Professional Documents
Culture Documents
Project Management-Cat 1
Project Management-Cat 1
Project Management
Activity
• Consider a personal project that
you have been involved with in
the last few years, such as
moving your residence or buying
a Vehicle. Describe the activities
related to that project that fit into
each of the four project phases.
Case Studies
Consider a project that involves the
merger of computer systems of two
banks. The acquiring bank wants to
convert the other bank’s computer
system to its own software, and the
project is to convert all the client
account files. The software used by
the acquiring bank is relatively new,
and only about a third of the project
team is familiar with it.
A steel company in Indiana purchased a new coal
injection technology that would improve the quality
of steel, reduce the cost to produce the steel, and
reduce air and water pollution. The contract to
design and construct the new plant was awarded to
an engineering and construction company. No one
on the engineering and construction team had
experience with the coal injection technology.
The client’s team understood the technology and
provided guidance to both the project engineering
and construction teams. The client owned the coal
injection technology, and the engineering and
construction team brought the project management
technology.
Project Classification
There is no standard classification of the
projects. However considering project goals,
these can be classified into two broad groups,
Industrial and Developmental.
Each of these groups can be further classified
considering nature of work (repetitive, non-
repetitive), completion time (long term, short
term etc.), cost (large, small, etc.), level of risk
(high, low, no-risk), mode of operation ( build,
build-operate-transfer etc.).
A ) Industrial Projects
Industrial projects also referred as
commercial projects, which are undertaken
to provide goods or services for meeting the
growing needs of the customers and
providing attractive returns to the
investors/stake holders.
Human Resources
Material Resources
Financial Resources
Time Resources
Project Management is the application of
Knowledge, Skills, Tools and Techniques to
project activities to meet project requirements.
A universal tool ……
Portfolio Management
Portfolio Management
A portfolio is a collection of projects, programs sub portfolios, and
operations that are grouped together to facilitate effective management of
that work to meet strategic business objectives. Organizations manage
their portfolios based on specific goals.
Design
Implementation
System Testing
D
E
L
A
Y
Vaporware
Project Management Activities
Initiation
Problem statement
definition
Project kickoff
Project kickoff
Steady state
Termination
f1:Function
p:Project
f2:Function
• Smallest unit of
work subject to
a1:Activity a2:Activity
management
• Large enough to
avoid micro
t1:Task t2:Task t3:Task management
Activities
f1:Function
p:Project
f2:Function
a1:Activity a2:Activity
• Major unit of work
with precise dates
a2.1:Activity a2.2:Activity
• Consists of smaller
activities or tasks
PMBOK Guide is the bible for Project Management. There are ten knowledge areas defined in PMBOK Guide, which are as
follows −
Management roles
Organization and execution of the project within constraints.
Examples: Project Manager, Team Leader.
Development roles
Specification, design and construction of subsystems.
Examples: Analyst, System Architect, Implementor.
Cross functional roles
Coordination of more than one team. Example: API Engineer,
Configuration Manager, Tester
Consultant roles
Support in areas where the project participants lack expertise.
Examples: End User, Client, Application Domain Specialist (
problem domain), Technical Consultant (solution domain).
Promoter roles
Promote change through an organization.
Group Activity
MSME & SSI
Project Planning
:Project Scheduling
Project planning involves a series of
steps that determine how to achieve a
particular community or organizational
goal or set of related goals. This goal can
be identified in a community plan or a
strategic plan. Project plans can also be
based on community goals or action
strategies developed through community
meetings and gatherings, tribal council or
board meetings, or other planning
processes.
Project Planning
WBS = Nouns
Schedule Activities = Verbs
Define Activities
Sequence activities
Estimate time and
Develop schedule
Project Scheduling Techniques
Gantt chart- This is represented by the graph or bar chart with
a specific bar for activities in the project that shows the
passage of time. Gantt chart limits a clear indication of
interrelation between the activities.
CPM- Critical path method was developed for industrial
projects where activity times are generally known.
