ASCOT PERMATA HIJAU

BILL OF QUANTITY MECHANICAL & ELECTRICAL


Tangerang,23 AGUSTUS 2021
Revise # 0

NO DESKRIPSI SPESIFIKASI VOL UNIT

I PRELIMINARY
1 Temporary power & lampu kerja 1 - lot
2 Safety tools 1 - lot
3 Mobilisasi & demobilisasi 1 - lot
4 Design ME 1 - lot
5 Shop drawing & asbuilt drawing 1 - lot

II ELEKTRIKAL
1 Suppply & install TL 2x18W Philips 8 bh
2 Supply & Install switching LED 20A 12V hiled 1 - bh
3 Supply & Install lampu emergency ecocity 2 - bh

4 Supply & install kabel titik lampu kabel metal/supreme + Ega/Clipsal 9 - ttk

5 Supply & install kabel titik lampu EL & NL kabel metal/supreme + Ega/Clipsal 3 - ttk
6 Supply & Install stop kontak kitchen Schneider 15 - bh
7 Supply & Install isolator switch 1P 25A Schneider 1 - bh
8 Supply & Install isolator switch 3P 40A Schneider 1 - bh

9 Supply & install kabel stop kontak general - NYM 3 x 2.5 mm2 + conduit
kabel metal/supreme + Ega/Clipsal 15 - ttk

10 Supply & install kabel stop kontak 3P - NYY 4 x 4 mm2 kabel metal/supreme + Ega/Clipsal 1 - ttk

11 Supply & Install saklar Schneider 4 - bh

12 Supply & install kabel saklar kabel metal/supreme + Ega/Clipsal 4 - ttk

13 Supply & install Kabel Feeder NYY 4x 16 mm2 + NYA 1x10 kabel metal/supreme - - m
14 Supply & Install DB Panel Schneider 1 - unit
15 Supply & install timer & contactor 1 - ttk
16 Supply & install kabel tray 200x100mm lokal 8 - m
17 Material bantu & fitting support 1 - lot
18 Megger instalasi & test commisioning 1 - lot

III ELEKTRONIK

1 Supply & install kabel titik data + terminasi - termasuk spare belden cat6 + Ega/Clipsal 5 - ttk
2 Supply & install kabel titik data wifi + terminasi belden cat6 + Ega/Clipsal - - ttk

3 Supply & install kabel telepon supreme/kabel metal + EGA/Clipsal 1 - ttk

4 Supply & Install outlet telepon Schneider 1 - bh


5 Material bantu 1 - lot
6 Alat ukur listrik (meteran)

A AIR BERSIH & AIR PANAS

1 Supply & install pipa air bersih dia. 1' Rifeng/PPR wavin/toro 24 - m
2 Supply & install pipa air bersih dia. 1/2' Rifeng/PPR wavin/toro 44 - m
3 Fitting accessories Rifeng/PPR wavin/toro 1 - ls
4 Supply & install ball valve dia 1' Onda 1 - bh
5 Supply & install ball valve dia 1/2' Onda 8 - bh
6 Testing commisioning 1 - lot
7 Taping Riser Air Bersih 1 - lot
8 Water heater 1 unit

B AIR BEKAS

1 Supply & install pipa PVC dia 6" AW Rucika 20 - m


2 Supply & install pipa PVC dia 3" AW Rucika 12 - m
3 Supply & install pipa PVC dia 2" AW Rucika 20 - m
4 Fitting accessories AW Rucika 1 - lot
5 Floor drain ( FD ) dia 2" antasan 2 - pcs
6 Clean out dia 2" antasan 2 - pcs
7 Coring lantai dia 4" 2 - pts
Interkoneksi pipa air bekas ke gutter + tes gelontor + kebocoran
8 2 - set
gutter

BILL OF QUANTITY LANTAI & TEMBOK


Tangerang,23 AGUSTUS 2021
Revise # 0

No Description Specification Unit Qty


A PEKERJAAN PERSIAPAN
1 Mob / Demobilisasi ls 1,00
2 Listrik & Air kerja ls 1,00
3 Unloading fee ls 1,00
4 Security ls 1,00
5 Safeti & Cleaning ls 1,00
6 Fit Out ls 1,00
7 Asuransi ls 1,00
8 As built drawing ls 1,00
9 Alat Bantu ls 1,00
10 Kontrakan Pekerja ls 1,00

B Pekerjaan kitchen area


B.1 Pekerjaan lantai
1 Screeding pasir & semen ; t=40mm m2 22,77
2 Water profing layar pertama Membrane t=4mm ; Lantai & Dinding h=1000mm m2 45,67
3 Screeding pasir & semen ; t=40mm m2 22,77
4 Water profing layar kedua Membrane t=4mm ; Lantai & Dinding h=1000mm m2 45,67
5 Screeding pasir & semen ; t=40mm m2 22,77
6 Raise Floor t : 20cm Bata ringan ; Ex Hebel m2 22,77
7 Floor finish Kramik 30x30cm grey Rock Tile Ex Roman m2 22,77

C Pekerjaan Dinding
1 Pasang Dinding Hebel Bekas jendela kaca Bata Ringan ;Ex Hebel m2 6,20
2 Plester + Aci h;172cm Pasair & Semen + Mu m2 39,90
3 Wall Finish h;200cm Kramik putih 30x30cm ;Ex Asia Tile m2 44,80
4 Cat minyak h;172cm Emulsion Paint Ex . Mowilex Interior m2 39,90

D Pekerjaan Ceilling
1 Perapihan Duck Beton ls 1,00
2 Cat Ceilling m2 22,77

GAS INSTALATION
1 Pipa SCH40 seamless 1 1/4" (by owner) 2
2 Pipa SCH40 seamless 1/2" (by owner) 1
3 Pressure gauge 0 - 10 bar 2

5 Regulator Medium 1
6 Regulator Low 2
7 Pig tail 12 Kg 2
8 Ball valve 1" 4
9 Ball valve 1/2" 3
10 Support, cat, klem, dan alat bantu lain 1
Intalasi gas alarm
1 panel alarm 2 zone 1
2 Detektor gas 2
3 Selenoid Valve 1" 1
4 Wiring alarm 1
INSTALASI EXHAUST
EXHAUST BLOWER AFD BY OWNER 1
1
2 Ducting BJLS 0.6 + Corner 400 x 200 x 1200 8
3 Elbow BJLS 0.6 + Corner 400 x 200 x 60° 6
4 Transisi Ducting Blower Ø20 2
5 Material Bantu : 1
Flank Blower
Kanvas
Kabel Power 3 x 2.5mm
Aluminium Foil Peredam
Push Button 3 phase
Sealant, Ropping, Long Dratt, Besi Siku

INSTALASI FRESH AIR


Ducting BJLS 0.6 + Corner 300 x 300 x 1200 6
Elbow BJLS 0.6 + Corner 300 x 300x 60° 6
Difusser Grill 300 x 300 4
Material Bantu : 1
Aluminium Foil Peredam
Sealant, Ropping, Long Dratt, Besi Siku