Project : PROPOSED TWO STOREY RESIDENCE

Location : LOT 16 BLK 7, VERDE GRANDE III LEONARDS PLACE, BRGY. SAN ROQUE, CAINTA, RIZAL
Owner : SPS. MARVIN R. ESTEBAN AND VENUS B. ESTEBAN
UNI
ITEM DESCRIPTION QTY T Unit Cost AMOUNT
A. PRELIMINARIES
1.0 Mobilization/Demobilization 1.00 lot 10,000.00 10,000.00
2.0 Temporary Facilities 1.00 lot 20,000.00 20,000.00
4.0 Safety Requirements 1.00 lot 5,000.00 5,000.00
5.0 Permits 1.00 lot 2,000.00 2,000.00
mon
6.0 Electric and Water Consumption 8.00 ths 2,000.00 16,000.00

7.0 Temporary Fence 1.00 lot 3,000.00 3,000.00


SUB-TOTAL 56,000.00
B. CONSTRUCTION
I. SITE WORKS -
1.0 Layouting 100.00 m² 50.00 5,000.00
II. EARTHWORKS -
ln.m
1.0 Concrete Cutting - . 120.00 -
2.0 Concrete Breaking - m² 350.00 -
3.0 Excavation 42.50 m³ 500.00 21,250.00
4.0 Backfill and Compaction 38.25 m³ 200.00 7,650.00
5.0 Gravel Bedding 4.25 m³ 1,200.00 5,100.00
III. REINFORCED CONCRETE WORKS -
1.0 Concrete 44.36 m³ 4,500.00 199,620.00
2.0 Rebars 5,032.82 kgs 47.00 236,542.54
3.0 Formworks 154.62 m² 510.00 78,856.20
4.0 Metal Decking 289.54 m² 1,100.00 318,494.00
5.0 Scaffoldings (slab shoring) 289.54 m² 100.00 28,954.00
IV. TINSMITHRY
1.0 Roofing ga. 24 Rib type prepainted 75.00 m² 585.00 43,875.00
2.0 Gutter 42.00 ln.m 500.00 21,000.00
3.0 Flashing 25.60 ln.m 650.00 16,640.00
4.0 Rigde Roll 44.00 ln.m 450.00 19,800.00
5.0 End Flashing 15.89 ln.m 400.00 6,355.86
6.0 Valley Gutter 5.30 ln.m 550.00 2,915.00
V. CEILING WORKS
1.0 Gypsum Boards on Metal Framing 140.00 m² 750.00 105,000.00
VI WATERPROOFING -
1.0 Comfort Rooms 9.00 m² 650.00 5,850.00
VII FINISHES -
1.0 Ceramic Tiles 30 x 30 (OSM) 6.81 m² 465.00 3,166.65
2.0 Homogeneous Tiles 60 x 60 (OSM) 102.84 m² 560.00 57,590.40
3.0 Plain Cement Toppings 2" 74.00 m² 290.00 21,460.00
4.0 Countertop Finish, Ceramic tiles (OSM) 2.00 m² 465.00 930.00
VIII FENESTRATIONS -
1.0 Doors -
D-1 Swing Panel door 100 x 214(OSM) 2.00 sets 4,000.00 8,000.00
D-2 Swing Panel door 86x 214 (OSM) 1.00 sets 3,500.00 3,500.00
D-3 Swing Panel door 80x 210(OSM) 3.00 sets 2,500.00 7,500.00
D-4 Swing Panel door 60X210 (OSM) 3.00 sets 2,500.00 7,500.00
2.0 Windows -
W1 120X180 1.00 sets 9,000.00 9,000.00
W2 120X120 4.00 sets 7,000.00 28,000.00
W3 120X60 1.00 sets 5,000.00 5,000.00
W3 60X60 2.00 sets 4,500.00 9,000.00
IX PAINTING WORKS -
1.0 Walls -
Exterior Walls 373.80 m² 289.00 108,028.20
Interior Walls 389.10 m² 250.00 97,275.00
2.0 Ceiling 140.00 m² 245.00 34,300.00
3.0 Columns 10.00 m² 245.00 2,450.00
4.0 Doors
Single Door 9.00 sets 2,400.00 21,600.00
X HANDRAILS
ln.m
1.0 Stair Handrail GI Pipe 1Ø 6 . 450.00 2,700.00
XI PLUMBING WORKS
1.0 Fixtures
1.1 Water Closets (OSM) 6.00 units 3,500.00 21,000.00
1.2 Countertop Lavatory (OSM) 7.00 sets 1,500.00 10,500.00
1.3 Faucets for Lavatory (OSM) 7.00 sets 500.00 3,500.00
Roughing Ins
2.0 Water Lines 1.00 lot 15,000.00 15,000.00
2.1 Sewer Lines 1.00 lot 20,000.00 20,000.00
2.2 Drainage Line 1.00 lot 15,000.00 15,000.00
3.0 Septic Tank 1.00 12,000.00 12,000.00
4.0 Catch Basin 8.00 unit 2,000.00 16,000.00
ELECTRICAL WORKS
XII Light Outlets (OSM) 55.00 sets 200.00 11,000.00
1.0 Duplex Outlet (OSM) 31.00 sets 100.00 3,100.00
4.0 Light Switch (OSM) 28.00 sets 100.00 2,800.00
5.0 Junction Box 65.00 pcs 60.00 3,900.00
6.0 Utility Box 20.00 pcs 60.00 1,200.00
7.0 Square Box 8.00 pcs 80.00 640.00
8.0 15mm Dia IMC Pipe 116.40 L 520.00 60,528.00
9.0 20mm Dia IMC Pipe 3.90 L 710.00 2,769.00
10.0 25mm Dia IMC Pipe 5.20 L 954.00 4,960.80
11.0 100mm IMC Pipe 2.00 L 6,200.00 12,400.00
12.0 3.5 mm2 THHN P.D. 1,646.00 mtrs 28.00 46,088.00
13.0 5.50 mm2 THHN P.D. 11.20 mtrs 40.00 448.00
14.0 8.0 mm2 THHN P.D. 7.70 mtrs 64.00 492.80
15.0 14 mm2 THHN P.D. 49.00 mtrs 102.00 4,998.00
16.0 50 mm2 THHN P.D. 6.00 mtrs 380.00 2,280.00
17.0 200 mm2 THHN P.D. 110.00 mtrs 1,370.00 150,700.00
18.0 Panel "MPB3" 1.00 set 58,360.00 58,360.00
19.0 Panel "PB5" 1.00 set 76,760.00 76,760.00
20.0 Panel "PB6" 1.00 set 76,760.00 76,760.00
21.0 300amp, 3P CB, Nema 3R 1.00 set 28,400.00 28,400.00
22.0 Pipe/Fittings/Connectors 1.00 lot 35,038.00 35,038.00
23.0 Miscellaneous Hardware 1.00 lot 6,982.00 6,982.00
24.0 Const/As Built Plan 1.00 lot 2,500.00 2,500.00
25.0 Mob/Demob (Electrical) 1.00 lot 5,000.00 5,000.00
26.0
2,261,007.4
SUB-TOTAL
5