PERT- Program evaluation and review technique were
developed for R&D projects where activity times are generally
uncertain. Its prime objective is taking the shortest possible
time.
Microsoft projects- All the work is performed on the computer
memory and changes can be saved only when the program is
asked to operate.
Project Managers Uses Three Principal
Types Network Diagrams
Precedence Diagramming Method (PDM)
Arrow Diagramming Method (ADM)
Conditional Diagramming Methods
Precedence Diagramming Method (PDM)
Rule 2 :
No two activities can be recognized by the same
end events
Rule 3 :
To assure the correct precedence relationship in
the arrow diagram, various questions must be
tested every time any activity is added to the
network
What activity must be finished immediately
before this activity can start?
What activities must occur at the same time
with this activity?
What activities must follow this activity?
For preparation of Paneer (Cottage Cheese)
the following list represents major activities
I. Receive whole cow/buffalo milk
ii) Standardize milk to obtain desired level of fat percentage
iii) Take citric acid and prepare 1% solution
iv) Heat the citric acid to 70 o C
v) Bring the standardized milk to boil on medium heat
vi) Cool the milk to 70 o C and add slowly the solution of citric acid till
yellowish whey separates
vii) Strain the mixture through a clean muslin cloth.
viii) Hold it under running water for a minute and then press out the excess
water.
ix) Hang the muslin for 15-20 minutes so that all the whey is drained out.
x) Prepare mould to form Paneer block
xi) Fill the mass into the block and tie the muslin
xii) Place it under something heavy for up to two hours
xiii) Cut the paneer into chunks and used as required.
Precedence table
Activity Description Preceding Activity
F Cool the milk to 70 o C and add slowly the solution of citric acid till D,E
yellowish whey separates.
H Hold it under running water for a minute and press out the excess G
water.
I Hang the muslin for 15-20 minutes and drain out all the whey. H
K Fill the mass into the block and tie the muslin J
g) Two events are numbered in such a way that the event of higher number
can happen only after the event of lower number is completed.
h) Arrows should be kept straight and not
curved. Avoid arrow which cross each other.
i) Avoid mixing two directions vertical and
standing arrows may be used if necessary.
j) Use dummy activity freely in rough graph
but final network should have only reluctant
dummy.
k) The network has only one entry point
called the start event and one point of
emergence called end event.
l) Angle between the arrows should be as
large as possible.
Labeling of a Network Diagram
A standard procedure called i-j rule developed by D.R.F Fulkerson is most
commonly used for this purpose.
Step 1: First, a start event is one which has arrows
emerging from it but not entering it. Find the start event and
label it as number1.
Step 2: Delete all arrows emerging from all numbered
events. This will create at least one new start event out of
the preceding events.
Step 3: Number all new start events �2�, �3� and so on.
No definite rule is necessary but numbering from top to
bottom may facilitate other users using the network when
there are more than one new start event.
Step 4: Go on repeating step no. 2 & 3 until the end
reached.
For preparation of Paneer (Cottage Cheese)
Common Errors in Drawing Networks
1.Dangling
2. Looping or Cycling
3.Redundancy
Two activities starting from a tail event must not have a same
end event. To ensure this, it is absolutely necessary to introduce
a dummy activity
Looping error should not be formed in a network, as it
represents performance
of activities repeatedly in a cyclic manner
In a network, there should be only one start
event and one ending event
The direction of arrows should flow from left to
right avoiding mixing of direction
Dangling
C Dangling
A B D E G
Dangling
F
Looping
Looping error is also called as cycling error in a network
diagram. Making an endless loop in a network is called as
error of looping.
A
Redundancy
When the dummy activity is introduced and it is not
required, it is called redundancy errors.
C
B
A D
A B C D
Event: An event (or node) will always occur at the
beginning and end of an activity. The event has no
resources and is represented by a circle. The ith event and
jth event are the tail event and head event respectively,
(Figure 8.2).
Activity Types
• Predecessor activity - Activities that
ought to be completed immediately
previous to the start of another activity
are known as predecessor activities.
