SHAURYA CEMENT INDUSTRIES PRIVATE LIMITED

DAILY REPORT: 18.02.2021

Man Power Statement for project


Description 13.02.2021 14.02.2021 15.02.2021 16.02.2021 17.02.2021 18.02.2021
Civil-plant building 250 229 250 250 235 238
Mechanical 240 225 225 225 225 225
Electrical 35 35 35 35 20 20
Ayoki staff 23 23 23 23 23 23
TOTAL 548 512 533 533 503 506
Shree Krishna 337 340 338 338 300 289
Engineering
Rajpooth 90 90 90 90 90 90
Grand total 975 942 961 961 893 885
Refractory Man power : 00
Insulation man power : 28 Shree Krishna man power details:
Mechanical: 195
Electrical : 40
Civil : 48
Staff : 06

Man Power Statement for Pyro Operation


Description 13.02.2021 14.02.2021 15.02.2021 16.02.2021 17.02.2021 18.02.2021
Civil 40 40
Mechanical 65 65
Electrical 14 14
Process & lab 16 16
TOTAL 136 136
Daily Progress Report as on 18.02.2021 Daily progress report Mechanical :

1. TT-3 & TT-4 :- Block massonery work under Fabrication


progress
2. Preheater :- Preparation for lift wall in progress * Pneumatic discharge to air slide chutes fabrication under
3. Drain: - Excavation work under progress. Also progress
rebar work under progress. * Control bin to air slides chutes fabrication under progress
4. Cooler House: - Grade slab work under * Packing plant venting lines fabrication under progress
progress. * Gratings fabrication under progress
5. Cooling Tower: - Wall rebar and shuttering * Cement silo feed chutes fabrication under progress
work under progress. * Packing plant chutes fabrication under progress
6. Clinker Silo: - Reject bin foundation work under
progress.
7. Cement Mill Feed: Soil filling work under Erection :
progress in this area.
8. Canteen Building: - Column rebar and * Blowers for silo aeration and bin aeration erection under
shuttering with RCC work under progress. progress
9. Store and workshop Building: - Excavation and * Blowers discharge to silo aeration and bin aeration piping under
backfilling work under progress. Also footings and progress
column rebar and shuttering work under * Compressed air lines to pneumatic flow control gate connection
progress. inside silo under progress
10. Plant housekeeping work under progress, * Cement mill building chutes erection under progress
Exuviation work in progress for weight bridge. * Belt conveyor 531.BC 010 skirt board erection under progress
11. ADM Building: - Internal finishing work and * Cement silo feed bucket elevator bearing skewness checking &
block massonery work under progress. grease filling completion
13. Staff quarter: - Ground floor finishing work * Cement silo-2 to packing plant bucket elevator air slides
under progress in C1, C2. assembly and erection preparation under progress
* Packing plant truss sheet work under progress
* Clinker silo penthouse sheet work under progress
* Cement mill building handrails painting and finishing under
progress
* Packing plant bucket elevator platforms erection under
progress
* Coal mill structure cladding runner erection under progress
* Packing plant venting lines erection under progress
* Packing plant compressed air line erection under progress
* Packing plant staircase erection under progress
* Belt conveyor 531.BC 200 skirt seal fixing under progress
* Cement silo-1 open air slides erection under progress
*Packing plant air slides platform erection under progress
*Packing plant truss erection under progress
* Cement silo top air slide support structure erection under
progress
* Cement mill building platform gratings fixing and handrails
fixing under progress
* Low alkali silo top bag filter venting lines erection completed.
* Packing plant building staircase handrails erection under
progress
* Cement mill building outside air line water line erection under
progress
* Cement silo-2 bin extraction system erection under progress
* Cement mill hot air duct pending jobs completion under
progress
* Cement silo - 2 to packing plant air slide structure erection
under progress
* Cement silo feed bucket elevator structure staircase and drive
platform members received under progress
* Cement silo-1 extraction system erection under progress
* Cement mill bag house weather enclosure structure assembly
and preparation for erection
* Outside building airline erection under progress
Rain status: 0.0mm

SCIPL / Stores Report / 18 Feb' 2021

>>>Inward>>>

1. Lime Stone - 3893.69 MT / 144 Loads from SCL Galter Mines


2. Steam Coal - 249.14 MT / 5 Loads from Ripley Overseas
3. Pet Coke - 11.32 MT ( As per lab report ) bill not received
4. Hollow Blocks 5562 nos from Jagdamba Concreto
5. Clay 399.32 MT / 18 Loads from Kriti Construction
6. Safety Helmet from Ganinath Machinery
7. Air FRL Pressure Guage 9 nos from Maruti Nandan

<<Outward <<

1. Limestone - Nil

LIME STONE REPORT


Opening Stock Inward Outward Closing Stock
730904.86 MT 3893.69 MT 0 MT 734798.55 MT
COAL REPORT
Opening Stock Inward Closing Stock
17348.65 MT 249.14 MT 17597.79 MT
Pet Coke
Opening Stock Inward Closing Stock
1361.38 MT 11.32 MT 1372.70 MT
Site photographs:

Cement silo -1 open air slides erection under progress

Cement silo-1 top closed air slide structure erection under progress
Blowers for silo and control bin aeration erection under progress

Cement mill baghouse weather enclosure structure erection under progress

Belt conveyors hood cover fitting uder progress


Cement mill diverter gate to reject bin chutes erection under progress

Photographs: Site:
Cooling tower shuttering work

Block massonery work underprogress

Block massonery work underprogress