Project : PROPOSED TWO STOREY RESIDENCE


Location : LOT 16 BLK 7, VERDE GRANDE III LEONARDS PLACE, BRGY. SAN ROQUE, CAINTA, RIZAL
Owner : SPS. MARVIN R. ESTEBAN AND VENUS B. ESTEBAN

TECHNICAL SPECIFICATIONS

I. GENERAL CONDITION

1.) The Drawing and Specifications are complimentary and supplementary to each
other. Anything mentioned in the specifications but not shown in the drawings or
vice-versa shall be of effect as if mentioned in both.

2.) All drawings are done according to scale. Numerical values are indicated in drawings.
But if there are indicated numerical values drawings shall be measured by the scale,
But if there is a discrepancy, the numerical value indicated are to be followed
instead of the scale.

3.) All works mentioned herein shall be final. Any revisions to be done shall be settled
between the owner and the Engineer in charge of the construction.

II. EARTH WORKS

1.) All trenches shall be brought true to line and grade as mentioned in the drawings.
Bottom shall be solid and undisturbed compaction.

2.) Before the laying of earth fill, all footings and ground beams are firmly established
as indicated in the drawings.

3.) In case of loose soil that the Engineer found to be unsuitable to hold the
foundations, all areas affected shall be subjected to further excavations and shall be
replaced by suitable earth, well compacted until the desired consistency is reached.

III. CONCRETE WORKS

1.) All concrete shall be done in accordance with the required strength as mentioned:

A. Concrete Mixed
Concrete Pedestal and Footing 4000 psi
Footing 4000 psi
Slab on fill 4000 psi
Others 4000 psi

B. Materials
Cement shall be Portland type.
Coarse aggregates shall be crushed ¾”
Fine aggregates shall be washed-quality, free from impurities.

