Affidavit/ Undertaking: Condition Road - 2021 - 1
Affidavit/ Undertaking: Condition Road - 2021 - 1
____________________________________________________________________________________
under take that after the completion of work (Name of work to be executed)
at the site of work. In the event of failure to shift the labour by me/us. I/we, am/are
liable for penal action either in the shape of penalty equal to 10% of the total cost of
work or my/our enlistment with HSVP or any other department of Haryana shall be
liable to be concealed.
Place ……………
DEPONENT
Dated …………..
VERIFICATION:-
I, the above named deponent to hereby verify that the above statement is
true and correct to the best of my knowledge and belief and nothing has been
concealed therein.
Place ……………
DEPONENT
Dated …………..
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
EXECUTIVE ENGINEER,
HSVP DIVISION NO-II, HISAR
The work will be carried out as per MORT&H (Roads wing) specification for
Roads and Bridge works 2013 (5th revision).
For item of B.M work, contractor shall intimate to the Engineer-in-charge in
writing 20 days (twenty days) before the start of work, the job mix formula proposed to
be used by him for the work and will take up the work only after approval of job mix
formula.
The unit of measurement of Bituminous Macadam will be weight in metric
tonne of Bituminous mix laid consolidated and finished which shall be determined as
under:-
a) Volume of the mix laid at site will be calculated by multiplying the area
covered with average thickness actually laid at site. Average thickness will
be based on thickness measured at suitable intervals both along length and
across width of road.
The weight shall then be worked out by multiplying the volume of the
mix on particular stretch of the road with the average field density of the
very particular stretch and the weight thus worked out above shall be
considered. The average density for the stretch shall be determined by the
actual determination of field density by sand replacement method.
b) (i) The contractor shall provide install, maintain and operate at his own
cost in good working condition weigh bridge of suitable capacity at the
site of the hot mix plant under the direction of Engineer-in-charge or his
representative.
(ii) Each truck before loading of the mix shall weighed on the weigh bridge
and its weight shall be recorded under the signature of the authorized
representative of the contractor and Engineer-in-charge.
(iii) The work shall again be weighed on the weigh bridge after loading the
mix and its weight recorded under the signature of the site
representative as per prescribed performa as given at condition number
35 on page ………. weight of mix material will be determined from
difference of (iii) & (ii).
c) Lowest of weights calculated under para 3 (a) & 3 (b) above will be
considered and paid for.
d) The minimum density for bituminous macadam work shall not be less than
95% of that obtained by job mix formula and deviation of actual density in
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
1. Wherever in the description of the item in the bill of the quantities the
specification clause No of MORT&H is missing the same shall be carried out
strictly in accordance with the MORT&H (Road wing) specification (5 th
revision) of 2013.
2. The contractor shall clear the site of work simultaneously as the work
proceeds failing which the same shall be got cleared by the Engineer-in-
charge at the risk and cost of the contractor.
4. The contractor shall store all materials in proper manner so as the avoid
contamination, deterioration and any accidents. He shall not store or keep
any material tools and plants in public through fares except for such as per
required for immediate use on the work. The place at site, where materials
are to be stored shall be subject to the approval of the Engineer-in-charge.
At the places where the materials are stored by the contractor he will take
his own arrangements to clear the place within such time as may be
instructed by the Engineer-in-charge or the same be got clear by the
Engineer-in-charge at the risk and cost of the contractor.
5. No compensation for any damage caused the work /materials by rain flood
or other natural calamities shall be paid to the contractor. The contractor
shall make good all such damages at own his cost as per directions of the
Engineer-in-charge.
7. The contractor shall make his own arrangement for obtaining electrical
connection, if required and make necessary payment directly to the
department concerned.