• Successor activity - These are those
activities that cannot be started until one
or more of other activities are finished
but immediately succeed them.
Dummy Activity
An imaginary activity which does not consume any resource and time is
called a dummy activity. Dummy activities are simply used to
represent a connection between events in order to maintain a logic in
the network. It is represented by a dotted line in a network.
Event
An event signifies a point in time representing the completion of several activities
and the starting of new ones. This is typically symbolizes by a circle in a network
which is also known as node or connector.
Merge event - Event in which more than one activity comes and connects an event is
called as merge event.
Burst event - It is event in which more than one activity leaves an event.
Merge and Burst event - An activity can be merge and burst event simultaneously,
as regard some activities it can be a merge event and with some other activities it
may be a burst event.
Guidelines for Drawing Network Diagram
a) Each activity is represented by one and only one arrow in the network. This implies that no
single activity can be represented twice in the network. This is to be distinguished from the
case where one activity is broken into segments. In such a case each segment may be
represented by a separate arrow.
b) No two activities can be identified by the same beginning and end event. In such cases, a
dummy activity is introduced to resolve the problem
c) In order to ensure the correct precedence relationship in arrow diagram following
question must be checked whenever any activity is added to a network.
What activity must be completed immediately before this activity can start?
What activities must follow this activity?
What activities must occur simultaneously with this activity?
e) The arrows depicting various activities are indicative of logical precedence only; hence length
and bearing of the arrows are of no significance.
g) Two events are numbered in such a way that the event of higher number can happen only
after the event of lower number is completed.
Labeling of a Network Diagram
A standard procedure called i-j rule developed by D.R.F Fulkerson is most
commonly used for this purpose.
Step 1: First, a start event is one which has arrows
emerging from it but not entering it. Find the start event
and label it as number1.
Step 2: Delete all arrows emerging from all numbered
events. This will create at least one new start event out of
the preceding events.
Step 3: Number all new start events �2�, �3� and so on.
No definite rule is necessary but numbering from top to
bottom may facilitate other users using the network when
there are more than one new start event.
Step 4: Go on repeating step no. 2 & 3 until the end
reached.
ERRORS TO BE AVOIDED IN
CONSTRUCTING A NETWORK
1.Dangling
2. Looping or Cycling
3.Redundancy
Two activities starting from a tail event must not have a same
end event. To ensure this, it is absolutely necessary to introduce
a dummy activity
In a network, there should be only one start event
A
The direction of arrows should flow from left to right
avoiding mixing of direction
Dangling
Whenever an activity is disconnected from the network it
is called dangling error.
C
A B Dangli E G
ng
D
Dangli
F ng
Redunda
ncy
When the dummy activity is introduced and it is not
required, it is called redundancy errors.
C
B
A D
A B C D
Example - 1
Extension to the Recreation center
Creating Facility For Lift Irrigation
1.
In A Farm
It is assumed that the competent authority has approved the
project and the project scheduling starts with the activity of “Site
selection”.
2. Irrigation would be provided from a newly dug well.
3. Field channels from the well would be laid after its digging.
4. Suitable pump would be procured and installed for lifting water.
5. Specification for the pump is finalized based on the groundwater
prospecting data before digging.
6. Pump and other inputs would not be procured until the site is
selected.
7. Pump would be installed after digging the well.
Step 1: Identify the activities
H Hold it under running water for a minute and press out the excess G
water.
I Hang the muslin for 15-20 minutes and drain out all the whey. H
J Prepare mould to form Paneer block H
K Fill the mass into the block and tie the muslin J
L Place it under something heavy for up to two hours. K
M Cut the paneer into chunks and use as required. L
Example – 4
It is suitable for projects which required research and It is suitable for construction projects.
development.
PERT & CPM
PROJECT COMPLETION
TIME
Four types of time required to accomplish an activity.
Optimistic time: The minimum possible time required to accomplish an activity (o)
or a path (O), assuming everything proceeds better than is normally expected
Pessimistic time: The maximum possible time required to accomplish an activity
(p) or a path (P), assuming everything goes wrong (but excluding major
catastrophes).
