PROJECT DAILY REPORT

PDR: 16MLD-HTT-STP-IG-IP-CON-000133 Date: November 25, 2021


Project Title: Design and Build of 16MLD Hinulugang Taktak Sewage Treatment Plant (STP)
Client: Manila Water Company Inc.
Project Consultant: ARUP/GHD
Contractor: FREY-FIL AND TOSHIBA WATER SOLUTIONS (IN CONSORTIUM)

Scope: Engineering, Procurement, Installation, Commissioning, Process proving to Defects


Liability
Location: Taktak Road, Brgy. Sta. Cruz, Antipolo City
Project Start: July 16, 2021
Project Finish: July 15, 2024 12 MN
Project Duration (Design, Construction to Trial ops. only): 760 Days F - Fair
C - Cloudy
Earned Days: 133 Days
Percent Time Elapsed 17.50% 6 PM
R- Red Rainfall Warning
6 AM
O- Orange Rainfall Warning
Y- Yellow Rainfall Warning
Description Cumm. Days Duration Key Dates S- Stormy
12 NN
Letter of Acceptance 0 May 21, 2021 R - Rainy
Effective Date 56 56 July 16, 2021
Design Completion 236 180 January 12, 2022
Construction Days (inc. 30 Days Trial Ops.) 786 550 July 16, 2023
Process Proving Period 1151 365 July 15, 2024
Defects Liability Period 1516 365 July 15, 2025

SAFETY/ ACCIDENT REPORT


Description No. Remarks
N/A

MANPOWER
ADMINISTRATION DAY NIGHT CIVIL WORKS DAY NIGHT ELECTRICAL MECHANICAL WORKS DAY NIGHT
Project Manager 1 Survey Engineer 0
Consortium Project Manager 1 Instrument man 0
Deputy Project Manager 1 Survey Aide 0
Rebar & Formworks MNGR II 1 Foreman 0
Contract & Administrator 1 Carpenter 3
QC Manager 1 Leadman 2
Electrical Engineer 1 Mason 8
Mechanical Engineer 0 Steelman 3
Planning Engineer 1 Scaffolder 1
Project Coordinator 1 Painter 4
Material Engineer II 0 Electrician 1
Cost Engineer 1 Welder 8
Field Engineer III 1
Site Engineer 1
QA/QC 1
Field Engineer I/DCC 1
IT Specialist 0
HR Assistant 1
Timekeeper 1
Safety officer 1
Pollution control officer 1
Warehouseman 1
Project Accountant 0
Disbursing Officer 0
CAD Operator 0
Lab. Technician 0
Service Vehicle Driver 1
Utility 0
Security Guard 1 1
TWS
Project Manager 1
Project Coordinator 1
Project Engineer 1
Design Manager 1
Design Coordinator 1
Process Engineer 1
License Engineer Electrical 1
License Engineer Instrument 1
License Engineer Mechanical 1
Mechanical Engineer 1
Electrical Engineer 1
Instrument Engineer 1
CAD Operator(Draftsman) 3
Cost Engineer 1
Project Accountant 1

FFC Design
Design Head 1
Project Coordinator / QAQC 1
Structural Lead 1
Structural Engineers 5
Architectural Lead 1
Architects 2
Cad 4
Mechanical Engineer 1

TOTAL MANPOWER (DAY) 84 TOTAL MANPOWER (NIGHT) 1


TOTAL MAN-HOUR (HR) 672 TOTAL MAN-HOUR 8
EQUIPMENT
Description Operational Idle Under Repair REMARKS
Major Equipment
PLATE COMPACTOR 1 0 0
ONE BAGGER MIXER 1 0 0
VIBRATOR ENGINE 1 0 0
WELDING MACHINE 1 1 0
GENSET 1 0 0
TOTAL STATION 0 0 0
SUBMERSIBLE PUMP 0 1 0
CONCRETE CUTTER 0 1 0
BACKOE 0 1
TOTAL: 5 4 0

Minor Equipment
BARETA TOOLS 2 0 0
SHOVEL 5 0 0
COMBI HAMMER SDS PLUS 0 3 0

COMBI HAMMER SDS MAX 0 1 0

CHIPPING GUN 3 0 0

CIRCULAR SAW 8' 1 1 0

HAND DRILL 1 4 0

CUTOFF MACHINE 1 0 0

BABY GRINDER 4'' 0 5 0

ANGLE GRINDER 7'' 0 1 0

VIBRATOR HOSE 2' 0 1 0


CUTTING OUTFIT 0 2 0

TOTAL: 13 18 0

TOTAL: 18 22 0
PROCUREMENT QTY. REMARKS

ACTIVITIES FOR TODAY START DATE TARGET ACCOMPLISH DATE


Ongoing compliance to the application of temporary power connection - electrical permits has been secured, for installation of
cable and wiring then for schedule of MERALCO's Inspection. 04-Oct-21 01-Dec-21
Ongoing Compliance to temporary water supply - application of excavation permits to OBO antipolo
04-Oct-21 01-Dec-21
Ongoing Preparation and Submission of Detailed Design
06-Aug-21 20-Aug-22
CHB laying for Septic tank 02-Dec-21
25-Nov-21
Demolition on the existing partially demolished building 23-Nov-21 01-Dec-21
Fabrication of steel stand support for barricade inteded for the demolition 25-Nov-21 26-Nov-21
Leveling and compacting along the office tempacil 25-Nov-21 01-Dec-21
Ongoing Preparation and Submission of
- Retaining Wall 06-Aug-21 26-Nov-21
on-going revision of drawings of temfacil 06-Aug-21 26-Nov-21
on-going of detailed drawings for structural MBBR 06-Aug-21 02-Dec-21

PLANNED ACTIVITIES FOR TOMORROW START DATE TARGET ACCOMPLISH DATE


compliance to the application of temporary power connection - for installation of cable and wiring 04-Oct-21 01-Dec-21
Compliance to temporary water supply - application of excavation permits to OBO antipolo 04-Oct-21 01-Dec-21
Ongoing Preparation and Submission of Detailed Design 06-Aug-21 20-Aug-22
Ongoing Compliance and Submission of some Outline Design 06-Aug-21 15-Dec-21
CHB laying on Septic tank 02-Dec-21
25-Nov-21
Demolition on the existing partially demolished building 23-Nov-21 01-Dec-21
Fabrication of steel stand for barricade inteded for the demolition 25-Nov-21 26-Nov-21
Leveling and compacting along the office tempacil 25-Nov-21 01-Dec-21
TARGET
MILESTONE SUMMARY COMPLETION REMARKS
DATE

Issues / Problems Encountered Special Visitors


Difficulty of delivery especially for heavy equipment on day time due to ongoing
Pipe laying HDPE-500mm dia. By Anden Construction Co.Inc.

Action Taken/ Recommendations


Closely coordination on the delivery and on the Anden construction so we can pass
the road at the night time
Lessons Learned/ Best Practice Other Remarks

Submitted by: Raul A Patubo Checked & Noted by: ARUP/GHD


Prepared by:

FFC Planner
Project Site

Demolition of existing partially demolished building

Project Site

Leveling and compacting along the office tempacil