8. The contractor shall not occupy by his operation more than ½ of the width
of any road or street. However, in special conditions, the contractor shall
obtain the consent of the Engineer-in-charge in writing before closing any
road for vehicular traffic and foot path shall be kept clear at all times. The
contractor shall make all the precaution to avoid any accidents and for
proper guidance of the traffic by providing necessary barriers, reflective
cautionary sign/ signal, speed limit board, red and green lags, electric light
focus type at night, which sufficient number of chowkidars and other
measures while work is in progress or blocking the road wherever otherwise
necessary. The material and the machinery shall be stocked/placed at the
site of work in such a way that there will be no obstruction to traffic and
inconvenience to public. No claim shall be entertained on account of such
10. The contractor shall make arrangement at his own cost for the least two
number of modern leveling instruments (wild type) for the purpose of
carrying leveling operation failing which the same shall be arranged by the
Engineer-in-charge at his risk and cost.
11. No work should be done in the absence of the contractor or his authorized
representatives. A technician and surveyor will be provided/ made available
for all working time by the contractor for carrying out quality control tests
and surveying. Nothing extra will be poid on this account.
13. The contractor will be responsible for setting out the work, establishing
benchmark, centre line etc will be carry out all such works at his own cost.
14. Before start of the work, the contractor shall submit the program of
execution of work, get it approved from the Engineer-in-charge and strictly
adhere to the same for timely completion of the project.
15. The contractor shall have to make approaches to the site, if so required and
keep them in good condition for transportation of labour and material as
well as inspection of work by Engineer-in-charge. Nothing extra shall be
paid on this account.
16. The contractor shall bear all incidental charges for cartage storage and safe
custody of materials issued to him by the department if any or his own
material.
17. The rate quoted by the agency/ contractor shall include the entire cost of
royalty. Municipal Tax, forest or an other tax whether local or state or
central or any other taxes, direct or indirect including all loading, unloading,
carriage on kacha/pacca bed or road and stacking including all labour
supply of material at the designation and nothing extra shall be paid. The
contractor shall quote his accordingly.
18. The contractor will arrange and use its own all type of machinery and T&P
incidental to all operation for the work. The rate to be quoted should be
inclusive of the same.
19. The stacking will be done at hot mix plant site for various of material in the
sequence as approved by the Engineer-in-charge, which will have tobe
maintained.
20. The contractor shall remove all bitumen spots on kerbs and channels and
all heaps of wasted mix from gulley grating bell mouth and other installation
at the end of the day work, failing which the same shall be done at his risk
and cost.
23. The quality control for road work and materials will be exercised as per
section of MORT&H specification (5th revision) 2013 and for determining the
quality of bitumen used by extraction method as per procedure laid for
doing such tests by IRC the frequency of sampling will be:-
a) MSS/Pre Mix carpet:- One test per 50 meter cube and not less than
two tests per day.
b) BM:- One test per 100 meter cube and not less than two tests per
day.
24. At the time of starts of work, the contractor shall get a sample work done in
presence of Engineer-in-charge who shall fix up the degree of compaction
consolidation required for a particular item of work and conduct suitable
tests at regular intervals to determine how far the work done approaches the
desired limit. In case tests reveal any deficiency the contractor shall make
good the same without extra payment or work will be rejected if not
according to required specification.
26. To arrive at the desired grading of materials for BM, the exact quantities of
material of different gauges shall be determined and stacked on the basis of
laboratory tests from time to time. The extra payment on this account would
not be admissible.
27. To ensure quality of intermediate fraction, tests check may be carried out on
sample taken from materials. In case that is not found according to
specification the work may be rejected. However, the Engineer-in-charge if
considered if expedient and in the interest of work, he may ask the
contractor of supply the missing fraction up to quantity as determined by
him separately free of cost.
28. Before tendering the tender shall inspect the site of work and shall fully
acquaint/satisfy himself about the condition with regard to site, nature of
soil, availability of material, suitable location for construction of godowns
stores and labour huts, the extent of lead and lifts is involved in the work
(over the entire duration of contract) including local conditions, traffic
restriction, obstructions and other conditions as required for a satisfactory
execution of work. His rate should take in to consideration all such factors
and contingencies. No claim what so ever shall be entertained by the
department on this account.