Most likely time: The best estimate of the time required to accomplish an activity
(m) or a path (M), assuming everything proceeds as normal.
Expected time: the best estimate of the time required to accomplish an activity
(te) or a path (TE), accounting for the fact that things don't always proceed as
normal (the implication being that the expected time is
the average time the task would require if the task were
repeated on a number of occasions over an extended period of time.
A formula to estimate the cost and/or time required to complete a task .
TE means Estimated Time, o Optimistic Time, m Most likely Time , p Pessimistic
Time
TE= (o + 4m + p) ÷ 6
For Activity A:
o = 4 hours (Optimistic time), m = 8
hours (Most likely time), p = 16 hours
(Pessimistic time) TE is Most likely
time
TE = (o + 4m + p) ÷ 6
E = (4 + 4(8) + 16) / 6
E = 52 / 6
E = 8.7 hours
Critical path: Critical path is the longest
sequence of activities in a project plan which
must be completed on time for the project to
complete on its due. It is the sequence of
activities which decides the total project duration
Variables within critical path
Float or slack is a measure of the excess time and
resources available to complete a task. How long a
task can be delayed without interrupting other tasks
or the whole project
It is the amount of time that a project task can be
delayed without causing a delay in any subsequent
tasks (free float) or the whole project (total float).
Positive slack would indicate ahead of schedule;
Negative slack would indicate behind schedule; and
Zero slack would indicate on schedule.
A project consists of the following activities and time estimates. Construct
the network. determine the expected task time. show the critical path. what
is the project duration?
The formula for expected task time (te) =
From this network diagram 1-4-7 represents the critical path and the
duration for project completion = total time along the critical path = 14+11 =
25 days
WBS & Project Network Diagram
The WBS creation involves:
Listing all the project outputs (deliverables and other direct
results)
Identifying all the activities required to deliver the outputs
Subdividing these activities into sub activities and tasks
Identifying the deliverable and milestone(s) of each task
Identifying the time usage of all the resources (personnel
and material) required to complete each task
The purpose of developing a WBS is to:
Allow easier management of each component
Allow accurate estimation of time, cost, and resource
requirements
Allow easier assignment of human resources
Allow easier assignment of responsibility for activities
The WBS is not a schedule, but it is the basis for
it. The network diagram is a schedule.
From this network diagram 1-4-7 represents the critical path and the
duration for project completion = total time along the critical path = 14+11 =
25 days
Concept, Need, Applicability
Crashing
Crashing
Crashing is a schedule compression technique used to
reduce or shorten the project schedule without changing
the scope. The project schedule and deliver the product, service, or
result earlier than what was originally planned
Crashing of a project is used only in emergency
situations. The decision should then take place only
after carefully analyzing all the possible alternatives.
The goal is to obtain the maximum reduction in project
completion time with the minimum additional cost.
Direct impact on two constraints, ie. Planning and
Costs.
Reasons to crash the project
A delay in the project timeline: If organization face penalties due to
delays in the project timeline, adding more resources to move up
the completion date may be worthwhile.
Availability of resources: If the team or organization has resources
available, using those resources can help to speed up the project
timeline.
Avoiding a future delay: Adding resources to prevent a delay in the
future will typically add some cost, but may be more beneficial
than facing later delays that will be more costly.
Resources available through training: When an organization is
training new staff members, they may assign those employees to
work on the project as they complete their training.
New project: If the team is working on a project and receives the
assignment to take on a new project, you may crash the original
project to finish it faster and focus on the new project
Two Methodologies
Method 1: Project Crashing / Increase the
number of resources
Social Aspects
Economic Aspects
Environmental Aspects Financial Aspects
Administrative/Management Aspects
Commercial Aspects
Technical Aspects
Technical Appraisal
❖Technical appraisal is an in-depth study to ensure that a project is
(i) soundly designed,
(ii) appropriately engineered and
(iii) follows accepted standards.
