PS
8x500MVA, 400/220
0 - 0.9325 0.5825
2x1500MVA, 765/400
Kutch Lakadia Lakadia PS
4x500MVA, 400/220
2 0 - 0 - -
Dwarka Jam Khambhaliya Jam Khambhaliya PS 4x500MVA, 400/220 2 0.9664 - 0.3014 - 0.3014
3x1500MVA, 765/400kV (Ph-A:
Khavda Khavda Khavda PS Ph-I) 3.5 - 1 - -
10
4x1500MVA, 765/400 kV (Ph-A:
Khavda Khavda Khavda II PS
Ph-I)
1.2 - 1.2 - 0

Subtotal 16 6.7164 0 4.1839 0.30 1.9339

Maharashtra

Solapur (PG) (1GW@400kV) & Solapur (PG) : 1 no. 400kV bay


Solapur
Solapur PP (1.5GW) Solapur PP:
2.5 0 - 0 - -
3x500MVA, 400/220
Wardha Wardha PP 5x500MVA, 400/220 2.5 0 - 0 - -
Kallam PS (1GW under ISTS & 1
Osmanabad GW to be developed under intra 2x500MVA, 400/220 2 0.3 - 0.3 - -
state)

Subtotal 7 0.3 0 0.3 0


Madhya Pradesh*
5x500MVA, 400/220
Rajgarh Pachora PS (near Agar) (3X500 MVA, 400/220 kV is 2.5 1 - 1 - -
under Ph-I:1500 MW)
Chhatarpur Chhatarpur PS 3x500MVA, 400/220 1.5 - - - - -
Neemuch Neemuch PS 2x500MVA, 400/220 1 0.5 - 0.5 - -
Subtotal 5 1.5 0 1.5 0 0
WR Total 28 8.5164 0 5.9839 0.30 1.9339
Rajasthan
Fatehgarh-III (erstwhile
Jaisalmer Fatehgarh
Ramgarh-II)
4x500MVA, 400/220 1.9 7.705 - 1.98 - 1.38
6x1500MVA, 765/400
Fatehgarh Fatehgarh-II
9x500MVA, 400/220
4.5 5.46 - 3.6600 - 3.6600
3x1500MVA, 765/400
Jodhpur Phalodi Bhadla-II
8x500MVA, 400/220
3.55 5.945 - 2.6450 - 2.6450

Bikaner Koyalat /Pugal Bikaner-II NA (400kV PS) 2.95 0.49 0.345 0 - -

3x1500MVA, 765/400
Jodhpur Phalodi Bhadla
8x500MVA, 400/220
1.05 1.25 - 1.2 - 1.2

Jaisalmer Fatehgarh Fatehgarh NA (400kV PS) 1.2 1.2 - 1.2 - 1.2

2x1500MVA, 765/400
Bikaner Bikaner Bikaner
2x500MVA, 400/220
1.85 3.645 - 2.975 - 2.34

Subtotal 17 25.695 0.345 13.6600 0.0000 12.4250


Rajasthan Intra-state 3 - - - - -
NR Total 20 25.695 0.345 13.6600 0.0000 12.4250
Andhra Pradesh
3x1500MVA, 765/400
Kurnool Gooty Kurnool-III
9x500MVA, 400/220
4.5 0 0
Ananthpuram Urvakonda Anantpur PS 7x500MVA, 400/220 3.5 0 0
Subtotal 8 0 0
Karnataka
Gadag Gadag PS 5x500MVA, 400/220 2.5 0.46 0.46
3x1500MVA, 765/400
Bidar Bidar PS
5x500MVA, 400/220
2.5 0 0
Koppal Koppal PS 5x500MVA, 400/220 2.5 1.2 0.11 0.6
Subtotal 7.5 1.66 0.11 1.06 0
Tamil Nadu
Karur Karur PS 5x500MVA, 400/230 2.5 0.42 0.1
Tirunelvelli Tuticorin-II 1x500MVA, 400/230 0.5 0.50 0.14
Subtotal 3 0.92 0.24 0
SR Total 18.5 2.58 0.11 1.3 0
All India Total 66.5 36.7914 0.455 20.9439 0.3000 14.3589
Phase-wise totals
*In addition, MNRE has identified 0.6GW REZ Potential at Khandwa and 1.25GW REZ Potential at Morena (Jhiniya)