29. Whether and seasonal limitation:- The work of laying shall not be taken up
during rainy or foggy weather or when base course is damp or set or during
dust storm or when atmosphere temperature is 10 0 C or less at site of work
of particular reach.
Condition Road_2021 - 10 -
30. The rate quote should include hire charges of land or purchase of land for
installation of Hot Mix plant etc.
31. Only actual quantities of work completed and accepted by the Engineer-in-
charge shall be paid for if any damage in done by the contractor to any
existing work during the course of execution of the work this shall have to
be made good by him at his own cost.
32. Samples will be got tested from CRRI or any other approved test house,
Sample will be given by the agency free of cost and testing charges will be
borne by the agency.
33. Before start of the work contractor will get his machinery inspected and
approved from the Engineer-in-charge of work.
34. Bitumen:- The bitumen shall be arranged by the contractor himself.
a) Bitumen for bituminous macadam shall be paving bitumen of
penetration Grade-S-65 or A-65 (VG-30) as per IS specification of
“Paving bitumen” IS-73. For BUSG Pre-mix and tack coat bitumen
with penetration grade VG-10 as per IS : 73 will be used.
b) Bitumen will be arranged by the contractual agency , who will have to
produce original vouches for all quantities in lieu of purchase of
bitumen from the original, manufacturer or other authorized dealers/
distributors to the satisfaction of the Engineer-in-change for
ascertaining the genuineness of material. Attested copy of voucher
will have to be submitted alongwith bills. Executive Engineer (in
charge of work) will himself attested the copy of the bill / voucher and
will also put a stamp on the original bill indicating that this bill has
been considered by HSVP for work of …
……………………………………….. the authenticity of bill/vouchers
shall be the entire responsibility of contractual agency.
c) Test report from the refinery regarding the lot of bitumen supplied to
the contractual agency will be submitted by the agency. The bitumen
will also be got tested from reputed lab. Samples of bitumen will be
given free of cost by the contractor and all the testing charge will be
borne by him.
d) Unloading of bitumen at plant site will be gone in the presence of
representative of Engineer-in-charge. The day to day receipt and
issue account of bitumen shall be maintained by the agency at his
authorized plant site.
35. The following record of mix will be maintained at plant & site:-
At plant & weight bridge:-
1) Tipper No.
2) Time of Departure
3) Type of material
4) a) Weight of empty tipper.
b) Weight of loaded tipper.
c) Weight of material/ Mix
d) Temperature at time of departure.
e) Remarks.
At site:-
a) Tipper No.
b) Time of arrival
c) Temperature at time of arrival
d) Approximate area of the road covered on Road No……..
Condition Road_2021 - 11 -
36. At least one authorized representative of the contractor should always be
available at site of work to take instructions from department officers and
ensure proper execution of work is done in the absence of the contractor.
Separate site order book will be maintained at plant and at site of work. Any
instruction given in site order book will have the same bearing as if, it is
given to contractor in person.
37. The contractor shall be required to produce samples of all materials
sufficiently in advance to obtain approval of the Engineer-in-change.
Subsequently the material to be used in the actual execution of work shall
strictly confirm to be quality of the samples approved in case of variation
such material such be liable to be rejected.
38. The agency shall provide suitable measuring arrangement at the site for
checking of various material supplied by him.
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
Condition Road_2021 - 12 -
QUALITY CONTROL
2. The quality control tests will be got done by departmental and the
material for such tests will be supplied by the contractor free of cost. In case the
material is not fond up the requirement the same will be rejected, cost of such
tests will be borne by contractor.
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
Condition Road_2021 - 13 -
ADDITIONAL TECHNICAL CONDITION
Condition Road_2021 - 14 -
The shall be measured for length breadth and thickness after the material as laid
compacted and finished.