Proximity of markets
Transportation facilities
Water
2
Feasibility means “practicability”. a feasibility analysis is necessary to
check that if we are going in the right direction or have we chosen the
right product.
Feasibility analysis has two most important aspects :
(a) Design Aspect (Technical know-how)
(b) Economic Aspect (Financially feasible)
If a product which we have chosen fails in one of the above
analysis i.e. either we are not technically sound to design it (Techno) or
we are unable to justify the cost of new product (Economic), then we
don’t proceed in this direction but choose some other alternative, say,
choosing another product or going for a job/ service.
The techno-economic analysis can be divided into 2 parts :
Technical Feasibility
Economical or Optimal Project Strategy
Contents of TEFR
Objective and scope of the report
Product characteristics.
Market position and trends.
Raw material requirement, prices, sources and properties of raw
materials.
Manufacturing processes, selection of process, production
schedule and techniques.
Plant and machinery.
Requirement of land area, building, construction schedule.
Financial implications.
Marketing channels, their trending practices and marketing strategies
Requirement of personnel, labour and expenses on wage system.
Factors to be considerd while
preparing report
Technical
considerations
Economic
considerations
Financial
considerations
Managerial
consideration
Implementation
schedule
8
Technical Considerations : It establishes whether the project is
technically feasible or not. In this various technical alternatives
on employment, ecology , infrastructure demands, capital
services , balance of payments and other factors are taken in
account.
Economic Considerations : Economic data relates to market, the data
required for analysis of this aspect can be obtained from secondary
sources like government agencies, trade associations. Data can also
be obtained through primary sources like mailed questionnaire and
market survey.
Financial Considerations : Financial considerations help the project to
evaluate the different measures of commercial profitability and the
magnitude of financing9 required . It requires the current status of the
market with respect to the project.
Managerial Competence : A proper assessment of the number and skills of
staff required for the project is to be considered under this aspect. For this
purpose an appropriate organization structure is decided, then the skills and
talents required by man power is determined.
Managerial competence consideration :
Activity analysis involving anticipated work flow and the activities involved in
the project.
Groupingof activities into tasks which employees can perform effectively.
Classification of tasks are the building blocks of the organization
structure.
Determining inter-relationships between different positions
to decide the chain of command
18
1. Quality parameters from the items suggested to
become created.
2. Product specifications.
3. Quantity to become created in every variety.
4. Suggested technology.
5. Highlights around the suggested technology.
6. Procedure for manufacture.
7. Production line balancing.
8. Listings of machines.
9. Supplier selections. 19
21
22
1. Profit on sales.
2. Profit on investment with various investment
options.
3. Break even point.
4. DET service coverage ratio.
5. Sensitivity analysis.
6. Internal rate of return.
23
Project Cost
The project cost is a cost required to procure all the needed products, services and
resources to deliver the project successfully.
Example: In an example of a construction project, the cost estimation starts from
land acquisition cost, construction cost, materials cost, administration cost, labor
cost and other direct and indirect costs.
No project starts without a budget. Project success is decided by how well the
project cost has been handled in the project. Many times it happens that, the
project may not be completed within the project cost. It means that when
compared the Project Cost Vs Project Profit, Project Cost might have exceeded
and it is of course considered as a project failure.
Hence it’s very important to come up with the correct cost estimation needed for
the project.
To come up with accurate cost estimation, it’s requiring to understand the types
of project costs involved in the project.
Types of Project Costs
Fixed Cost
Variable Cost
Direct Cost
Indirect Cost
Sunk Cost
Fixed Cost
Sunk Costs are costs which are already spent, but failed to
incur any business value and cannot be recovered and
permanently lost.
You have bought few vegetables and kept it in the
fridge. However, you forgot to use one of them and you
found it only when cleaning the fridge. By the time you see
it, it has got totally spoiled and hence you threw it away. The
cost of the vegetable is called a sunk cost. This cost did not
solve any purpose and also cannot be recovered and
permanently lost.
Total Project Cost