2.) Before the pouring of all foundations, all trenches shall be thoroughly compacted,
filled with four inches thick of aggregates and free from impurities.

3.) Concrete shall be kept moist for a minimum of seven (7) consecutive days
immediately after pouring by the use of wet burlap, fog spraying, or other approved
methods.

IV. REINFORCING BARS

1.) All rebars shall be of quality, structural grade.

2.) Before any concrete is poured, all rebars shall be cleaned free from mills, rusts,
scales, and other imperfection that may lose bond.

3.) All rebars shall be connected to each other by G.I. Tie Wire gauge 16 done properly
and twisted.

4.) Structural Grade of Rebars


10 mm. Dia. Grade 40
12 mm. Dia. Grade 40
16 mm. Dia. Grade 60
20 mm. Dia. Grade 60
25 mm. Dia. Grade 60

5.) Splices shall be securely wired together and shall lap or extend in accordance with
the minimum splice and anchorage length requirements.

V. STRUCTURAL STEEL

1.) Materials

A. I-Beams
Steel to be used for fabrication and erection of the structure shall comply with
all the pertinent provisions of AISC Specifications for its design.

B. Bolts
All bolts, nuts and washers shall conform to A325 or A307 unless otherwise
indicated.

C. Welds
All welds shall be in accordance with AWS Structural Weld Code, for shielded
metal arc welding process. Electrodes shall conform to AWS AS-1.

2.) Fabrications
A. All welded connections shall develop the full strength of the members
connected. The minimum length of fillet weld shall not be less than 4 times this
nominal size, where intermittent welds may be used. The length of segment
shall not be less than 4 times the weld size with minimum of 40mm.
B. Side of end fillet welds terminating at ends or sides shall be returned
continuously for a distance not less than twice the nominal size of the weld.

C. The maximum edge distance from bolt center shall be 12 times the thickness of
the plate but not to exceed 50mm.

D. The frame of steel structure skeleton shall be carried up true and plumb within
the limits, thus, temporary bracing shall be provided to resist all loads, as
defined in AISC Code of Standard Practice.

E. No permanent bolting, welding, or riveting shall be done until structure has


been properly aligned.

F. All Structural Steel shall conform to ASTM-36, Fy = 414 Mpa.

VI. EXTERIOR FINISH

1.) All exterior surfaces shall be of plain cement finished, trowel-smoothed and ready
to accept coats of paint.

2.) The general finishing material for all exterior masonry surfaces shall be Acrylic Latex
Paint either by Boysen or any approved equivalent brands.

VII. ELECTRICAL WORKS

1. All electrical wires shall be of standard type (PHELP DODGE or equivalent).


2. All electrical conduits shall be flexible type (MOLDIFLEX or equivalent).
3. Switches, convenience outlets including plates shall be NATIONAL or equivalent.
4. Circuit Brakes shall be GENERAL ELECTRIC or equivalent.

VIII. PAINTS & VARNISHES

1.) Unless specified all brand of paint shall be Boysen or Davies.

2.) All exposed wood work shall be applied first with wood stain.

1.) Sanding is an essential part of painting works. Therefore, all cracks joints and nails
shall be glued and concealed first with wood filler.

2.) Paints shall be applied in three coats.


*Masonry Surfaces Acrylic paint semi-gloss
*Wood & Metal Surfaces Quick Drying Enamel & Varnish
*Ceiling Flat Wall Enamel
DESIGN
IX. OF C2
FLOOR FINISHES B. Determine the required footing area
All tiles shall be
homogeneous for
office and toilets D. Materials
rooms. Other areas All materials to be used
such as electrical shall conform with the
rooms, genset standard below:
rooms and 1. Sanitary Pipes and
mechanical rooms Fittings
shall epoxy paint PVC Pipes - Emerald
finish. or approved equal
2. Hot and Cold Water
X. TOILET FIXTURES System
Water Closet and Urinals by
HCG or approved equal.

XI. PLUMBING WORKS


A. Excavation
Trenches for all
underground pipe lines
shall be excavated to
the required depths
and grades.

B. Pipe Laying
Pipe in
trenches shall be laid
true to line and grade
on a stable or suitably
prepared foundation,
each section of the
pipe being bedded and
bottom of the
trench shaped to fit the
lowest quadrant of the pipe
circumference.
Pipes shall not
pass through columns,
footings, beam, except
noted on the drawings.

C. Backfilling
After pipe lines
have been tested, inspected
and approved by the
Architect and prior to
backfilling, all forms and
bracing shall be removed
and the excavation shall be
cleaned from trash and
debris.