12. Road roller for item No. __________________ of NIT for road work shall be
arranged by the contractor out of his own sources. The maximum progress achieved per
8 hours per day from the road roller shall be restricted as under:-
(i) For preparation of sub grade item No. _____ of DNIT 1860 Sqm per 8 hours
working per day.
(ii) For preparation of granular sub base item No. _______ of DNIT 51 Cum per 8
hours working per day.
(iii) For preparation of soiling coat as per WBM specification item No. ____ of DNIT
51 cum per 8 hours working per day.
(iv) For preparation of wearing coat as per WBM /WMM specification item No. _____
of DNIT 45 cum per 8 hours working per day.
(v) For consolidation of tarring coat Item No. _____ of DNIT 900 Sqm per 8 hours
working per day.
(vi) For consolidation of 50mm BM Item No. _____ of DNIT 18 M.T. per 8 hours
working per day.
(vii) For consolidation of 25mm thick premix carpet Item No. _____ of DNIT 450 Sqm
and for seal coat 1300 Sqm per 8 hours working per day.
In case it is found that the progress as achieved is more than the hours prescribed above
the work shall be rejected and got re-done from the contractor. In case of failure of the
contractor to carry out the direction of the Engineer-in-charge in this regard the work
shall be got done departmentally at the risk and the cost of the contractor + 14%
departmental charges.
13. Third party inspection of work will be got done from reputed
institution/consultant at the cost of Department for better quality control before
releasing the running payment/final payment.
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
Condition Road_2021 - 15 -
ADDITIONAL CONDITIONS FOR CARRYING OUT BITUMINOUS ROAD WORKS:-
That the rate of bitumen/ emulsion at the refinery on the date of receipt
of tender shall be considered as base rate. If during execution of works, the rate of
bitumen/ emulsion increases or decreases at refinery, the difference in cost shall be
paid/ recouped from the contractor in the bill subject to the following conditions:-
2. The contractor shall submit original bill/ voucher of the refinery while
claiming the payment for the work done. The bill/ voucher should pertain to
the period of original contractual time limit and should correspond with the
progress of work. No extra payment due to increase in rate of bitumen/
emulsion will be paid if the original bill/vouchers are not submitted by the
agency no increase in process of the bitumen/ emulsion shall be reimbursed
to the contractor beyond the original time period allowed for construction as
per contract agreement irrespective of extension of time limit granted to the
agency for any reason what so ever.
3. After approval of tender the contractor shall submit the work programme for
execution of work and get it approved from the Engineer-in-Charge in the
time limit prescribed in the tender documents. The increase in rates of
bitumen/ emulsion shall only by paid if the bituminous work is carried out
within the prescribed period as per the approved work programme.
Important Note:-
The difference in rate of bitumen shall be paid only after obtaining approval
from Superintending Engineer, HSVP, Circle, Hisar.
The basic rate at the time of receipt of tenders will be conveyed by Executive
Engineer concerned in the allotment.
EXECUTIVE ENGINEER,
HSVP DIVISION NO. II, HISAR
Condition Road_2021 - 16 -
Performance Security:-
Within 21 days of receipt of the letter of Acceptance, the successful Bidder shall
deliver to the Engineer-in-Charge a Performance Security in any of the forms given
below for and amount equivalent to 5% of the contract price.
i) A bank Guarantee in favour of the Engineer-in-Charge.
ii) Banker Cheque/ Bank Draft/ Pay Order in favour of the Engineer-in-
Charge.
If the performance security is provided by the successful Bidder in the form of a
bank Guarantee, it shall be issued either (a) at the Bidder option, by a Nationalized/
Scheduled Indian Bank or (b) by a foreign Bank located in India and acceptable to the
Engineer-in-Charge.
Failure of the successful Bidder to comply with the requirement shall constitute
sufficient grounds for cancellation of the award and forfeiture of the Earnest Money.
