METHOD STATEMENT OF

DYWIDAG FORM TRAVELLER


CURRENT DYWIDAG FORMTRAVERLLER

Strong and light weight


structure
Onlyy 8.2m p
piertable length
g is
required
Standard max. 5m segments
Standard 2A-frame with 240
ton capacity
Increase capacity up to 300
ton with strengthening and
stiffening
Kapasitas Form Traveller

Kapasitas Form Traveller ??


Input Beban + Dimensi FT

SAP 2000

Output = Beban / Kapasitas FT


output SAP 2000
Tabel Output SAP 2000

RESUME PERHITUNGAN :

FORM TRAVELLER AMAN


JIKA PERBANDINGAN
BEBAN DAN KAPASITAS
FORM TRAVELER < 1
Superstructure Construction – Step 1: Pier Construction
Superstructure Construction – Step 2: Piertable Construction
Superstructure Construction – Step 3: Formtraveller Assembly
Superstructure Construction – Step 4: Segment Construction
Superstructure Construction – Step 5: Sidespan Construction
Superstructure Construction – Step 6: Sidespan Closure
Superstructure Construction – Step 7: Center Closure
Piertable Construction

Install support beam( P1 & P2)

I t ll
Install scaffolding
ff ldi
Remove  innerweb and end 
formwork
Install bottom & outer formwork
Install scaffolding from bottom 
slab
Install 1st stage rebar, embeds
g
Install inner web and top slab 
Install  innerweb and end  formwork 2nd stage
formwork
Install top slab rebar, PT duct, 
embeds
Pour concrete  1st stage
g

Pour concrete final stage
Curing

Install remaining web rebar Curing

Install  innerweb and end 
Install tendon
formwork

Pour concrete  2nd stage Prestressing 

Curing Grouting
DYWIDAG-SYSTEMS INTERNATIONAL

Piertable Construction ((Bracket


Bracket System)
System
y )

a company of
DYWIDAG
Piertable Construction ((S
Shoring
g System)
System
y )
Preassembly
y of Formtraveller - Ground

Preassembly of Main Frames

Preassembly of Front
and Rear Trusses
Preassembly
easse b y o
of Formtraveller
o t a e e - Ground
G ou d

Preassembly of Bottom Form


Installation of Formtraveller - Piertable

Installation of Rail
Installation of Formtraveller - Piertable

Installation of Main Frames and Trusses


Installation of Formtraveller - Piertable

Hydraulic
Pump

Anchor of Main Frames Arrangement


y
of Hydraulic Pumps
p
Installation of Formtraveller - Piertable

Installation of formwork system


Installation of Formtravel
Formtravelller - Piertable

Finish installation Form Traveler


Operation of Form Traveller

Operation of Form Traveller


Rail moving

Release rail anchorage


Operation of Form Traveller

Operation of Formtraveller Rail moving

Advance rails to next segment


Operation of Form Traveller

Install and tension rail anchorage (front & rear)


Operation of Form Traveller

Loosen the rear bar of


longitudinal beam, let it sit on
the rollerbracket

Loosen the rear bar of bottom


form, use chain block to lower
bottom formwork
botto o o
Operation of Form Traveller

Release rear anchorage, advance the form traveller


Operation of Form Traveller

Tension rear anchorage, raise up the formtraveller,


install formwork anchor
Survey of Form Traveller

8.600

1% 1%
1

0.200
2 2
0.200
0

0
3 5 5 3
4 4

Section : 35
Y= 5.500

0.200

0.400
6 6

0.500 3.500 0.500


4.500

Point Pre-camber Value Design Elev. Formwork Elev.


1 0.0041 226.995 226.999
2 226.952 226.956
3 226 752
226.752 226 756
226.756
4 226.573 226.577
5 226.787 226.791
6 221.495 221.499
7 NA NA

Elevation check by surveyor based on


Pre-chamber calculation
CONCRETE BY HOSE CONNECTION
CONCRETE PIPE RUNNING ON DECK
CONSTRUCTION CYCLE TIME
OF DYWIDAG FORM TRAVELER
Cycle time of Balance Cantilever

Form traveler in concreting 
position

Fixing of formwork
Fixing of  formwork

Installation of rebar, inserts and 
PT ducts

S
Survey Ch
Checkk
Installation of end  formwork, 
anchor block

Repeat
p this cycle
y from
f Pouring of concrete 
segment 1 to segment-15
of P1 and P2 both sides
Curing

Installation of  tendon

Prestessing

Advance  Form Traveler to the 
next segment

Survey
Construction Schedule – Day 1 AM

Advance Rails

Fix Rails
Advance Roller Brackets
Construction Schedule – Day 1 PM

Advance Formtraveller
Release
anchors

Release
F
Formworkk
Construction Schedule – Day 2

Install Bottom Rebar


Install Web Rebar

Install Bottom Duct


Install Web Duct
Construction Schedule – Day 3 AM

Install Bottom Rebar


Install Web Rebar

Install Bottom Duct


Install Web Duct

Install Bottom Bulkhead Form


Install Web Bulkhead Form
Construction Schedule – Day 3 PM

Install Top Slab Rebar


Construction Schedule – Day 4

Install Top Slab Rebar

I
Install
ll Top
T Slab
Sl b Duct
D

Install Top
p Slab Bulkhead
Form
Construction Schedule – Day 5

P
Pouring
i Concrete
C
Construction Schedule – Day 6

C
Concrete C
Curing
i
Construction Schedule – Day 7

Install Strand
Install Wedge
Install Wedge Plate

Stress Tendon