Maintenance and Defect Liability Period (One years without any extra cost):-
A defect is any part of the works not completed in accordance with the Contract
or distressed development in the work irrespective of any cause.
The defects Liability Period in the Period named in the contract data and
calculated from the completion date.
The Maintenance and Defect Liability Period is three years without any extra
cost calculated from the Completion date. It is contingent to work and nothing extra is
payable.
The Maintenance and Defect Liability Certificate is the certificate issued by
Engineer-in-Charge after the defect liability periods has ended and upon correction of
Defects by the Contractor.
The performance security shall be provided to the Engineer-in-Charge not later
that the date specified in the letter of acceptable and shall be issued in an amount
and form and by a bank or surety acceptable to the Engineer-in-Charge, and
denominated in Indian Rupees. The Performance Security shall be valid until a date
28 days from the date of expiry of Defects Liability Period .
EXECUTIVE ENGINEER
HSVP DIVN. NO. - II, HISAR
Condition Road_2021 - 17 -
SPECIAL CONDITION REGARDING PREVERNTION OF AIR POLUTION AS PER ORDERS OF
NATIONAL GREEN TRIBUNAL (NGT), NEW DELHI.
1. The agency shall ensure that there should be no hot mixing on the road side during construction
and maintenance of road; it shall be also ensured that coal tar, bitumen and asphalt is brought in
molten condition and same is neither burnt nor fire is put to melt these substances on open
roads.
2. The demolition material and construction material is transported by contractor with proper
coverage and precautions, in order not to cause serious air pollution.
3. Contractor/builders would not be permitted to store and dump construction material or debris on
the metalled road.
4. The agency will ensure that such storage does not cause any observation to the free flow of traffic
and / or inconvenience to the pedestrians. The construction material is completely covered by
tarpaulin, to ensure that no dust particles are permitted to pollute the air quality as a result of
such storage.
5. The builder/contractor will be responsible and ensure that their activity does not cause any air
pollution during the course of the construction and / or storage of material or construction
activity as per NGT orders time to time. Defaulter shall be liable to be prosecuted under the law in
force.
6. All trucks or vehicles of any kind which are used for construction purpose and / or are carrying
construction material like cement, sand and other allied material shall be fully covered dust free
and / or other precautions would be taken to ensure that en-route their destination, the dust,
sand or others particles are not permitted to be released in the air and / or contaminate air. Any
truck which is not complying with these directions may not be permitted to enter the region.
7. The agency shall put tarpaulin on scaffolding around the area of construction and the building.
Builder/ agency shall not be permitted to store any construction material particularly sand on any
part of the street, roads in any colony.
8. The construction material of any kind that is stored in the site will be fully covered in all respects
so that it does not disperse in the air in any form.
9. All the construction material and debris shall be carried in the trucks or others vehicles which are
fully covered and protected so as to ensure that the construction debris of the construction
material does not get dispersed into the air of atmosphere in any form what so ever.
10. The dust emissions from the construction side should be completely controlled and all precautions
taken in that behalf.
11. The vehicles carrying construction material and construction debris of any kind should be cleaned
after unloading of any type of material.
12. Every worker working on the construction on site and involved in loading, unloading and carriage
of construction material and construction debris shall be shall be provided with mask to prevent
inhalation of dust particles.
13. The agency shall be under obligation to provide all medical help, investigation and treatment to
the workers involved to the construction of building and carrying of construction material and
debris relatable to dust emission.
14. The agency will transport construction material and debris waste to the construction site dumping
site or any other place in accordance with rule.
15. The agency will take appropriate measures and to ensure that the terms and conditions of the
orders already passed and to be passed by National Green Tribunal should be strictly complied
with.
16. In case of non compliance of any condition the executing agency shall be liable for action to be
taken as per law and as per terms and conditions of the agreement.
EXECUTIVE ENGINEER,
HSVP DIVISION NO-II, HISAR
Condition Road_2021 - 18 -